About this file

This is a USDOT Federal Highway Administration Grant Agreement between the U.S. Department of Transportation and the City of Detroit for the Detroit Safe Access to Transit (DSAT) program, executed on December 12, 2024. The project aims to implement safety improvements for transit riders accessing transfers between routes and stops through physical improvements and bus driver training over a five-year period. The grant-funded initiative includes three implementation phases: Base Phase (Preliminary Engineering) with a planned NEPA completion date of March 30, 2025; Option Phase 1 (Final Design) with draft plan completion by October 30, 2025 and final plan adoption by August 30, 2026; and Option Phase 2 (Construction) with construction start on April 30, 2026 and substantial completion by December 30, 2027. The project encompasses improvements at over 50 identified intersections, 24 planned Safer Bus Stops locations, and 32 planned Safer Transfers locations, with construction activities including curb bump-outs, sidewalk improvements, transit islands, signal improvements, lighting upgrades, ADA improvements, and bus driver training.

The total project cost is $31,000,000, comprising a federal SS4A grant of $24,800,000 and local match funding of $6,200,000. The federal obligation structure allocates $3,520,000 for Base Phase Preliminary Engineering, $1,280,000 for Option Phase 1 Final Design, and $20,000,000 for Option Phase 2 Construction, with contingencies of $2,000,000 included in the eligible project costs. The agreement requires compliance with the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (2 CFR Part 200), the National Environmental Policy Act, the Build America, Buy America Act, and all civil rights requirements including Title VI of the Civil Rights Act and the Americans with Disabilities Act. Recipients must expend SS4A funds within five years of grant agreement execution and provide performance measurements including fatalities, serious injuries, crash data by road user category, equity funding allocation, project costs, quantitative and qualitative project benefits, and lessons learned within 120 days after the period of performance ends on May 30, 2029.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Federal Award No.

693JJ32540170

2. Effective Date

See No. 16 Below

3. Assistance Listings No.

20.939

4. Award To City of Detroit 2 Woodward Ave. Suite 1026

Detroit, MI, 48226-3403

Unique Entity Id.: GS94M2VMNMJ3 TIN No.: 38-6004606

5. Sponsoring Office U.S. Department of Transportation Federal Highway Administration Office of Safety 1200 New Jersey Avenue, SE HSSA-1, Mail Drop E71-117 Washington, DC 20590

6. Period of Performance

Effective Date of Award – 5 years

7. Total Amount Federal Share:

Recipient Share:

Other Federal Funds:

Other Funds:

Total:

$24,800,000 $ 6,200,000 $0 $0 $31,000,000

8. Type of Agreement Grant

9. Authority Section 24112 of the Infrastructure Investment and Jobs Act (Pub. L. 117–58, November 15, 2021; also referred to as the “Bipartisan Infrastructure Law” or “BIL”)

10. Procurement Request No.

HSA240242PR

11. Federal Funds Obligated Base Phase – Preliminary Engineering: $3,520,000

12. Submit Payment Requests To See Article 5.

14. Description of the Project

13. Accounting and Appropriations Data

15X0174E50.0000.055SR30500.5592000000.41010.6106600

To implement safety improvements for transit riders to access transit transfers between routes and stops with physical improvements and bus driver training in an implementation project with demonstration elements.

RECIPIENT

15. Signature of Person Authorized to Sign

Signature Date Name: Ron Brundidge Title: Director – Department of Public Works

FEDERAL HIGHWAY ADMINISTRATION

16. Signature of Agreement Officer

Signature Date Name: David Villalobos Title: Agreement Office

Docusign Envelope ID: 45E77D95-D85D-45E3-93CD-9EAA7BBE3BFD

12/12/2024

U.S. DEPARTMENT OF TRANSPORTATION

GRANT AGREEMENT UNDER THE

FISCAL YEAR 2023 SAFE STREETS AND ROADS FOR ALL GRANT PROGRAM

This agreement is between the United States Department of Transportation’s (the “USDOT”) Federal Highway Administration (the “FHWA”) and the City of Detroit (the “Recipient”).

This agreement reflects the selection of the Recipient to receive a Safe Streets and Roads for All (“SS4A”) Grant for the Detroit Safe Access to Transit (DSAT).

The parties therefore agree to the following:

ARTICLE 1

GENERAL TERMS AND CONDITIONS

1.1 General Terms and Conditions.

(a) In this agreement, “General Terms and Conditions” means the content of the document titled “General Terms and Conditions Under the Fiscal Year 2023 Safe Streets and Roads for All (“SS4A”) Grant Program,”, which is available at https://www.transportation.gov/grants/ss4a/grant-agreements under “Fiscal Year 2023.”

Articles 7–30 are in the General Terms and Conditions. The General Terms and Conditions are part of this agreement.

(b) The Recipient acknowledges that it has knowledge of the General Terms and Conditions.

Recipient also states that it is required to comply with all applicable Federal laws and regulations including, but not limited to, the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (2 CFR part 200); National Environmental Policy Act (NEPA) (42 U.S.C. § 4321 et seq.); and Build America, Buy America Act (BIL, div. G §§ 70901-27).

