1-00 Combined Project Manual 11-14-25.pdf
PDF 7 MB Posted
- Attached to
- WWTP Driveway Paving
- Solicitation number
- US.210686
- Issued by
- Potter County, Pennsylvania
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-2025.11.20 WWTP Driveway Paving Bid Drawings - SS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
BIDDING & CONTRACT DOCUMENTS
WWTP Driveway Paving
Contract No. 1 – General Construction
Prepared for:
Galeton Borough Authority
24 West Main Street
Galeton, Pennsylvania 16922
Prepared by:
LARSON DESIGN GROUP
1000 Commerce Park Drive, Suite 201
Williamsport, PA 17701
LDG Project No. 5252-064
November 2025
THIS PAGE INTENTIONALLY LEFT BLANK
LDG 5252-064
TABLE OF CONTENTS 000110 - 1
TABLE OF CONTENTS
SERIES 00 PROCUREMENT AND CONTRACTING REQUIREMENTS
Cover
000110 Table of Contents
000101 Project Title Page
001100 (C-111) Advertisement for Bids
002113 (C-200) Instructions to Bidders
003100 Available Project Information
Davis-Bacon Wage Rates
Davis Bacon Wage Rate Compliance Form
004113.1 (C-410) Bid Form – Contract No. 1
004303 (C-430) Bid Bond (Penal Sum)
004393 Bid Submittal Checklist
004513.2 (C-451) Qualifications Statement
004519 Non-Collusion Affidavit
005100.1 (C-510) Notice of Award – Contract No. 1
005213 (C-520) Agreement
005500.1 (C-550) Notice to Proceed – Contract No. 1
006113.13 (C-610) Performance Bond
006113.16 (C-615) Payment Bond
006363 (C-941) Change Order Form
006516.1 (C-625) Certificate of Substantial Completion
006519.16 Affidavit of Release of Liens Form
006519.19 Consent of Surety to Final Payment Form
007213 (C-700) General Conditions
007314 (C-800) Supplementary Conditions
009113.xx Addendum
DIVISION 01 - GENERAL REQUIREMENTS
011000 Summary
012100 Allowances
012500 Substitution Procedures
012600 Contract Modification Procedures
012900 Payment Procedures
012900.1 Contractor’s Application for Payment
013100 Project Management and Coordination
013100.1 RFI Form
013200 Construction Progress Documentation
013233 Photographic Documentation
013300 Submittal Procedures
013300.1 Contractor’s Certification
014000 Quality Requirements
014200 References
015000 Temporary Facilities and Controls
016000 Product Requirements
TABLE OF CONTENTS 000110 - 2
017300 Execution
017700 Closeout Procedures
017823 Operation and Maintenance Data
017839 Project Record Documents
DIVISION 32 – Exterior Improvements
321200 Flexible Paving
END OF SECTION 000110
PROJECT TITLE PAGE 000101 - 1
DOCUMENT 000101 - PROJECT TITLE PAGE
1.1 PROJECT MANUAL– BIDDING & CONTRACT DOCUMENTS
A. Project: WWTP Driveway Paving
B. Owner: Galeton Borough Authority
24 West Main Street
Galeton, PA 16922
C. Owner Phone: 814-435-2275
D. Engineer’s Project No: 5252-064
E. Engineer: Larson Design Group
1000 Commerce Park Drive, Suite 201
Williamsport, PA 17701
F. Engineer Phone: (570) 244-3454
G. Engineer Fax: (570) 323-9902
H. Engineer Web Site: www.larsondesigngroup.com
I. Issued: November 20, 2025
END OF DOCUMENT 000101
http://www.larsondesigngroup.com/
EJCDC® C-111, Suggested Advertisement for Bids for Construction Contracts.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 1
GALETON BOROUGH AUTHORITY
GALETON BOROUGH, POTTER COUNTY, PENNSYLVANIA
CONTRACT No. 1 – GENERAL CONSTRUCTION
ADVERTISEMENT FOR BIDS
Sealed Bids for the construction of the WWTP Driveway Paving project will be received electronically via PennBid (https://pennbid.bonfirehub.com) by Galeton Borough Authority until 2 P.M. local time on January 19, 2026.
