This is a technical specification for a roof replacement project at a U.S. Army Corps of Engineers facility. The specification outlines requirements for demolishing and disposing of the existing powerhouse and elevator penthouse roofs, and furnishing and installing new roofs along with guardrails at the site. It also describes requirements for monolith joint sealing, replacing damaged roof decking areas or panels, and optional asbestos abatement work. The specification provides detailed instructions on project scheduling, submittals, site restrictions, measurement, payment terms for various contract line items, safety protocols, and quality control procedures to be followed for the roof replacement work at the Little Goose Powerhouse and Elevator Penthouse located in Dayton, Washington.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LGA Powerhouse and Elevator Penthouse Roof Replacement W912EF21B0001
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 01 15.00 28 LIST OF DRAWINGS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 00 00.00 28 GENERAL REQUIREMENTS
01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS
01 14 00.10 28 PROJECT SITE RESTRICTIONS
01 14 00.90 28 INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY
(OPSEC)
01 22 00.00 28 MEASUREMENT AND PAYMENT
01 32 01.00 28 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.00 28 CONTRACTOR QUALITY CONTROL
01 51 00.00 28 TEMPORARY UTILITIES
01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS
01 57 20.00 28 ENVIRONMENTAL PROTECTION
01 78 00.00 28 CLOSEOUT SUBMITTALS
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 82 13.01 28 CLASS II ASBESTOS ABATEMENT
DI VI SI ON 03 - CONCRETE
03 60 00.01 28 CONCRETE CORE DRILLING, REPAIR OF CONCRETE SURFACES
03 62 16.00 28 CHEMICAL GROUTING
DI VI SI ON 05 - METALS
05 30 00.00 28 STEEL DECKS
05 50 13.00 28 MISCELLANEOUS METAL FABRICATIONS
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 01 50.10 28 REMOVAL AND DISPOSAL
07 18 00.00 28 TRAFFIC-BEARING POLYURETHANE WATERPROOF SYSTEM AND
POLYURETHANE JOINT SEALANT
07 22 00.00 28 ROOF INSULATION
07 53 23.00 28 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING
07 56 00.00 28 PMMA FLUID-APPLIED ROOFING
07 61 00.00 28 SHEET METAL FLASHING AND DRAIN INSERTS
07 72 00.00 28 ROOF ACCESSORIES
07 92 00.00 28 JOINT SEALANTS
DI VI SI ON 26 - ELECTRI CAL
26 05 00.00 28 GENERAL ELECTRICAL WORK
26 05 19.00 28 INSULATED WIRE AND CABLE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 01 15.00 28
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
1.2 CONTRACT DRAWINGS
1.2.1 Use Of Government Prepared Contract CAD Electronic Files
1.3 RESOURCE DRAWINGS (R)
-- End of Section Table of Contents --
DOCUMENT 00 01 15.00 28
SECTION 00 01 15.00 28
LIST OF DRAWINGS
PART 1 GENERAL
1.1 SUMMARY
This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."
1.2 CONTRACT DRAWINGS
Contract drawings are as follows:
SHEET
NUMBER
DESCRIPTION FILE NUMBER Revision Number
Date
GENERAL
G-001 COVER SHEET AND LOCATION MAPS LGG-1-0-1/464
G-002 INDEX SHEET LGG-1-0-1/465
G-003 GENERAL LEGEND LGG-1-0-1/466
G-101 SITE PLAN LGG-1-0-28/1
G-401 ENLARGED PLAN VIEW LGG-1-0-28/2
STRUCTURAL
S-101 POWERHOUSE AND ELEVATOR PENTHOUSE ROOF
GUARDRAIL PLANS
LGP-1-5-1/21
S-501 POWERHOUSE AND PENTHOUSE GUARDRAIL
DETAILS
LGP-1-5-1/22
S-502 GUARDRAIL CONNECTION DETAILS LGP-1-5-1/23
ARCHITECTURAL
AD101 ROOF DEMOLITION PLAN LGP-1-2-1/15
A-101 ROOF PLAN LGP-1-2-1/16
A-201 VERTICAL MONOLITH JOINT ELEVATIONS LGP-1-2-1/17
SHEET
NUMBER
DESCRIPTION FILE NUMBER Revision Number
Date
A-401 ENLARGED ROOF PLAN ERECTION PLAN LGP-1-2-1/18
A-402 ENLARGED FLOOR PLAN BAYS 1 AND 2 LGP-1-2-1/19
A-403 ENLARGED ROOF PLAN BAYS 3 AND 4 LGP-1-2-1/20
A-404 ENLARGED ROOF PLAN BAYS 5 AND 6 LGP-1-2-1/21
A-405 ENLARGED ROOF PLAN ELEVATOR PENTHOUSE LGP-1-2-1/22
A-406 ENLARGED ROOF PLAN INTAKE DECK SEALING LGP-1-2-1/23
A-501 ROOF DETAILS 1 LGP-1-2-1/24
A-502 ROOF DETAILS 2 LGP-1-2-1/25
A-503 ROOF DETAILS 3 LGP-1-2-1/26
A-504 ROOF DETAILS 4 LGP-1-2-1/27
A-505 MONOLITH JOINT SEALANT DETAILS 1 LGP-1-2-1/28
A-506 MONOLITH JOINT SEALANT DETAILS 2 LGP-1-2-1/29
A-507 SHEET METAL PROFILES DETAILS LGP-1-2-1/30
A-901 PHOTOS LGP-1-2-1/31
A-902 PHOTOS LGP-1-2-1/32
A-903 PHOTOS LGP-1-2-1/33
A-904 PHOTOS LGP-1-2-1/34
ELECTRICAL
E-101 ELECTRICAL POWERHOUSE AND PENTHOUSE
ROOF PLAN
LGP-1-6-1/10
E-301 ELECTRICAL SECTIONS LGP-1-6-1/11
E-401 ELECTRICAL PENTHOUSE ROOF PLAN LGP-1-6-1/12
E-402 ELECTRICAL PENTHOUSE ROOF DETAILS &
PLAN VIEW
LGP-1-6-1/13
E-403 CONDUIT ROUTING LGP-1-6-1/14
NUMBER
DESCRIPTION FILE NUMBER Revision Number
Date
E-404 ELECTRICAL GUARD RAIL GROUNDING DETAIL
BAYS 5 & 6
LGP-1-6-1/15
E-501 DETAILS LGP-1-6-1/16
1.2.1 Use Of Government Prepared Contract CAD Electronic Files
a. No Resource (R)("For Information Only") drawings are available on
CAD.
b. The Contractor assumes all risks associated in using electronic CAD drawings.
c. Electronic copies of CAD drawings are only available in Bentley DGN format.
d. The contract drawings shall govern if there are any discrepancies between the electronic copy and the contract drawing. The Contractor shall promptly notify the Contracting Officer of any discrepancies.
