2026 Safe Routes to School: Awbrey Park Elementary Pedestrian Access Project
This is a specification document and bid package prepared by the City of Eugene's Engineering Division within the Public Works Department for an Invitation to Bid (ITB #14, Job #900647) for the 2026 Safe Routes to School: Awbrey Park Elementary Pedestrian Access Project. The project scope includes asphalt road widening, concrete traffic separator curb installation, pedestrian crossing modifications at Awbrey Park Elementary and Spring Creek Drive including concrete sidewalk and ramp construction, permanent landscaping repair, temporary pedestrian and traffic control, and temporary erosion control. The bid closing date is June 16, 2026, at 2:00 PM. Work shall not begin prior to June 16, 2026, and must be completed by August 31, 2026, excluding seeding and plant establishment periods. Inquiries regarding the plans, specifications, and contract documents should be directed to Daniel Koziol at (541) 501-0353 or dkoziol@eugene-or.gov. The specifications incorporate the 2024 Oregon Standard Specifications for Construction as amended, along with City of Eugene Standard Drawings and supplemental specifications specific to this project. The project involves coordination with multiple utility providers and service organizations including EWEB, Comcast, CenturyLink/Lumen, Northwest Natural Gas, AT&T, Zayo Fiber, Hunter Communications, Lane Transit District, Sanipac, Royal Refuse, Lane Apex, and the U.S. Postal Service, with required 5 business days' advance notification to affected parties.
No bid guaranty is required for this project. Liquidated damages for failure to complete work on time are assessed at $950.00 per work day. The contractor must maintain records of all subcontracts and payments to Minority/Women Business Enterprise (MWBE), Emerging Small Business (ESB), and Disadvantaged Business Enterprise (DBE) firms, submitting a Subcontractor Utilization Monthly Report within 20 days of receiving payment from the City. The project is subject to prevailing wage rate requirements as published by the Oregon Bureau of Labor and Industries, effective January 5, 2026, with amendments dated February 18 and April 5, 2026. Build America Buy America Act requirements apply, requiring final assembly of manufactured products within the United States for projects obligated after October 1, 2025. The project requires 35% asphalt binder replacement from recycled asphalt pavement (RAP) or recycled asphalt materials (RAM) in asphalt concrete production. Approximately 2,000 square feet of lawn seeding and 2,000 square feet of bark mulch are estimated, with landscape repair work billed on a lump sum basis. Progress payments will be retained at a percentage to be held by the City until final payment, with all retainage to be included in the final payment. Workers' compensation and employer's liability coverage is required as specified in the contract documents.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 900647 Bid Forms.pdf | ||
| 900647 Instructions to Bidders.pdf | ||
| 900647 plans.pdf | ||
| 900647 contract and bonds.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
C I T Y O F E U G E N E
2026 SAFE ROUTES TO SCHOOL
AWBREY PARK ELEMENTARY
PEDESTRIAN ACCESS PROJECT
BID NUMBER 14, JOB #900647
BID CLOSING: JUNE 16, 2026
2:00 P.M.
CONTRACT DOCUMENTS
AND
SPECIFICATIONS
CITY OF EUGENE
ENGINEERING DIVISION
PUBLIC WORKS DEPARTMENT
180 W. 8TH AVENUE, SUITE 200
EUGENE, OREGON 97401
(541) 682-5291
Standard Specifications – Updated 3/2026 Page 1
STANDARD SPECIFICATIONS AND STANDARD DRAWINGS
As of March 12, 2026 the 2024 Oregon Standard Specifications for Construction (Oregon Specifications) and the City of Eugene Standard Drawings, both as revised by Amendments #1, #2, #3 and #4, have been adopted as the Standard Specifications and Standard Drawings for the City of Eugene in accordance with City Code section 7.085. Amendments #1, #2, #3 and #4 are hereby made a part of the Standard Specifications and Standard Drawings of the City of Eugene as fully and completely as if it were set forth therein. The Standard Specifications, Standard Drawings and all Amendments may be examined on-line at https://www.eugene-or.gov/444.
SUPPLEMENTAL SPECIFICATIONS
The section, subsection and drawing numbers of the Supplemental Specifications correlate to the section and subsection numbers of the adopted Standard Specifications, which consist of the 2024 Oregon Standard Specifications and the General Conditions for Construction for the City of Eugene, and Standard Drawings.
00110.05(e) Reference to Websites
(ADD)
• American Traffic Safety Services Association (ATSSA) www.atssa.com
• City of Eugene Quality Assurance Program https://www.eugene-or.gov/444/Standard-Specifications-for-Construction
• City of Eugene Field Tested Materials Assurance Guide (FTMAG)
• City of Eugene Purchasing and City of Eugene Public Contracting Rules https://www.eugene-or.gov/108/Purchasing
• City of Eugene Standard Specifications for Construction
• City of Eugene Traffic Sign Manual https://www.eugene-or.gov/183/Traffic-Sign-Manual
• Equipment Watch https://equipmentwatch.com/
• ODOT Construction Section www.oregon.gov/odot/construction/pages/index.aspx
• ODOT Construction Section - Qualified Products List (QPL) www.oregon.gov/ODOT/Construction/Pages/Qualified-Products.aspx
• ODOT Estimating www.oregon.gov/ODOT/Business/Pages/Steel.aspx
• ODOT Traffic Control Plans Unit www.oregon.gov/ODOT/Engineering/Pages/Work-Zone.aspx http://www.atssa.com/ https://www.eugene-or.gov/444/Standard-Specifications-for-Construction https://www.eugene-or.gov/444/Standard-Specifications-for-Construction https://www.eugene-or.gov/108/Purchasing https://www.eugene-or.gov/444/Standard-Specifications-for-Construction https://www.eugene-or.gov/183/Traffic-Sign-Manual https://equipmentwatch.com/ http://www.oregon.gov/odot/construction/pages/index.aspx http://www.oregon.gov/ODOT/Construction/Pages/Qualified-Products.aspx http://www.oregon.gov/ODOT/Business/Pages/Steel.aspx http://www.oregon.gov/ODOT/Engineering/Pages/Work-Zone.aspx
Standard Specifications – Updated 3/2026 Page 2
• ODOT Traffic Standards www.oregon.gov/ODOT/Engineering/Pages/Signals.aspx
• OregonBuys https://oregonbuys.gov/bso
• Oregon Legislative Counsel www.oregonlegislature.gov/lc
• Oregon Secretary of State: State Archives https://sos.oregon.gov/archives/Pages/default.aspx
00110.10 Abbreviations
(ADD) PCD – Pedestrian Channelizing Device
00110.20 Definitions
(ADD) Pedestrian Accessible Route - An area for the use of pedestrians to navigate along sidewalks, driveways, curb ramps, crossings, and pedestrian facilities.
