9-Attachment C - Voigt Park WC 23-24 24-25 Improvements - Bid Form (1).xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- Voigt Park Improvement
- Solicitation number
- 541913
- Issued by
- Wayne County, Detroit City, Michigan
About this file
This is a bid form for the Voigt Park Improvement project issued by the City of Detroit Office of Contracting and Procurement on behalf of the General Services Department. The project encompasses tree removal (6"-18" diameter trees), installation of 3,660 square feet of 4" concrete paths and pads with exposed aggregate finish, and placement of site amenities including two 6-foot benches and four trash receptacles. The contract is for a two-year term covering fiscal years 2023-24 and 2024-25. Bidders must submit pricing for base bid items, bid alternates, and unit rates for potential future work, including concrete sidewalk/pavement per detail, topsoil at 50 cubic yards, and topsoil seed/mulch installations.
The bid form requires contractors to provide fully burdened hourly labor rates for eight construction management positions, including Project Manager, Project Superintendent, Project Engineer, Project Estimator, Accounting, Clerical, Journeyman for General Contractor, and Laborer roles. All soft costs including site restoration, mobilization, layout and field survey, bonds, insurance, general conditions, and miscellaneous close-out work must be itemized by the bidder. An allowance of $5,000 is provided for additional services as a fixed fee. The spreadsheet contains calculated fields that automatically compute the total base bid upon completion of all cost entries. Bidders must include all fees, bonds, and insurance costs in their pricing and ensure unit price proposals are completed to avoid bid disqualification.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Sheet
| VOIGT PARK IMPROVEMENTS - Bid Form | |||||
| DO NOT EDIT ANY OF THE COLUMNS - THESE ARE CALCULATED FIELDS - PRICE SHEET TO BE ISSUED IN EXCEL | |||||
| BIDDING CONTRACTOR: | |||||
| BASE | BID COST | QTY | UNIT | All Fees/Bonds/Insurance/GC's listed under Soft Costs | |
| 1 | DEMOLITION | ||||
| Tree Removal, 6"-18" | $ - 0 | 2 | EA | ||
| 2 | CONCRETE PATHS AND PADS | sf | |||
| 4" Concrete w/ Exposed Aggregate Finish | $ - 0 | 3,660 | SF | ||
| 3 | PARK SITE AMENITIES | ||||
| 6' Bench | $ - 0 | 2 | EA | ||
| Trash Receptacles | $ - 0 | 4 | EA | ||
| SOFT COSTS | |||||
| 11 | Site Restoration | $ - 0 | |||
| 12 | Mobilization | $ - 0 | |||
| 13 | Layout & Field Survey | $ - 0 | |||
| 14 | Bonds & Insurance | $ - 0 | |||
| 15 | General Conditions | $ - 0 | Fixed duration cost. To include staffing | ||
| 16 | Miscellaneous & Close-Out Work | $ - 0 | |||
| ALLOWANCES | All fees/Bonds/Insurance to be calcualted for Allowances below under soft costs | ||||
| 17 | Additional Services | $ 5,000.00 | Fixed Fee | ||
| TOTAL BASE BID | ERROR:#REF! |
| BID ALTERNATES - ALTERNATES TO BE LISTED ON SCHEDULE FOR DURATION & ALL PRICING MUST INCLUDE ALL COSTS (FEE/GCS/BONDS/INSURANCE) | |
| L1 | 1. Alternate 1 - |
| L2 | 2. Alternate 2 - |
| L3 | |
| L4 |
BELOW USED FOR EVALUATION PURPOSES AND MUST BE COMPELTED
| UNIT RATES FOR FUTURE WORK WITHIN CONTRACT - FAILURE TO NOT INCLUDE UNIT PRICE CAN DISQUALIFY BID | |||
| Description | Value | Unit | |
| CONCRETE SIDEWALK/PAVEMENT | $ - 0 | PER DETAIL 4" CONCRETE PRICE - INCLUDES ALL LABOR/EQUIPMENT/MATERIALS | |
| TOPSOIL | $ - 0 | 50 CYD PRICE- INCLUDES ALL LABOR/EQUIPMENT/MATERIALS | |
| TOPSOIL SEED/MULCH | $ - 0 | PER DETAIL SF PRICE- INCLUDES ALL LABOR/EQUIPMENT/MATERIALS |
| Construction Manager's Project Personnel | *Hourly Rate* | *Provide Fully Burdened Labor Rates* | |
| Project Manager | $0.00 | ||
| Project Superintendent | $0.00 | ||
| Project Engineer | $0.00 | ||
| Project Estimator | $0.00 | ||
| Accounting | $0.00 | ||
| Clerical | $0.00 | ||
| Journeyman for General Contractor | $0.00 | ||
| Laborer | $0.00 | ||
| Others: | $0.00 |