The Government will not be responsible to correct the electronic CAD drawing.
1.3 RESOURCE DRAWINGS (R)
These R drawings are included with the drawings for information only. The Government does not warrant the accuracy of the R drawings. The Government recommends that the Contractor verify the accuracy of R drawings.
Resource (R) drawings are as follows:
SHEET
NUMBER
DESCRIPTION FILE NUMBER Revision Number
Date
RESOURCE
R-001 POWERHOUSE REROOFING ROOFING SYSTEM DETAILS1
R-002 MISCELLANEOUS STRUCTURE ROOFING ROOF PLANS
AND DETAILS
LGB-1-2-1/1
R-003 MISCELLANEOUS STRUCTURE ROOFING ROOF
DETAILS
LGB-1-2-1/2
R-004 POWERHOUSE ARCHITECTURAL EXTERIOR
ELEVATIONS
LGP-1.1-2-0/1
R-005 POWERHOUSE UNITS 4-6 EMBEDDED PIPING ROOF
SECTIONS
LGP-1.9-3-8/55
NUMBER
DESCRIPTION FILE NUMBER Revision Number
Date
RESOURCE
R-006 POWERHOUSE UNITS 4-6 STRUCTURAL STEEL ROOF
FRAMING SHEET 1
LGP-1.9-5-1/1
R-007 POWERHOUSE UNITS 4-6 STRUCTURAL STEEL BUS
SUPPORT STRUCTURE SHEET 1
LGP-1.9-5-1/3
R-008 POWERHOUSE ROOF PLANS LGP-1-2-0/1
R-009 POWERHOUSE ROOFING DETAILS SHEET 1 LGP-1-2-0/2
R-010 POWERHOUSE ROOFING DETAILS SHEET 2 LGP-1-2-0/3
R-011 POWERHOUSE ROOFING DETAILS SHEET 3 LGP-1-2-0/4
R-012 POWERHOUSE ELEVATOR UPGRADE ARCHITECTURAL
DETAILS II ELEVATOR PENTHOUSE ROOF PLAN
LGP-1-2-5/2
R-013 POWERHOUSE GENERATOR BAYS - CONCRETE
OUTLINE TRANSVERSE SECTION BAYS 1, 2, & 3
LGP-1-4-2/1
R-014 POWERHOUSE ERECTION BAY - CONCRETE OUTLINE
ELEVATOR PENTHOUSE
LGP-1-4-3/39
R-015 POWERHOUSE MISCELLANEOUS METAL ROOF
FRAMING - SHEET 1
LGP-1-5-0/1
R-016 POWERHOUSE REROOFING LITTLE GOOSE
POWERHOUSE ROOF PLANS
LGP-1-13-1/1
R-017 POWERHOUSE REROOFING DETAILS LGP-1-13-1/2
R-018 POWERHOUSE UNITS 4-6 EMBEDDED CONDUIT &
GROUNDING SYSTEM MAIN UNIT SECTION
LGP-1.9-6-7A0/1
R-019 POWERHOUSE GROUNDING SYSTEM SCHEMATIC
DIAGRAM
LGP-1-6-7A0/1
R-020 PROPOSED ROOF DRAIN PIPING 28-19
R-021 PROPOSED ROOF DRAIN PIPING 28-19
R-022 POWERHOUSE UNITS 4-6 EMBEDDED PIPING ROOF
PLAN
LGP-1.9-3-8/54
R-023 POWERHOUSE MISCELLANEOUS METAL
MISCELLANEOUS DETAILS SHEET NO 1
LGP-1.9-5-0/1
NUMBER
DESCRIPTION FILE NUMBER Revision Number
Date
RESOURCE
R-024 POWERHOUSE UNITS 4-6 STRUCTURAL STEEL ROOF
FRAMING - SHEET 2
LGP-1.9-5-1/2
R-025 POWERHOUSE EMBEDDED PIPING MISC ROOF
SECTIONS
LGP-1-3-8/3
R-026 POWERHOUSE EMBEDDED PIPING GENERATOR BAYS
TRANSVERSE SECT & DETAILS
LGP-1-3-8/4
R-027 POWERHOUSE EMBEDDED PIPING GENERATOR BAY
ROOF & EL 558 BALCONY PLANS
LGP-1-3-8/5
R-028 POWERHOUSE EMBEDDED PIPING GENERATOR BAYS
SECTIONS & DETAILS
LGP-1-3-8/8
R-029 POWERHOUSE EMBEDDED PIPING ERECTION BAY
CROSS SECTION THRU SUMP
LGP-1-3-8/17
R-030 POWERHOUSE EMBEDDED PIPING ERECTION BAY
ROOF PLAN & TAILRACE DECK PLAN
LGP-1-3-8/21
R-031 ERECTION BAY - REINFORCEMENT INTAKE
PENTHOUSE - SHEET 1
LGP-1-4-3/75
R-032 ERECTION BAY - REINFORCEMENT INTAKE
PENTHOUSE - SHEET 2
LGP-1-4-3/76
R-033 ERECTION BAY - REINFORCEMENT INTAKE
PENTHOUSE - SHEET 3
LGP-1-4-3/77
R-034 GENERATOR BAYS - REINFORCEMENT INTAKE BASE
SLAB - PIER DOWELS
LGP-1-4-2/62
R-035 ERECTION BAY - REINFORCEMENT END WALL
ABOVE EL.558
LGP-1-4-3/104
R-036 ERECTION BAY - CONCRETE OUTLINE END WALL
ABOVE EL.558
LGP-1-4-3/15
R-037 ERECTION BAY - REINFORCEMENT DOWNSTREAM
WALL ABOVE EL. 558
LGP-1-4-3/105
R-038 ERECTION BAY - CONCRETE OUTLINE DOWNSTREAM
WALL ABOVE EL. 558
LGP-1-4-3/14
R-039 GENERATOR BAYS - REINFORCEMENT DOWNSTREAM
WALL ABOVE EL 542.0 BAYS 1,2,&3
LGP-1-4-2/137
NUMBER
DESCRIPTION FILE NUMBER Revision Number
Date
RESOURCE
R-040 GENERATOR BAYS - CONCRETE OUTLINE
DOWNSTREAM WALL ABOVE EL. 542
LGP-1-4-2/31
R-041 DOWNSTREAM WALL LGP-1.9-4-4/15
R-042 END WALL LGP-1.9-4-4/16
R-043 BUS SUPPORT STRUCTURE 5-450
R-044 BUS SUPPORT STRUCTURE 5-450
R-045 TRANSVERSE SECTION BAYS 1,2, & 3 LGP-1.9-0-0/3
R-046 ARCHITECTURAL EXTERIOR ELEVATIONS LGP-1.9-2-0/1
R-047 LOADING DIAGRAMS GENERATOR BAY LGP-8-0-0/21
R-048 LOADING DIAGRAMS ERECTION BAY LGP-8-0-0/22
R-049 ERECTION DWG POWERHOUSE E-75
R-050 STEEL ROOF, DECK AND SECTIONS 10-1
R-051 POWERHOUSE MISCELLANEOUS METAL ROOF
FRAMING - SHEET 2
LGP-1-5-0/2
-- End of Document --
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran Employment Information http://www.fedshirevets.gov/index.aspx
Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/
Department of Veterans Affairs-VOW to Hire Heroes Act http://benefits.va.gov/vow/
Army Wounded Warrior Program -http://wtc.army.mil/modules/employers/index.html
U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/
Guide to Hiring Veterans - Reference Material ht t ps: / / duckduckgo. com/ l / ?kh=- 1&uddg=ht t ps%3A%2F%2Fwww. ebenef i t s. va. gov%2Febenef i t s- por t al %2Fdownl oads%2Fvet er ans- hi r i ng- gui de- 2014. pdf
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 FIELD VERIFICATION OF SITE CONDITIONS
1.4 DEFINITIONS
1.5 REGULAR CLEANUP AND DEBRIS DISPOSAL
1.6 GOVERNMENT-FURNISHED PROPERTY
1.7 REGISTERED PROFESSIONAL ENGINEER (PE) REQUIREMENTS
1.8 CONTRACTOR TESTS FOR ASBESTOS
1.9 CONTRACTOR TESTS FOR RCRA METAL BASED PAINT
1.10 TOUCH-UP AND FIELD PAINTING
1.11 EQUIPMENT LIST
1.12 TESTING OF EQUIPMENT
1.13 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT
1.14 AIR PURITY CONTROL IN THE POWERHOUSE AND ELEVATOR PENTHOUSE
1.15 PROTECTION OF POWERHOUSE FLOORS
1.16 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.17 PRE-CONSTRUCTION ON-SITE INSPECTION
1.18 CONSTRUCTION PROGRESS PHOTOS
1.19 PROJECT SUPERINTENDENT
1.20 KEY PERSONNEL SUBSTITUTION
1.21 POST AWARD MEETINGS
1.21.1 Pre-Work Meeting
1.21.2 Pre-Construction Meeting
1.21.2.1 Minutes
1.21.2.2 Demobilizing And Remobilizing
1.21.2.3 RMS Orientation Meeting
1.22 WEEKLY PRODUCTION MEETINGS
1.22.1 Minutes
1.23 ADDITIONAL MEETINGS
1.24 PARTNERING
1.24.1 General
1.24.2 Partnering Meetings
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
ATTACHMENTS:
Weekly Meeting Agenda
Look-Ahead
SECTION 01 11 01.00 28
-- End of Section Table of Contents --
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)
ASCE 7-10 (2010; Errata 2011; Supp 1 2013) Minimum Design Loads for Buildings and Other Structures
SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC Paint 41 (2008) Moisture-Cured Polyurethane Primer or Intermediate Coat, Micaceous Iron Oxide Reinforced, Performance-Based
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
Comply with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only.
Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Equipment List ; I, C
Pre-Construction On-Site Inspection report ; I, C
Project Superintendent ; I, C
Air Purity Control Program ; G, C
Asbestos Test Results ; G, ECC
RCRA Metal Based Paint Test Results ; G, ECC
Registered Civil Professional Engineer (PE) ; G, ST
Property Management Plan ; G, C
SD-03 Product Data
Manufacturer's Product Data Sheet ; G, GE
SD-07 Certificates
Key Personnel Substitution ; G, C
1.3 FIELD VERIFICATION OF SITE CONDITIONS
Field verify all elevations, dimensions, and coordinates of existing features indicated on the contract drawings that affect new construction.
Any deviations shall be updated as per SECTION 01 78 00.00 28 , CLOSEOUT SUBMITTALS, paragraphs WORKING AS-BUILT DRAWINGS.
1.4 DEFINITIONS
a. Qualified Person.
As defined in EM 385-1-1 ; "DEFINITIONS", unless otherwise specified.
b. F.O.B.
An abbreviation for free on board, which means that a vendor or consignor will deliver goods on a railroad car, truck, vessel, or other conveyance without any expense to the purchaser or consignee.
1.5 REGULAR CLEANUP AND DEBRIS DISPOSAL
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all wastes and demolished materials shall become the property of the Contractor and shall be removed from the job site daily in accordance with Federal, State, and local regulations. The Contractor shall furnish waste containers. All small waste containers provided by the contractor shall be emptied daily, large bin containers shall be emptied when full or once a week.
1.6 GOVERNMENT-FURNISHED PROPERTY
Submit a Property Management Plan in accordance with FAR Clause 52.245-1 Government Property.
1.7 REGISTERED PROFESSIONAL ENGINEER (PE) REQUIREMENTS
a. A Registered Civil Professional Engineer (PE) is required to complete tasks specified in this contract. Submit Certification of current PE registration, and documentation of required work experience, as specified. Required PE related submittals must be submitted no later than the Pre-Work meeting. See paragraph "Pre-Work Meeting" in this SECTION for additional information. The PE must be a registered engineer in one or more of the following states:
Washington, Idaho, Oregon, Utah, and/or California.
b. The following work experience is required, and must be supported by submitted documentation:
1. Minimum of 10 years' experience in the investigation, design, replacement and repair of low-slope roofing systems.
2. Low-slope roofing system work experience.
3. Work experience with the following work elements for a minimum of two projects completed within the last ten years on low-sloping roofs:
i. Determination of steel metal deck and its supporting structure adequacy to support dead and live loads.
ii. Performance of wind uplift calculations on polyisocyanurate insulation and sheathing in accordance with
ASCE 7-10 .
iii. Steel metal deck repair.
c. The PE must remain certified for the duration of this contract.
Certifications scheduled to expire during the contract performance period must be renewed and submitted to the Contracting Officer prior to expiration.
1.8 CONTRACTOR TESTS FOR ASBESTOS
a. Contractor shall test for asbestos containing materials (ACM) in the Powerhouse Roofing system and submit Asbestos Test Results to the Contracting Officer (KO) a minimum of 30 calendar days prior to mobilizing to the Project site. Contractor work on Powerhouse Roof removal will not be allowed to proceed until Asbestos Test Results have been reviewed and accepted by the KO.
b. If ACM is present in the roofing materials, follow all abatement requirements of SECTION 02 82 13.01 28 CLASS II ASBESTOS ABATEMENT, and other applicable requirements in these Specifications.
c. Asbestos tests require the following:
1. Coordinate anticipated test day(s) a minimum of 15 calendar days prior to anticipated start.
2. Anticipate taking samples at 12 locations over a minimum of 2 Powerhouse roof bays. Locations for test samples will be identified by the KO.
3. Approximately 2 inch diameter sample size per sample. Include all roofing layers down to the roofing deck.
4. Patch all sample locations with a Government accepted patching system on the same day samples are taken.
1.9 CONTRACTOR TESTS FOR RCRA METAL BASED PAINT
a. Contractor shall test for RCRA Metal Based Paint on the interior Powerhouse Roof decking and submit RCRA Metal Based Paint Test Results to the KO. Contractor work affecting the interior Powerhouse roof decking paint system will not be allowed to proceed until test results have been reviewed and accepted by the KO.
b. If RCRA Metal Based Paint is present in the roof decking paint, follow all RCRA Metal Based Paint abatement requirements of SECTION 01 57 20.00 28 ENVIRONMENTAL PROTECTION and other applicable requirements in these Specifications.
c. The Powerhouse was built in 2 phases (Bays for Turbine Units 1-3, and Bays for Turbine Units 4-6). Test paint in 2 locations over Bays 1-3, in 2 locations over Bays 4-6.
1.10 TOUCH-UP AND FIELD PAINTING
a. Field and touch-up paint for metal surfaces to be painted, shall conform to Paint System 23-D, unless otherwise specified or approved.
Submit Manufacturer's Product Data Sheet prior to paint purchase.
b. Field paint the underside of new steel roof decking with an approved finish, and color, to match existing surrounding sections.
The Contractor shall be responsible to provide matching repair paint color(s), which shall be approved as an acceptable match by the Government.
c. For Paint System 23-D, apply the coating system in accordance with the manufacturer's written instructions. It must be a 3-coat system plus an additional stripe coat applied by brush to all edges, corners, welds, fasteners, and other surface irregularities. Allow the stripe coat to dry as recommended by the manufacturer, prior to the application of the first full coat. Procure all paint materials (including thinners and solvents) from the same coating manufacturer.
The individual paints comprising the system must have been tested and passed all requirements of the applicable SSPC Paint 41 standard.
Application shall be by spray, brush, or roller. Comply with the manufacturer's recommendations regarding mixing and thinning requirements, and pot life requirements, dry film thickness per coat and minimum and maximum dry time between coats. Do not use coating material that has thickened appreciably, or passed the manufacturer's recommended use-by date. Areas of bubbling noted upon curing of any individual coat must be removed by sanding or screening, the edges feathered, and the coat reapplied to the repaired areas before a subsequent coat is applied.
1.11 EQUIPMENT LIST
Furnish a complete list of all equipment to be used on the Project 30 days prior to commencement of on-site work. Submit a revised list in the event of change of equipment. Lists shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial list and the revised lists shall indicate dates equipment is assigned to or removed from the Project and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
1.12 TESTING OF EQUIPMENT
Before any machinery or mechanized equipment is put to use on the job, it shall be inspected and tested by a qualified person and determined to be in safe operating condition. Cranes or derricks shall be tested by the Contractor or a qualified testing agency in accordance with EM 385-1-1 .
Equipment shall be large enough to safely handle proposed picks or tasks without exceeding the crane rating established by these tests.
1.13 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT
Unless otherwise specified in other sections of the specifications, all existing equipment removed and not reinstalled shall become the property of the Contractor, removed from the Project site, and disposed of in a legal manner. Materials that cannot be removed daily may be temporarily stored on-site at an approved area. Salvaged materials shall not be sold on the project site.
1.14 AIR PURITY CONTROL IN THE POWERHOUSE AND ELEVATOR PENTHOUSE
a. Take all necessary precautions to maximize the control, and prevention, of all dust and fumes (from products and all construction operations) created by operations under this contract from escaping into the powerhouse and elevator penthouse. To the maximum extent possible, all dust and dirt shall be removed by vacuum cleaning. A minimum of 30 calendar days prior to commencement of work at the Project, submit in writing, a proposed Air Purity Control Program .
Air Purity Control Program shall include, but not be limited to, the following:
(1) Adequate isolation and ventilation protection of roofing removal in installation operations.
(2) Provision to protect mechanical systems, open vents, exhaust ducts, and air intakes from dust and fume entry.
(3) Adequate isolation and ventilation of air arcing, welding, burning, and grinding operations.
(4) Provision of exhaust ducts that shall discharge outside the powerhouse structure where mechanical ventilation is used.
(5) Controlled operation of power driven tools.
(6) Furnishing and removing of oiled sawdust or other dust preventatives in areas that cannot be properly rendered free from excessive dusting by vacuum cleaning or other methods.
(7) Vacuum cleaning of spaces within the work areas where dust accumulates.
(8) Air-, electrical-, or battery-driven equipment may be used inside the powerhouse.
(9) Internal-combustion engine powered equipment will not be permitted to operate inside the powerhouse unless exhausted to the exterior except for short periods of time (not to exceed 15 minutes in a 2 hour window) to unload materials and equipment.
b. The shutting down or shutting off of ventilation and air supply fans must be coordinated with the KO and the Project personnel a minimum of 14 calendar days prior to sealing to ensure fan motors and other power-operated equipment associated with the grills or louvers are properly tagged out.
c. All protection to be left on the grills or louvers overnight, or over a weekend, requires KO approval a minimum of 5 calendar days in advance. If approval is granted, Project personnel will ensure the ventilation or air supply fan will not accidentally be turned on with the protection in place.
d. If the fresh air intakes are covered for a period longer than one work day, make provisions to remove the covers to allow fresh air for powerhouse and elevator penthouse ventilation each night. Coordinate extended covering of the fresh air intakes with the KO.
e. Depending upon the Contractor's plant, equipment, and methods of operation, additional provisions for satisfactory air purity control will be required and shall be included in the proposed Air Purity Control Program.
1.15 PROTECTION OF POWERHOUSE FLOORS
a. Care shall be taken to prevent damage to all floors and curbs within the Powerhouse. If Contractor moving and/or lifting equipment will be operated inside the Powerhouse, floor protection, as specified below, shall be in place prior to use of equipment.
1. Protection shall include a continuous layer of oil-impervious kraft paper over the existing floor surface with joints of the kraft paper joined with an appropriate tape. In addition, tongue and groove 3/4-inch-thick Oriented Strand Board (OSB) plywood shall be installed over the craft paper at all work and storage areas.
2. Plywood joints shall be fastened to ensure edges of plywood sheets are, and remain, flush with each other and do not pose a tripping hazard during execution of this work. Minimum nominal 2"x4" wood shall be installed along existing curb features within the contractor work areas and along perimeters of the work areas.
Wood used for curb protection shall be secured in place without anchoring into the existing floors or curbs.
3. Pipe trenches shall remain accessible even if covered. All designations relating to fire protection equipment that get covered shall be marked on the temporary floor covering. Provide additional blocking and wood supports when required. Also suitably protect other surfaces of work.
4. Work in the powerhouse shall not start until floor and curb protection is in place.
b. Damage to floors or curbs caused by the Contractor's operations shall be repaired at no additional cost to Government. Repairs shall match the surrounding area in material type, color, texture, and surface finish and are subject to approval.
1.16 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Reference FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984).
1.17 PRE-CONSTRUCTION ON-SITE INSPECTION
Prepare a Pre-Construction On-Site Inspection report of existing conditions, prior to start of on-site work, with the Contracting Officer (KO). Document existing site conditions prior to Construction by digital photographs, and/or videos along with descriptive narrative report to the KO within five (5) days after completion.
1.18 CONSTRUCTION PROGRESS PHOTOS
During on site construction activities record construction progress with weekly progress photographs. Photographs provided are for unrestricted use by the Government.
a. Photos shall be submitted at the end of each work week.
b. Furnish digital photographs, Utilize JPEG file format for all photograph and image files.
c. Provide full-color photos with photo resolution of not less than 4 megapixels and not more than 12 megapixels. Photos shall show the sequence and progress of work.
d. Take a minimum of 20 digital photographs each week throughout the entire project.
e. Submit digital photographs weekly for use at the Weekly Production Meeting. See paragraph WEEKLY PRODUCTION MEETINGS for additional information.
Ensure that the photographs are digitally dated. Log shall be furnished for each photograph that records the following information:
a. Photograph number (the specific format should be tied to the filename of the electronic photograph).
b. Date the photograph was taken.
c. A brief description of the location, what the photograph depicts, and the orientation of the view.
1.19 PROJECT SUPERINTENDENT
The Contractor's Project Superintendent shall be on the worksite during performance of work on this contract. The Project Superintendent is required on the worksite, at all times work is being performed, until work on this contract is completed and accepted. Assign a competent superintendent as per FAR Clause 52.236-6 "Superintendence by the Contractor". Submit Superintendent name and contact information prior to start of on-site construction. The Project Superintendent may also be the Installation Supervisor as long as the Project Superintendent also meets the qualifications for the Installation Supervisor.
1.20 KEY PERSONNEL SUBSTITUTION
If the Contractor plans on replacing any Key personnel (Project Superintendent, CQC System Manager, or CQC staff Members) they must have the approval of the Contracting Officer. Personnel shall possess the qualifications that meet or exceed those stated in this contract for the position of the individual they are replacing. Submit qualifications of new personnel at least 15 calendar days in advance of date of replacement.
1.21 POST AWARD MEETINGS
1.21.1 Pre-Work Meeting
Within Thirty (30) calendar days after receipt of Notice to Proceed, attend a Pre-Work Meeting. Senior Level members of the Contractor's staff involved with this contract shall participate in this meeting to discuss the overall contract requirements. The Government will lead this meeting and take the meeting minutes.
1.21.2 Pre-Construction Meeting
a. Coordinate with the Contracting Officer and establish the date of the Pre-Construction Meeting. The meeting will be held at the Project site at least one (1) week prior to mobilizing to the job site. If COVID 19 restrictions preclude meeting at the Project site, the meeting will be held by teleconference. Lead the Pre-Construction Meeting discussing the Contractor's plan on executing the work at the project site, schedule, required clearances and timeframe for them, and plan for implementing safety and quality control. The Government will have key members from the Project staff to discuss environmental and clearance issues. Key members of the contractor staff shall attend this meeting including the Quality Control (QC) System Manager, Site Safety and Health Officer (SSHO) and any other members determined by the Government to be required.
b. Topics for discussion will include the following:
1. Schedule for de-energizing the Electrical Bus.
2. Schedule for Government Doble Testing.
3. Coordination requirements and restrictions for Contractor work near the Coupling Capacitor Voltage Transformers (CCVTs).
c. See SECTION 01 14 00.10 28 PROJECT SITE RESTRICTIONS, paragraph SITE CONDITIONS AND OPERATIONAL RESTRICTIONS for additional information on the above topics.
1.21.2.1 Minutes
Contractor is responsible for taking the meeting minutes and shall send them electronically within 48 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.21.2.2 Demobilizing And Remobilizing
Anytime the Contractor demobilizes from the site and remobilizes at a later date, another Pre-Construction Meeting shall be held and shall follow the requirements listed above.
1.21.2.3 RMS Orientation Meeting
a. An RMS (Resident Management System) Orientation Meeting will be held within Fifteen (15) calendar days after receipt of Notice to
Proceed. See SECTION 01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) for additional information. Orientation meeting will be at District Headquarters, and may occur in conjunction with, but not at the same time as, the Pre-Work meeting. Coordinate meeting date and time with the Contracting Officer a minimum of 7 calendar days prior to the meeting.
b. At a minimum, the Contractor's RMS-CM Administrator and QC system manager shall attend the RMS Orientation meeting. A Government Representative will lead the orientation. Anticipate the following at the meeting:
1. Allow for a maximum 4 hour duration.
2. Cover the following topics, at a minimum, in RMS Contractor Mode (CM):
i. Contractor use of RMS (CM) system.
ii. Contractor Data.
iii. Quality Control Reports.
iv. Submittals.
v. RFIs.
vi. Payment.
3. Receive a follow-up handout/guide for reference on the above items.
c. Contractor employees shall bring a computer with Wi-Fi capability (to gain access to the Internet), with RMS pre-loaded.
d. The RMS Orientation Meeting is required for Contractors with no prior RMS experience. The RMS Orientation Meeting, is optional, but may be requested, for all other Contractors.
1.22 WEEKLY PRODUCTION MEETINGS
During all fabrication and onsite construction work, hold a weekly production meeting to brief the Government on the status of the project.
a. Use the attached "Weekly Meeting Agenda" and discuss all elements of this agenda.
b. Provide a three (3) week 'look ahead'. The "Look-Ahead" shall be generated in P6 and then copied into Excel for more detail (see look-ahead examples at the end of this section).
1. Describe all planned construction activities, on-site and off-site over the next three (3) weeks.
2. ENSURE these activities align to the overall construction SCHEDULE submitted under SECTION 01 32 01.00 28 PROJECT SCHEDULE.
3. RECORD any changes to the Project Schedule AND INCLUDE IN the next scheduled update.
c. Key members of the Contractor's staff including the Quality Control System Manager and the SITE SAFETY AND HEALTH OFFICER shall attend.
d. The Quality Control System Manager shall discuss all QC aspects outlined in SECTION 01 45 04.00 28 CONTRACTOR QUALITY CONTROL.
e. The Government reserves the right to require any person from the Contractor's staff such as the Project Manager, Engineer, Scheduler or Key Subcontractor Personnel to attend the meeting.
f. Submit each meeting agenda, along with Construction Progress Photos, to the COR 24 hours prior to the meeting. See paragraph CONSTRUCTION PROGRESS PHOTOS for additional information.
1.22.1 Minutes
The Contractor shall be responsible for taking the meeting minutes and shall send them electronically within 24 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer.
1.23 ADDITIONAL MEETINGS
Record the minutes of all meetings, including all conference calls, that occur between the Contractor and Government. Send minutes electronically within 24 hours of the meeting to the Contracting Officer for concurrence.
E-mail subject line shall include project name and meeting topic.
1.24 PARTNERING
1.24.1 General
The Government intends to encourage the foundation of a cohesive partnership with the Contractor and its subcontractors by informally partnering this contract. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objectives are effective and efficient contract performance with the intent to achieve a safe completion of the work - within budget, on schedule, and in accordance with plans and specifications. This partnership would be bilateral in makeup and participation will be totally voluntary. If Partnering is pursued, meetings would be held as identified in the following paragraph.
1.24.2 Partnering Meetings
Within 30 calendar days of receipt of Notice to Proceed, the initial partnering meeting will be scheduled if the meeting is requested by the Contractor. The Contractor's key personnel will attend a face-to-face partnering meeting (typically one day in duration) together with key Government personnel, to discuss project goals and communication.
Follow-up meetings will be held periodically, as required, throughout the duration of the contract, as agreed to by the Contractor and the Government.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --
Weekly Meeting agenda template
Schedule - Work scheduled over the next week Three week look ahead Overall Schedule Review
Submittals Review- Submittal Register Submittals approved by QC Outstanding Submittals RFI’s Letters
Coordination - Clearances required over the next week, include the following:
A description of the work to be performed under the Clearance.
Determine the correct energy isolation points needed to perform the work safely.
Physical barriers, protective grounds, piping blanks, or bulkheads that shall be used, including locations.
Determine the procedure and method of testing for stored energy if applicable.
The date and time the Clearance shall be required.
The estimated length of time the system or equipment shall be out of service and the time to return the system or equipment to service in an emergency.