(ADD) Pedestrian Channelizing Device - Devices used for channelizing pedestrians along a temporary pedestrian accessible route.
00150.50 (c) Contractor’s Responsibilities
(REVISE) In the tenth bullet change OAR 952-001-0090(6) to OAR 952-001-0090(7)
00160.20 (d) Build America Buy America Act Requirements
(ADD) FHWA issued a final rule on January 14, 2025 amending FHWA's Buy America regulation to terminate FHWA's general waiver for manufactured products and establish Buy America requirements for manufactured products with respect to Federal-aid highway projects. https://www.federalregister.gov/documents/2025/01/14/2024- 31350/buy-americarequirements-for-manufactured-products
For manufactured products, the final assembly of the product shall occur within the United States for projects obligated on or after October 1, 2025. For projects obligated after October 1, 2026, the cost of the components of the product that are mined, produced or manufactured in the United States shall be more than 55 percent of the total cost of all components of the product.
00170.61 Industrial Accident Protection:
(REPLACE) (a) Workers’ Compensation with
00170.61(a) Workers’ Compensation and Employer’s Liability - The Contractor shall provide workers' compensation and employer’s liability coverage for on-the-job injuries as required by 00170.70(e).
http://www.oregon.gov/ODOT/Engineering/Pages/Signals.aspx https://oregonbuys.gov/bso http://www.oregonlegislature.gov/lc https://sos.oregon.gov/archives/Pages/default.aspx
2/14/2019
Supplemental MWBE, ESB, DBE Contract Provisions
1.0 Definitions
Directory of Certified Firms – A directory of firms certified as Minority/Women Business Enterprise (MWBE), Emerging Small Business (ESB), and Disadvantages Business Enterprise (DBE) is available electronically on the Office for Business Inclusions and Diversity (COBID) website http://www.oregon4biz.com/How-We-Can- Help/COBID/ (specific url is subject to change). The Directory is provided to the Contractor for use in identifying MWBE/ESB/DBE firms.
2.00 Contractor Payments to Subcontractors and Suppliers:
(a) Subcontractor-Related Records - The Contractor shall maintain records of all subcontracts or other agreements. Such records shall show the name and business address of each MWBE/ESB/DBE subcontractor or vendor and the total dollar amount actually paid to each MWBE/ESB/DBE subcontractor or vendor. Identify the COBID Certification status for each Subcontractor as shown in the Directory of Certified Firms.
(b) Paid Summary Reports - The Contractor shall submit the Subcontractor Utilization Monthly Report to the Agency certifying payments made to all of the following:
• All subcontractors
• DBE suppliers and service providers.
A copy of the Subcontractor Utilization Monthly Report is included in the Contract and a fillable PDF form is available on the Eugene Standard Specifications website (See 0110.05(e)). The Contractor shall submit the completed Subcontractor Utilization Monthly Report to the Agency via email to EIC@ci.eugene.or.us within 20 days of receipt of payment from the Agency for each month in which payments were made to each subcontractor, supplier or service provider. At the completion of the project, submit the form recapping the total amounts paid to each subcontractor, supplier, and service provider.
The Contractor shall require each subcontractor at every tier to comply with the requirement to submit the Subcontractor Utilization Monthly Report within 20 days of receipt of payment from its controlling contractor and provide a recap of the total amounts paid at the completion of the project or completion of their Work.
Forms shall be submitted to an email address provided to the Contractor at the Preconstruction Conference.
3.00 Remedies - Failure of any Contractor to meet the requirements cited in Section 2.00 constitutes a breach of contract for which the imposition of the following sanctions could occur:
• Temporarily withholding progress payments until the Contractor complies with these provisions through future performance.
• Permanently withholding payment for work already performed in a manner that constitutes a breach of contract.
• Suspension of work according to the Oregon Standard Specifications for Construction, subsections
00150.00 and 00180.70.
S u b c o n t r a c t o r
U t i l i z a t i o n
M o n t h l y
R e p o r t
C i t y o f
E u g e n e
F i n a n c e
P u r c h a s i n g
O f f i c e
W t h
A v e
S u i t e
E u g e n e
O
R
P h o n e
F a x r o j e c t
N a m
C o n t r a c t o r
C o m p a n y
N a m n t r a c t
N u m b e r
A g e n c y u s
T is m o n th ly r e p o rt i s re q u ir e d f o r a ll c o n tr a ct s.