(c) The Recipient acknowledges that the General Terms and Conditions impose obligations on the Recipient and that the Recipient’s non-compliance with the General Terms and Conditions may result in remedial action, termination of the SS4A Grant, disallowing costs incurred for the Project, requiring the Recipient to refund to the FHWA the SS4A Grant, and reporting the non-compliance in the Federal-government-wide integrity and performance system.

ARTICLE 2

APPLICATION, PROJECT, AND AWARD

2.1 Application.

Application Title: Detroit Safe Access to Transit (DSAT)

Application Date: 7/10/23

2.2 Award Amount.

SS4A Grant Amount: $24,800,000

2.3 Federal Obligation Information.

Federal Obligation Type: Multiple

Obligation Condition Table

Phase the Project Allocation of the SS4A Grant

Obligation Condition

Base Phase – Preliminary Engineering:

$3,520,000

Option Phase 1 – Final Design:

$1,280,000 The Recipient shall not expend any funds (Federal or non- Federal) for, seek reimbursement of eligible costs, or otherwise begin any part of the final design and construction of an Implementation Project unless and until:

(1) The requirements of the

National Environmental Policy Act (42 U.S.C. § 4321 et seq.) (“NEPA”), Section 106 of the National Historic Preservation Act (16 U.S.C. § 470f) (“NHPA”), and any other applicable environmental laws and regulations have been met; and

(2) FHWA, or a State with applicable NEPA Assignment authority, has

Obligation Condition Table

Phase the Project Allocation of the SS4A Grant

Obligation Condition approved the NEPA document for the Project and provided the Recipient with a written notice that the environmental review process is complete; and

(3) FHWA has obligated additional funds for this phase and notified the Recipient in writing that the Recipient may proceed to the next activity after NEPA approval, and the Recipient has acknowledged receipt in writing of FHWA’s notification. Recipient shall not proceed with any such activities until (2) and (3) as described in this section are met. Costs that are incurred before (2) and (3) as described in this section are met are not allowable costs under this agreement.

Extent of activities that are permissible before NEPA is complete are those activities constituting “preliminary design” as specified in FHWA Order 6640.1A.

Option Phase 2 – Construction:

$20,000,000 The Recipient shall not expend any funds (Federal or non- Federal) for, seek reimbursement of eligible costs, or otherwise begin any part of the construction or final design and construction of an Implementation Project unless and until:

(1) The requirements of the National Environmental Policy Act (42 U.S.C. § 4321 et seq.)

Obligation Condition Table

Phase the Project Allocation of the SS4A Grant

Obligation Condition

(“NEPA”), Section 106 of the National Historic Preservation Act (16 U.S.C. § 470f) (“NHPA”), and any other applicable environmental laws and regulations have been met;

and FHWA is provided a reasonable engineers cost estimate for the funds to be expended during the construction phase.

(2) FHWA, or a State with applicable NEPA Assignment authority, has approved the NEPA document for the Project and provided the Recipient with a written notice that the environmental review process is complete; and

(3) FHWA has obligated additional funds for this phase and notified the Recipient in writing that the Recipient may proceed to the next activity after NEPA approval, and the Recipient has acknowledged receipt in writing of FHWA’s notification. Recipient shall not proceed with any such activities until (2) and (3) as described in this section are met. Costs that are incurred before (2) and (3) as described in this section are met are not allowable costs under this agreement.

Extent of activities that are permissible before NEPA is complete are those activities constituting “preliminary design” as specified in FHWA Order 6640.1A.

2.4 Budget Period.

Base Phase Budget Period: See Item 6 of Page 1 for Effective Start Date – 3 Years After Effective Date of Award

Option Phase 1 Budget Period: Reserved

Option Phase 2 Budget Period: Reserved

2.5 Grant Designation.

Designation: Implementation

ARTICLE 3

SUMMARY PROJECT INFORMATION

3.1 Summary of Project’s Statement of Work.

Detroit Safe Access to Transit (DSAT) includes implementation, supplemental planning, and demonstration activities to address severe crashes that impact transit riders in Detroit. DSAT is a tailored, pinpointed safety program that advances Detroit’s Safe Streets for Detroit (SS4D) program and DDOT Reimagined to accelerate the City’s current efforts to reduce and eliminate severe crashes by 2050 and provide the high-quality transit service the Detroiters want and deserve. The project will utilize extensive coordination between the City of Detroit’s Department of Public Work (DPW), the Detroit Department of Transportation (DDOT), the Michigan Department of Transportation (MDOT), and Wayne County to realize the region’s safety goals.

The project will make first- and last-mile connections to transit safer and more accessible by implementing proven safety countermeasures at bus stops, providing safe driver training to bus operators, and updating Detroit’s Comprehensive Safety Action Plan and non-motorized plan. Over 50 intersections have been identified for improvement with more than five fatal or serious injury crashes and/or five crashes involving people walking or bicycling over the past five years. DSAT will include funding to equitably engage Detroiters and transit riders to ensure the proposed improvements meet residents’ expectations and support neighborhood goals. The project will also include robust evaluation of proposed activities to ensure they are effective toward addressing Detroit’s traffic safety issues.