Coordination issues
Safety- Review of AHA’s for ongoing work Pending AHA’s
Required for new work Status of Gov’t approval
Safety issues
QC -
Preparatory meetings Held over last week- status of meeting minutes
Required over the next week Initial meetings over the next week Follow up over the next week Rework list Review Deficiency tracking log
Activity ID Activity Name Original Duration
Remaining Duration
Start Finish Physical
C l t
Total Float Critical
TotalTotal 32d 32d 26-Feb-15 11-Apr-15 194d
3 Week Look A3 Week Look Ahead 32d 32d 26-Feb-15 11-Apr-15 194d
Preparatory & AdPreparatory & Admin 5d 5d 26-Feb-15 02-Mar-15 311d 0001 Dive Operations 5d 5d 26-Feb-15 02-Mar-15 0% 311d
PreconstructionPreconstruction 20d 20d 26-Feb-15 25-Mar-15 167d Design & SubmitDesign & Submittals 20d 20d 26-Feb-15 25-Mar-15 162d
0002 Tests,Insp, and Verifications 20d 20d 26-Feb-15 25-Mar-15 0% 162d ProcurementProcurement 0d 0d 0d Fabrication & MaFabrication & Machining 0d 0d 0d Pre-Work CoordiPre-Work Coordination 0d 0d 0d
Field WorkField Work 16d 16d 26-Feb-15 19-Mar-15 210d Unit AUnit A 0d 0d 0d Unit BUnit B 0d 0d 0d Unit CUnit C 16d 16d 26-Feb-15 19-Mar-15 210d
Unit C Pre-RehUnit C Pre-Rehab Inspections 0d 0d 0d Unit C Box #1 Unit C Box #1 Removal 13d 13d 26-Feb-15 16-Mar-15 205d
0006 Remove Box 1 Screen 2d 2d 26-Feb-15 27-Feb-15 0% 93d 0007 Remove Box 2 Screen 2d 2d 02-Mar-15 03-Mar-15 0% 93d 0008 Remove Box 3 Screen 2d 2d 04-Mar-15 05-Mar-15 0% 93d 0009 Screen Slot 1 Measurement 1d 1d 06-Mar-15 06-Mar-15 0% 205d 0010 Install shafts 21-24 4d 4d 09-Mar-15 12-Mar-15 0% 205d 0011 Pressure Wash Slot 2 1d 1d 13-Mar-15 13-Mar-15 0% 205d 0012 Pressure Wash Slot 3 1d 1d 16-Mar-15 16-Mar-15 0% 205d
Unit C Box #2 Unit C Box #2 Removal 10d 10d 06-Mar-15 19-Mar-15 100d 0013 Lower Lifting Beam & Attach 2d 2d 06-Mar-15 09-Mar-15 0% 93d 0014 Raise Screen to Deck & Support 1d 1d 10-Mar-15 10-Mar-15 0% 93d 0015 Fuel Removal 1d 1d 11-Mar-15 11-Mar-15 0% 93d 0016 Fuel Screen Inspect & Measure 1d 1d 12-Mar-15 12-Mar-15 0% 93d 0017 Separate Widget from Screen 1d 1d 13-Mar-15 13-Mar-15 0% 93d 0018 Haul Screen to Laydown 1d 1d 16-Mar-15 16-Mar-15 0% 103d 0019 Remove Box 4 Screen 2d 2d 16-Mar-15 17-Mar-15 0% 93d 0020 Remove Box 5 Screen 2d 2d 18-Mar-15 19-Mar-15 0% 93d
Unit C Box #3 Unit C Box #3 Removal 0d 0d 0d Unit C Fuel ScUnit C Fuel Screen Field Modifications 14d 14d 26-Feb-15 17-Mar-15 103d
0039 Position Screen 1 on Slab 1d 1d 26-Feb-15 26-Feb-15 0% 116d 0040 Position Screen 2 on Slab 1d 1d 17-Mar-15 17-Mar-15 0% 103d
Unit C Wagner Unit C Wagner Horn Plugs Installation 0d 0d 0d Unit C Fish ScUnit C Fish Screens Installatin 0d 0d 0d Unit C Fish ScUnit C Fish Screen Slot Closure 0d 0d 0d
Unit DUnit D 0d 0d 0d Unit D Pre-RehUnit D Pre-Rehab Inspections 0d 0d 0d Unit D Screen Unit D Screen #1 Removal 0d 0d 0d
A S O N D J F M A M J J A S O N D J F 2015 2016
11-Apr-15, Total
11-Apr-15, 3 Week Look Ah
02-Mar-15, Preparatory & Admi Dive Operations
25-Mar-15, Preconstruction 25-Mar-15, Design & Submitt Tests,Insp, and Verifications
19-Mar-15, Field Work
19-Mar-15, Unit C
16-Mar-15, Unit C Box #1 Rem Remove Box 1 Screen Remove Box 2 Screen Remove Box 3 Screen Screen Slot 1 Measurement Install shafts 21-24 Pressure Wash Slot 2 Pressure Wash Slot 3 19-Mar-15, Unit C Box #2 Rem
Lower Lifting Beam & Attach Raise Screen to Deck & Suppo Fuel Removal Fuel Screen Inspect & Measur Separate Widget from Screen Haul Screen to Laydown Remove Box 4 Screen Remove Box 5 Screen
17-Mar-15, Unit C Fuel Scree Position Screen 1 on Slab
Position Screen 2 on Slab
3 Week Look Ahead Three Week Look Ahead 02-Mar-15 10:02
Actual Work Remaining Work
Critical Remaining Work Milestone
Summary Page 1 of 3 TASK filter: 3 Week Look Ahead.
© Oracle Corporation
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 POWERHOUSE ROOF DEMOLITION RESTRICTION
1.4 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS
1.4.1 Electrical Bus Restrictions: Bays 2 through 6
1.4.2 Coupling Capacitor Voltage Transformers (CCVT) Restrictions
1.4.3 Government Doble Testing
1.4.4 Elevator Penthouse Roof Guardrail Installation
1.5 INTERIOR POWERHOUSE PROTECTION BARRIER DURING ROOFING WORK
1.5.1 General
1.5.2 Protection Barrier Requirements
1.6 USE OF POWERHOUSE BRIDGE CRANE
1.6.1 General
1.6.2 Crane Operators
1.6.3 Use of the Cranes
1.6.4 Riggers
1.6.5 Bridge Crane Work Platforms
1.7 PROJECT SECURITY
1.7.1 Contractor Vehicle Access
1.7.2 Identification of Employees
1.8 DELIVERY OF EQUIPMENT
1.9 FACILITY OCCUPANCY CLOSURE
1.10 WORK SCHEDULES
1.10.1 Contractor's Work Schedule
1.10.2 Government's Work Schedule
1.11 USE OF WALLA WALLA DISTRICT PARKS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
ATTACHMENTS:
Security Badge Form
-- End of Section Table of Contents --
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE C2 (2020) National Electrical Safety Code
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Health Requirements Manual
Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. A designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Security Badge Form ; G, C
Qualifications ; G, C
Bridge Crane Work Platforms ; G, C
Interior Powerhouse Protection Plan ; G, C
1.3 POWERHOUSE ROOF DEMOLITION RESTRICTION
a. A maximum of one roof bay may be reroofed at a time, unless approved otherwise, in writing, by the Contracting Officer. Written approval must be received by the Contractor prior to beginning work on ANY additional roof area.
b. Roofing of any bay where demolition has begun shall be completed, as shown and specified, prior to beginning demolition on another roofing area, unless approved otherwise by the Contracting Officer.
Ensure all exposed roofing area (where demolition has begun, but installation of new roof is not complete) is protected from water intrusion at the end of each work day, or when precipitation is imminent.
1.4 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS
1.4.1 Electrical Bus Restrictions: Bays 2 through 6
a. The Powerhouse roof over Bays 2 through 6 has a high voltage electrical bus that is too low to allow safe roof access while energized. All Contractor work in the area, while the bus is energized, must maintain the minimum required approach distance. For minimum require approach distance, reference EM 385-1-1 and IEEE C2 .
If there's a conflict between requirements, the Contractor shall follow the more conservative requirement. See Contract Clause 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK for anticipated Contractor access date to these areas.
b. For approximately 5 calendar days following de-energizing the bus, Contractor access to Bays 2 through 6 will be limited to the following:
1. That required for guardrail installation over all Bays.
2. Contractor access to Bays 5 and 6. See Contract Clause 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK for roof work restrictions over Bays 5 and 6.
c. At the end of the approximate 5 calendar day period, Contractor shall have access to the entire Powerhouse roof, subject to identified restrictions. Actual access dates and time period for limited Contractor activity will be provided at the Pre-Construction Meeting.
See SECTION 01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS, paragraph "Pre-Construction Meeting" for additional information.
1.4.2 Coupling Capacitor Voltage Transformers (CCVT) Restrictions
Three high voltage CCVTs are located over Bays 2 and 3. CCVTs will typically be energized during the entire Contract period. Restrictions apply to work within 25 feet, in plan view, of the CCVTs. Coordinate work in these areas with the Contracting Officer a minimum of 14 calendar days prior to anticipate start. See Resource Drawing R-004, POWERHOUSE ARCHITECTURAL EXTERIOR ELEVATIONS for additional information on approximate CCVT locations.
1.4.3 Government Doble Testing
Project personnel are scheduled to conduct Doble testing on the CCVTs during the first week of August each year. Anticipate Government employees on the intake and tailrace decks, in the vicinity or Contractor work access areas, and on the Powerhouse roof during this time. Actual Doble test dates for a given year, will be provided at the corresponding Pre-Construction Meeting. See SECTION 01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS, paragraph "Pre-Construction Meeting" for additional information.
1.4.4 Elevator Penthouse Roof Guardrail Installation
Contractor shall install guardrails on the Elevator Penthouse Roof prior to any roof demolition/installation work in the area. The Government will remove the electrical equipment from the roof prior to the Contractor proceeding with roofing work. Anticipate 1 or more antenna mounts to remain in place on the Elevator Penthouse Roof. Coordinate anticipated guardrail installation dates for the Elevator Penthouse Roof a minimum of 21 calendar days prior to anticipated start of guardrail installation.
The Government will re-install the electrical equipment after Penthouse roof installation is completed. Reference Contracting clause 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK for additional information.
1.5 INTERIOR POWERHOUSE PROTECTION BARRIER DURING ROOFING WORK
1.5.1 General
a. Interior Powerhouse Protection Barrier shall be in place prior to beginning work on the Powerhouse roof (including Erection Bay area).
Design protection barrier to protect all areas of the Powerhouse during all aspects of roofing work. Prevent the following, at a minimum, from passing below the barrier:
1. Metal shavings, dust, dirt, and all similar items.
2. All water, liquid, etc..
3. All tools or other Contractor items.
b. The barrier shall include a waterproof membrane, and be designed to protect all items and equipment inside the powerhouse during overhead work. Due to the amount of electrical equipment in the Powerhouse, the likely presence of asbestos in the existing roof system, and Project personnel working in the Powerhouse during roof replacement, it is imperative that the barrier provides protection from all outside infiltrations during the roof replacement process.
c. If the Interior Powerhouse Protection Barrier does not provide adequate protection, as specified, the Contractor shall immediately stop overhead roofing work and modify the Protection Barrier to meet specifications, at no additional cost to the Government.
d. While the protection barrier may be installed in sections, roofing work over any Powerhouse and Erection Bay areas will not be allowed to proceed without an installed protection barrier that completely protects the Powerhouse from the work overhead. The protection barrier shall be in place during all overhead roofing demolition and installation, and once installed shall not be removed until installation of the new roofing system protected by the barrier, is complete.
e. Submit an Interior Powerhouse Protection Plan a minimum of 60 calendar days prior to anticipated start of earliest plan activity.
Plan shall include, but not be limited to, the following:
1. Schedule detailing installation and removal of all phases of the Interior Powerhouse Protection Barrier.
2. Materials to be used for membrane, anchorage, and all related items, as well as design of waterproof seams.
3. Method of anchoring protection barrier, and repair of surfaces upon removal of anchors.
4. Design of any work platforms to be used during installation and removal of Interior Powerhouse Protection Barrier, including anchorage systems of platforms.
f. The Contractor shall maintain the protection barrier(s) and perform repairs or replacement, as needed. This includes repairing incidents of protection barrier damage or failure within 4-hours following notification by the Contracting Officer. If failure or needed repairs pose a life/safety concern or impact operation of the Powerhouse Bridge Crane repairs are required within 1 hour of notification. The Contractor shall be responsible for all damage caused to Government Property and/or personnel due to damage to and/or failure of the protection barrier.
1.5.2 Protection Barrier Requirements
a. Waterproof Membrane and Anchorage Requirements:
1. Membrane shall extend the entire width of the bay (from east wall to west wall) and extend the length of half a bay to the north and half a bay to the south beyond the bay over which the roof work is taking place, at a minimum. For example, if work is taking place above Bay 2, then the protective membrane must extend half of the distance north into Bay 3 and half of the distance south into Bay 1. For end bays, the waterproof membrane shall extend completely to the adjacent end wall.
2. Provide a continuous waterproof barrier with seams overlapped no less than 24 inches and adequately sealed with waterproof means.
3. Transparent, permitting the maximum amount of light to pass through.
4. Supported and/or hung by wire cables, or other accepted method, attached to overhead beams and/or anchored into the walls of the interior Powerhouse. Only use of Government accepted anchorage systems will be allowed. If concrete anchors are used, image concrete by GPR to avoid concrete embedment damage caused by anchor hole drilling. See SECTION 05 50 13.00 28 MISCELLANEOUS METAL FABRICATIONS, paragraph CONCRETE IMAGING REPORT-ANCHORS for additional information.
5. NOTE: Anchorage and attachment system shall NOT attach to or penetrate roofing deck. Anchorage and attachment system shall NOT penetrate or damage overhead beams and other items, including paint systems. Assume existing Powerhouse Roof framing and related items are coated with RCRA Metal Based paint. See SECTION 01 57 20.00 28 ENVIRONMENTAL PROTECTION for additional information.
b. Location Requirements:
1. Install the protection barrier above the bridge crane and below the overhead lights.
2.…