T h e c o n tr a ct o r sh a ll c o m p le te a n d s u b m it t h is f o rm t o t h e C it y o f E u g e n e b y t h e th d a y f e v e ry m o n th to r e p o rt o n t h e p re v io u s m o n th
T h is i n fo rm a ti o n w il l b e u se d t o t ra ck u ti li z a ti o n o f ce rt if ie d D
/M W
E S B f ir m s w it in it y c o n tr a ct in g
U se t h e
S u b m it R e p o rt b u tt o n t o s u b m it t h e r e p o rt d ir e ct ly t o t h e E q u it y i n C o n tr a ct in g p ro g ra m
B y s u b m it t in g t is r m t h e c o n t r a c t o r c e r t if ie s t h a t t c u r a t ly p r e s e n t s t h e u t il iz a t io n o f t h e f ir m s l is t e d b e lo w r p e r f o r m a n c e o n t p o j e c t l e a s e l i s t a l l f i r m s r e g a r d l e s s o f s t a t u s
If r e s p a c q u ir e d p le a s e p r o v id e t h e a d d it io n a l in f o r m a t io n o n a s e c o n d s h e e
A s t h e
A u t h o r iz e d
R e p r e s e n t a t iv e I c e r t if y t h a t t h e in f o r m a t io n c o n t a in e d m p le t e a n d a c c u r a t e t o t h e b e s t o f m y k n o w le d g
Y t h o r i z e d
R e p r e s e n t a t iv t h o r i z e d
R e p r e s e n t a t iv e
T it le t h o r i z e d
R e p r e s e n t a t iv e
P h o n t h o r i z e d
R e p r e s e n t a t iv e
E m a i
N m e o f a l l
S u b c o n t r a c t o r x
I D m b
O
B r t i f i c a t i a t u h e c k a l l t h a t a p p ly a n d
I D t a l
C o n t r a c t
A m o u o u n t
P a i d
T h i s
P e r io o u n t
P a i d t o
D a t
C
O B
ID
r t if ie d b u s in e s s e s a n
C e r t if ic a t io n f o r s o c ia ll y a n d e c o n o m i c a a d v a n t a g e d b u s in e s s e e
S t a t e o f
O r e g o v a il a b le e e o f c h a r g e t h r o u g h t h e
C e r t if ic a t io n
O f f ic e f o r
B u s in e s s
In c lu s io n a n d
D iv e r s it y
C
O B
ID
P le a s e v is it w w w o r e g o n b iz c o m
H o w
W e C a n H e lp
C
O r m o r e in f
B r t i f i c a t i a t u s c h e c k a l l t h a t a p p ly a n d
I D
R p o r t
D a
M
W
V
D
V
D
V
D
V
D
V
D
V
D
V
D
V
D
V
D
C h ec k b o x i f su b m it ti n g F
IN
A
L p ro je ct r ep o rt
U p d at ed
/1
/2 http://www.oregon4biz.com/How-We-Can-Help/COBID
Special Provisions - Job #900647 Page 1
SPECIAL PROVISIONS FOR
2026 SAFE ROUTES TO SCHOOL:
AWBREY PARK ELEMENTARY PEDESTRIAN ACCESS PROJECT
PROJECT #900647
All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications and Supplemental Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.
00120.15 Examination of Work site and Solicitation Documents; Consideration of
Conditions to be Encountered
(ADD) Inquiries regarding the plans, specifications, and contract documents shall be made to: Daniel Koziol – (541) 501-0353 or dkoziol@eugene-or.gov
00120.40(e) Bid Guaranty
(REPLACE) A bid guaranty is not required for this project.
00140.00 Purpose of Contract
(ADD) 00140.00(a) Scope of Work
The scope of work for this contract includes:
• Asphalt road widening
• Concrete traffic separator curb installation
• Pedestrian crossing modifications at Awbrey Park Elementary and Spring
Creek Drive (concrete sidewalk and ramp)
• Permanent landscaping repair
• Temporary pedestrian and traffic control
• Temporary erosion control
00150.50 Cooperation with Utilities
(ADD) (f) Utility Information:
This Project is located within the Oregon Utility Notification Center area which is a Utilities notification system for notifying owners of Utilities about Work being performed in the vicinity of their facilities. The Utilities notification system telephone number is 811 or 1-800-332-2344.
Utility Contact Person's
Name and Phone Number(s)
1. EWEB Water & Steam Ryan Nossaman 541-685-7685
2. EWEB Electrical (Distribution Engineering Tech) Josh Simmons 541-685-7184
3. Comcast Brian Klopp 541-228-1829 Gabe Norbury 541-731-1498
Special Provisions - Job #900647 Page 2
4. CenturyLink/ Lumen/ Quantum
(Const. Project Administrator) Roman Hernandez 541-636-7074 (Cable Maint. Supervisor) Matt Seeley 503-580-7857
5. Northwest Natural Gas Tom Lepley 971-376-1293 Brian Brown 541-214-6639
6. AT&T Local Facilities Dayla Kerwin 213-688-4219
7. AT&T Long Distance Fiber Dan McGeogh 425-896-9830
8. Zayo Fiber David Miner 503-710-6296 Don Aichlamyr (RBC) 503-586-3493
9. Hunter Communications Jason Robinson 541-799-1132
00150.60 Construction Equipment Restrictions
(ADD) (d) Staging and Storing of Equipment and Materials
Obtain written permission from the City prior to storage of construction equipment, materials, supplies, temporary office or sanitary facilities outside of the construction zone but within City rights-of-way. Obtain written permission from affected private property owners prior to storage of construction equipment, materials, supplies, temporary office or sanitary facilities on private property.
Provide copies of written permission to the Engineer prior to using the Right-of- Way or accessing private property.
Erosion and pollution control measures, in addition to those shown on the plans, may be required in and around storage areas of materials and equipment in the right of way. Per City Code, erosion and pollution control measures are also required, as needed, in and around such storage areas on private property.
Parking regulations outside of the immediate construction zone will remain in effect for the project. Space Rental Permits may be purchased through City of Eugene Parking Services.
00170.07 Records Requirements
(c) Record Retention Period
(REPLACE) The subsection with the following:
The Contractor shall maintain the records and keep the records accessible and available at reasonable times and places for at least 6 years from the date of final payment under the Contract, or until the conclusion of all audits, litigation, administrative proceedings, disputes and claims arising out of or related to the Contract, whichever date is later.
00170.82(c) Protection and Restoration of Non-Agency Property and Facilities
(ADD) Protect all fences adjacent to the work. Remove and reinstall panels or portions of fences per 01050.49 as necessary to complete the work.
Special Provisions - Job #900647 Page 3
00180.40 Limitations of Operations
(a) In General –
(ADD)
• All excavation will be backfilled by means of landscaping, paving, or concrete
Work within 5 calendar days of excavation. This includes Work occurring during the winter months.
• All soil within proposed concrete Work areas shall be kept moist and protected from drying out until concrete is placed.
• Completion of a ramp and location includes all landscape preparation Work including, but not limited to: grading, removing forms, removing concrete waste, backfilling edges, lighting foundations and conduit in place, preparing and final grading lawn areas, adjusting or relocating irrigation system, applying a compost erosion blanket to disturbed areas, removing barricades and cones and installing bark mulch, seeding, or rock mulch. Completion also includes all Work associated with proposed illumination.
• At each crossing location, only one ramp may be constructed and completed at a time, unless otherwise approved by Engineer.
• Separate crossing locations may be worked on simultaneously.
• Prime contractor and sub-contractors shall coordinate Work to ensure they are not working at the same crossing, but on opposite sides of the crossing at once.