Bids will be received for Contract No. 1 – General Construction.
Bidding and Contract Documents may be viewed and downloaded online at no cost on PennBid (https://pennbid.bonfirehub.com). Following registration, complete sets of Bidding & Contract Documents may be downloaded from the website as portable document format (PDF) files. The cost of printing Bidding and Contract Documents will be the sole responsibility of the interested party. For questions pertaining to access and use of the website, contact PennBid at 610-693-4769, or by email at info@pennbid.net.
There will be no Pre-Bid Conference.
Each bid must be accompanied by a certified check or bid bond in the amount of ten (10%) percent of the total bid, as a guarantee that the bidder will execute the contract and furnish the necessary bonds if the contract is awarded to him.
This Project is being funded in part by federal funding. The Supplementary Conditions set forth requirements for the payment by the Contractor and all Subcontractors of minimum wage rates for all classes of laborers and mechanics as set forth by all applicable provisions of the Davis Bacon Wage Rate, and the Bid shall be prepared accordingly.
The Contractor shall ensure that employees and applicants for employment are not discriminated against because of race, age, color, religion, sex, national origin or handicap status; and comply with the Nondiscrimination/Sexual Harassment Clause included in the Supplementary Conditions, the Americans with Disabilities Act, the Pennsylvania Human Relations Act, federal and Pennsylvania laws and regulations, relating to non-discrimination and sexual harassment, drug-free workplaces and disadvantage business enterprises.
Galeton Borough Authority reserves the right to waive any irregularities and to reject any and all bids and to award either contract to the lowest responsible bidder for the total of all bid items.
No bidder may withdraw his or her bid within ninety (90) days after the actual opening thereof.
Galeton Borough Authority is an Equal Opportunity Employer.
https://pennbid.bonfirehub.com/
EJCDC® C-111, Suggested Advertisement for Bids for Construction Contracts.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 2
Advertise Date:
Proof of Publication requested.
END OF ADVERTISEMENT FOR BIDS
EJCDC® C-200 (Rev. 1), Suggested Instructions to Bidders for Construction Contracts.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page i
INSTRUCTIONS TO BIDDERS
TABLE OF CONTENTS
Page
Article 1 – Defined Terms
Article 2 – Copies of Bidding Documents
Article 3 – Qualifications of Bidders
Article 4 – Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;
Other Work at the Site
Article 5 – Bidder’s Representations
Article 6 – Pre-Bid Conference
Article 7 – Interpretations and Addenda
Article 8 – Bid Security
Article 9 – Contract Times
Article 10 – Liquidated Damages
Article 11 – Substitute and “Or-Equal” Items
Article 12 – Subcontractors, Suppliers, and Others
Article 13 – Preparation of Bid
Article 14 – Basis of Bid
Article 15 – Submittal of Bid
Article 16 – Modification and Withdrawal of Bid
Article 17 – Opening of Bids
Article 18 – Bids to Remain Subject to Acceptance
Article 19 – Evaluation of Bids and Award of Contract
Article 20 – Bonds and Insurance
Article 21 – Signing of Agreement
Article 22 – Sales and Use Taxes
Article 23 – Contracts to be Assigned
Article 24 - Wage Rate Requirements
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 1
ARTICLE 1 – DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office – The office from which the Bidding Documents are to be issued and where the Bidding procedures are to be administered:
Larson Design Group 1000 Commerce Park Drive, Suite 201 Williamsport, PA 17701
B. Bidder – The individual or entity who submits a Bid.
C. Bidding Documents – Project Manual Bidding & Contract Documents.
D. Successful Bidder – The lowest responsible Bidder submitting a responsive Bid to whom Owner makes an award.
ARTICLE 2 – COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents may be obtained from the following website: PennBid (bonfirehub.com). Bidders are required to register on the website for the ability to view and/or acquire the Bidding Documents.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.
