This is a Performance Work Statement (PWS) for the Jackson Levee Riprap Supply IV project, covering riprap (stone) supply for flood fight and annual maintenance of levees in Teton County, Wyoming from 2025-2030. The project involves supplying angular stone between 75-3,000 pounds in weight to five different stockpile locations: Main Stockpile Site, WYDOT, Taylor Creek, Solitude Levee, and Imeson Levee sites. The total project encompasses 27 levees, 48 levee access roads, and multiple stockpile sites near the Snake River.
Key requirements include delivering riprap by November 15th each contract year to avoid wet winter conditions, conducting wildlife-sensitive deliveries (avoiding nesting periods), and meeting strict material quality standards. The contractor must perform gradation testing, ensure rock is clean and free of soil/debris, and handle materials to minimize breakage. Delivery is restricted to 7:00 a.m. to 6:30 p.m. Monday through Saturday, with specific access and environmental protection protocols. The U.S. Army Corps of Engineers Walla Walla District will oversee the contract, with payment based on tonnage delivered and additional surcharges for remote site deliveries beyond the main stockpile.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 3.pdf | ||
| Amendment 2.pdf | ||
| Amendment W912EF25QA0150001.pdf | ||
| A.02.12 25QA015_Plans.pdf | ||
| Solicitation - W912EF25QA015.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JACKSON LEVEE RIPRAP SUPPLY IV, 2025-2030 W912EF25QA015
PROJECT TABLE OF CONTENTS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 42 37.85 28 RIPRAP SUPPLY
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
SECTION 35 42 37.85 28
RIPRAP SUPPLY
PART 1 GENERAL
1.1 SUMMARY OF WORK
1.2 REFERENCES
1.3 PROJECT SCHEDULE
1.4 PRE-WORK MEETING
1.5 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
1.6 WORKING HOURS AT THE STOCKPILE SITES
1.7 LEVEE ACCESS
1.7.1 Pedestrian Access
1.7.2 Road And Bridge Restrictions
1.7.3 Pre-Work and Post-Work Surveys
1.8 GATE SECURITY AT STOCKPILE LOCATIONS
1.8.1 Gate Keys
1.9 CONTRACTOR STAGING AND STORAGE
1.10 ROAD MAINTENANCE AND REPAIR
1.11 Snow Removal Areas
1.11.1 Snow Removal
1.11.2 Snow Removal Equipment
1.11.3 Road Repair
1.12 DUST CONTROL
1.13 OTHER CONTRACTS
1.14 Equipment List
1.15 TESTING OF EQUIPMENT
1.16 KEY PERSONNEL SUBSTITUTION
1.17 ENVIRONMENTAL
1.17.1 Protection And Restoration Of Existing Facilities and Lands
1.17.2 Sanitation Facilities
1.17.3 Regular Cleanup And Debris Disposal
1.17.4 Weed Free Certification
1.17.5 Water Quality Protection
1.17.6 Spillage
1.17.7 Fuel And Lubricants
1.18 ENVIRONMENTAL PROTECTION PLAN
1.18.1 Compliance
1.18.2 Contents
1.19 CONTRACTOR QUALITY CONTROL
1.19.1 Quality Control Manager
1.19.2 Documentation
1.20 GOVERNMENT QUALITY ASSURANCE
1.21 RIPRAP
1.22 RIPRAP SOURCES
1.22.1 Contractors Responsibility
1.22.2 Special Mineral Permits
1.22.3 Acceptance of Materials
1.22.3.1 Visual Inspections And Measurements
SECTION 35 42 37.85 28 Page 1
1.23 Riprap Delivery
1.23.1 Remote Site Delivery of Riprap
1.24 MEASUREMENT AND PAYMENT
1.24.1 Measurement
1.24.2 Payment
1.24.3 Remote Site Delivery
1.24.4 Gradation testing
PART 2 PRODUCTS
2.1 RIPRAP
2.1.1 General
2.1.2 Evaluation Testing Of Stone
2.1.3 Gradation And Size
2.1.3.1 Gradation Testing
2.1.4 Rock Character And Cleanliness
2.1.5 Rock Quality, Gradation, And Size
PART 3 EXECUTION
3.1 RIPRAP DELIVERY
3.2 STOCKPILING
3.2.1 General
3.2.2 Stockpile Locations
3.2.2.1 Main Stockpile Site
3.2.2.2 Taylor Creek Stockpile
3.2.2.3 390 Stockpile
3.2.2.4 Solitude Levee Stockpile
3.2.2.5 Imeson Levee Stockpile
ATTACHMENTS:
Activity Hazard Analysis
-- End of Section Table of Contents --
SECTION 35 42 37.85 28 Page 2
SECTION 35 42 37.85 28
RIPRAP SUPPLY
PART 1 GENERAL
1.1 SUMMARY OF WORK
This summary of work is a generalized description of work and is not all inclusive.
The project is located in Teton County, Wyoming, near the town of Jackson.
The project consists of 27 levees, 48 levee access roads, 4 small riprap stockpile sites, and the major stockpile site near the Highway 22 bridge over the Snake River. This work is to replenish the stockpile of riprap (stone)to support flood fight and annual maintenance efforts for the Jackson Hole Project for up to a five year period. This project will supply riprap to the main stockpile site, with optional quantities to the project's various stockpiles. In the event the Government directs riprap to be delivered directly to work sites on the levees, the contractor will be reimbursed a surcharge, based on additional haul mileage.