• Temporary Traffic Control phases for ramp construction may be completed in any order.
(ADD) 00180.40(c) Specific Limitations - Limitations of operations specified in these
Special Provisions include, but are not limited to, the following:
Limitations Subsection
Cooperation with Utilities ........................................... 00150.50 Contract Time ....................................................... 00180.50(h)
00180.41 Project Work Schedules
(ADD) After the paragraph that begins "One of the following Type…" add the following paragraph:
In addition to the "look ahead" Project Work schedule, a Type “A” schedule as detailed in the Standard Specifications is required on this Contract.
Recording of the elapse of Calendar Days will begin according to 00180.50(c).
00180.50(c) Beginning of Contract Time
(ADD) Work shall not begin prior to June 16, 2026.
Special Provisions - Job #900647 Page 4
00180.50 Contract Time to Complete Work
(Add) (h) Contract Time
Complete all Work to be done under the Contract, except for (seeding establishment) (and) plant establishment, not later than August 31st , 2026.
00180.85(b) Liquidated Damages
(ADD) The liquidated damages for failure to complete the Work on time required by
00180.50(h)(1) will be $950.00 per Work Day.
00195.50 Progress Payment and Retained Amounts
(c)(1) Cash, Alternate A
(REPLACE) The second paragraph that begins with “Except as otherwise provided…” with the following:
Except as otherwise provided, the Agency will hold the cash retainage withheld in a bank or other financial institution deemed appropriate by the Agency. If any interest is accrued on the withheld retainage, it shall accrue to the Agency.
Amounts retained will be included in the final payment made according to 00195.90, unless otherwise specified in the Contract.
00220.02 Public Safety and Mobility
(a) General Requirements
(ADD) The following bulleted item(s) to the end of this subsection:
• Maintain local traffic access at all times.
• Open full road width on weekends and holidays not scheduled for Work and all other non-work hours. Full road width shall also be open other days the Contractor is not Working.
• In areas where surfacing is altered or removed from crosswalks, marked or unmarked, or sidewalks, resurface the areas with asphalt concrete or concrete in accordance to ADA standards each day if the areas are open to pedestrian or bicycle traffic.
• No ramp or sidewalk location shall be closed for more than 4 Calendar Days without written approval by the Engineer.
• When construction requires the closure of a sidewalk or sidewalk ramp, set up traffic control according to TM844.
• A contiguous, ADA-compliant, pedestrian access route must be available through or alongside the work zone at all times. Construct temporary ramps as needed to bypass closed sidewalk ramps. A sidewalk or sidewalk ramp may be closed per Standard Drawings TM844 and TM844(A) if an appropriate route is available via the other three corners of the intersection.
• Before activating a modified traffic signal, revising lane usage, implementing new roadway geometry, or removing a "STOP" sign, protect traffic by installing "NEW TRAFFIC PATTERN AHEAD" (W23-2-48) signing according to 00222.10. Keep the signs in place for 14 calendar days after completing the modifications.
Special Provisions - Job #900647 Page 5
• When construction requires closure of a driveway, construct driveway one half at a time, plate driveway, or get verbal agreement from resident to close their driveway for no more than 7 calendar days
00220.02(b) Temporary Pedestrian Accessible Route Plan
(ADD) Furnish materials and construct temporary pedestrian ramps and routes as shown or needed in order to provide ADA-Compliant passage around sidewalk and driveway work within the project limits. Surfacing for the temporary pedestrian route shall meet Section 00740.
00220.03(c) Public Notice
(ADD) The following bulleted item(s) to the end of this subsection:
• Provide 5 business days prior notification to all residents affected by associated Work. Attempts shall be made to make face to face contact with residence to be affected by associated Work. In addition, provide written notice to residence.
• Provide 5 business days prior notification to Lane Transit District (LTD) Operations office, 541-682-6199 for all activities which will affect their operations. Notify LTD on a daily basis of specific Work activities, location, and schedule.
• Provide 5 business days prior notification to Sanipac Dispatch office, (541)
736-3618 for all activities which will affect their operations. Upon request the contractor shall also notify Sanipac on a daily basis of specific Work activities, location, and schedule.
• Provide 5 business days prior notification to Royal Refuse Dispatch office,
(541) 688-5622 for all activities which will affect their operations. Upon request the contractor shall also notify Royal Refuse on a daily basis of specific Work activities, location, and schedule.
• Provide 5 business days prior notification to Lane Apex Dispatch office, (541)
607-2042 for all activities which will affect their operations. Upon request the contractor shall also notify Lane Apex on a daily basis of specific Work activities, location, and schedule.
• Provide 5 business days prior notification to the U.S. Postal Service (USPS),
(541) 688-1657 for all activities which will affect their operations. Upon request the contractor shall also notify USPS on a daily basis of specific Work activities, location, and schedule.
00221.06 Traffic Control Plan
(DELETE) The first sentence.
(ADD) The Traffic Control Plan in the plan set has been approved by the Agency for use by the Contractor. It is the Contractor’s responsibility to modify this TCP as necessary to provide a complete TCP for the Contractor’s Work operation. To propose modifications to this plan, submit a detailed Work schedule showing
Special Provisions - Job #900647 Page 6 stage construction, along with the TCP, in writing 5 Work Days before the pre-construction conference for approval. If, as determined by the Engineer, the TCP does not meet these requirements the TCP will be rejected, and no adjustment of Contract Time will be allowed.
00221.88 Measurement Method “B”
(ADD) Temporary Pedestrian Access Routes will not be measured.
00221.98 Payment, Method “B”
(ADD) Temporary Pedestrian Access Routes are incidental to the Temporary Work
Zone Traffic Control, Complete pay item. No separate payment will be made for Temporary Pedestrian Access Routes including restoration of existing conditions due to Temporary Pedestrian Access Routes.
00222.15 Temporary Electrical Signs
(ADD) (d) Proximity Actuated Audible Information Devices
Use Empco Model 400 ADA Audible Device or approved equivalent.
00222.45 Temporary Electrical Signs
(ADD) (e) Proximity Actuated Audible Information Devices
A proximity actuated Audible Information Device shall be placed accompanying temporary pedestrian traffic control signs conveying the information that identifies the alternate pedestrian access route.
Mount at a height of 3 to 5 feet from the bottom of the sign to ground.
