A.01.13 USCG SFO Eastern Shore Specs. Final March 2021.pdf

PDF 4 MB Posted

Attached to
USCG Sector Field Office Eastern Shore Maintenance Dredging Project Federal contract opportunity
Solicitation number
W9123621B5010
Issued by
Department of the Army Corps of Engineers Engineering District Norfolk

About this file

This federal contract opportunity solicitation seeks maintenance dredging and earthwork upgrade services for the U.S. Coast Guard Sector Field Office Eastern Shore in Chincoteague, Virginia. The solicitation involves dredging approximately 11,000 cubic yards of material from the Coast Guard station's boat basin, access channel, and mooring area to provide operational depths of -10 feet with 2 feet of allowable overdepth. The work also includes refurbishing portions of the confined upland placement site and repairing a spillbox. Services will be performed with a mechanical bucket dredge and material will be transported via leakproof dump trucks to the designated upland area adjacent to the Curtis Merritt Harbor complex approximately 2 miles away. The agency is the Department of the Army Corps of Engineers Norfolk District. No response date or award date is included in the solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to USCG Sector Field Office Eastern Shore Maintenance Dredging Project, newest first.
File Type Posted
A.01.25 ABSTRACT OF OFFERORS_Page 2.pdf PDF
A.01.25 ABSTRACT OF OFFERORS_Page 3.pdf PDF
B.01.02 ABSTRACT OF OFFERORS Page 1.pdf PDF
A.01.04 Released Solicitation Amendment 0002_21B5010.pdf PDF
A.01.25 USCG SFO Eastern Shore facility layout.pdf PDF
A.01.04 Released Solicitation Amendment 0001_21B5010.pdf PDF
A.01.13 USCG SFO Eastern Shore Plan Drawings Final March 2021.pdf PDF
D.01.04 Released Solicitation_W9123621B5010.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2021 Chincoteague USCG Base Dredging 2021CHINCOUSCG

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 15 LIST OF DRAWINGS

DIVISION 01 - GENERAL REQUIREMENTS

01 14 00 SPECIAL WORK CONDITIONS

01 22 00 MEASUREMENT AND PAYMENT

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 29 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 CONTRACTOR QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 20 ENVIRONMENTAL PROTECTION

01 57 23 TEMPORARY STORMWATER POLLUTION CONTROL

01 57 30 ENVIRONMENTAL PERMIT WORK REQUIREMENTS

01 78 00 UPLAND PLACEMENT SITE AS-BUILT DRAWINGS

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 11 00 CLEARING AND GRUBBING

31 32 11 SOIL SURFACE EROSION CONTROL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 92 19 SEEDING

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 20 23 DREDGING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

SECTION 00 01 15

LIST OF DRAWINGS

06/07

PART 1 GENERAL

1.1 INDEX OF CONTRACT DRAWINGS

PART 2 PRODUCTS (This Division not used)

PART 3 EXECUTION (This Division not used)

-- End of Section Table of Contents --

DOCUMENT 00 01 15 Page 1

SECTION 00 01 15

LIST OF DRAWINGS

06/07

PART 1 GENERAL

1.1 INDEX OF CONTRACT DRAWINGS

The list of drawings below are included as a part to this Solicitation.

Norfolk District Sheet No. Sheet Title

1 COVER SHEET

2 LOCATION MAP

3 LEGEND AND GENERAL NOTES

4 PLANS FOR DREDGING

5 EXISTING CONDITIONS

6 BORING LOCATIONS

7 SOIL DESCRIPTION SHEETS

8 SOIL DESCRIPTION SHEETS (CONT'D)

9 SOIL DESCRIPTION SHEETS (CONT'D)

10 SOIL DESCRIPTION SHEETS (CONT'D)

11 LIMITS OF CONSTRUCTION

12 DIKE LAYOUT PLAN

13 BORROW AREA LAYOUT PLAN

14 GRADING PLAN

15 EROSION CONTROL PLAN

16 TYPICAL DIKE CROSS-SECTIONS

17 EROSION CONTROL DETAILS

18 SPILLBOX DETAIL

19 SPILLBOX DETAIL (CONT'D)

20 SPILLBOX DETAIL (CONT'D)

21 SPILLBOX DETAIL (CONT'D)

22 SPILLBOX PHOTOS

PART 2 PRODUCTS (This Division not used)

PART 3 EXECUTION (This Division not used)