The contractor's schedule should reflect completion of riprap deliveries by 15 November of the contract year, to avoid vehicle traffic impacts to the levees due to wet conditions from the onset of winter.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
100 Barr Harbor Drive, P.O. Box C700 West Conshohocken, PA 19428-2959 Ph: 610-832-9585 Ph: 877-909-2786 Internet: http://www.astm.org
ASTM C127 (2015) Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate
ASTM C535 (2016) Standard Test Method for Resistance to Degradation of Large-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine
ASTM D2488 (2017; E 2018) Standard Practice for Description and Identification of Soils (Visual-Manual Procedure)
ASTM D5240/D5240M (2013) Standard Test Method for Evaluation of Durability of Rock for Erosion Control Using Sodium Sulfate or Magnesium Sulfate
SECTION 35 42 37.85 28 Page 3
U.S. National Archives and Records Administration (NARA)
8601 Adelphi Road College Park, MD 20740-6001 Ph: 866-272-6272 Fax: 301-837-0483 Internet: http://www.archives.gov Order documents from:
Superintendent of Documents U.S.Government Printing Office (GPO) 710 North Capitol Street, NW Washington, DC 20401 Ph: 202-512-1800 Fax: 202-512-2104 E-mail: contactcenter@gpo.gov Internet: http://www.gpoaccess.gov
40 CFR 112 Oil Pollution Prevention
40 CFR 261 Identification and Listing of Hazardous Waste
FEDERAL ACQUISITION REGULATIONS (FAR)
Internet: https://www.acquisition.gov/browse/index/far
FAR 52.222-54 Employment Eligibility Verification
FAR 22.18 Employment Eligibility Verification
U.S. ARMY CORPS OF ENGINEERS (USACE)
CRD-C DOCUMENTS available on Internet:
http://www.wbdg.org/ccb/browse_cat.php?c=68 Order Other Documents from:
USACE Publications Depot Attn: CEHEC-IM-PD 2803 52nd Avenue Hyattsville, MD 20781-1102 Ph: 301-394-0081 Fax: 301-394-0084 E-mail: pubs-army@usace.army.mil Internet: http://www.publications.usace.army.mil/ or http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx
EM 385-1-1 Safety and Occupational Health Requirements
Comply with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.3 PROJECT SCHEDULE
Following award of each Task Order the Contractor shall coordinate and establish a project delivery schedule with the USACE Walla Walla District Representative, (REP).
SECTION 35 42 37.85 28 Page 4
1.4 PRE-WORK MEETING
The Contractor shall meet with the REP at the Teton County Office Building located in Jackson, Wyoming, or virtually as coordinated with the REP, at least ten (10) working days prior to the beginning of work. The purpose of this meeting is to discuss and develop mutual understandings relative to the general and technical, safety, quality control program, scheduling of work, and environmental protection provisions of the contract. Provide the following items to the Contracting Officer electronically, in pdf format, prior to this meeting:
a. A list of all equipment to be used by the Contractor in the performance of work under this contract. See paragraph EQUIPMENT LIST in this section.
b. A list of names and addresses of all employees and authorized site supervisor who will be working for the Contractor, including subcontractors and their employees.
Using this list furnish verification to the Contracting Officer (KO) of compliance with Pre-Screening of employees under the E-Verify Program. See paragraph PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM in this section.
c. Safety plan and Activity Hazard Analysis (AHA) to include the Accident Prevention Plan (APP) as specified in EM 385-1-1 .
d. A list of vehicles to be used and license plate numbers.
e. Environmental protection plan. See paragraph ENVIRONMENTAL PROTECTION PLAN in this section
f. Certified Scale, suggested by the contractor, to be used for the project. Bring a copy of the current State Certification to the meeting. See paragraph Measurement in this section
g. Evaluation Test data performed on the stone from the Contractor's source, performed by a state-certified laboratory. See paragraph Evaluation Testing of Stone in this section.
h. Documentation from the state showing riprap source is a state certified source. See paragraph RIPRAP SOURCES in this section.
i. Letters designating the employee who will serve as the contractor's Site Safety Health Officer (SSHO), Site Supervisor, and Quality Control Manager. These functions may be performed by the same person as long as that person meets or exceeds the functions qualifications as specified in EM 385-1-1 .
j. Pre-work and post-work surveys of work areas and access roads to document their condition, as appropriate. See paragraph Pre-Work and Post Work Surveys in this section.
k. Certification the pit source is weed-free, as documented by the local authority. See paragraph Weed Free Certification in this section.
SECTION 35 42 37.85 28 Page 5
1.5 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
a. Contractors shall comply with the requirements set forth in FAR 52.222-54 Employment Eligibility Verification and FAR 22.18 in using the E-Verify Program to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). The E-Verify Program is located at the following website:
https://www.nww.usace.army.mil/Business-With-Us/Contracting/AT-OPSEC-for-Contractors/
1.6 WORKING HOURS AT THE STOCKPILE SITES
The Contractor's delivery of riprap to the stockpile sites shall be accomplished between the hours of 7:00 a.m. to 6:30 p.m. each workday.
Workdays are Monday through Saturday. No work allowed on Sunday, unless otherwise specified herein, or authorized in advance by the REP.
1.7 LEVEE ACCESS
The levees are located on private property. There is a speed limit of 15 mph while traveling on the levees, unless reduced by the REP.