2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.
ARTICLE 3 – QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder’s qualifications to perform the Work, Bidder shall submit the following information with the Bid.
A. Qualifications Statement.
B. Non-Collusion Affidavit.
3.02 A Bidder’s failure to submit required qualification information may disqualify Bidder from receiving an award of the Contract.
3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.
https://pennbid.bonfirehub.com/portal/?tab=login https://pennbid.bonfirehub.com/portal/?tab=login
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 2
ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S
SAFETY PROGRAM; OTHER WORK AT THE SITE
4.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor. In addition, the Contractor is responsible for contacting Galeton Borough (814-435-2275) regarding any bonding requirements for the use of the Galeton Borough roads that provide access to the Site.
4.02 Existing Site Conditions
A. Subsurface and Physical Conditions; Hazardous Environmental Conditions
1. The Supplementary Conditions identify:
a. those reports known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.
b. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).
c. reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.
d. Technical Data contained in such reports and drawings.
2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.
3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.
B. Underground Facilities: Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or adjacent to the Site are set forth in the Contract Documents and are based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others. Call Before You Dig! Pennsylvania State law requires a three (3) business day notice (does not include state holidays or weekends), but not more than ten (10) business days prior to the start of excavation and 10 business day notice, but not more than 90 business days in Design Stage.
Call 8-1-1 or 1-800-242-1776, PA One Call Serial No. 20192061989. The Designer has obtained this Serial Number(s) as required by PA Act 287, as amended.
C. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 3 furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 5.06 of the General Conditions.
4.03 Site Visit and Testing by Bidders
A. Bidder shall conduct the required Site visit during normal working hours, and shall not disturb any ongoing operations at the Site.
B. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.
C. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site.
D. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
E. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.
4.04 Owner’s Safety Program
A. Site visits and work at the Site may be governed by an Owner safety program. As the General Conditions indicate, if an Owner safety program exists, it will be noted in the Supplementary Conditions.
4.05 Other Work at the Site
A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.
ARTICLE 5 – BIDDER’S REPRESENTATIONS
5.01 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, and any data and reference items identified in the Bidding Documents;
B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 4
C. become familiar with and satisfy itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work;
D. carefully study all: (1) reports of explorations and tests of subsurface conditions at or adjacent to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings, and (2) reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, especially with respect to Technical Data in such reports and drawings;
E. consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs;
F. agree, based on the information and observations referred to in the preceding paragraph, that at the time of submitting its Bid no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;
G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;
H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;
I. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work;
and
J. agree that the submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
ARTICLE 6 – PRE-BID CONFERENCE
6.01 A Pre-Bid Conference will not be required.
ARTICLE 7 – INTERPRETATIONS AND ADDENDA
7.01 Bidder shall submit all questions about the meaning or intent of the Bidding Documents via the “Messages/Vendor Discussions” feature in PennBid no later than seven (7) days prior to the date for receipt of bids.
7.02 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all parties recorded as having received the Bidding Documents. Questions received less than seven days prior to the date for opening of Bids may
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 5 not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.
7.03 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.
ARTICLE 8 – BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a certified check, bank money order, or a Bid bond (on the form included in the Bidding Documents) issued by a surety meeting the requirements of Paragraphs 6.01 and 6.02 of the General Conditions.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award or Notice of Award, and the Bid security of that Bidder will be forfeited to the Owner as liquidated damages for such failure and not as a penalty.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Contract or 90 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within seven days after the Bid opening.
ARTICLE 9 – CONTRACT TIMES
9.01 The number of days within which, or the dates by which the Work is to be substantially completed, and completed and ready for final payment, are set forth in the Agreement.