The project will be completed in three phases as follows:

Base Phase: Preliminary Engineering: Base Phase will include Preliminary Engineering, NEPA documentation, and initial community engagement. Preliminary Engineering tasks will include conducting additional planning activities to assess existing conditions, crash analysis, NEPA documentation, and engineering design (30% and 60% design milestones).

Base Phase will also include a training for DDOT bus drivers and updates to the City’s non-motorized transportation plan and Comprehensive Safety Action Plan (CSAP). Base Phase will also include an evaluation component that will extend through the Option Phase 1 and Option Phase 2 timeline to determine the effectiveness of the safety countermeasures deployed. Community engagement activities will be included throughout Base Phase, Option Phase 1, and Option Phase 2.

Option Phase 1: Final Design: Final Design will include developing 90%, and the final contract documents for the design elements identified in the Preliminary Engineering activities. Design elements and safety countermeasures may include, but will not be limited to, targeted curb bump-outs, sidewalk improvements, transit islands, signal improvements, lighting upgrades, pavement markings, sidewalk widening, ADA improvements, and centerline hardening.

Option Phase 2: Construction: The Construction phase will include implementing the design solutions identified in Base Phase and Option Phase 1. Types of construction activities will include Safer Bus Stops (24 planned locations) and Safer Transfers (32 planned locations).

Option Phase 2 will include Capital Maintenance activities to monitor and replace or repair interventions deployed during the project period of performance. Construction Engineering & Inspection activities will also be included in Option Phase 2.

3.2 Project’s Estimated Schedule.

Demonstration Activity Schedule

Milestone Schedule Date Planned NEPA Completion Date: 3/30/25 Planned Construction Start Date 6/30/25 Planned Evaluation Period End Date: 12/30/28 Planned SS4A Final Report Date: 5/30/29

Supplemental Planning Schedule

Milestone Schedule Date Planned NEPA Completion Date: 3/30/25 Planned Draft Plan Completion Date: 10/30/25 Planned Final Plan Completion Date: 3/30/26 Planned Final Plan Adoption Date: 8/30/26

Implementation Schedule (Construction)

Milestone Schedule Date Planned NEPA Completion Date: 3/30/25 Planned Construction Start Date 4/30/26 Planned Construction Substantial Completion and Open to Public Use Date:

12/30/27

3.3 Project’s Estimated Costs.

(a) Eligible Project Costs

Eligible Project Costs

SS4A Grant Amount: $24,800,000

Other Federal Funds: $0

State Funds: $0

Local Funds: $6,200,000

In-Kind Match: $0

Other Funds: $0

Total Eligible Project Cost: $31,000,000

(b) Cost Classification Table – Planning and Demonstration Grants with demonstration activities and Implementation Grants Only

Cost Classification Total Costs

Non-SS4A Previously

Incurred Costs Eligible Costs

Architectural and engineering fees $6,000,000 $6,000,000 Project inspection fees $3,000,000 $3,000,000 Construction $20,000,000 $20,000,000 Contingencies $2,000,000 $2,000,000 Project Total $31,000,000 $31,000,000

(c) Indirect Costs

Indirect costs are allowable under this Agreement in accordance with 2 CFR part 200 and the Recipient’s approved Budget Application. In the event the Recipient’s indirect cost rate changes, the Recipient will notify FHWA of the planned adjustment and provide supporting documentation for such adjustment. This Indirect Cost provision does not operate to waive the limitations on Federal funding provided in this document. The Recipient’s indirect costs are allowable only insofar as they do not cause the Recipient to exceed the total obligated funding.

ARTICLE 4

RECIPIENT INFORMATION

4.1 Recipient Contact(s).

Erin McCargar City Planner City of Detroit – Department of Public Works 2 Woodward Ave, Suite 611, Detroit MI 48226

(313) 569-9764 Erin.McCargar@detroitmi.gov

Bashar Dimitry Program Analyst City of Detroit – Office of Development and Grants 313-224-4195 dimitryb@detroitmi.gov

4.2 Recipient Key Personnel.

Name Title or Position

Christina Peltier Deputy Director – Complete Streets

Bashar Dimitry Program Analyst

Victoria Jones Accountant

Erin McCargar City Planner

4.3 USDOT Project Contact(s).

Safe Streets and Roads for All Program Manager Federal Highway Administration Office of Safety HSSA-1, Mail Stop: E71-117 1200 New Jersey Avenue, S.E.

Washington, DC 20590 202-366-2822 SS4A.FHWA@dot.gov and

Agreement Officer (AO) Federal Highway Administration Office of Acquisition and Grants Management HCFA-42, Mail Stop E62-310

1200 New Jersey Avenue, S.E.

Washington, DC 20590 202-493-2402 HCFASS4A@dot.gov and

Division Administrator – Michigan Agreement Officer’s Representative (AOR) 315 West Allegan Street, Room 201 Lansing, MI 48933

(517) 377-1844 Michigan.FHWA@dot.gov and

Jami Trudelle Michigan Division Office Lead Point of Contact Safety Engineer 315 West Allegan Street, Room 201 Lansing, MI 48933

(517) 702-1859 Jami.Trudelle@dot.gov

ARTICLE 5

USDOT ADMINISTRATIVE INFORMATION

5.1 Office for Subaward and Contract Authorization.

USDOT Office for Subaward and Contract Authorization: FHWA Office of Acquisition and Grants Management

SUBAWARDS AND CONTRACTS APPROVAL

Note: See 2 CFR § 200.331, Subrecipient and contractor determinations, for definitions of subrecipient (who is awarded a subaward) versus contractor (who is awarded a contract).