Provide a solar/battery power source.
Record a message for each phase of construction requiring Temporary
Pedestrian Access Routes that conveys the following details about the active phase:
• Brief announcement to get pedestrian’s attention.
• Current location of the pedestrian.
• Directions that do not require vision. Use cardinal directions to avoid ambiguity.
• Description of the TPAR the pedestrian must follow describing the number of blocks to be traversed or other landmarks to be passed.
• Description of conditions along the TPAR that may cause confusion such as major garage or retail driveways that could be mistaken as intersections.
• Duration of the active TPAR phase if an accurate duration is known.
Modify the recorded message when TPAR phases change or as directed by the
Inspector or Engineer.
Special Provisions - Job #900647 Page 7
Additional information about audible devices for TPAR can be found in the City’s draft Temporary Pedestrian Accessible Routes (TPAR) Manual: Access for People with Disabilities, available at the following link: https://www.eugene-or.gov/DocumentCenter/View/81758/Temporary-Pedestrian-Accessible-Routes- TPAR-Manual-Access-for-People-with-Disabilities?bidId=
00222.65 Portable Electrical Signs
(REPLACE) When directed, repair or replace sequential arrow signs, radar speed signs, proximity actuated audible signs, and PCMS that are damaged or destroyed before continuing Work that requires use of the signs
00222.80(b) Unit Basis
(ADD) “Proximity Actuated Audible Information Devices” will not be measured.
00280.00 Scope
(ADD) The City provided CSMP and permit described in this sub-section is attached to the Contract Documents and titled, “Annual Erosion Prevention Permit - Narrative Construction Site Management Plan 2026.” The Contractor shall keep a copy of the permit at the project site at all times during the Work.
00280.90 Payment
Pay Item Unit of Measurement
(MODIFY) (h) Concrete Washout Facility………………………….Lump Sum
(ADD) Item (h) includes maintaining, disposal, transporting and replacement of the
Concrete Washout Facility as needed.
00320.80 Measurement
(ADD) To the end of the bulleted list:
• Each - Under this method items will be measured on the unit basis by count of units removed.
00320.90 Payment
(ADD) The accepted quantities of tree removal will be paid for at the Contract unit price, per unit of measurement, for the item "Remove Tree".
00330.03(a) General
(ADD) The following to the end of the paragraph:
Earthwork is incidental to each associated Work item.
00641.10 (a) Materials
(DELETE) Shoulder Aggregate shall be either 1” – 0 or ¾” – 0 size as the Contractor elects.
Special Provisions - Job #900647 Page 8
(ADD) Aggregate Shoulder shall be ¾ open graded
(DELETE) Shoulder Aggregate…………………………………………...02640
00744.10 Aggregate
(ADD) The use of RAP or RAM materials used in the production of new ACP is required.
The percentage of asphalt binder replacement from RAP or RAM shall be 35.0% for base and wearing courses in ACP.
00744.10(b) Reclaimed Asphalt Pavement
(DELETE) The second sentence that begins, “No more than 30 percent…”
00744.10(c)(4) Allowable Percentages
(DELETE) In the first paragraph, the last sentence that begins, “Restrict the maximum percentage….”
(DELETE) The second paragraph that begins, “When RAS is used in conjunction with
RAP….”
00744.11 Asphalt Cement Additives
(a) Asphalt Cement
(REVISE) The grade of asphalt to be used for Level 2 mixes to PG 58-28.
00744.13(b) JMF Requirements
(ADD) To the table: Asphalt Binder Replacement, % = 35 for all Levels
00748.00 Scope
(REPLACE) Replace the paragraph with the following:
This Work consists of excavating and removing existing asphalt concrete surfaces, removing or reconditioning the existing Aggregate base as shown, and constructing new Subbases, bases, and asphalt concrete surfaces to the lines and grades shown or directed.
00748.43 Aggregates
(REPLACE) ”1 ½ inch – 0” with “aggregate”.
00759.13 Pre-Fabricated Traffic Separator
(ADD) Furnish a pre-fabricated traffic separator meeting the following specifications:
• Two drainage scuppers
• Rebar in the concrete for structural support
• 72” length
• Maximum 5” height
Special Provisions - Job #900647 Page 9
00759.80 Measurements
(ADD) Measurement of concrete traffic separator will be made as a 6’ section per each.
If smaller sections are used the payment will be as a proportional amount to the 6’ equivalent.
00759.90 Payments
Pay item Unit of Measurement
(ADD) (q) Concrete Traffic Separator…………………………….…………Foot (ADD) (r) Pre-Fabricated Traffic Concrete Traffic Separator………….…Each
Item (p) includes installation of concrete traffic separators which includes epoxy and anchorage to secure concrete to the existing asphalt pavement.
(ADD) Reverse curb and gutter will be paid as “Concrete Curb, Curb and Gutter”.
00840.90 Payment
(ADD) Removal of existing flexible delineators will be incidental to the Pre-Fabricated
Traffic Separator pay item. No separate payment will be made.
00850.41 Projects With Striping Plans
(ADD) Request pavement marking layout from the Inspector at least five (5) business days prior to planned pavement marking application. The Agency will require a minimum of three (3) business days after completion of top lift paving to layout pavement marking types and locations.
00867.90 Payment
Pay Item Unit of Measurement
(ADD) (v) Pavement Legend, Type B-HS: Off Street Bike/Ped Marking.…Each
00869.45 Installation
(ADD) The following bullet to the end of the subsection:
• Methyl Methacrylate, Sprayed – Apply according to 00865.45 along full height of curb face, back of curb, and along full width of top of curb. Apply each application of painted methyl methacrylate marking at a thickness of 60 mils.
00869.90 Payment
Pay Item Unit of Measurement
(ADD) (d) Yellow Curb Marking, Methyl Methacrylate.............................. Foot
(DELETE) Section 01030 Seeding and Section 01040 Planting
Special Provisions - Job #900647 Page 10
(ADD) Section 01035 Landscape Repair as follows:
Section 01035 – Landscape Repair
Description
01035.00 Scope - This work consists of small area repair of existing lawn or planted areas as shown on the Plans, typically under 150 square feet per location. This work addresses landscape repairs required due to construction of adjacent concrete sidewalk, accessible ramps, or stormwater/wastewater pipe repairs.