ARTICLE 10 – LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.
ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS
11.01 The Contract for the Work, if awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer at least 15 days prior to the date of receipt of Bids in the case of a proposed substitute and 5 days prior in the case of a proposed “or-equal.” Each such request shall comply with the requirements of Paragraphs 7.04 and 7.05 of the General Conditions. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 6 item, such approval will be set forth in an Addendum issued to all prospective Bidders. Bidders shall not rely upon approvals made in any other manner. Substitutes and “or-equal” materials and equipment may be proposed by Contractor in accordance with Paragraph 7.04 and 7.05 of the General Conditions after the effective date of the Contract.
11.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.
11.03 If an award is made, Contractor shall be allowed to submit proposed substitutes and “or-equals” in accordance with the General Conditions.
ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS
12.01 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or Contractor to retain any Subcontractor, Supplier, or other individual or entity against which Contractor has reasonable objection.
12.02 If required by the bid documents, the apparent Successful Bidder, and any other Bidder so requested, shall submit with the bid, a list of the Subcontractors or Suppliers proposed for all portions of the Work.
If requested by Owner after bid submission, such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, or other individual or entity. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder shall submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.
12.03 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, or other individuals or entities. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.06 of the General Conditions.
12.04 Contractor shall not be required to employ any Subcontractor, Supplier, individual, or entity against whom Contractor has a reasonable objection.
12.05 The Contractor shall not award work to Subcontractor(s) in excess of the limits stated in SC7.06.
ARTICLE 13 – PREPARATION OF BID
13.01 The Bid Form is included with the Bidding Documents for Reference. Bidders shall complete the electronic bid form within PennBid (“Prepare Your Submission” tab)
13.02 A Bid by a corporation shall be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation shall be shown.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 7
13.03 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign.
The partnership’s address for receiving notices shall be shown.
13.04 A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the firm’s address for receiving notices shall be shown.
13.05 A Bid by an individual shall show the Bidder’s name and address for receiving notices.
13.06 A Bid by a joint venture shall be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture’s address for receiving notices shall be shown.
13.07 All names shall be printed in ink below the signatures.
13.08 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.
13.09 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.
13.10 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.
ARTICLE 14 – BASIS OF BID
14.01 Base Bid with Alternates
A. Bidders shall submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form.
The price for each alternate will be the amount added to or deleted from the base Bid if Owner selects the alternate.
14.02 Unit Price
A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.
B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity” (which Owner or its representative has set forth in the Bid Form) for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
14.03 Allowances
A. For cash allowances the Bid price shall include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 8
ARTICLE 15 – SUBMITTAL OF BID
15.01 Bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com) by the date and time indicated in the Invitation for Bids along with the Bid security and the other documents required to be submitted as identified herein.
Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.
ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID
16.01 A Bid may be withdrawn or modified at any time within PennBid prior to the due date and time identified in the Invitation for Bids.
16.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 16.01 and submit a new Bid prior to the date and time for the opening of Bids.
16.03 If within two (2) business days after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.
ARTICLE 17 – OPENING OF BIDS
ARTICLE 18 – A SUMMARY OF BIDS RECEIVED WILL BE ISSUED VIA A PUBLIC NOTICE ON PENNBID SHORTLY AFTER BID OPENING, THE TIME OF WHICH IS LISTED IN THE INVITATION TO BID. IT SHOULD BE NOTED THAT BID RESULTS ARE SUBJECT TO FURTHER REVIEW AND SHOULD NOT BE CONSTRUED
AS ISSUANCE OF AN AWARD. BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT
19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the Owner will reject the Bid as nonresponsive; provided that Owner also reserves the right to waive all minor informalities not involving price, time, or changes in the Work.
19.02 If Owner awards the contract for the Work, such award shall be to the responsible Bidder submitting the lowest responsive Bid.