1.7.1 Pedestrian Access
There is public pedestrian access on the Walton Levee, the primary access to the main stockpile site, immediately adjacent to Highway 22 right after Emily Stevens Pond Park, Contractor vehicles will reduce speed to 5 miles per hour to ensure public safety while in the proximity of pedestrians on the levee.
This restriction also applies to the Public and Boat Ramp Levees, which also allow public access.
1.7.2 Road And Bridge Restrictions
There are road and bridge restrictions in the area. Contractor is responsible for following the local road and bridge restrictions in the Project area. Contact the Teton County Roads and Levees Department for current information. There are weight limitations on some roads and levees. Coordinate with the REP on which roads have weight limitations.
1.7.3 Pre-Work and Post-Work Surveys
Conduct a pre-work survey prior to start of on-site work and a post-work survey during project closeout. In particular, document damaged facilities such as gates, damage to lawns, cracked or potholed pavement, and washboarding on roads. Document the results of the survey by digital photographs and descriptive narrative reports. Submit a color copy of the survey photographs and narrative reports.
Document the conditions of the levee, access roads, and structures including gate and cattle guards in a report submitted before the start of the work. Submit a new survey at the conclusion of the work and note any changes.
SECTION 35 42 37.85 28 Page 6
1.8 GATE SECURITY AT STOCKPILE LOCATIONS
Gate security shall be the responsibility of the Contractor. Each stockpile location is protected by one or more gates. To ensure landowner privacy and prevent cattle and other livestock from escaping, the gates shall be kept closed at all times, except when trucks are passing through, unless the contractor has performed prior coordination with affected landowner(s).
1.8.1 Gate Keys
The Contractor shall maintain a key register to document employee possession of Government keys. The Contractor, upon request from the REP, shall make available for inspection the key register or a photocopy of
it. Extra keys shall be kept in a locked and secured key cabinet.
Discharged employees shall be required to turn in all Government keys.
All occurrences of lost keys shall be reported to the REP within 24 hours of loss. For each occurrence of a key being lost or stolen, the Contractor shall be required to reimburse the Government for actual costs of a new key(s). Keys shall not be duplicated.
1.9 CONTRACTOR STAGING AND STORAGE
The Contractor may request to store equipment long term at the main stockpile site. The Government will not be liable for the theft or destruction of any Contractor's tools or equipment left at stockpile sites.
1.10 ROAD MAINTENANCE AND REPAIR
1.11 Snow Removal Areas
Access roads to the main stockpile site and other stockpile sites may be covered with snow from October until late spring. Heavy snow accumulation is common in the Jackson area and can remain on the ground well into or throughout the spring. Snow plowing operations required to maintain access to the designated stockpile area(s) shall be the responsibility of the Contractor.
1.11.1 Snow Removal
Remove snow from all or part of the access roads and levees traveled to facilitate safe and efficient PROJECT use and to protect the roads and levees. Perform work in a manner to preserve and protect roads, levees, and appurtenances, and to prevent damage to adjacent land. Do not undercut banks, nor blade gravel or other surfacing material off the roads or levees. Drainage ditches and culverts shall be functional during and after completion of snow removal operations.
1.11.2 Snow Removal Equipment
Any type of equipment may be used to remove snow, providing the equipment is of the size and type commonly used to remove snow and will not cause damage to the roads or levees. On roads and levees that have a crushed rock surface, dozers shall be equipped with shoes or runners to keep the dozer blade a minimum of two (2) inches above the road or levee surface, unless agreed otherwise.
SECTION 35 42 37.85 28 Page 7
1.11.3 Road Repair
Any damage to the access roads and levee surfaces caused by contractors operations is the responsibility of the Contractor to repair. This includes asphalt damage and wash-boarding of gravel surfaces. Repairs and grading of access roads and levee surfaces shall be the responsibility of the Contractor
1.12 DUST CONTROL
Hauling and stockpiling operations shall be controlled to eliminate all unnecessary dust creating activities. Control dust so that vehicles are visible within the stopping sight distance for the average user speed on a particular section. As a minimum, water shall be used for dust abatement, unless otherwise agreed. Adequate dust-control measures shall be employed as are directed or approved by the REP. Sprinkling, or other approved dust palliatives or stabilizing materials, as required to satisfactorily control dust, shall be applied at no additional or direct cost to the Government. Temporary construction roads, access haul roads (excluding streets and roads maintained by Teton County or State of Wyoming), levee crowns and work areas shall be maintained free from excessive dust by an approved program of either adequate sprinkling, graveling, chemical treatment, or other approved method, or combination thereof, for the duration of the Contractor's hauling.
1.13 OTHER CONTRACTS
The Government may undertake or award other contracts for additional work, and the Contractor shall fully cooperate with such other contractors and Government employees and carefully fit his own work to such additional work as may be directed by the KO. The Contractor shall not commit or permit any act which will interfere with the performance of work by any other contractors or Government employees.
1.14 Equipment List
Furnish a complete list of all equipment to be used on the project at the pre-work/pre-construction meeting. Submit a revised list in the event of change of equipment. Lists must include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial and revised lists must indicate the dates equipment is assigned to or removed from the Project and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
1.15 TESTING OF EQUIPMENT
Before any machinery or mechanized equipment is put to use on the job, it shall be inspected and tested by a qualified person and determined to be in safe operating condition. Cranes or derricks shall be tested by the Contractor or a qualified testing agency in accordance with EM 385-1-1 .