Note: Recipients with a procurement system deemed approved and accepted by the Government or by the Agreement Officer (the “AO”) are exempt from the requirements of this clause. See 2 CFR 200.317 through 200.327.

In accordance with 2 CFR 200.308(f)(6), the recipient or subrecipient shall obtain prior written approval from the USDOT agreement officer for the subaward, if the subaward activities were not proposed in the application or approved in the Federal award. This provision is in accordance with 2 CFR 200.308(f)(6) and does not apply to procurement transactions for goods and services. Approval will be issued through written notification from the AO or a formal amendment to the Agreement.

The following subawards and contracts are currently approved under the Agreement by the AO. This list does not include supplies, material, equipment, or general support services which are exempt from the pre-approval requirements of this clause.

5.2 Reimbursement Requests

(a) The Recipient may request reimbursement of costs incurred within the budget period of this agreement if those costs do not exceed the amount of funds obligated and are allowable under the applicable cost provisions of 2 C.F.R. Part 200, Subpart E. The Recipient shall not request reimbursement more frequently than monthly.

(b) The Recipient shall use the DELPHI iSupplier System to submit requests for reimbursement to the payment office. When requesting reimbursement of costs incurred or credit for cost share incurred, the Recipient shall electronically submit supporting cost detail with the SF-270 (Request for Advance or Reimbursement) or SF-271 (Outlay Report and Request for Reimbursement for Construction Programs) to clearly document all costs incurred.

(c) The Recipient’s supporting cost detail shall include a detailed breakout of all costs incurred, including direct labor, indirect costs, other direct costs, travel, etc., and the Recipient shall identify the Federal share and the Recipient’s share of costs. If the Recipient does not provide sufficient detail in a request for reimbursement, the Agreement Officer’s Representative (the “AOR”) may withhold processing that request until the Recipient provides sufficient detail.

(d) The USDOT shall not reimburse costs unless the AOR reviews and approves the costs to ensure that progress on this agreement is sufficient to substantiate payment.

(e) In the rare instance the Recipient is unable to receive electronic funds transfers (EFT), payment by EFT would impose a hardship on the Recipient because of their inability to manage an account at a financial institution, and/or the Recipient is unable to use the DELPHI iSupplier System to submit their requests for disbursement, the FHWA may waive the requirement that the Recipient use the DELPHI iSupplier System. The Recipient shall contact the Division Office Lead Point of Contact for instructions on and requirements related to pursuing a waiver.

(f) The requirements set forth in these terms and conditions supersede previous financial invoicing requirements for Recipients.

ARTICLE 6

SPECIAL GRANT TERMS

6.1 SS4A funds must be expended within five years after the grant agreement is executed and DOT obligates the funds, which is the budget period end date in section 10.3 of the Terms and Conditions and section 2.4 in this agreement.

6.2. The Recipient demonstrates compliance with civil rights obligations and nondiscrimination laws, including Titles VI of the Civil Rights Act of 1964, the

Americans with Disabilities Act (ADA), and Section 504 of the Rehabilitation Act, and accompanying regulations. Recipients of Federal transportation funding will also be required to comply fully with regulations and guidance for the ADA, Title VI of the Civil Rights Act of 1964, Section 504 of the Rehabilitation Act of 1973, and all other civil rights requirements.

6.3 SS4A Funds will be allocated to the Recipient and made available to the Recipient in accordance with FHWA procedures.

6.4 The Recipient of a Planning and Demonstration Grant that involves a demonstration activity agrees to provide an assessment of each demonstration activity and update the existing Action Plan, which will incorporate the information gathered in the Action Plan’s list of projects or strategies and/or inform another part of the existing Action Plan. The Recipient also agrees that demonstration activities are temporary in nature and must be removed and/or ended following the conclusion of the project if the assessment of the demonstration activities does not affirm that the activities provide safety benefits.

6.5 The Recipient of an Implementation Grant agrees to update its Action Plan within two years of the date of this agreement to: align with all Comprehensive Safety Action Plan components in Table 1 of the SS4A FY 2023 NOFO corresponding with any “no” responses in the Self-Certification Eligibility Worksheet; ensure that the Action Plan’s safety focus includes all road users, including pedestrians, bicyclists, and motor vehicle safety; and ensure that the Action Plan was last updated not more than three years prior.

6.6 The Recipient acknowledges that it is required to conduct certain environmental analyses and to prepare and submit to FHWA, or State with applicable NEPA Assignment authority, documents required under NEPA, and other applicable environmental statutes and regulations before the Government will obligate funds for Option Phase 1 under this agreement and provide the Recipient with a written notice to proceed with Option Phase 1.

6.7 The Government’s execution of this agreement does not in any way constitute pre-approval or waiver of any of the regulations imposed upon Recipient under the applicable Federal rules, regulations and laws regarding SS4A projects undertaken in accordance with the terms and conditions of this agreement. The Recipient shall comply with all applicable Federal requirements before incurring any costs under this agreement.