This work excludes planting work and irrigation system modifications or repairs.
01035.01 Contractor’s Qualifications - A valid Oregon Landscape Contractor’s license and a valid Oregon Landscape Business License are required.
All work of this section, with the exception of placing temporary compost and performing temporary seeding, shall be performed by a single firm specializing in landscape work. Supply and application of landscape materials (topsoil, mulch, seed) by automated equipment may be performed by others under the direction of the Landscape Contractor.
01035.02 Definitions:
Certified Seed - A grass or legume seed named variety that has been reviewed and accepted into the Oregon Certified Seed program. Currently certified seed is individually sold in bags with a blue-colored Oregon Certification Tag, thus the name commonly used for such seed is "blue tag stock".
Establishment Period - A period when planting work has been performed and initially accepted, and there is a Contract requirement to care for the planted areas in some way until the period ends.
Noxious Weed - All weed designated by the Oregon State Weed Board as injurious to public health, agriculture, recreation, wildlife, or all public or private property. The Oregon Department of Agriculture (ODA) will be the authority in determination of noxious weed species.
Pure Live Seed (PLS) - The amount of living seed in the total quantity of seed when non-viable seed or non-seed material is excluded.
Weed - A plant that is undesirable where it is growing.
Weed Free - For these Specifications, "Weed Free" is defined as the following maximum amount of living weeds per square yard:
• Zero "Type A" or "Type T" Noxious Weeds
• One "Type B" Noxious Weed
• One of each non-noxious weed listed in the Special Provisions
The ODA Noxious Weed Policy and Classification System lists Type "A", "B", and "T" Noxious Weeds.
Special Provisions - Job #900647 Page 11
01035.03 General - Ensure that work meets the following requirements:
(a) Existing Vegetation - Do not disturb existing desirable vegetation that is to remain or is designated for protection, unless approved by the Agency prior to construction.
(b) Weather Conditions – Work will not be allowed during the following conditions, unless otherwise approved:
• Cold weather - When air or ground temperatures are expected to be below 32 °F.
• Hot weather - When air or ground temperatures are expected to be above 88 °F.
• Wet weather - When the ground reaches saturation.
• Windy weather - When wind velocity exceeds 25 mph.
(c) Seeding Installation Dates – Perform this seeding during the dates shown below. If work done within the seeding dates does not provide coverage according to 01035.60, re-seed according to 01035.44 and as directed.
• Lawn Seeding - March 1 through May 15 and September 1 through October 15. If new seed areas are regularly watered, they can be seeded from March 1 through October 15.
For permanent seeding done outside the seeding dates, ensure that the coverage of live plants required by 01035.60 is achieved no later than 3 weeks into the next permanent seeding period.
If this coverage is not achieved, re-seed and re-fertilize areas of insufficient coverage according to the permanent seeding requirements, at no additional cost to the Agency.
01035.04 Coordination - Coordinate with other trades affecting and being affected by work under this Section. Coordinate the following elements with the Agency prior to construction:
(a) Submittals - Contractor shall provide the following submittals for the Engineer’s approval at least 30 days prior to installation:
• Topsoil -o Give the Agency notice of intent to use the specified source o Provide soil test results for each imported topsoil. Test Reports shall be no more than 12 months old.
o Provide access to the source for Agency inspection o Provide one 1 gallon representative soil sample of topsoil.
o Obtain approval of the source before excavation of topsoil begins.
• Seed - Provide a list of sources and certification information for all specified seeds.
Verify that all specified seed has been located and will be available for use on the Project.
• Mulch - Provide supplier source, product, and testing information for all required mulches. Test reports shall be no more than 12 months old.
(b) Notice for Inspections - Notify the Agency a minimum of 24 hours prior to each required inspection.
Special Provisions - Job #900647 Page 12
(c) Site Conditions - Ensure that the area is properly prepared prior to the start of the planting operation.
(d) Utility Use - Provide required water for seed and sod establishment at no additional cost to the Agency.
(e) Verification - Verify actual ground dimensions prior to construction. Notify the Agency of any discrepancies before beginning work.
(f) Required Inspections - At a minimum the following inspections will be required:
(1) Subgrade preparation and scarification - prior to placement of topsoil.
(2) Finish grade - prior to seeding, laying sod, or mulching.
Materials
01035.10 Topsoil - Furnish topsoil containing no substance detrimental to the growth of plants and that is free of plants designated by the Oregon Department of Agriculture as Type "A" or Type "B" weeds. Unsuitable topsoil, or topsoil placed by the Contractor without approval in areas to be planted, may be required to be replaced at no additional cost to the Agency.
Furnish submittals in accordance with 1035.04.
(a) Selected Topsoil - Furnish native topsoil from the required excavations meeting the requirements of 00330.10 or from other Agency-controlled lands. The general limits of topsoil materials will be indicated on the plans. The Agency will make the final determination of the areas where the most suitable materials exist. Furnish topsoil that is the fertile part of a soil profile commonly referred to as the "A" horizon, typically ranging in depth from 3 inches to 12 inches. Do not take material for topsoil from a depth greater than 12 inches below existing ground, unless approved.
Select only sources that are well-drained and, before stripping, have a healthy crop of vegetative growth. Remove and dispose of all heavy grass or other vegetation before taking materials from the source.