Equipment shall be large enough to safely handle proposed picks or tasks without exceeding the crane rating established by these tests.
1.16 KEY PERSONNEL SUBSTITUTION
If the Contractor plans on replacing any Key personnel (i.e.: Site Supervisor, CQC Manager, or CQC staff Members) they must have the approval
SECTION 35 42 37.85 28 Page 8 of the REP. Personnel shall possess qualifications that meet or exceed those stated in this contract for the position of the individual they are replacing. Submit qualifications of new personnel at least 15 calendar days in advance of date of replacement
1.17 ENVIRONMENTAL
1.17.1 Protection And Restoration Of Existing Facilities and Lands
Take precautions to prevent damage to existing facilities and lands while performing work under this contract. Upon completion of the work, ensure all existing facilities not included as a portion of the work are in a condition better than, or equal to the condition existing at time of contract award. Costs for maintenance, repair and restoration of any facilities are considered as incidentals, and included in the contract price.
1.17.2 Sanitation Facilities
The Contractor shall furnish sanitation facilities in accordance with EM 385-1-1 . The location of all facilities will be subject to the REP's approval. Provide wind anchorage to prevent any spillage. Provide freeze protection to sanitation facilities starting the 1st of October through November 15th.
1.17.3 Regular Cleanup And Debris Disposal
Collect and remove all debris resulting from the work regardless of size, such as packing cases, scrap lumber, metal grindings, and all other debris from the project site daily, then dispose of debris in a safe, legal manner. All costs for removing debris are incidental to the work, and no separate payment will be made therefore. The Government's trash cans, dumpster's, etc. cannot be used.
1.17.4 Weed Free Certification
Prior to the commencement of work for each year of this contract, the contractor shall furnish documentation that the riprap material source is certified weed free by the local noxious weed control board or entity.
1.17.5 Water Quality Protection
All equipment will be inspected for oil, gas, diesel, anti-freeze, hydraulic fluid, and other petroleum leaks. All leaks will be properly repaired and equipment cleaned with a high pressure wash prior to being brought on-site. Leaks that occur after the equipment is on-site shall be repaired within one day or removed from the project area. The equipment will not be allowed to continue operating upon discovery of a leak.
1.17.6 Spillage
Take special measures to prevent chemicals, fuels, oils, greases, bituminous materials, waste washings, and sewage from entering surface and subsurface waters. All prevention/cleanup materials must comply with all applicable federal and state laws and regulations. Provide and utilize the following prevention/cleanup materials:
a. Fuel dispensing vehicles must carry a tanker fueling berm spill
SECTION 35 42 37.85 28 Page 9 kit on board at all times.
b. Approved means such as drip pans must be placed under every vehicle and piece of equipment to catch all leaks when parked.
c. An emergency spill response kit must be carried on board each piece of equipment performing work. For heavy equipment such as excavators, the spill kit must be located at the work site.
d. Emergency spill response kits must be sufficient for the largest quantity spill that could occur based on equipment being used and must be appropriate for spills on land or in water.
e. All containers of fuel, oil, and other hazardous materials stored on-site must be stored with secondary containment.
f. Any releases of oil or hazardous substances into state waters must be reported to Government Official and to National Response Center (EPA and Coast Guard 1-800-424-8802), Wyoming Department of Environmental Quality (DEQ) at https://deq.wyoming.gov/spill-and-complaints/ or 307-777-7501. Any spills of these substances of greater than 25 gallons on land must be reported to Wyoming DEQ at https://deq.wyoming.gov/spill-and-complaints/ or 307-777-7501, immediately, for both land and water spills, by the contractor.
Stabilization and cleanup of the spill must begin immediately.
1.17.7 Fuel And Lubricants
Special measures shall be taken to prevent chemicals, fuels, oils, greases, bituminous materials, and waste washings from entering public lands or waters. Provide and utilize the following prevention/cleanup materials during the course of this contract:
1. If the fuel dispensing or storage tanks are not double walled, Contractor shall utilize secondary containment. All secondary containment shall be capable of containing a minimum of 100 percent of the holding tank without release plus free board in compliance with 40 CFR 112 .
2. Emergency spill kits shall be immediately available to enable rapid cleanup with sufficient quantities and types of spill control materials to contain any spills that can be anticipated.
Contractor shall be responsible for ascertaining the types/quantities of spill equipment required based on types and quantities of chemicals, oils, POLs, they will use and/or what they will be working on.
3. Emergency spill absorbent mats (10-18" x 18" or appropriately sized) shall be carried on board or be in the immediate vicinity of all equipment performing work. Mats shall be of a quilted cotton pillow design, and absorbent (not adsorbent) filled, to encapsulate hydrocarbons (oils, coolants and solvents).
1.18 ENVIRONMENTAL PROTECTION PLAN
Prior to the pre-work meeting, submit an Environmental Protection Plan (EPP) for review and approval by the Contracting Officer. The purpose of the Environmental Protection Plan is to present a comprehensive overview
SECTION 35 42 37.85 28 Page 10 of known or potential environmental issues which shall be addressed during work. Define issues of concern within the Environmental Protection Plan as outlined in this SECTION. Address each topic at a level of detail commensurate with the environmental issue and required work task(s).