6.8 There are no other special grant requirements.

ATTACHMENT A

PERFORMANCE MEASUREMENT INFORMATION

Study Area:

Baseline Measurement Date: 5/30/2025 Baseline Report Date: 7/30/2025

Table 1: Performance Measure Table

Measure Category and Description

Measurement Frequency and

Reporting Deadline

Safety Performance

[for Implementation Grants and Planning and

Demonstration Grants with demonstration activities]

Fatalities: Total annual fatalities in the project location(s)

Annually and within 120 days after the end of the period of performance

Safety Performance

[for Implementation Grants and Planning and

Demonstration Grants with demonstration activities]

Serious Injuries: Total annual serious injuries in the project location(s) [if available]

Annually and within 120 days after the end of the period of performance

Safety Performance

[for Implementation Grants and Planning and

Demonstration Grants with demonstration activities]

Crashes by Road User Category: Total annual crashes in the project location(s) broken out by types of roadway users involved (e.g., pedestrians, bicyclists, motorcyclist, passenger vehicle occupant, commercial vehicle occupant)

Annually and within 120 days after the end of the period of performance

Equity

[for all Grants]

Percent of Funds to Underserved Communities: Funding amount (of total project amount) benefitting underserved communities, as defined by USDOT

Within 120 days after the end of the period of performance

Costs

[for all Grants]

Project Costs: Quantification of the cost of each eligible project carried out using the grant

Within 120 days after the end of the period of performance

Measure Category and Description

Measurement Frequency and

Reporting Deadline

Outcomes and Benefits

[for Implementation Grants and Planning and

Demonstration Grants with demonstration activities]

Quantitative Project Benefits:

Quantification of evidence-based projects or strategies implemented (e.g., miles of sidewalks installed, number of pedestrian crossings upgraded, etc.)

Within 120 days after the end of the period of performance

Outcomes and Benefits

[for Implementation Grants and Planning and

Demonstration Grants with demonstration activities]

Qualitative Project Benefits: Qualitative description of evidence-based projects or strategies implemented (e.g., narrative descriptions, testimonials, high-quality before and after photos, etc.)

Within 120 days after the end of the period of performance

Outcomes and Benefits

[for Implementation Grants and Planning and

Demonstration Grants with demonstration activities]

Project Location(s): GIS/geo coordinate information identifying specific project location(s)

Within 120 days after the end of the period of performance

Lessons Learned and Recommendations

[for all Grants]

Lessons Learned and Recommendations:

Description of lessons learned and any recommendations relating to future projects or strategies to prevent death and serious injury on roads and streets.

Within 120 days after the end of the period of performance

ATTACHMENT B

CHANGES FROM APPLICATION

Describe all material differences between the scope, schedule, and budget described in the application and the scope, schedule, and budget described in Article 3. The purpose of Attachment B is to clearly and accurately document any differences in scope, schedule, and budget to establish the parties’ knowledge and acceptance of those differences. See Article 11 for the Statement of Work, Schedule, and Budget Changes. If there are no changes, please insert “N/A” in Section 3.3 of the table.

Scope: No changes from application.

Schedule: No changes from application.

Budget: The total project cost did not change from the application. Budget line items in the original SF-424C have been revised in the final SF-424C to accurately classify project line-item costs.

Updates included removing miscellaneous costs and moving some costs out of the construction line item to accurately list architectural and engineering fees and project inspection fees.

The table below provides a summary comparison of the project budget.

Fund Source Application Section 3.3

Previously Incurred Costs (Non-Eligible Project Costs) Federal Funds 0 0 0 0 Non-Federal Funds 0 0 0 0

Total Previously Incurred Costs 0 0 0 0 Future Eligible Project Costs

SS4AFunds 0 0 0 0 Other Federal Funds Non-Federal Funds 0 0 0 0

Total Future Eligible Project Costs

Total Project Costs 0 0 0 0

ATTACHMENT C

RACIAL EQUITY AND BARRIERS TO OPPORTUNITY

1. Efforts to Improve Racial Equity and Reduce Barriers to Opportunity.

The Recipient states that rows marked with “X” in the following table align with the application:

X A racial equity impact analysis has been completed for the Project. (Identify a report on that analysis or, if no report was produced, describe the analysis and its results in the supporting narrative below.)

X

The Recipient or a project partner has adopted an equity and inclusion program/plan or has otherwise instituted equity-focused policies related to project procurement, material sourcing, construction, inspection, hiring, or other activities designed to ensure racial equity in the overall delivery and implementation of the Project. (Identify the relevant programs, plans, or policies in the supporting narrative below.)

The Project includes physical-barrier-mitigating land bridges, caps, lids, linear parks, and multimodal mobility investments that either redress past barriers to opportunity or that proactively create new connections and opportunities for underserved communities that are underserved by transportation. (Identify the relevant investments in the supporting narrative below.)

X The Project includes new or improved walking, biking, and rolling access for individuals with disabilities, especially access that reverses the disproportional impacts of crashes on people of color and mitigates neighborhood bifurcation.

(Identify the new or improved access in the supporting narrative below.)