19.03 Evaluation of Bids
A. In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Intent to Award.
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 9
B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form. To determine the Bid prices for purposes of comparison, Owner shall announce to all bidders a “Base Bid plus alternates” budget after receiving all Bids, but prior to opening them. For comparison purposes alternates will be accepted, following the order of priority established in the Bid Form, until doing so would cause the budget to be exceeded. After determination of the Successful Bidder based on this comparative process and on the responsiveness, responsibility, and other factors set forth in these Instructions, the award may be made to said Successful Bidder on its base Bid and any combination of its additive alternate Bids for which Owner determines funds will be available at the time of award.
19.04 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 20 – BONDS AND INSURANCE
20.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the Agreement (executed by Successful Bidder) to Owner, it shall be accompanied by required bonds and insurance documentation.
ARTICLE 21 – SIGNING OF AGREEMENT
21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder shall execute and deliver the required number of counterparts of the Agreement (and any bonds and insurance documentation required to be delivered by the Contract Documents) to Owner. Within ten days thereafter, Owner shall deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.
ARTICLE 22 – SALES AND USE TAXES
22.01 Owner is exempt from Pennsylvania state sales and use taxes on materials and equipment to be incorporated in the Work. Said taxes shall not be included in the Bid. Refer to Paragraph SC-7.09 of the Supplementary Conditions for additional information.
ARTICLE 23 – CONTRACTS TO BE ASSIGNED
Not Used
Copyright © 2013 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved. Page 10
ARTICLE 24 – WAGE RATE REQUIREMENTS
24.01 Wage Rates: The Supplementary Conditions set forth requirements for the payment by the Contractor and its’ Subcontractors of minimum wage rates for all classes of laborers and mechanics as set forth by all applicable provisions of the Davis Bacon Wage Act.
AVAILABLE PROJECT INFORMATION 003100 - 1
DOCUMENT 003100 - AVAILABLE PROJECT INFORMATION
1.1 SUMMARY
A. Available Project Information Includes:
1. Davis Bacon Wage Rate Decision
B. Related Documents:
1. Document 00 21 13 - Instructions to Bidders
1.2 DAVIS BACON WAGE RATE DECISION
A. A copy of the Davis Bacon Wage Rate Decision is included in the Project Manual.
END OF SECTION 003100
"General Decision Number: PA20250062 10/03/2025
Superseded General Decision Number: PA20240062
State: Pennsylvania
Construction Type: Building
County: Potter County in Pennsylvania.
BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |. Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |. The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.75 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2025. | |If the contract was awarded on|. Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |. The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $13.30 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours spent performing on | | | that contract in 2025. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/03/2025 1 01/10/2025
2 01/24/2025 3 02/07/2025 4 02/21/2025 5 03/07/2025 6 03/14/2025 7 08/08/2025 8 10/03/2025
BOIL0154-007 01/01/2025
Rates Fringes
BOILERMAKER......................$ 48.28 33.17
BRPA0009-011 12/01/2022
Rates Fringes
TILE FINISHER....................$ 28.76 17.16
TILE SETTER......................$ 35.64 21.63
* CARP0423-012 06/01/2025
Rates Fringes
CARPENTER (Scaffold Building Only)............................$ 34.76 20.64