Identify and discuss topics or issues which are not identified in this SECTION, but which is considered necessary, after those items formally identified in this SECTION. The Environmental Protection Plan shall be current and maintained on site.
1.18.1 Compliance
No requirement in this SECTION relieves the Contractor of any applicable Federal, State, and local environmental protection laws and regulations.
During work, identify, implement, and submit for approval any additional requirements to be included in the Environmental Protection Plan.
1.18.2 Contents
The Environmental Protection Plan (EPP) shall include, but not be limited to, the following:
a. Name(s) and phone numbers of individual(s) within the Contractor's organization responsible for ensuring adherence to the Environmental Protection Plan.
b. Description of the Contractor's environmental protection personnel training program.
c. Contractor's process for immediately notifying the REP of any spills. The Contractor is responsible for all spill notifications to regulatory agencies (Federal, State, and local). This plan will include the contact information for Federal, State, and local agencies. In the event of a spill, provide a copy of the notification reports to the REP.
d. Solid Wastes Management Plan
1. Solid waste is as defined in 40 CFR 261 . The EPP shall describe how solid wastes will be picked up and placed in covered containers which are emptied regularly.
2. Housekeeping measures to prevent contamination of the site or other areas when handling and disposing of solid waste.
f. Fugitive dust control plan.
1.19 CONTRACTOR QUALITY CONTROL
Contractor Quality Control (CQC) is the means by which the Contractor ensures that the work, to include that of subcontractors, complies with the requirements of the contract. The Contractor is responsible for quality control and shall establish and maintain an effective inspection system. The quality control inspection system shall be adequate to ensure that all riprap complies with the contract requirements. The system shall cover all work operations and shall be keyed to the proposed work sequence.
1.19.1 Quality Control Manager
The Contractor shall identify an individual within the organization who
SECTION 35 42 37.85 28 Page 11 will be the point of contact for the REP. This individual shall be responsible for overall management of quality control (QC) and have the authority to act in all QC matters for the Contractor. This Manager shall be employed by the Contractor. An alternate for the QC Manager shall be identified in the plan to serve in the event of the system manager's absence. The requirements for the alternate shall be the same as for the designated QC Manager.
1.19.2 Documentation
Maintain current records of quality control operations, activities, and inspections, including the work of subcontractors. These records shall be on an acceptable form and shall include factual evidence that required quality control activities and inspections have been performed, including but not limited to the following:
a. Contractor/subcontractor and their area of responsibility.
b. Operating plant/equipment with hours worked, idle, or down for repair.
c. Quality Control activities performed with results and references to specifications requirements. List deficiencies noted along with corrective action.
d. Job safety evaluations stating what was checked, results, and instructions or corrective actions.
e. List instructions given/received and conflicts in specifications.
f. Work performed today, giving location, description, and by whom.
g. The QC manager shall have a copy of all reports and weight tickets on site and available for review by the REP.
h. Copies of all weight tickets shall be scanned and emailed to the REP within 5 business days of each Riprap delivery.
Mailing Address:
District Commander ATTN: CENWW-OD-B Kenneth Koebberling Walla Walla District Corps of Engineers 201 North Third Avenue Walla Walla, WA 99362-1876
Email address: Kenneth.E.Koebberling@usace.army.mil
1.20 GOVERNMENT QUALITY ASSURANCE
a. The Government will monitor the Contractor's performance under this contract using quality assurance procedures developed by the Government. Typical procedures might include random sampling, checklists and observations.
b. The Government reserves the right to inspect and test all materials called for by the contract, to the extent practicable at all times and places during the term of the contract. The Government will perform inspections and tests in a manner that will not unduly delay
SECTION 35 42 37.85 28 Page 12 the work.
c. If any of the materials do not conform to contract requirements, the Government will request the Contractor to remove the materials and replace them with materials that conform with contract requirements.
1.21 RIPRAP
All stone for riprap shall conform to the quality and gradation requirements hereinafter defined and as approved by the REP. In this specification, riprap is defined as angular stone produced from bedrock, which requires drilling, and blasting for removal or angular stone meeting the specified size and physical quality requirements. The stone shall be clean and reasonably free from soil, quarry fines, and shall contain no refuse or organic matter.
1.22 RIPRAP SOURCES
The Contractor shall designate in writing only one source or one combination of sources from which he proposes to furnish stone. The stone source shall be approved by a state or other government agency, and proof of the government approval shall be included with the written stone source designation. This approval is not to be construed as approval of the stone source required under this contract. This designation shall also include any test results for the source stone, the location by section, township, and range, pit name, owner, and operator using the pit. It is the Contractor's responsibility to determine that the stone source or combination of sources selected is capable of providing the quality, quantities, and gradation needed to meet the requirements of these specifications and at the rate needed to maintain the scheduled progress of the work.
1.22.1 Contractors Responsibility
The Contractor shall make his own arrangements concerning availability of all riprap sources. The payment of royalties, disposal of wastes, and restoration of the borrow areas or quarry upon completion of the work shall be the Contractors responsibility. The Contractor shall also comply with all applicable local, State, and Federal laws and regulations.
1.22.2 Special Mineral Permits
The USACE occasionally obtains and uses special mineral permits from the Bridger-Teton National Forest. The permit allows the USACE to obtain riprap rock located on land permitted to the Jackson Hole Ski Corporation. The Contractor may not use, in conjunction with this contract, any rock that is already available to the USACE from the Bridger-Teton National Forest.
1.22.3 Acceptance of Materials
Acceptance of a source of stone is not to be construed as acceptance of all material from that source. The right is reserved to reject materials from certain localized areas, zones, or strata when such materials are unsuitable for stone as determined by the REP. The REP also reserves the right to reject individual units of produced specified materials upon delivery to the stockpile when such materials are determined to be unsuitable.
SECTION 35 42 37.85 28 Page 13
1.22.3.1 Visual Inspections And Measurements
During the contract period, both prior to and after materials are delivered to the stockpile, visual inspections and measurements of the stone materials may be performed by the REP. If the REP, during the inspection, finds that the stone quality or gradation of stone being furnished is not as specified or is questionable, re-sampling and retesting shall be required. Sampling of the delivered stone for testing and the manner in which the testing is to be performed, shall be as directed by the REP. This additional sampling and testing shall be performed at the Contractor's expense when test results indicate that the materials do not meet specified requirements. When test results indicate that materials meet specified requirements, an equitable adjustment in the contract price will be made for the sampling and testing. Any material rejected shall be removed or disposed of at the Contractors expense.
1.23 Riprap Delivery
The delivery schedule will take into account wildlife concerns and anticipated weather conditions. To avoid impacts to nesting bald eagles and ground nesting migratory birds, deliveries of riprap to stockpile sites and levees will typically begin 15 August where eagles may be affected and 1 August for ground nesting migratory birds. If the Corps determines that there are no significant impacts to eagles or ground nesting birds at the levees work areas and/or stockpile sites the REP may request earlier deliveries of riprap. The contractor's schedule should reflect completion of riprap deliveries by 15 November of the contract year, to avoid vehicle traffic impacts to the levees due to wet conditions from the onset of winter.
1.23.1 Remote Site Delivery of Riprap
When delivering riprap directly to a worksite, the Contractor shall take precautions to ensure riprap is not dumped on the crushed travel surface of levee. This will prevent damage to the levee crest. Instead, the Contractor should use side dump trailers or back end dumps at a safe angle to ensure riprap is deposited on the levee slope. Ensure trucks and trailers are not at an unsafe angle to the levee slope.
1.24 MEASUREMENT AND PAYMENT
1.24.1 Measurement
Riprap will be measured for payment as the number of tons of satisfactory riprap material delivered to the delivery site. Measurement will be made from weight tickets furnished to the REP. Trucks shall be weighed on a state certified scale furnished by the Contractor or on a state certified permanently installed commercial scale. Scales shall be self-printing for producing weight tickets. Contractor furnished scale shall be furnished, erected, and maintained by the Contractor. After erection, the scale shall be certified by the State in which the scale is located. A copy of the state certificate shall be furnished to the REP before the scale is put into use. Trucks used to haul riprap shall be weighed empty weekly at times directed by the REP. Each truck shall bear a plainly legible identification mark.
SECTION 35 42 37.85 28 Page 14
1.24.2 Payment
Payment will be made at the contract unit price per ton for Item Nos.
ending in AB, AC, AD, AE, AF and AG, "Produce and Stockpile Riprap".
These prices and payments shall be full compensation for furnishing all plant, equipment, materials, and labor and for performing all work required to test, produce, load, weigh, deliver, unload, and stockpile riprap, complete, as specified and as approved. No payment will be made for any rejected materials and no separate payment will be made for disposal of rejected materials.
1.24.3 Remote Site Delivery
In the event the REP directs Riprap delivery to other than the stockpile sites specified, to support ongoing levee rehabilitation, the Contractor will be paid an additional surcharge, per Schedule Items AG, for road mileage greater than 5 miles, as measured from the Highway 22 bridge.
Surcharges will not be paid for deliveries to the four (4) Game and Fish levees, South Park levee, or Evans levee if the distance actually traveled by the contractor to those locations is shorter than travel to the main stockpile.
1.24.4 Gradation testing
Gradation testing will be measured for payment as the number of tests actually performed. Payment will be made at the contract unit price for Item Nos. ending in AA, "Gradation testing", which price and payment shall be full compensation for furnishing all equipment, materials, and labor and for performing all work required to perform gradation testing, as specified and as approved. Gradation tests not passing will not be paid for.
PART 2 PRODUCTS
2.1 RIPRAP
2.1.1 General
Laboratory tests, visual examination, service records, gradation, and size shall be used to determine the acceptability of stone from the source selected by the Contractor. However, the approval of the Contractor's rock source does not preclude the REP from refusing delivery of rock should the rock not meet the specified requirements for quality, gradation, or size.
2.1.2 Evaluation Testing Of Stone
After contract award the Contractor shall provide riprap quality testing of the Contractor selected source prior to initial delivery. If multiple sources are to be used, each source shall have its own suite of testing performed. Testing is also required for each rock type within a quarry if rock quality or type vary significantly in the quarry. This testing shall be performed at the Contractor's expense. The test results are intended to verify rock quality at the source. Sampling for the initial testing will be conducted during a prearranged joint inspection. Selection of samples shall be made by the Contractor and the REP at the source within 30 calendar days after award of the Contract. The Contractor shall notify the Government as to the time and location of the meeting. If recent testing as outlined in the table below is already available, this data may
SECTION 35 42 37.85 28 Page 15 substitute for the new testing at the REP's discretion. The inspection and subsequent laboratory testing shall not relieve the Contractor of the requirement to deliver the riprap within the specified delivery periods.
All riprap materials shall meet the following test requirements for quality:
EVALUATION TESTING OF STONE
TEST DESIGNATION TEST METHOD REQUIREMENTS TESTING RECENCY
ASTM C127 Density, Relative Density (Specific Gravity), and Absorption
Specific Gravity:
minimum 2.5;
Absorption:
maximum 2.5%
Perform new testing after award of this contract. Test data within the past 3 years from the same rock and source may be substituted at the REP's discretion.ASTM C535 Resistance to
Degradation of Large-Size Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine
30% maximum loss by weight
ASTM D5240/D5240M Evaluation of Durability of Rock for Erosion Control Using Sodium Sulfate or Magnesium Sulfate
(5 Cycles) Not greater than 10% loss
Perform new testing after award of this contract. Test data within the past 6 years from the same rock and source may be substituted at the REP's discretion.
In addition to the above test requirements, the stones will be subjected to visual field examination, the stone may be rejected solely on the basis of such visual examination, regardless of laboratory test results when the examination shows the stone to be unsuitable.
2.1.3 Gradation And Size
Material for riprap shall be obtained by careful selection of individual pieces. Riprap shall be reasonably graded, and shall have the minimum, average, and maximum weights as specified below. Neither the breadth nor the thickness of any piece of riprap shall be less than one- third of its length. Rounded alluvial material and/or subrounded rock will not be acceptable. Rounded alluvial and subrounded rock shall be as defined in the American Society for Testing and Materials standard ASTM D2488.
GRADATION REQUIREMENTS
Minimum Wt. - Lbs. Average Wt. - Lbs. Maximum Wt. - Lbs.
75 450-550 3,000
2.1.3.1 Gradation Testing
When directed by the KO, the Contractor shall perform gradation tests.
The gradation test shall take place at the Contractor's rock source or at
SECTION 35 42 37.85 28 Page 16 a location mutually agreed upon by the Contractor and the REP. The Government will give the Contractor a minimum of 1 working day notice prior to testing in order to allow the Contractor time to furnish all labor and equipment required for the testing. The day of the test, one truckload will be randomly selected for testing by the REP. Each rock from the truckload shall be individually weighed on certified scales with verifiable accuracy of 2%(+/-). The Government will record all results.
In addition, the test results shall be indicative of a well-graded material. The first gradation test will be required during the first week of delivery. Upon acceptance by the REP, this load may be set aside and used as a comparison example for future loads delivered to the site. A minimum of one, and a maximum of two additional passing tests of riprap may be performed during each year the rock is being delivered. The REP will direct when tests are to be performed. All rejected rock shall be removed from the site at the Contractors expense.
2.1.4 Rock Character And Cleanliness
Clean riprap has less of an effect on river turbidity levels during rehabilitations. The Contractor shall ensure that rock is free from attached soil and debris. The Contractor shall ensure that its activities do not promote the spread of noxious weeds.
2.1.5 Rock Quality, Gradation, And Size
If the material being delivered to the delivery site does not meet specified requirements, delivery will be refused by the REP and the material shall be removed at the Contractor's expense. The REP will be looking at the following criteria during rock delivery:
a. QUALITY - Does the rock meet the specified requirements for quality. Is the stone of the same quality as the material accepted for the source?
b. GRADATION - Is the rock well graded between 75 pounds and 3000 pounds? Does the load look similar to the example load?
c. SIZE - Is all of the material somewhat equal dimensional and between 75 and 3000 pounds? Does the load look similar to the example load?
d. CHARACTER - Is the rock free of clumps of attached soil and debris?
PART 3 EXECUTION
3.1 RIPRAP DELIVERY
After the Contractor has begun delivery of riprap, he shall continue delivery, without interruption, until the total specified quantity of riprap has been delivered to the designated site. The Contractor's scheduled days off will not be considered an interruption in the delivery of the riprap.
3.2 STOCKPILING
3.2.1 General
All riprap material shall be stockpiled within a designated area of the specified stockpile location. The final height of the stockpile shall not
SECTION 35 42 37.85 28 Page 17 exceed 15 feet. The contractor shall employ a tracked excavator equipped with a bucket thumb to stockpile all riprap. Handle the riprap in a manner to minimize rock breakage and minimize the introduction of soils to the stockpile. When stockpiling riprap, the Contractor shall maintain as constant and regular a cross section as possible to facilitate surveying for quantities if necessary. The stockpile sites only have a minimum amount of room for stockpiling material so the Contractor shall move the material accordingly to get the maximum amount of rock in the defined stockpile location.
3.2.2 Stockpile Locations
A designated area within the main stockpile site, the WYDOT stockpile site, the Taylor Creek stockpile site, the Solitude Levee stockpile site, and Imeson Levee stockpile site shall be used to stockpile the riprap. The actual stockpile locations and limits of the stockpile areas will be staked and/or flagged in the field by the REP prior to delivery of riprap materials.
3.2.2.1 Main Stockpile Site
The main stockpile is located approximately one mile north of the Highway 22 Bridge over the Snake River, Teton County, Wyoming, in the NE 1/4 of Section 24, Township 41 North, Range 117 West, Latitude 43.50800, Longitude -110.83000. Access to the main stockpile is via east Snake River Levee Road immediately east of Snake River Bridge on Highway 22.