-- End of Section --

DOCUMENT 00 01 15 Page 2

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 00

SPECIAL WORK CONDITIONS

07/07

PART 1 GENERAL

1.1 SUBMITTALS

1.2 REFERENCES

1.3 CONTRACTOR WORK REQUIREMENTS

1.3.1 Security and Public Safety of Work Areas

1.3.2 Noise Control and Abatement

1.3.3 Coordination with Other Contractors

1.4 PERSONNEL RESTRICTIONS

1.5 TRANSPORTATION FACILITIES

1.5.1 Use of Roads

1.5.2 Cleated Vehicles

1.6 PHYSICAL DATA

1.6.1 Physical Conditions Information

1.6.2 Obstruction of Channel

1.6.3 Responsibility

1.6.4 Condition of Dredging Areas

1.7 WORK RESTRICTIONS

1.7.1 Channel Traffic

1.7.2 Interference with Coast Guard, Curtis Merritt Harbor and

Placement Area and Town of Chincoteague Operations

1.7.3 Oyster Grounds

1.7.4 Holidays

1.8 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

1.8.1 Costs

1.8.2 Rentals

1.8.3 Data

1.9 SPECIAL COAST GUARD REQUIREMENTS

1.9.1 Site Visit

1.9.2 Local Notice To Mariners

1.9.3 Relocation of Navigation Aids

1.9.4 Use of Coast Guard Navigation Aid Structures

1.10 ENVIRONMENTAL LITIGATION

1.10.1 Litigation

1.11 HISTORICAL AND ARCHAEOLOGICAL FINDS

1.12 PROFIT

1.12.1 Weighted Guidelines

1.12.2 Values

1.12.2.1 Degree of Risk

1.12.2.2 Relative Difficulty of Work

1.12.2.3 Size of Job

1.12.2.4 Periods of Performance

1.12.2.5 Contractor's Investment

1.12.2.6 Assistance by Government

1.12.2.7 Subcontracting

1.13 PARTNERING

SECTION 01 14 00 Page 1

1.14 SUBCONTRACTS AND WORK COORDINATION

1.15 ACCOMMODATIONS ABOARD DREDGE FOR CONSTRUCTION REPRESENTATIVES

1.15.1 Accommodations

1.15.2 Costs

1.16 CONTINUITY OF WORK

PART 2 PRODUCTS (THIS PART NOT USED)

PART 3 EXECUTION (THIS PART NOT USED)

SECTION 01 14 00 Page 2

SECTION 01 14 00

SPECIAL WORK CONDITIONS

07/07

PART 1 GENERAL

1.1 SUBMITTALS

The Contractor shall make submittals for the following listed reports and certificates as required by the specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. Prior to submittal, all items shall be checked and approved by the Contractor's Quality Control (CQC) representative and each item shall be stamped, signed, and dated by the CQC representative indicating action taken in accordance with SECTION 01 45 00. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ENGINEERING PAMPHLET, U.S. ARMY

EP 1110-1-8 (2018) Construction Equipment Ownership and Operating Expense Schedule

1.3 CONTRACTOR WORK REQUIREMENTS

The work consists of dredging by bucket or clamshell dredge the Entrance Channel, Mooring Birth and Boat Basin at the Chincoteague Coast Guard Base to the depth(s) indicated. All dredged material shall be placed in barges or scows, transported to the Chincoteague Coast Guard Base Boat Basin docking area, placed in dump trucks, and transported to the Town of Chincoteague Curtis Merritt Harbor disposal area approximately 2-1/2 miles away at the southern tip of Chincoteague Island. Dredged material shall be hauled to the approved disposal area by water-tight dump trucks equipped, designed, loaded and operated to prevent any leakage or spillage onto roadways. Any leakage or spillage shall be immediately removed at the Contractor's expense. The contractor shall comply with all rules and regulations regarding the use of roads leading to the disposal area and all material shall only be placed in areas as indicated and specified.

1.3.1 Security and Public Safety of Work Areas

The dredging and disposal sites are accessible to the general public;

however, the Contractor is informed the Government will not undertake to exclude the public or restrict public access to the dredging or disposal sites during the work. The Contractor shall be solely responsible for

SECTION 01 14 00 Page 3 protection of the public at all times for the duration of the contract and fully comply with the provisions of OSHA safe working practices and the Safety and Accident Prevention requirements of these specifications. Unless directed otherwise, the Contractor may perform the scheduled dredging work 24 hours a day, 7 days a week; however, the Contractor's work operations at the Coast Guard Base and placement area are restricted to 7:00am to 7:00pm.

All lighting associated with the project shall be limited to the immediate area of active construction only. Such lighting shall be shielded, low-pressure sodium vapor lights directed to the maximum extent practical away from populated areas where applicable and to avoid excessive illumination of the water.

1.3.2 Noise Control and Abatement

The Contractor shall employ the use of properly installed and maintained mufflers, silencers, and manufacturer's recommended sound suppressors on all plant, machinery, and equipment used on this work. The use of sound signals such as whistles, horns, or bells shall not be used if two-way radio communication can accomplish the required function.