(b) Imported Topsoil - No imported topsoil shall be placed until the material and the source have been approved. At the Engineer’s discretion, a reinspection of the source or additional testing may be required when the quality of the imported topsoil changes significantly during placement. Furnish imported topsoil conforming to the following:
(1) Sandy Loam Topsoil – Furnish a consistent and well-blended mix which conforms to the following standards:
Clay 5% - 15% Sand 40% - 60% Silt 35% - 55% Organic Matter 2% - 4% pH Range 5.6 - 6.5
01035.11 Seed - Furnish seed meeting the following requirements:
(a) Label - Deliver all seed in standard, sealed containers. Label each container with the following:
Special Provisions - Job #900647 Page 13
• The kind and variety of each seed of 5 percent or more in a mixture, by weight. Be sure that seed mix labels include the words "mixture" or "mixed seed" when the seed is a mixture
• The country or state where the seed is grown
• The lot number or other lot identification
• The total percentage, by weight, of other crop seed
• The total percentage, by weight, of weed seed
• The total percentage, by weight, of inert matter
• Statement of "No Noxious (weed) Found"
• For each named seed:
• Percentage of germination
• Percentage of hard (non-living) seed, if more than 1 percent
• Percent of PLS for each kind of seed
• Percent and kind of other crop
• Month and year of seed test
• Net weight of contents
• Name and address of seed labeler or seller
• Origin for each seed (state or foreign country)
• If seed inoculant is used, the claimed date that inoculant effectiveness ends
• For treated seeds (if any):
• Statement that the seeds have been treated
• Name of all chemical used in the treatment
• Description process used in the treatment
• Warning statement for all residual chemicals used
• Net weight of each container
• For seeds listed as native, date and location of collection of source (first generation) seed
• For native seeds specified to be collected for direct use on a project, label containers with the date and location of collection sites for each seed species
(b) Quality - Furnish seed meeting the following requirements:
• The seed and labeling complies with Oregon Seed Law and Federal Seed Act.
• The seed has been tested within 18 months of the planting date.
• The seed is not sprouted, moldy, or showing evidence of having been wet or otherwise damaged.
• The seed is labeled as "Oregon Certified Seed" or the equivalent from another state when identified in the Special Provisions. Information about certified seed is available from County Extension Offices, Oregon State University, and the Oregon Department of Agriculture.
(c) Pure Live Seed - Obtain the amount of seed to apply by using the purity and germination percentages from the label on actual bags of seed to be used on the Project.
To calculate the amount of seed to be applied:
• Obtain the PLS factor - Multiply the seed label germination percentage times the seed label purity percentage.
• Divide the specified PLS rate by the PLS factor.
Example: A PLS seeding rate of 10 pounds per acre is specified. The seed label shows a purity of 80 percent and germination is 90 percent. After converting percentages to decimals, Special Provisions - Job #900647 Page 14
0.80 x 0.90 equals a factor of 0.72. The specified PLS rate, 10 pounds per acre, divided by the factor of 0.72 equals 13.88. In order to meet a PLS seeding rate of 10 pounds per acre, about 14 pounds of seed needs to be applied per acre. For a seed mix, make this calculation for every seed to obtain the total amount to be applied.
(d) Inspection - Each lot of seed is subject to inspection upon delivery to the Project. Seed that is not labeled or that does not conform to the Specifications will be rejected and shall be replaced at no additional cost to the Agency.
(e) Mixes - Furnish seed mixes that meet the labeling, quality and inspection requirements stated above. Submit all other proposed seed or seed mixes for consideration and receive written approval before seeding work begins. Replace rejected seed before planting.
(f) Types of Seed Mixes -
• Lawn Seeding - Seed mix shall be a 3-Way Perennial Rye blend. Submit supplier information for approval by Engineer.
01035.12 Fertilizer - Furnish standard, commercial grade fertilizer meeting the following requirements:
(a) General - Deliver fertilizers to the site in original, unopened containers bearing the manufacturer’s guaranteed analysis, including the percentage of total nitrogen, available phosphoric acid, and water- soluble potash (NPK) in the amounts specified. Label each container with a quality compliance certificate that includes the container mass (weight), the percentage of each ingredient, and the source of each component in the mixture. Ensure that each container is labeled with a Quality Compliance Certificate that meets the applicable requirements of Section 00165. All fertilizer products shall be uniform in composition, dry, free-flowing (if granular), or palletized and shall be approved by the Engineer prior to application.
Furnish fertilizer according to State and Federal regulations. Fertilizer is subject to testing by the State Department of Agriculture.
(b) Type of Fertilizer - Provide the following fertilizer:
• Lawn Seed Starter Fertilizer – Fertilizer containing a minimum percentage by weight of 16 percent nitrogen, 16 percent phosphoric acid and 16 percent potash.
• Lawn Seed Establishment Fertilizer – Ammonium sulfate.
01035.13 Mulch - Furnish mulch materials free of all weed or plant seeds and containing no substances detrimental to plant life. The kind of mulch materials acceptable for use will be shown on the plans, listed in the Special Provisions, or will be as approved. Furnish mulch meeting the following requirements:
(a) Seed Compost Mulch - Commercially manufactured fine or medium compost material meeting the requirements of Section 03020.
(b) Bark Mulch - Ground, shredded or broken particles from the bark of fir, pine or hemlock trees which is free of non-bark debris, harmful bacteria, disease spores, pests and substances toxic to plant growth. Provide mulch that is the standard trade size known as "medium fine mulch".
Special Provisions - Job #900647 Page 15
(c) Rock Mulch – ¾”-0 dense graded aggregate meeting the requirements of section 02630.
01035.15 Tackifier - If a fine compost is used for temporary stabilization or as seeding mulch, or a Seeding Compost Blanket is required, furnish a tackifier meeting the following requirements:
• Commercially produced tackifier containing no agent toxic to plant life.
• Either a liquid stabilizing emulsion or a dry powder.
• Contains tackifier and bacteria and fungi nutrient resource which is comprised of natural and biodegradable organic ingredients.
• Ingredients shall consist of a blend of organic sucrose, hydrophilic powder from natural sources, and seed meal from the genus Gossypium, or approved equal.
Construction
01035.40 General - Notify the Agency not less than 24 hours in advance of operations. Do not begin work until prepared slopes in an area have been approved by the Engineer.
Do not disturb or damage existing desirable vegetation to be left in place. Do not disturb areas previously seeded and mulched, with the exception of disturbances caused by stage construction. If previously seeded areas are disturbed, rework and reseed as directed, at no additional cost to the Agency.
All areas shall be Weed Free before seeding or mulching operations begin. Identify, kill, and remove weeds according to 01035.62(a-3).
01035.41 Topsoil:
(a) Subsoil Preparation - Ensure areas to received topsoil are free of all construction debris, concrete spoils, and concrete base rock. Grade and finish areas that are to receive topsoil, allowing for the specified amounts of topsoil. Scarify or rip subsoil that is not loose and friable according to 00330.48, and obtain approval from the Agency before placing topsoil. Do not work saturated or frozen subsoils.
(b) Hauling and Spreading - Haul and spread material without compacting the topsoil or areas where it is placed. Protect from damage any surrounding objects, pavement, structures and areas that are traveled, crossed, or mounted by equipment.
