A.02.12 Seed Task Order Pricing Schedule.pdf

PDF 33 KB Posted

Attached to
Electrical Equipment Rehabilitation and Replacement MATOC
Solicitation number
W9127S22R0001
Issued by

About this file

This document contains a pricing schedule for a seed task order solicitation for electrical equipment rehabilitation and replacement. Work includes replacement of motor control centers, switchgear, transformers, panelboards, cables, controls, variable frequency drives, motors, programmable logic controllers, conduit, busway, essential AC/DC systems, and other power distribution equipment at 15kV class and below. Rehabilitation efforts may include manufacturing, fabrication, supply, installation, testing, certification, training, incidental design, and submittals. Logistics support includes determination and availability of spare parts. Rehabilitation may also include construction, repair, replacement, and upgrade of worn electrical system components. Task order work may involve removal of lead-based paint, asbestos, and hazardous materials, as well as painting, inspections, testing, and product marking. Detailed as-built documentation is required at completion. Task orders will be administered by USACE districts in Fort Worth, Vicksburg, Little Rock, Tulsa, St. Louis, and Kansas City for work at various locations.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Line Item

No. Description Quantity

Unit of

Measure Unit Price Total Price

0001 Motor Control Center Switchyard 1 Job $ $

0002 Motor Control Center Air Conditioning 1 Job $ $

0003 Motor Control Center Pump and Compressor 1 Job $ $

0004 Motor Control Center Spare 1 Job $ $

0005 Motor Control Center Unit 1 1 Job $ $

0006 Motor Control Center Unit 2 1 Job $ $

0007 Panelboard Lighting 1 Job $ $

0008 Motor Control Center Oil Pump 1 Job $ $

0009 480V Switchgear and Assemblies 1 Job $ $

0010 Generator Connections 1 Job $ $

0011 Electrical, Controls, Demolition & Chain Link Gates 1 Job $ $

Miscellaneous Items (Included in Base)

0012 Electrical Hire 10 Hours $ $

0013 Skilled Craftsman Hire 40 Hours $ $

0014 Welding Services Hire 15 Hours $ $

Transportation, Services, Equipment Rental, and Parts and Materials NTE Each 1.00$ 20,000.00$

0016 Inspect Embedded Conduit 6 Hours $ $

0017 Hydro Clean 100

Linear

Feet $ $

0018 Design Replacement of 125VDC System 1 Job $ $

0019 Remove and Replacement of 125VDC System 1 Job $ $

0020 Design & Replacement of the MG Distribution Center 1 Job $ $

Design and Replacement of Battery System and

Chargers 1 Job $ $

SEED TASK ORDER PRICING SCHEDULE

BASE ITEMS (Motor Control Center Replacement)

Proposed Price for Base Items

OPTIONAL ITEMS (Essential AC & DC Distribution System Design and Others)

0022 Submittal Preparation for Asbestos Abatement Work 1 Job $ $

Sampling: Mobilization & Demobilization for Asbestos

Bulk Sampling 2 Each $ $

Sampling: Collecting and Analyzing Asbestos Bulk

Samples 30 Each $ $

Mobilization & Demobilization for Asbestos

Abatement 3 Each $ $

0026 Abatement: Wiring 8,000 Pounds $ $

Disposal: Transportation of Asbestos-Containing

Materials Per Trip 1 Each $ $

0028 Disposal: Asbestos-Containing Materials 8,000 Pounds $ $

0029 Lead Paint Abatement 1 Job $ $

Submittal Preparation for Asbestos Abatement Work -

MCC 1 Job $ $

Sampling: Mobilization & Demobilization for Asbestos

Bulk Sampling - MCC 2 Each $ $

Sampling: Collecting and Analyzing Asbestos Bulk

Samples - MCC 30 Each $ $

Mobilization & Demobilization for Asbestos

Abatement - MCC 3 Each $ $

0034 Abatement: Wiring - MCC 8,000 Pounds $ $

Disposal: Transportation of Asbestos-Containing

Materials Per Trip - MCC 1 Each $ $

0036 Disposal: Asbestos-Containing Materials - MCC 8,000 Pounds $ $

0037 Lead Paint Abatement - MCC 1 Job $ $

Air Supply, Distribution, Ventilation, and Exhaust

Systems 1 Job $ $

**Should other Optional CLINs 0022-0029 or 0030-0037 become exercised, the period of performance will be extended 30 calendar days.

Proposed Price for Optional Items

TOTAL PROPOSED SEED TASK ORDER PRICE

*The period of performance equals 545 calendar days and is inclusive of Optional CLINs 0016 - 0021 and 0038 if exercised within 180 days of task order award.

File details come from the government source that posted it. Updated .