1.3.3 Coordination with Other Contractors

During the period of this contract, other contracts may be in force for the construction of other features of work on or adjacent to the site of work being accomplished under this contract. The Contractor shall arrange his plant, and shall schedule and perform this work, so as to effectively cooperate with all other contractors and Government agencies. It shall be the responsibility of the Contractor on this contract to be fully informed of the extent of the limits of work to be performed by other contractors.

Should there be any conflict between these limits, the Contractor shall immediately notify the Contracting Officer of the conflict, and the Contracting Officer's decision shall be final.

1.4 PERSONNEL RESTRICTIONS

Personnel are limited to the immediate site areas where respective work features are performed and shall not enter property, buildings or facilities not involved in the work. All employees of the Contractor will be subject to all rules and regulations of the Chincoteague Coast Guard Facility and Town of Chincoteague Curtis Merritt Harbor Facility, as applicable, which pertain to personnel. Contractor shall comply with current Coast Guard security and safety requirements and schedule his work to minimize disruptions to Coast Guard activities.Point of contact for access and security requirements at the Chincoteague Coast Guard Base is Jim Petrik, phone (757) 336-2842 or e-mail: James.M.Petrik@uscg.mil.

1.5 TRANSPORTATION FACILITIES

The vehicular access to the Coast Guard Base and Town of Chincoteague Curtis Merritt Harbor Facility is served by an all weather surfaced road network; however, access within the Placement Area is dirt road. Road(s) proposed to be used by the Contractor shall be subject to prior approval of the CO and such roads, if used, shall be maintained throughout construction and shall be restored to as good condition as existed prior to their use.

The Contractor shall also construct, subject to approval, such temporary haul roads and bridges as may be necessary for conducting his work. Any such temporary construction shall be removed and the affected area restored to its original condition. All costs for the use of existing transportation

SECTION 01 14 00 Page 4 facilities, for the construction of temporary facilities, and for maintenance, repair, removal and restoration shall be borne by the Contractor.

1.5.1 Use of Roads

The Contractor shall keep all roads clear of all obstructions and free of mud and other foreign materials resulting from operations. The Contractor's vehicles shall at no time follow a vehicle closer than 50 feet, and all vehicles shall pull off the road and come to a complete stop when meeting emergency vehicles and vehicles with flashing lights. Speed limits and traffic controls will be observed. Any damage to utilities, roads, grounds, or other items on Coast Guard property shall be restored to pre-construction conditions at a minimum. Roads shall be left in such a condition that a standard 4 wheel passenger vehicle may utilize the road.

Any damage or changes to public roads, including the unpaved Curtis Merritt Harbor Road, due to the hauling operations shall be restored to Pre-Construction conditions or better. The Contractor shall submit both pre and post construction photographs of the access road(s) for verification that road quality is maintained or improved.

1.5.2 Cleated Vehicles

Cleated vehicles shall not be moved over surfaced roads.

1.6 PHYSICAL DATA

1.6.1 Physical Conditions Information

The physical conditions indicated on the drawings and in the specifications are the result of site investigations and surveys. Information and data furnished or referred to below is furnished for the Contractor's information; however, it shall be expressly understood that the Government will not be responsible for any interpretation or conclusion drawn from this information or data by the Contractor. The approximate mean range of tide at the dredging areas is noted on the respective drawings. The dredging areas are in mostly protected waters; however, high winds and seas in the channel area may at times cause suspension of work.

1.6.2 Obstruction of Channel

The Government will not undertake to keep the area of channels free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act, approved 3 August 1917. The Contractor will be required to conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractors' plant so obstructs the channel as to make difficult or endanger the passage of vessels, said plant shall be promptly moved on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon the completion of the work, the Contractor shall promptly remove his plant, including ranges, buoys, piles, and other marks placed by him under this contract in navigable water or on shore.

1.6.3 Responsibility

The Contractor shall hold and save harmless the United States, its officers, and employees from all claims that may arise as a result of the Contractor's negligence in connection with the work performed under the

SECTION 01 14 00 Page 5 contract, from noncompliance by the Contractor with the provisions of the contract drawings and specifications, or from the instruction of the Contracting Officer.

1.6.4 Condition of Dredging Areas

The plans for dredging show the condition of the dredging areas at the time of the most recent survey; however, the condition of the dredging areas will be verified by a survey made before dredging. The Government has no knowledge of cables, pipes, wrecks, or other artificial obstructions in the dredging area; however, the dredging area may contain trash, debris, and other obstructions not shown on the plans for dredging. Dredging directly beneath floating docks and fixed piers is not required; however, material adjacent to such features is required to be dredged. Accordingly, the Contractor shall exercise due care in all dredging and attendant plant operations to prevent damage to adjacent structures, bulkheads, piers, docks, mooring piles, vessels and any other items to remain in the work area during dredging operations. The Contractor shall take photographs of all existing conditions at the Coast Guard Base prior to conducting the work. Photographs shall be submitted to the Government prior to commencing the work.

1.7 WORK RESTRICTIONS

The contractor is expected to adhere to the work restrictions stated in paragraph 1.3.1 of this section. Delays from work restrictions shall be the contractor's responsibility and should be reflected in the construction schedule submittal.

1.7.1 Channel Traffic

The vessel traffic to be encountered during dredging operations consists of large commercial fishing vessels, U.S. Coast Guard vessels, various smaller fishing vessels and pleasure craft. The Contractor shall expect that the traffic will cause periodic delays and interruptions of his operations.

1.7.2 Interference with Coast Guard, Curtis Merritt Harbor and Placement Area and Town of Chincoteague Operations

Minimize interference with the operations of Coast Guard personnel and vessels at the Coast Guard Base. The Contracting Officer will direct the shifting or moving of dredges or the interruption of dredging/hauling operations to accommodate the movement of Coast Guard vessels and floating equipment, if necessary. Comply with Town of Chincoteague laws and regulations and all requirements for use and access to Curtis Merritt Harbor and Placement Area.

1.7.3 Oyster Grounds

There are no known oyster grounds in the vicinity of the areas to be dredged.

1.7.4 Holidays

The Town of Chincoteague's economy is largely based on tourism and local

SECTION 01 14 00 Page 6 events. The Contractor shall coordinate with the Town of Chincoteague to minimize work efforts on special dates. Known dates for the contractor to minimize work are May 29 - 31, July 4 - 6, July 26 - 31, and September 3 - 5, 2021. Other dates may be applicable upon the town's event schedule.

Chincoteague's events in no way relieve the contractor of meeting their obligated schedule as indicated herein.

1.8 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE

1.8.1 Costs

Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a Contractor or subcontractor at any tier shall be based on actual cost data when the Government can determine both ownership and operating costs for each piece of equipment or equipment groups of similar serial and series from the Contractor's accounting records. When both ownership and operating costs cannot be determined from the Contractor's accounting records, equipment costs shall be based upon the applicable provisions of EP 1110-1-8, "Construction Equipment Ownership and Operating Expense Schedule", Region II. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the Contracting Officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retrospective pricing, the schedule in effect at the time the work was performed shall apply.

1.8.2 Rentals

Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36 substantiated by certified copies of paid invoices. Rates for equipment rented from an organization under common control, lease-purchase or sale-leaseback arrangements will be determined using the schedule except that rental costs leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees are allowable. Costs for major repairs and overhaul are unallowable.

1.8.3 Data

When actual equipment costs are proposed and the total amount of the pricing action is over $25,000, cost or pricing data shall be submitted on the Standard Form 1411, "Contract Pricing Proposal Cover Sheet". By submitting cost or pricing data, the Contractor grants to the Contracting Officer or an authorizing representative the right to examine those books, records, documents and other supporting data that will permit evaluation of the proposed equipment costs. After price agreement the Contractor shall certify that the equipment costs or pricing data submitted are accurate, complete and current.

SECTION 01 14 00 Page 7

1.9 SPECIAL COAST GUARD REQUIREMENTS

1.9.1 Site Visit

Visits to the site for the purposes of verifying existing conditions shall be arranged with the Contracting Officer's Representative.

1.9.2 Local Notice To Mariners

The Local Notice To Mariners (LNM) for the Fifth Coast Guard District is available by phone at (757) 398-6367. Additionally, LNM are on the Internet at:

http://www.navcen.uscg.gov/?pageName=lnmDistrict®ion=5, and e-mail address: D5Local@LANTD5.uscg.mil.

The LNM is the primary means for disseminating information concerning aids to navigation, hazards to navigation, and other items of marine information of interest to mariners on the waters of the United States, its territories, and possessions. These notices are essential to all navigators for the purpose of keeping their charts, light lists, Coast Pilots and other nautical publications up-to-date. These notices are published weekly. They may be obtained free of charge, by making application to the Fifth Coast Guard District, Federal Building, 431 Crawford Street, Portsmouth, Virginia 23704. If the Contractor encounters any objects on the channel bottom during dredging operations or transport of his plant that could be a hazard to navigation, he shall notify the Coast Guard immediately as to location and at the same time notify the Contracting Officer.

1.9.3 Relocation of Navigation Aids

The Contractor shall not relocate or move any aids to navigation that have been established by the U.S. Coast Guard. If it becomes necessary to have any aid to navigation moved in order to complete dredging operations under this contract, the Contractor shall notify the U.S. Coast Guard in writing at the address above with a copy to the Contracting Officer not less than 15 calendar days prior to such need for movement. The Contractor shall notify the U.S. Coast Guard of the approximate time the navigation aid may be relocated to its original position. All notifications to the U.S. Coast Guard shall at the same time be provided to the Contracting Officer and recorded in the Daily Report of Operations. In the event that the Contractor disturbs or damages any navigation aid during work operations, which includes during mobilization or demobilization of his plant, the Contractor shall immediately stop the activity which disturbed or damaged the navigation aid, take immediate corrective action to prevent further disturbances or damage, and shall notify the Coast Guard immediately as to location, and at the same time notify the Contracting Officer.

1.9.4 Use of Coast Guard Navigation Aid Structures

The Commander, Fifth Coast Guard District, has authorized the Norfolk District, Corps of Engineers, and its Contractors to use fixed Federal aids to navigation structures, established and maintained by the U. S. Coast Guard, for support of temporary dredging tide gauges when performing Federal dredging operations. If a Contractor chooses to use navigation aid structures for this purpose, he shall abide by the following requirements:

a. The Contractor shall advise the Commander, Fifth Coast Guard

SECTION 01 14 00 Page 8

District, Aids to Navigation Branch, Federal Building, 431 Crawford Street, Portsmouth, Virginia 23704, in writing, of his intention to attach tide gauges to navigation aid and structures, prior to commencing a dredging project. This notice shall include the name of each aid to navigation to which tide gauges are to be attached, and the anticipated dates the gauges will be attached and removed. A copy of this notice shall be furnished at this time to the Contracting Officer.

b. The Contractor shall be required to remove any temporary tide gauges immediately upon completion of dredging operations and demobilization of dredging plant. The Contractor shall at his expense repair or replace any aids that he has damaged or destroyed as a result of the Contractor's use of such aids.

c. This provision refers only to Federal aids to navigation structures and does not authorize the Contractor to utilize aids that are not established and maintained by the U. S. Coast Guard. This provision also does not authorize the Contractor to utilize Federal navigation aid structures for any purposes other than the support of temporary tide gauges.

1.10 ENVIRONMENTAL LITIGATION

1.10.1 Litigation

If the performance of all or any part of the work is suspended, delayed, or interrupted due to an order of a court of competent jurisdiction as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the "Suspension of Work" clause of this contract. The period of such suspension, delay, or interruption shall be considered unreasonable, and an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) as provided in that clause, subject to all the provisions thereof. The term "environmental litigation" means, a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.

1.11 HISTORICAL AND ARCHAEOLOGICAL FINDS

Federal legislation provides for the protection, preservation, and collection of scientific, prehistoric, historic, and archaeological data, including relics and specimens that might otherwise be lost as a result of any Federal construction project. Should the Contractor, or any of the Contractor's employees, or parties operating or associated with the Contractor, in the performance of this contract discover evidence of possible scientific, prehistoric, historic, or archaeological data, the Contractor shall immediately cease work at that location, and notify the Contracting Officer, giving the location and nature of the findings. The Contractor shall forward written confirmation to the Contracting Officer as directed. The Contractor shall exercise care so as not to disturb or damage shipwrecks, artifacts or fossils uncovered during excavation, SECTION 01 14 00 Page 9 dredging and material placement operations, and shall provide such cooperation and assistance as may be necessary to preserve the findings for removal or other disposition. Any person who, without written permission, injures, destroys, excavates, appropriates, moves or removes any historic or prehistoric artifact, object of antiquity, or archaeological resource is subject to arrest and penalty of law. Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance or changes in the work, or both. If such delays or changes are ordered, an equitable adjustment will be made in accordance with the applicable clauses of the contract.

1.12 PROFIT

1.12.1 Weighted Guidelines

Weighted guidelines method of determining profit shall be used on any equitable adjustment change order or modification issued under this contract. The profit factors, expressed as a percent, shall be as follows:

Factor Rate Weight Value

Degree of Risk 20 Relative difficulty of work 15 Size of Job 15 Period of performance 15 Contractor's investment 5 Assistance by Government 5 Subcontracting 25

1.12.2 Values

Based on the circumstances of each procurement action, each of the above factors shall be weighted from .03 to .12 as indicated below. The value shall be obtained by multiplying the rate by the weight. The value column when totaled indicates the fair and reasonable profit percentage under the circumstances of the particular procurement.

1.12.2.1 Degree of Risk

Where the work involves no risk or the degree of risk is very small, the weighting should be .03; as the degree of risk increases, the weighting should be increased up to a maximum of .12. Job items will have, generally, a higher weighted value than the unit price items for which quantities are provided. Other things to consider: the portion of the work to be done by subcontractors, nature of work, where work is to be performed, reasonableness of negotiated costs, amount of labor included in costs, and whether the negotiation is before or after performance of work.

1.12.2.2 Relative Difficulty of Work

If the work is most difficult and complex, the weighting should be .12 and should be proportionately reduced to .03 on the simplest of jobs. This factor is tied in to some extent with the degree of risk. Some things to consider: the nature of the work, by whom it is to be done, where, and what is the time schedule.

SECTION 01 14 00 Page 10

1.12.2.3 Size of Job

All work not in excess of $100,000 shall be weighted at .12. Work estimated between $100,000 and $5,000,000 shall be proportionately weighted from .12 to .05.

1.12.2.4 Periods of Performance

Jobs in excess of 24 months are to be weighted at .12. Jobs of lesser duration are to be proportionately weighted to a minimum of .03 for jobs not to exceed 30 days. No weight where additional time not required.

1.12.2.5 Contractor's Investment

To be weighted from .03 to .12 on the basis of below average, average, and above average. Things to consider: amount of subcontracting, mobilization payment item, Government furnished property, equipment and facilities, and expediting assistance.

1.12.2.6 Assistance by Government

To be weighted from .12 to .03 on the basis of average to above average.

Things to consider: use of Government owned property, equipment and facilities, and expediting assistance.

1.12.2.7 Subcontracting

Shall be weighted inversely proportional to the amount of subcontracting.

Where 80 percent or more of the work is to be subcontracted, the weighting is to be .03 and such weighting proportionately increased to .12 where all the work is performed by the Contractor's own forces.

1.13 PARTNERING

In order to most effectively accomplish this contract, the Government is willing to form a cohesive partnership with the Contractor. This partnership would strive to draw on the strengths of each organization in an effort to achieve a quality project done correctly, within budget, and on time. This partnership would be bilateral in make-up and partnership will be totally voluntary. Any cost associated with effectuating this partnership will be agreed to by all parties and will be shared equally with no change in contract price.

1.14 SUBCONTRACTS AND WORK COORDINATION

Contract Clauses "SUBCONTRACTS", "PERMITS AND RESPONSIBILITIES", and "MATERIAL AND WORKMANSHIP" are supplemented as follows:

(a) Divisions or sections of specifications are not intended to control the Contractor in dividing the work among subcontractors, or to limit work performed by any trade.

(b) Contractor shall be responsible for coordination of the work of the trades, subcontractors, and materials.

(c) The Government or its representative will not undertake to settle any difference between the Contractor and Contractor's subcontractors, or between subcontractors.

SECTION 01 14 00 Page 11

(d) The Government reserves the right to refuse to permit employment on the work or require dismissal from the work of any subcontractor who, by reason of previous unsatisfactory work on Corps of Engineers projects, or for any other reason is considered by the Contracting Officer to be incompetent or otherwise objectionable.

1.15 ACCOMMODATIONS ABOARD DREDGE FOR CONSTRUCTION

REPRESENTATIVES

1.15.1 Accommodations

(a) Work Space - The Contractor shall furnish regularly to Government construction representatives on board the dredge a suitable working and storage space, equipped and maintained to the satisfaction of the Contracting Officer or his representative. As a minimum the facilities shall include a desk with chair for plan study, and a file drawer, approximately 15" by 24", capable of being locked with a padlock. The working space need not be a separate room, but shall be properly lighted, ventilated, and heated.

1.15.2 Costs

The entire cost to the Contractor for furnishing, equipping, and maintaining the foregoing accommodations shall be included in the contract price. If the Contractor fails to meet these requirements, the Contracting Officer will secure the facilities referred to above, and their costs will be deducted from payments due to the Contractor.

1.16 CONTINUITY OF WORK

No payment will be made for work done in any area designated by the Contracting Officer until the full depth required under the contract is secured in the whole of such area, unless prevented by ledge rock, nor will payment be made for excavation in any area not adjacent to and in prolongation of areas where full depth has been secured, except by decision of the Contracting Officer. Should any such nonadjacent area be excavated to full depth during the operations carried on under the contract, payment for all work therein may be deferred until the required depth has been made in the area intervening. The Contractor may be required to suspend dredging at any time when, for any reason, the gauges or ranges cannot be seen or properly followed.

PART 2 PRODUCTS (THIS PART NOT USED)

PART 3 EXECUTION (THIS PART NOT USED)

SECTION 01 14 00 Page 12

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

07/07

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 Job PAYMENT ITEMS

1.3.1 Payment Item No. 0001 Mobilization and Demobilization

1.3.1.1 Mobilization

1.3.1.2 Demobilization

1.3.2 Payment Item No. 0002 Earthwork Upgrades

1.4 UNIT PRICE PAYMENT ITEMS

1.4.1 Payment Item No.0003 Dredging

1.5 MISPLACED MATERIAL

1.6 EXCESSIVE DREDGING

1.7 MONTHLY PARTIAL PAYMENTS

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 1

SECTION 01 22 00

MEASUREMENT AND PAYMENT

07/07

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ENGINEERING MANUALS, U.S. ARMY

EM 1110-2-1003 (2013) Hydrographic Surveying Manual;

1.2 SUBMITTALS

Not Used.

1.3 Job PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, shall be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.3.1 Payment Item No. 0001 Mobilization and Demobilization

All costs connected with the mobilization and demobilization of all of the Contractor's dredging plant and equipment as defined below will be paid for at the contract job price for this item. Sixty percent of the job price will be paid to the Contractor upon completion of his mobilization at the work site. The remaining forty percent will be paid to the Contractor upon completion of demobilization. In the event the Contracting Officer considers that the amount in this item, sixty percent which represents mobilization and forty percent which represents demobilization, does not bear a reasonable relation to the cost of the work in this contract, the Contracting Officer may require the Contractor to produce cost data to justify this portion of the bid. Failure to justify such price to the satisfaction of the Contracting Officer will result in payment of actual mobilization costs, as determined by the Contracting Officer, at the completion of mobilization, and actual demobilization costs, as determined by the Contracting Officer, at the completion of demobilization. The determination of the Contracting Officer is not subject to appeal.

SECTION 01 22 00 Page 2

1.3.1.1 Mobilization

Mobilization shall include all costs for operations accomplished prior to commencement of actual dredging operations. This shall include as a minimum the following:

a. Transfer of dredge and attendant plant, barges, excavators and other like equipment and machinery.

b. All costs for any other associated work that is necessary in advance of the actual dredging operations.

1.3.1.2 Demobilization

Demobilization shall include general preparation for transfer of plant to its home base.

1.3.2 Payment Item No. 0002 Earthwork Upgrades

Payment shall include all work associated with earthwork upgrades to the Curtis Merritt Harbor of Refuge Upland Placement Site, including all associated work as shown on the drawings and specified in the specifications, as well as all required equipment.

1.4 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.4.1 Payment Item No.0003 Dredging

Payment to be made for all costs associated with dredging shall include the cost of removal, transportation and disposal of dredged material in the placement area, and maintenance of the placement area during dredging as indicated and specified, exclusive of the mobilization and demobilization as defined above. The total amount of material removed and to be paid for under this payment item will be measured by the cubic yard in place by computing the volume between the bottom surface shown by soundings of the last surveys made before dredging, and the bottom surface shown by the soundings of surveys made as soon as practicable after the work has been completed. The volume for measurement and payment shall include the material within the limits of overdepth and side slopes described in paragraph "Required Dredging Prism, Overdepth, and Side Slopes" of SECTION 35 20 23, less any deductions that may be required for misplaced material described in subparagraph "Misplaced Material", below. The drawings are believed to accurately represent conditions at the time of the surveys indicated. New soundings will be taken immediately before dredging as specified in paragraph "Before Dredging Surveys" of SECTION 35 20 23. The Contractor's unit price for dredging, based on the above method of computation of the quantity for payment, shall include his evaluation of shoaling, other natural changes in the waterway, or changes caused by the Contractor's operations that might occur during the period between the surveys before dredging and the surveys for acceptance of the work.

Computations for payment purposes will be made by the Government for the

SECTION 01 22 00 Page 3

Entrance Channel and Mooring Berth using, as defined in the USACE Hydrographic Survey Manual EM 1110-2-1003, the Average End Area (AEA) method, Triangulated Irregular Network (TIN) method, or a combination of these methods at the discretion of the Government, utilizing electronic data processing software and machines for the calculations. Computations for payment purposes will be made by the Government for the Boat Basin using, as defined in the USACE Hydrographic Survey Manual EM 1110-2-1003, the Triangulated Irregular Network (TIN) method. Volumes at this location only will be computed without regard for the spatial location of any floating docks or permanent piers. This will result in the Contractor being compensated for sloughing that may occur from material that was located under the docks/piers prior to dredging. Determination of quantities removed and the deductions made to determine quantities in place to be paid for in the areas specified, after having once been made, will not be reopened except on evidence of collusion, fraud, or obvious error.

1.5 MISPLACED MATERIAL

Any material that is deposited elsewhere than in places designated or approved by the Contracting Officer will not be paid for, and the Contractor may be required to remove such misplaced material and deposit it where directed by the Contracting Officer at the Contractor's expense.

1.6 EXCESSIVE DREDGING

Material taken from outside the specific areas to be dredged or beyond the limits as extended in paragraph "Required Dredging Prism, Overdepth, and Side Slopes" will be considered as excessive overdepth dredging, or excessive side slope dredging, for which payment will not be made. Nothing in these specifications shall be construed to prevent payment for the removal of shoals performed in accordance with the applicable provisions of Paragraphs SHOALING and FINAL EXAMINATION AND ACCEPTANCE of Section 35 20 23.

1.7 MONTHLY PARTIAL PAYMENTS

Monthly partial payments will be based on estimated quantities determined by the Contracting Officer.

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

SECTION 01 22 00 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROJECT SCHEDULER QUALIFICATIONS

1.4 QUALITY ASSURANCE

PART 2 PRODUCTS

2.1 SOFTWARE

2.1.1 Government Default Software

2.1.2 Contractor Software

2.1.2.1 Primavera

2.1.2.2 Other Than Primavera

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.1.1 Approved Project Schedule

3.1.2 SCHEDULE STATUS REPORT

3.1.3 DEFAULT TERMS

3.2 BASIS FOR PAYMENT AND COST LOADING

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Progress Schedule Format

3.3.2 Level of Detail Required

3.3.3 Activity Durations

3.3.4 Procurement Activities

3.3.4.1 Critical Activities

3.3.5 Government Activities

3.3.6 Definable Features of Work Coding (FOW1, FOW2, FOW3)

3.3.7 Contract Milestones

3.3.7.1 Project Start Date

3.3.7.1.1 Schedule Constraints and Open End Logic

3.3.7.1.2 Early Project Completion

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Project Schedule Submission

3.4.2 Periodic Schedule Updates

3.5 Standard Activity Coding Dictionary

3.6 WEEKLY PROGRESS MEETINGS

3.7 OWNERSHIP OF FLOAT

3.8 PRIMAVERA P6 MANDATORY REQUIREMENTS

SECTION 01 32 01.00 10 Page 1

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2008; Errata 1-2010; Changes 1-3 2010;

Changes 4-6 2011; Change 7 2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES::

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Preliminary Project Schedule; G

Initial Project Schedule; G

Periodic Schedule Update; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

1.4 QUALITY ASSURANCE

The Contractor CQC representative shall be responsible for the preparation and certification as complete all required project Progress Schedule submittals and reports.

SECTION 01 32 01.00 10 Page 2

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.

2.1.1 Government Default Software

The Government intends to use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

2.1.2.2 Other Than Primavera

If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.

3.1.1 Approved Project Schedule

Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

SECTION 01 32 01.00 10 Page 3

3.1.2 SCHEDULE STATUS REPORT

Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained

3.1.3 DEFAULT TERMS

Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN." With "Lack of an approved schedule update, or qualified scheduling personnel, may result in the inability of the Contracting Officer to evaluate contract earned value for the purposes of payment.

Failure of the Contractor to provide all required information will result in the disapproval of subsequent schedule updates. In the event schedule revisions are directed by the Contracting Officer and those revisions have not been included in subsequent revisions or updates, the Contracting Officer may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the Contracting Officer."

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

The Contractor shall submit his Progress Schedule to the Contracting Officer for approval at the Pre-Construction Conference specified in SECTION ADMINISTRATIVE REQUIREMENTS. The Progress Schedule shall be submitted and certified as complete by the Contractor's Quality Control Representative in the form of a chart graphically indicating the sequence proposed to accomplish each work feature or operation. The chart shall be prepared to show the starting and completion dates of all work features on a linear horizontal time scale beginning with date of Notice to Proceed, arrival date of Contractor's plant to the job site, all activities scheduled prior to dredging, dredging start and completion dates, calendar days to completion of all work, and contract completion date.

The Contractor shall indicate on the chart the important work activities that are critical to the timely overall completion of the project. Key dates for important features or portions of work features are milestone dates and shall be so indicated on the chart.

SECTION 01 32 01.00 10 Page 4

3.3.1 Progress Schedule Format

Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule and prepare the Project Schedule using the Precedence Diagram Method (PDM) OR prepare the Progress Schedule in the form of a Gantt Chart.

3.3.2 Level of Detail Required

Develop the Project Schedule to an appropriate level of detail. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer, will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.3 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

3.3.4 Procurement Activities

The schedule must include activities associated with the submittal, approval, procurement, fabrication and delivery of long lead materials, equipment, fabricated assemblies and supplies as applicable. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days. A typical procurement sequence includes the string of activities: submit, approve, procure, fabricate, and deliver.

3.3.4.1 Critical Activities

The following activities shall be listed as separate line activities on the Contractor's Project Schedule. This list represents a partial lists and is not considered complete:

a. Submission and approval of Accident Prevention Plan.

b. Submission and approval of all environmental submittals.

c. Submission and approval of dredge plan and auxiliary equipment.

d. Submission and approval of pre-work plan and schedule.

e.

This is the start of the file's text. The full file is on GovTribe.