Smoothly spread the topsoil over the specified areas to the thickness, grades, and slopes shown on the plans.
01035.42 Area Preparation - Prepare designated areas as follows:
(a) Method "A" (Planting or Mulching Areas, Non-lawn) - Perform rough grading to within 3" of finish grade. Grade according to the profiles or contouring shown on Plans or as required to match surrounding grades and adjacent elevations. Hold grade 3" below adjacent walks, curbs, or turf areas, to allow for mulching. Spread the pulled-back soil evenly and do not create a mounded effect or low areas.
Finish grades by raking to a grade tolerance of plus or minus 1 inch, with a smooth and firm condition, and an even grade that is free of undulations or low areas that could create standing water.
Special Provisions - Job #900647 Page 16
(b) Method "C" (Seeded Lawn Areas) - Remove all vegetation, rocks larger than 2 inch diameter, clods, roots, sticks, debris, and other matter detrimental to the growth of seed or sod.
Fine-grade and roll areas to be seeded with a 200 pound water-filled roller to provide a fine-textured, smooth, firm surface, free of undulations, irregularities or low areas that could create standing water.
For areas to be seeded, grade so the final soil level, including any settled seed application mulch material, is ½” to 3/4” below edges of sidewalks, curbs, mowing strips, and utility covers.
Scarify soil surface to ¼” depth and a friable consistency for good soil seed contact.
Prior to completion of any seeding, re-grade ruts, footprints, washouts, or any other irregularities, and re-seed repaired areas as originally specified.
01035.43 Fertilizer Application:
Apply Lawn Starter Fertilizer at the rate of 1.5 lbs actual nitrogen per 1000 sq.ft. Apply the fertilizer either immediately prior to the seeding or during seeding if appropriate to the Seed Application method specified.
01035.44 Seed Application - The following application methods are acceptable for lawn seeding:
(a) Method 1: Hydroseeding, Fertilizing, Hydromulching, and Tacking - Apply seed, fertilizer, mulch, and tackifier as follows:
Use hydraulic equipment that continuously mixes and agitates the slurry and applies the mixture uniformly through a pressure-spray system providing a continuous, non-fluctuating delivery.
Ensure the equipment and application method provides a uniform distribution of the slurry.
Place seed, fertilizer, mulch, and tackifier in the hydroseeder tank no more than 30 minutes prior to application.
(1) Hydroseeding Operation - Perform hydroseeding according to the following:
a. One-step Operation - Apply materials in one step only for the following situations:
• When seeding in conjunction with erosion control matting. Apply seed, fertilizer, and tracer before installing matting.
• When treating small areas according to 01030.48(e). Double the amount of seed to compensate for seed suspended above soil by the mulch.
b. Two-step Operation - Except for the one-step method situations in 01030.48(a-1-a), use the two-step method for all hydroseeding operations:
1. Step 1 - Apply seed, fertilizer, and tracer. The seed and fertilizer may be applied separately or together. If hydromulch is used as a tracer, apply it at a rate of 500 pounds per acre.
2. Step 2 - Apply mulch and tackifier. Hydromulch, if used as a tracer in Step 1, will be included as part of the specified hydromulch rate specified in 01030.48(a-3).
(2) Seed - Thoroughly mix seeds when more than one kind is to be used.
Special Provisions - Job #900647 Page 17
(3) Mulch - Apply hydromulch at the following rates based on dry fiber weight:
a. Slopes Flatter Than 1V:2H - Apply cellulose fiber that includes a tackifier at a rate of 2,000 pounds per acre.
b. Slopes 1V:2H or Steeper - Apply cellulose fiber that includes a tackifier at a rate of 3,000 pounds per acre.
(4) Tackifier for Cellulose Fiber Applications - Use one of the following:
a. Liquid Stabilizer Emulsion - Dilute the emulsion with water at a rate of one part emulsion to 30 parts water. Apply the diluted mixture at the rate of 865 gallons per acre unless the manufacturer recommends a greater rate of application.
b. Dry Powder Tackifier - Apply at the following rates unless the manufacturer recommends a greater rate of application:
1. Slopes flatter Than 1V:2H - 60 pounds per acre mixed with hydromulch fibers at the rate specified.
2. Slopes of 1V:2H or Steeper - 100 pounds per acre mixed with hydromulch fibers at the rate specified.
(b) Method 5: Seeding Compost Mulch - Evenly apply seeding compost mulch, incorporating seed at a rate of 8 pounds per 1000 square feet and fertilizer at the specified rate, manually or with a pneumatic blower or other equipment that propels the material directly at the soil surface and achieves direct contact with the soil. Apply compost at a uniform depth of 1 inch. Apply at least 1 foot over the top of the slope or overlap the material into existing vegetation when applicable.
If manual application is selected uniformly apply the specified seed mix by hand or drop spreader at a rate of 4 pounds per 1000 square feet to the soil surface prior to mulch application.
As a secondary step apply additional seed at a rate of 4 pounds per 1000 square feet to the mulch surface after mulch installation. Lightly rake the seed into the compost blanket to a maximum depth of 1 inch.
(c) Method 7: Seeding Compost Blanket - Evenly apply seeding compost mulch, incorporating seed, fertilizer, and seeding compost blanket tackifier; at the specified rates with a pneumatic blower or other equipment that propels the material directly at the soil surface and achieves direct contact with the soil. Apply compost at a uniform depth of 1 inch. Apply at least 1 foot over the top of the slope or overlap the material into existing vegetation when applicable.
01035.45 Work Quality:
(a) Drift - Prevent drift and displacement of seed and fertilizer regardless of equipment and methods used. Use protective covering on structures and objects where coverage and stains would be objectionable and when tacking agents are used with mulch. Protect vehicles and people from drifting spray. If equipment and methods of application result in wasting material, make corrections to prevent waste.
(b) Displacement - Prevent seed, fertilizer, and mulch from falling or drifting onto areas occupied by rock base, rock shoulders, plant beds, or other areas where grass is detrimental.
Remove material that falls on plants, roadways, gravel shoulders, structures, and other surfaces where material is not specified.
Special Provisions - Job #900647 Page 18
(c) Damage - Prevent damage to prepared areas and to completed fertilizer, seed, and mulch work.