Travel north on levee road approximately 1 mile to the entrance to the stockpile site.
3.2.2.2 Taylor Creek Stockpile
The Taylor Creek stockpile site is located approximately eight miles southeast of Wilson, Teton County, Wyoming, on the Fall Creek Road in the SW 1/4 of Section 24, Township 40 North, Range 117 West, Latitude 43.4132, Longitude -110.8321.
3.2.2.3 390 Stockpile
The 390 stockpile site is located approximately two miles south of Teton Village, Teton County, Wyoming on the Moose-Wilson Road in the SE 1/4 of Section 36, Township 42 North, Range 117 West, Latitude 43.5531, Longitude -110.8263.
3.2.2.4 Solitude Levee Stockpile
The Solitude Levee Stockpile is located West of Jackson Hole Airport in the NW 1/4 of Section 21, Township 42 North, Range 116 West, Latitude
43.5948 and Longitude -110.7785. The stockpile is located 2.6-miles from the upstream end of the levee.
3.2.2.5 Imeson Levee Stockpile
The Imeson Levee stockpile is located south of Jackson in the NW 1/4 of section 14, Township 40 North, Range 117 West, Latitude 43.4362, Longitude -110.8495. Access to the Morgan Levee, which leads to the Imeson levee stockpile, is via Crane Creek Ranch Road just east of Snake River Bridge on Highway 22. An alternate route to this stockpile, when traveling from south of Jackson, is from the Shootin' Iron Road, off of South Park Road.
Coordinate with the REP for access from this direction. The stockpile
SECTION 35 42 37.85 28 Page 18 location is 4.8-miles from the Highway and the route runs along the levee system.
-- End of Section --
SECTION 35 42 37.85 28 Page 19
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 35 42 37.85 28 Page 20
| PROJECT TABLE OF CONTENTS |
| DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION |
| 35 42 37.85 28 - RIPRAP SUPPLY |
| 35 42 37.85 28 - RIPRAP SUPPLY |
| PART 1 GENERAL |
| 1.1 SUMMARY OF WORK |
| 1.2 REFERENCES |
| 1.3 PROJECT SCHEDULE |
| 1.4 PRE-WORK MEETING |
| 1.5 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM |
| 1.6 WORKING HOURS AT THE STOCKPILE SITES |
| 1.7 LEVEE ACCESS |
| 1.7.1 Pedestrian Access |
| 1.7.2 Road And Bridge Restrictions |
| 1.7.3 Pre-Work and Post-Work Surveys |
| 1.8 GATE SECURITY AT STOCKPILE LOCATIONS |
| 1.8.1 Gate Keys |
| 1.9 CONTRACTOR STAGING AND STORAGE |
| 1.10 ROAD MAINTENANCE AND REPAIR |
| 1.11 Snow Removal Areas |
| 1.11.1 Snow Removal |
| 1.11.2 Snow Removal Equipment |
| 1.11.3 Road Repair |
| 1.12 DUST CONTROL |
| 1.13 OTHER CONTRACTS |
| 1.14 Equipment List |
| 1.15 TESTING OF EQUIPMENT |
| 1.16 KEY PERSONNEL SUBSTITUTION |
| 1.17 ENVIRONMENTAL |
| 1.17.1 Protection And Restoration Of Existing Facilities and Lands |
| 1.17.2 Sanitation Facilities |
| 1.17.3 Regular Cleanup And Debris Disposal |
| 1.17.4 Weed Free Certification |
| 1.17.5 Water Quality Protection |
| 1.17.6 Spillage |
| 1.17.7 Fuel And Lubricants |
| 1.18 ENVIRONMENTAL PROTECTION PLAN |
| 1.18.1 Compliance |
| 1.18.2 Contents |
| 1.19 CONTRACTOR QUALITY CONTROL |
| 1.19.1 Quality Control Manager |
| 1.19.2 Documentation |
| 1.20 GOVERNMENT QUALITY ASSURANCE |
| 1.21 RIPRAP |
| 1.22 RIPRAP SOURCES |
| 1.22.1 Contractors Responsibility |
| 1.22.2 Special Mineral Permits |
| 1.22.3 Acceptance of Materials |
| 1.22.3.1 Visual Inspections And Measurements |
| 1.23 Riprap Delivery |
| 1.23.1 Remote Site Delivery of Riprap |
| 1.24 MEASUREMENT AND PAYMENT |
| 1.24.1 Measurement |
| 1.24.2 Payment |
| 1.24.3 Remote Site Delivery |
| 1.24.4 Gradation testing |
| PART 2 PRODUCTS |
| 2.1 RIPRAP |
| 2.1.1 General |
| 2.1.2 Evaluation Testing Of Stone |
| 2.1.3 Gradation And Size |
| 2.1.3.1 Gradation Testing |
| 2.1.4 Rock Character And Cleanliness |
| 2.1.5 Rock Quality, Gradation, And Size |
| PART 3 EXECUTION |
| 3.1 RIPRAP DELIVERY |
| 3.2 STOCKPILING |
| 3.2.1 General |
| 3.2.2 Stockpile Locations |
| 3.2.2.1 Main Stockpile Site |
| 3.2.2.2 Taylor Creek Stockpile |
| 3.2.2.3 390 Stockpile |
| 3.2.2.4 Solitude Levee Stockpile |
| 3.2.2.5 Imeson Levee Stockpile |