The Project includes new or improved freight access to underserved communities to increase access to goods and job opportunities for those underserved communities. (Identify the new or improved access in the supporting narrative below.)

X The Recipient has taken other actions related to the Project to improve racial equity and reduce barriers to opportunity, as described in the supporting narrative below.

The Recipient has not yet taken actions related to the Project to improve racial equity and reduce barriers to opportunity but intends to take relevant actions described in the supporting narrative below.

The Recipient has not taken actions related to the Project to improve racial equity and reduce barriers to opportunity and will not take those actions under this award.

2. Supporting Narrative.

• A racial equity impact analysis has been completed for the Project.

o Equitable access to the city’s transportation is one of the primary values of the Strategic Framework for Transportation and the Streets for People (SFP) transportation master plan. Building an understanding of where the city’s most vulnerable populations live is critical to developing strategies that address equity in a targeted manner. Basic demographic data was gathered to create an overall profile of the city, and specific equity measures were determined that would reflect populations that are most susceptible to being underserved by the existing transportation system. As documented in the SFP plan, and supporting whitepapers, the majority of Detroit’s population (82.2%) is Black, while white (7.8%) and Hispanic (6.8%) residents are the other prominent racial groups in the city. Given that minorities make up over 90% of the population, race was not included in the equity analysis to allow for a more targeted focus on other groups. However, the detailed equity analysis further evaluated the following additional factors through an intersectional lens with racial equity as the overarching umbrella: Seniors (65 and over), Youth (under 18), Disabled, Low-income, Zero-Car Households, and Population (density).

o The SFP plan also engaged thousands of Detroiters, who voiced strong support for reducing driving speed through street design and safety improvements. 84% of respondents were concerned about speeding and dangerous driving and 79% were supportive of street safety improvements that will reduce speed and increase safety. The production of the CSAP and the SS4D Program grant is the City’s direct response to Detroiters’ strong and unequivocal message for safer streets. SS4D will continue to include the community to get the most out of safety investments and mitigate the potential unintended consequences to underserved and marginalized people.

• The Recipient or a project partner has adopted an equity and inclusion program/plan or has otherwise instituted equity-focused policies related to project procurement, material sourcing, construction, inspection, hiring, or other activities designed to ensure racial equity in the overall delivery and implementation of the Project.

o The SFP plan identified Equity, Dignity, & Transparency as one of the core values toward improving access and mobility for Detroiters. Several of the recommendations and strategies in the plan outline actions the City will take to addressing racial disparities and inequity. The Comprehensive Safety Action Plan (CSAP) also established project prioritization criteria to assess and select all safety projects. Candidate projects will be scored for Safety Impact; Equity; and Sustainability, Climate Change, & Economic Competitiveness. A project can earn up to 15 points (out of 50) for Equity if it is an Equity Area (as defined in the SFP plan) and has prior community support. Almost all of the proposed HIN corridors for the SS4D project would receive the full 15 points for Equity.

o The procurement process will include DBE (Disadvantaged Business Enterprise) requirements as is standard with all City of Detroit contracts. The city has also adopted executive orders to provide additional points in the evaluation process that hire over 50% Detroiters and/or are Detroit based businesses. The City also has a Civil Rights, Equity and Inclusion Office, which will support the procurement process by ensuring that high-quality and good-paying job creation meets all free and fair choice union standards and will ensure that all state and federal prevailing wage standards are met.

• The Project includes new or improved walking, biking, and rolling access for individuals with disabilities, especially access that reverses the disproportional impacts of crashes on people of color and mitigates neighborhood bifurcation.

o The project aligns with the Streets for People Plan, which includes ACCESS FOR ALL, meaning the commitment to ensure easy mobility throughout the city, no matter age or ability. The SS4D also supports transit ridership and multi-modal shifts by closing gaps in the sidewalk network and improving ADA compliant connections to DDOT stops on HIN and commercial corridors.

• The Recipient has taken other actions related to the Project to improve racial equity and reduce barriers to opportunity, as described in the supporting narrative below.

o Throughout the SS4D implementation program, the City will follow Detroit’s Community Outreach Ordinance and the policies in SFP, tailoring engagement to project scope. As the size of the project rises, so will the public’s impact on design. Basic investments necessary to keep up state of good repair and improve safety will be driven by data, with information distributed to the public prior to construction. More transformative projects will involve closer community consultation, with impacts on final design.

ATTACHMENT D

CLIMATE CHANGE AND ENVIRONMENTAL JUSTICE IMPACTS

1. Consideration of Climate Change and Environmental Justice Impacts.

The Recipient states that rows marked with “X” in the following table align with the application:

X The Project directly supports a Local/Regional/State Climate Action Plan that results in lower greenhouse gas emissions. (Identify the plan in the supporting narrative below.)

X The Project directly supports a Local/Regional/State Equitable Development Plan that results in lower greenhouse gas emissions. (Identify the plan in the supporting narrative below.)

The Project directly supports a Local/Regional/State Energy Baseline Study that results in lower greenhouse gas emissions. (Identify the plan in the

The Recipient or a project partner used environmental justice tools, such as the EJScreen, to minimize adverse impacts of the Project on environmental justice communities. (Identify the tool(s) in the supporting narrative below.)

X The Project supports a modal shift in freight or passenger movement to reduce emissions or reduce induced travel demand. (Describe that shift in the

The Project utilizes demand management strategies to reduce congestion, induced travel demand, and greenhouse gas emissions. (Describe those strategies in the supporting narrative below.)

The Project incorporates electrification infrastructure, zero-emission vehicle infrastructure, or both. (Describe the incorporated infrastructure in the supporting narrative below.)

The Project supports the installation of electric vehicle charging stations.

(Describe that support in the supporting narrative below.)

The Project promotes energy efficiency. (Describe how in the supporting narrative below.)

The Project serves the renewable energy supply chain. (Describe how in the supporting narrative below.)

The Project improves disaster preparedness and resiliency (Describe how in the

The Project avoids adverse environmental impacts to air or water quality, wetlands, and endangered species, such as through reduction in Clean Air Act criteria pollutants and greenhouse gases, improved stormwater management, or improved habitat connectivity. (Describe how in the supporting narrative below.)

X The Project repairs existing dilapidated or idle infrastructure that is currently causing environmental harm. (Describe that infrastructure in the supporting narrative below.)

The Project supports or incorporates the construction of energy- and location-efficient buildings. (Describe how in the supporting narrative below.)

The Project includes recycling of materials, use of materials known to reduce or reverse carbon emissions, or both. (Describe the materials in the supporting narrative below.)

X The Recipient has taken other actions to consider climate change and environmental justice impacts of the Project, as described in the supporting narrative below.

The Recipient has not yet taken actions to consider climate change and environmental justice impacts of the Project but will take relevant actions described in the supporting narrative below.

The Recipient has not taken actions to consider climate change and environmental justice impacts of the Project and will not take those actions under this award.

2. Supporting Narrative.

• The Project directly supports a Local/Regional/State Climate Action Plan that results in lower greenhouse gas emissions.

o The project supports the 2022 Detroit Climate Action Strategy, which establishes a holistic approach to addressing racial equity, climate change, and to fulfill the requirements of the city’s Greenhouse Gas Inventory ordinance to reduce greenhouse gas emissions from city operations by 35% by the year 2024 and 100% by the year 2050.

• The Project directly supports a Local/Regional/State Equitable Development Plan that results in lower greenhouse gas emissions. (Identify the plan in the supporting narrative below.)

o The project supports the Streets for People Plan, which is rooted in (1) EQUITY, DIGNITY, AND TRANSPARENCY, including: Transparent planning and rigorous community engagement. (2) ACCESS FOR ALL, including easy mobility throughout the city, no matter age or ability. (3) ECONOMIC OPPORTUNITY: Access to jobs, empowerment, and neighborhood support.

• The Project supports a modal shift in freight or passenger movement to reduce emissions or reduce induced travel demand. The Project repairs existing dilapidated or idle infrastructure that is currently causing environmental harm.

o The program will also support transit ridership and multi-modal shifts by closing gaps in the sidewalk network and improving ADA-compliant connections to DDOT stops on HIN and commercial corridors where DDOT and community members identify opportunities. By doing this, we are making repairs to existing dilapidated or idle infrastructure that is currently causing environmental harm.

• The Recipient has taken other actions to consider climate change and environmental justice impacts of the Project, as described in the supporting narrative below.

o The CSAP also established project prioritization criteria to assess and select all safety projects. Candidate projects will be scored for Safety Impact; Equity;

and Sustainability, Climate Change, & Economic Competitiveness. A project can earn up to 10 points (out of 50) for Sustainability, Climate Change, & Economic Competitiveness if improvements support transit or transit access through safer crossings, enhanced transit amenities, or enhanced transit operations and if improvements increase tree canopy and/or decrease impermeable surfaces. Many of the proposed improvements for the SS4D project will score highly in this category and advance citywide goals to address climate change and environmental injustice.

o During the development of the CSAP, the project considered the equity impacts, including systemic racism through environmental injustices. As we continue community engagement, we will work to facilitate conversations about the environmental impact of the project.to understand the concerns residents may have.

ATTACHMENT E

LABOR AND WORKFORCE

1. Efforts to Support Good-Paying Jobs and Strong Labor Standards

The Recipient states that rows marked with “X” in the following table align with the application:

X The Recipient demonstrate, to the full extent possible consistent with the law, an effort to create good-paying jobs with the free and fair choice to join a union and incorporation of high labor standards. (Identify the relevant agreements and describe the scope of activities they cover in the supporting narrative below.)

X The Recipient or a project partner has adopted the use of local and economic hiring preferences in the overall delivery and implementation of the Project.

(Describe the relevant provisions in the supporting narrative below.)

The Recipient or a project partner has adopted the use of registered apprenticeships in the overall delivery and implementation of the Project.

(Describe the use of registered apprenticeship in the supporting narrative below.)

The Recipient or a project partner will provide training and placement programs for underrepresented workers in the overall delivery and implementation of the Project. (Describe the training programs in the

The Recipient or a project partner will support free and fair choice to join a union in the overall delivery and implementation of the Project by investing in workforce development services offered by labor-management training partnerships or setting expectations for contractors to develop labor-management training programs. (Describe the workforce development services offered by labor-management training partnerships in the supporting narrative below.)

X

The Recipient or a project partner will provide supportive services and cash assistance to address systemic barriers to employment to be able to participate and thrive in training and employment, including childcare, emergency cash assistance for items such as tools, work clothing, application fees and other costs of apprenticeship or required pre-employment training, transportation and travel to training and work sites, and services aimed at helping to retain underrepresented groups like mentoring, support groups, and peer networking.

(Describe the supportive services and/or cash assistance provided to trainees and employees in the supporting narrative below.)

X The Recipient or a project partner has documented agreements or ordinances in place to hire from certain workforce programs that serve underrepresented groups. (Identify the relevant agreements and describe the scope of activities they cover in the supporting narrative below.)

X

The Recipient or a project partner participates in a State/Regional/Local comprehensive plan to promote equal opportunity, including removing barriers to hire and preventing harassment on work sites, and that plan demonstrates action to create an inclusive environment with a commitment to equal opportunity, including:

a. affirmative efforts to remove barriers to equal employment opportunity above and beyond complying with Federal law;

b. proactive partnerships with the U.S. Department of Labor’s Office of Federal Contract Compliance Programs to promote compliance with EO 11246 Equal Employment Opportunity requirements and meet the requirements as outlined in the Notice of Funding Opportunity to make good faith efforts to meet the goals of 6.9 percent of construction project hours being performed by women and goals that vary based on geography for construction work hours and for work being performed by people of color;

c. no discriminatory use of criminal background screens and affirmative steps to recruit and include those with former justice involvement, in accordance with the Fair Chance Act and equal opportunity requirements;

d. efforts to prevent harassment based on race, color, religion, sex, sexual orientation, gender identity, and national origin;

e. training on anti-harassment and third-party reporting procedures covering employees and contractors; and

f. maintaining robust anti-retaliation measures covering employees and contractors.

(Describe the equal opportunity plan in the supporting narrative below.)

X The Recipient has taken other actions related to the Project to create good-paying jobs with the free and fair choice to join a union and incorporate strong labor standards. (Describe those actions in the supporting narrative below.)

The Recipient has not yet taken actions related to the Project to create good-paying jobs with the free and fair choice to join a union and incorporate strong labor standards but, before beginning construction of the project, will take relevant actions described in the supporting narrative below.

The Recipient has not taken actions related to the Project to improving good-paying jobs and strong labor standards and will not take those actions under this award.

2. Supporting Narrative.

The Office of Contracting and Procurement in the City has various contract provisions that protect the right to have free and fair choice to join a union and incorporation of high labor standards. In addition, City of Detroit works with the Detroit Employment Solutions Corporation (DESC) to create good-paying jobs with the free and fair choice to join a union and incorporation of high labor standards for all City contracts (including all grant-funded contracts). DESC is the City’s designated fiduciary agent to receive federal Workforce Opportunity and Innovation Act (WIOA) funds.

The City of Detroit has adopted a Community Benefits Ordinance that supports the use of local and economic hiring preferences in the overall delivery and implementation of the Project. This CBO is paired with EO 2021-02, which provides preference in the bid process for any construction contractor that employs 50% or more Detroiters and/or is a Detroit based business.

The DESC through the Detroit at Work (DAW), they are identifying digital barriers facing Detroiters seeking training in order to coordinate quick and effective solutions, as well as providing wrap around services like childcare and transportation to allow people to get to and from training programs, apprenticeships and jobs.

The City of Detroit Civil Rights, Inclusion & Opportunity Department (CRIO) was created via ordinance to ensure in part to ensure that underrepresented groups have access to employment and training opportunities. CRIO also promotes equal opportunity, including removing barriers to hire and preventing harassment on work sites through the Civil Rights Team. The Civil Rights Team investigates charges of discrimination, harassment and workplace violence for City of Detroit employees and citizens and fields complaints remotely and safely in person.

This helps ensure that all Detroiters have opportunities in the City’s various workforce development programs.

ATTACHMENT F

CRITICAL INFRASTRUCTURE SECURITY AND RESILIENCE

1. Efforts to strengthen the Security and Resilience of Critical Infrastructure against both Physical and Cyber Threats.

The Recipient states that rows marked with “X” in the following table are accurate:

X The Recipient demonstrates, prior to the signing of this agreement, effort to consider and address physical and cyber security risks relevant to the transportation mode and type and scale of the activities.

The Recipient appropriately considered and addressed physical and cyber security and resilience in the planning, design and oversight of the project, as determined by the Department and the Department of Homeland Security.

For projects in floodplains: The Recipient appropriately considered whether the project was upgraded consistent with the Federal Flood Risk Management Standard, to the extent consistent with current law, in Executive Order 14030, Climate-Related Financial Risk (86 FR 27967), and Executive Order 13690, Establishing a Federal Flood Risk Management Standard and a Process for Further Solicit and Considering Stakeholder Input (80 FR 6425).

2. Supporting Narrative.

The City of Detroit, through its Office of Contracting and Procurement, ensures that any and all technology related procurements meet all federal, state and locally required cyber security rules and regulations.

2024-12-13T09:31:20-0500
DAVID JAMES VILLALOBOS

File details come from the government source that posted it. Updated .