This document is a Statement of Work (SOW) for a federal contract opportunity from the U.S. Department of Agriculture (USDA) Forest Service to replace the windows, siding, doors, and motion sensors at the Radio Shop located at the Placerville Auto Shop and Work Center.
The key objectives are to increase security at the Radio Shop, which has been repeatedly burglarized, by replacing the windows with modern vinyl-clad windows, installing a new steel security door with a keypad deadbolt and locking door handle, and adding new high-power LED security lighting. The work also includes removal and replacement of the aluminum siding, repair of any damaged framing, and abatement of any hazardous materials such as lead or asbestos that may be present. The contractor will be required to provide a project schedule, submit product samples for approval, and develop site safety and hazardous materials abatement plans. No travel is required, and the government will not be providing any furnished equipment or materials. The project must be completed in accordance with the detailed technical requirements and specifications provided in the attachments.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A-6_J-1_SOI.xlsx | XLSX spreadsheet | |
| A-6_J-8_BiobasedStatementLetter.docx | DOCX document | |
| A-6_J-7_ProgressSched (FS 6300-7).rtf | RTF text file | |
| A-6_J-5_PicturesofDamageandRepairs.pdf | ||
| A-6_J-4_Plan and elevation.pptx | PPTX presentation | |
| A-6_J-10_WageDet_CA20240007_07122024.pdf | ||
| A-6_J-3_Fire Plan_GeorgetownDistrict.doc | DOC document | |
| A-6_01_SF1442_12970224Q0050_07292024.pdf | ||
| A-6_J-6_Experience Questionnaire (FS 6300-27).docx | DOCX document | |
| A-6_J-9_DesignationofKTRKeyPersonnel-Reps.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents
| Project | 3 |
| General Information | 3 |
| 1.0 Scope of Work | 3 |
| 2.0 Background | 3 |
| Contractor Requirements | 3 |
| 3.0 Technical Requirements / Tasks | 3 |
| 4.0 Government Furnished | 3 |
| 5.0 Deliverables / Schedule | 3 |
| 6.0 Travel | 4 |
| 7.0 Contractor’s Key Personnel | 4 |
| 8.0 Security Requirements | 4 |
| 9.0 Data Rights | 4 |
| 10.0 Section 508 – Electronic and Information Technology Standards | 4 |
| Attachment | 4 |
Project Eldorado NF Radio Shop Windows
General Information
1.0 Scope of Work
The goal of this project is to replace the windows at the Radio Shop with modern vinyl clad windows. Repairs will be made to the aluminum siding up to replacement of panels as needed. Repairs will be made to any damaged lumber found during replacement. The current door will be replaced with a steel security door. Replacement and/or repair of the door frame will be made as needed. At completion, there will be increased security for the radio shop with new windows, a steel security door, and repairs made to the exterior as needed.
2.0 Background
The radio shop on the Placerville Auto Shop and Work Center, located at 2350 Carson Road in Placerville. The location has been repeatedly burglarized and there is concern that the radio shop may soon be a target. The radio shop contains a large amount of high value property and parts to maintain the items and if broken into could significantly impact operations.
Contractor Requirements
3.0 Technical Requirements / Tasks
1. Test for lead and asbestos. If present, the contractor will provide an abatement plan including cost. Abatement to be performed by licensed contractors in the state of California and IAW state and local laws and regulations. Contractor to dispose of Hazmat IAW all local laws and regulations.
2. Remove and dispose of all windows except for one (a newer vinyl clad window located next to the Trails door, will be clearly marked).
3. Remove and replace all the aluminum siding for the entire building (including windows to be abandoned, over doors and under new window at front of radio shop) approximately 3000 SF. Remove and replace the 1’ fascia around building exterior, approximately 300 LSF.
4. Perform any framing repairs as a part of new windows and doors installation and damaged lumber behind siding. Infill all previous window openings and areas not flush with the building. Prep for siding installation over these areas.
5. Remove and replace existing door to radio shop (identified on sketch). Reframe for new door installation. New door to be Republic DL Level 3 flush door. Lock to be Trilogy (or equal) DL2700WP/26D Weatherproof Keypad Programmable Pushbutton Lock with handles.
6. Remove and replace 2 existing doors (for the Botany and Trails bays, identified on sketch). Reframe for new door installation. Frame opening to be flush with existing building and cover with new siding to match. New doors to be Republic DL Level 2 flush door or equal. Lock to be Trilogy (or equal) DL2700WP/26D Weatherproof Keypad Programmable Pushbutton Lock with handles.
7. Install 6 new windows for radio shop. This includes installation of weatherproofing, trim, and any framing needed. Windows to be Milgard Style Line V250 (or equal). Rough window opening 48”x48”. Window model half vent.
8. Install trim (both interior and exterior) around doors, windows and new overhead doors. Repair drywall and interior office painting
9. Install new Defiant (or equal) MaxDetect 240-Degree White Motion Activated Wired Outdoor 3-Head Dusk-to-Dawn LED Security Flood Light 3000 Lumens over radio shop door.
10. Remove and replace 4 ea 10’x10’ rollup doors. Doors to be the Amarr (or equal) 2042 Extra Heavy-Duty door with lock and manual chain hoist, with no window lites and must be the same design as previously installed doors. Install new trim.
11. Remove and replace 1 ea 11’(h)x10’(w) rollup doors. Door to be the Amarr (or equal) 2042 Extra Heavy-Duty door with lock and manual chain hoist, with no window lites and must be the same design as previously installed doors. Install new trim.
At the completion of the project, all hazardous material will have been tested for and abated. The windows will have been replaced with modern tempered glass vinyl windows that are trimmed out both inside and outside. The existing doors will be replaced with a new steel security door that will open outwards with new keypad deadbolt and locking door handle. New high power LED security lights will be operational. All debris will have been removed and disposed off-site IAW local laws and regulations.
4.0 Government Furnished
N/A
5.0 Deliverables / Schedule0
Key Deliverables
1. Project Schedule. Include lead time for materials
2. Submittals. At a minimum: security door, overhead doors, windows, keypad dead bolt, LED lights will be submitted. Other submittals as needed or requested,
3. Plans. Submit the following: Site Safety plan, Hazardous Materials abatement plan (to include mitigation of materials during abatement if hazmat is detected).
6.0 Travel
No travel necessary.
7.0 Contractor’s Key Personnel
Provide name and previous experience on similar projects for the Construction Superintendent.
8.0 Security Requirements
High value sensitive equipment is stored in building. Contractor to ensure all external openings to the office are secured before leaving job site each day.
9.0 Data Rights
N/A
10.0 Section 508 – Electronic and Information Technology Standards N/A
Attachment See attached specifications for window and door selection image1.png