* CARP0423-013 06/01/2025
Rates Fringes
CARPENTER (Includes Acoustical Ceiling Installation, Drywall Hanging, Metal Stud Installation, Floor Laying-Carpet and Vinyl, Form Work and Gutter Installation;
Excludes Scaffold Building)......$ 34.76 20.64
CARP0443-004 06/01/2024
Rates Fringes
MILLWRIGHT.......................$ 43.00 23.44
ELEC0005-018 12/27/2024
Rates Fringes
ELECTRICIAN (Alarm Installation, Installation of Sound and Communication System and Low Voltage Wiring, HVAC/Temperature Controls Installation Only)......$ 50.86 31.78
ELEC0812-014 06/01/2024
Rates Fringes
ELECTRICIAN (Excludes Alarm Installation, Installation of Sound and Communication
Systems, HVAC/Temperature Control Installation, and Low Voltage Wiring)..................$ 38.44 26.20
* ENGI0066-034 07/01/2024
Rates Fringes
POWER EQUIPMENT OPERATOR
Backhoe/Excavator/Trackhoe, Bobcat/Skid Steer/Skid Loader, Loader, Crane*, Bulldozer...................$ 36.87 21.32 Oiler.......................$ 29.70 21.32 Paver (Asphalt, Aggregate, and Concrete)...............$ 36.87 21.32 Roller......................$ 32.25 21.32
*Add to Crane rate:
Booms 101-150 jibs- Add $.75 Booms 151-200 jibs- Add $1.50 Booms 201-251 jibs- Add $2.25
IRON0003-013 06/01/2023
Rates Fringes
IRONWORKER (Ornamental, Reinforcing, Rigger, and Structural)......................$ 32.29 32.41
LABO0910-004 01/01/2025
Rates Fringes
LABORER (Concrete Worker)........$ 25.98 19.53
PAIN0041-001 05/01/2014
Rates Fringes
PAINTER (Spray Only).............$ 27.95 16.12
PAIN0057-001 06/01/2023
Rates Fringes
PAINTER: Brush and Roller Only...$ 30.56 23.72 PAINTER: Drywall Finishing/Taping Only............$ 32.39 23.26
PAIN0751-002 09/01/2023
Rates Fringes
GLAZIER..........................$ 25.40 25.47
PLAS0526-014 01/01/2025
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 31.97 21.35
PLUM0354-010 06/01/2024
Rates Fringes
PIPEFITTER (Industrial)..........$ 47.75 26.55
PLUM0354-011 06/01/2024
Rates Fringes
PLUMBER..........................$ 40.02 26.55
PLUM0354-020 06/01/2024
Rates Fringes
PIPEFITTER (Includes HVAC Pipe Installation and HVAC Unit Installation, Excludes Work on Industrial Sites)........$ 40.02 26.55
SFPA0669-004 04/01/2025
Rates Fringes
SPRINKLER FITTER (Fire Sprinklers)......................$ 49.75 28.96
SHEE0012-008 07/01/2022
Rates Fringes
SHEET METAL WORKER (Excludes HVAC Duct Installation)..........$ 39.50 30.79
* UAVG-PA-0001 01/01/2025
Rates Fringes
BRICKLAYER, including pointing, caulking cleaning and brick refractory work........$ 37.17 22.94
* UAVG-PA-0002 01/01/2025
Rates Fringes
LABORER: Mason Tender - Brick...$ 23.23 18.53
* UAVG-PA-0003 01/01/2025
Rates Fringes
MASON - STONE....................$ 34.00 22.63
* UAVG-PA-0004 01/01/2025
Rates Fringes
OPERATOR: Mechanic..............$ 36.53 22.01
SUPA2011-020 08/20/2014
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR - MECHANICAL (Duct, Pipe & Mechanical System Insulation)......................$ 33.62 18.79
LABORER: Common or General, Including Cement Mason Tending...$ 18.43 9.74
OPERATOR: Forklift, All Types....$ 23.69 12.97
PLASTERER........................$ 20.97 10.78
ROOFER...........................$ 27.00 12.19
SHEET METAL WORKER (HVAC Duct Installation Only)...............$ 30.58 24.04
TRUCK DRIVER: Dump Truck........$ 24.98 12.17
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
Union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage determination
b) an existing published wage determination
c) an initial WHD letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION"
3850-FM-BCW0471 7/2017 COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
BUREAU OF CLEAN WATER
DAVIS-BACON WAGE RATE COMPLIANCE FORM
Recipient Contact Information:
Recipient Name:
Galeton Borough Authority
Penn…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .