8-Voigt Park General and Tech Specs - WC 23-24 24-25.pdf
PDF 1 MB Posted
- Attached to
- Voigt Park Improvement
- Solicitation number
- 541913
- Issued by
- Wayne County, Detroit City, Michigan
About this file
This document is a comprehensive General and Technical Specifications document prepared by the City of Detroit Office of Contracting and Procurement (OCP) on behalf of the General Services Department (GSD) for the Voigt Park Improvements project. The specifications cover a two-year contract period for removal of trees, installation of new walkways, site furnishings, concrete work, landscaping, site amenities including benches and picnic tables, drainage systems, and related park improvements. The work includes permits and inspections, topsoiling, sod lawn work, and miscellaneous site restoration activities. Key deliverables required from contractors include a complete list of major products within four business days of the Notice to Proceed, construction progress schedules within ten days, pre-construction conference attendance, project meeting participation (minimum monthly during construction), and submission of shop drawings, samples, certificates, and material specifications for all proposed products. The contractor must establish property lines, benchmarks, staking points, and grades at the contractor's expense, with all work completed in accordance with City of Detroit codes and applicable state regulations.
The specifications establish comprehensive quality assurance and submittal requirements, with all materials subject to testing and approval before site delivery unless expressly waived by the City Representative. The contractor assumes all risks related to soil conditions, existing utilities, and site protection, and is responsible for obtaining all necessary permits, trade permits, and paying all associated inspection fees and costs. Specific provisions include mandatory daily maintenance of temporary facilities, erosion control measures compliant with Michigan Department of Environmental Quality standards, dewatering at the contractor's sole expense regardless of duration or extent, and a one-year warranty period with settlement correction obligations extending five years for sewer line work. The contractor must employ a full-time field superintendent, maintain a testing laboratory for material verification, and provide comprehensive operation and maintenance data, as-built drawings, and equipment warranties upon project completion. All costs for security, fencing, temporary facilities, traffic maintenance, and site restoration resulting from construction activities are included in the bid proposal with no additional compensation permitted for unforeseen conditions or weather-related impacts.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Detroit
Office of Contracting and Procurement (OCP)
Voigt Park – Improvements Request for Proposal
GENERAL AND TECHNICAL
SPECIFICATIONS
GENERAL REQUIREMENTS AND TECHNICAL
SPECIFICATIONS
TABLE OF CONTENTS
DIVISION ONE: GENERAL REQUIREMENTS
GS General Specifications
1. Specifications GS 1
2. Publications by Reference GS 1-3
3. Abbreviations GS 3
4. Materials by Reference GS 3
5. Equipment GS 3-4
6. Information by Contractor GS 4-6
7. Samples, Certifications, and Tests GS 6-8
8. Materials, Delivery, Storage, and Handling GS 8-9
9. Water for Construction GS 9
10. Temporary Power and Light GS 9
11. Hours of Work GS 9-10
12. Progress Schedule GS 10
13. Working Area and Maintenance of Traffic GS 11
14. Signs + Attachment A (Project Sign) GS 12
15. Field Office GS 12
16. Temporary Construction Facilities, Controls & Fencing GS 13-14
17. Cleanliness of Work and Streets GS 14
18. Sanitary Requirements GS 15
19. First Aid GS 15
20. Barricades and Lights GS 15
21. Cleanout of Manholes, and Catch Basins GS 15
22. Temporary Enclosures GS 15
23. Temporary Heat GS 16
24. Final Cleaning and Building GS 16
25. Equipment Startup and Testing GS 16-17
26. Soil Conditions GS 17
27. Ventilation GS 17
28. Existing Utilities GS 17-18
29. Maintenance Sewage Flow and Drainage GS 18-19
30. Detroit Water and Sewerage Department Stop Boxes and Gate Wells GS 19
31. Name and Date GS 19
32. Existing Structures GS 19
33. Safety Precautions GS 19-20
34. Pumping and Drainage GS 20
35. Connections to Existing Sewers GS 20
36. Provisions for the Handicapped GS 21
37. Government Regulations GS 21
38. Erosion Control Program GS 21
39. Code Requirements GS 21
40. Existing Landscaping GS 21
41. Historical Specimens GS 21
01000 Summary of Work………………………………………………………………. 01000-1-01000-6
01200 Project Meetings & Coordination……………………………………………….. 01200-1-01200-2
01300 Submittals……………………………………………………………………….. 01300-1-01300-5
01400 Construction Staking……………………………………………………………. 01400-1-01400-3
01700 Project Close Out………………………………………….…………………….. 01700-1-01700-3
DIVISION TWO: TECHNICAL SPECIFICATIONS
02100 Clearing & Demolition …….………………………………………….……….… 02100-1-02100-2
02200 Earthwork………………………………………………………………………… 02200-1-02200-10
02235 Cu-Structural Soil……….………………………………………………………...02235-1-02235-12
02700 Site Drainage and Utilities………………………………………………………...02200-1-02200-5
02830 Site Amenities………...…….………………………………………………….….02830-1-02830-6
02900 Landscaping Work…………………………………………..……………………..02900-1-02900-19
02920 Turf Restoration Blanket & Maint……………………………………..…………..02920-1-02920-6
02931 Lawn Hydro-Seeding & Landscape Maint. Work………………………..………..02931-1-02931-8
02932 Site Restoration……………………………………………………………………02932-1-02932-7
02990 Landscape Guarantee Maintenance Period…..………………………..…………..02990-1-02990-8
03300 Concrete Work………………………………………………………………….…03300-1-03300-10
GENERAL SPECIFICATIONS 1
1. SPECIFICATIONS
Specifications are divided into two sections - General Specifications and Detailed Specifications.
A. GENERAL SPECIFICATIONS
Cover matters generally applicable to more than one or all phases of the work.
B. DETAILED SPECIFICATIONS
The detailed specifications are subdivided into divisions with each division pertaining to a particular phase of work. It is not the intent, nor shall it be so construed, that work included in any one division must be performed by a particular trade or by subcontract. Likewise, the work to be performed by a particular trade is not necessarily restricted to that of any one division. Any item mentioned under any heading must be supplied even though it is not called for again under the heading for the respective work.
Specific requirements stated in various divisions of the detailed specifications as though applicable to a single item or one unit of work shall also apply to all additional items or units required by the contract and shall not be interpreted as designating that only a single item or one unit is required.
2. PUBLICATIONS BY REFERENCE
Where reference is made in the detailed specifications to publications, such as sspecificationsor standards of a technical society, trade association, governmental agency and the like, it is understood and agreed that such publications are part of the detailed specifications, to the extent indicated by the specific references thereto, as though fully repeated therein.
In interpreting any referenced publication, terms such as “Purchaser”, “Owner”, etc.
shall be understood to mean the City of Detroit; terms such as “Manufacturer”, “Supplier” and the like shall mean the contractor, or their material vendors. It is also understood and agreed that the use of any referenced publication shall not necessarily be restricted to matters, which may be named in its title but shall be used or applied as set forth in the detailed specifications.
A copy of each referenced publication is on file in the City Engineers Office and is available for inspection by the contractor. However, it is assumed that a contractor experienced in the type of work involved will have his/her own source of access to the referenced publications.
In certain divisions of the detailed specifications, the publications pertaining to the particular divisions are individually listed in this section under the article heading “Abbreviations & Materials by Reference” publisher, full title, basic designation, and specific issue identification. Thereafter, each publication, where used will be referred to only by publisher and basic designation. The abbreviation used elsewhere to denote; the respective publisher is shown in parenthesis following the full name in the listing. Where only the publisher’s abbreviation and basic code number is used alone, with a designated material or test method, it shall be understood that such referenced publication establishes the requirement to be met, complied with or followed, as for examples:
GENERAL SPECIFICATIONS 2
A. MATERIALS
“Cement – A.S.T.M. C 150, Type I” shall mean and be interpreted as though written – “The cement shall conform to the requirements of A.S.T.M.
Specifications for Portland Cement, C 150-65, Type I.”
or Gas pipe – Fed. Spec. WW-P-406b, Weight A, Class 1” as written –
“Gas pipe shall conform to the requirements of Federal Specifications Pipe, Steel (Seamless and Welded) (for Ordinary Use), June 26, 1961.”
or “Manhole frames and covers shall be gray iron castings, A.S.T.M. A48, Class No. 30B.” as written – Manhole frames and covers shall be gray iron castings conforming to the requirements of A.S.T.M. Specification for Gray Iron Castings, A 48-64, Class No. 30B.”
B. TEST METHODS
“Aggregate Sampling – A.S.T.M. D75” shall mean and be interpreted as though written – “The aggregates shall be sampled in accordance with the requirements of A.S.T.M. Method of Sampling Stone, Slag, Gravel, Sand, and Stone Block for Use as Highway Materials, D 75-59.”
or “Painting Materials Testing – Fed. Stand. 141” as though written –
“Painting materials shall be inspected and tested in accordance with the requirements of Federal Standard 14 (Change 3), Paint, Varnish, Lacquer, and Materials: Methods of Inspection, Sampling, and Testing, March 18, 1963.”
C. PROCEDURE
“Surfaces of ferrous materials prior to being painted shall be cleaned and prepared – Fed. Spec. TT-C-490” shall mean and be interpreted as though written – “Surfaces of ferrous material prior to being painted shall be cleaned and prepared in accordance with the requirements of Federal Specification – “ Cleaning Methods and Pretreatment of Ferrous Surfaces for Organic Coatings, March 30, 1961, as amended to date.”
In Certain divisions of the Detailed Specifications, a referenced publication may be used alone with a designated material or test method even though not previously listed in Part I under “Referenced Publication”. In title, basic designation, and specific identification. When so used, it is understood to have the same intent and meaning as above provided.
3. ABBREVIATIONS
The following listed letters and abbreviations, while all do not necessarily appear elsewhere in this Contract, when used, shall mean and the interpreted as follows:
A.A.N. - American Association of Nurserymen A.N.S.I. - American National Standards Institute A.R.E.A. - American Railway Engineering Association A.S.C.E. - American Society of Civil Engineers A.S.H.R.A.E. - American Society of Heating, Refrigerating and Air
Conditioning Engineers, Inc.
GENERAL SPECIFICATIONS 3
A.A.S.H.O. - American Association of State Highway Officials A.S.L.A. - American Society of Landscape Architects A.S.M.E. - American Society of Mechanical Engineers A.S.T.M. - American Society for Testing and Materials A.W.G - - American Wire Gauge A.W.W.A. - American Water Works Association
D - B.S.E.D. - Detroit - Buildings & Safety Engineering Department D - D.O.T. - Detroit - Department of Transportation DFD - Detroit Fire Department DPD - Detroit Police Department DPW - Department of Public Works DRD - Detroit Recreation Department DWSD - Detroit Water & Sewerage Department GSD - General Services Department PLD - Public Lighting Department
I.E.E.E. - Institute of Electrical and Electronics Engineers M - DEQ - Michigan - Dept. of Environmental Quality M - DNR - Michigan - Dept. of Natural Resources M - D.O.T - Michigan - Department of Transportation M - OSHA - Michigan - Occupational, Safety, & Health Admin.
N.E.C. - National Electrical Code N.E.M.A. - National Electrical Manufacturers Association N.P.S.I. - National Playground Safety Institute
“Building Code”- BOAC Basic Plumbing Code – 1970, and Accumulative
Supplement – 1973, as amended by City of Detroit Ordinance 62-H effective October 20, 1975.
“Plumbing Code”-BOAC Basic Plumbing Code – 1970, and Accumulative Supplement, and as amended to date – 1973, as amended by City of Detroit Ordinance 39-H effective May 16, 1975, and as amended to date
“Fed. Spec.” - Federal Specification issued by the Federal Supply Service, General Services Administration, U.S. Government.
SE & SC Soil Erosion & Sedimentation Control (GSD Permit)
4. MATERIALS BY REFERENCE
A material included in more than one division of the detailed specifications will, in general, be specified in detail in only one of the divisions. In the other division containing the detailed specifications for the same material, and such detailed specifications shall be considered as much a part of the other divisions as if they were therein repeated in full.
5. EQUIPMENT
It is the intent of the specifications that all equipment be of reliable make and of a design that has proven satisfactory through successful use under comparable conditions, and that no experimental or untried type of equipment, machinery, or apparatus be furnished.
GENERAL SPECIFICATIONS 4
All items of equipment of standard design and manufacturer shall be latest stock catalog products of a reputable manufacturer, where two or more items of the same kind or type of equipment are required they shall be the products of a single manufacturer.
The contractor shall provide proper equipment and personnel at the site to unload and handle materials and equipment in a manner to avoid damage. Materials and equipment shall be handled only at designated lifting points by methods to prevent bending or overstressing.
6. INFORMATION BY CONTRACTOR
Information to be submitted by the Contractor shall be pursuant to the requirements as stated within the Contract Documents, relative to materials and equipment which he proposes to furnish and the manner and arrangements for incorporating them in the work, shall be submitted as herein prescribed.
A. PRODUCTS LIST
Within four (4) business days of request or issuance of the project Notice To Proceed, the Contractor shall submit a complete list of major products proposed to be used, with the name of the manufacturer and the installing subcontractor, if applicable, to the City.
B. CONTRACTOR'S PRODUCT OPTIONS & SHOP DRAWINGS
For products specified only by reference or performance standard, the contractor shall select any product meeting that standard.
For products specified by naming several products or manufacturer's, the contractor shall select any one of the products or manufacturers named, which complies with the specifications.
For products specified by naming one or more products or manufacturers and "or equal," the contractor must submit their Substitution Request Form for any product or manufacturer not specifically named. For products specified by naming only one product and manufacturer, there is no option.
Shop drawings, in general, will be required to show shop and field fabrication, assembly or erection, and arrangement of the work. Specifications shall be furnished to supplement the shop drawings when, in the judgement of the City Representative, such are required or when shop drawings are not required
For such materials, equipment, or arrangements, which are standard or stock catalog items, the City Representative may waive the requirements of special drawings and specifications. In such instances, the contractor shall furnish full information in the way of lists, cuts, samples, or otherwise, which the City Representative determines as adequate and sufficient to clearly show what the contractor proposes to furnish.
C. MANUFACTURER’S INSTRUCTIONS
When the Contract Documents require that installation of work shall comply with manufacturer's instructions, the contractor shall obtain and distribute
GENERAL SPECIFICATIONS 5
copies of such instructions to parties involved in the installation, including two (2) copies to the City Representative. The contractor shall handle, install, connect, clean, condition and adjust products in strict accordance with such instructions and in conformity with specified requirements. Should project conditions or specified requirements conflict with manufacturer's instructions;
consult with City Representative for further instructions.
D. CHECKING & APPROVAL BY CONTRACTOR
A stamp of approval or other positive means acceptable to the City Representative shall indicate all information, including that prepared by others for the contractor, before being submitted to the City Representative shall first be checked and approved by the contractor and evidence of such approval.
Information submitted without such evidence of approval by the contractor will not be considered and will be returned to the contractor for proper approval.
The contractor shall thoroughly check the information in regards to measurements, sizes, materials, and details for conformity with the detailed contract requirements. Information found incorrect, incomplete, or otherwise in error shall be corrected before submission to the City Representative.
1. Submission:
A minimum of four copies of the information shall be submitted to the City Representative. In general, the information shall be submitted in order in which the materials, equipment, or arrangements will be needed on the work, without necessarily waiting for the completion of all information before submitting part of it for approval. However, as far as practicable, all information of any particular or related parts of the work shall be submitted at the same time so that the City Representative may intelligently judge the acceptability of the proposed materials, equipment, or arrangements. The City Representative shall have the right to decline to check any information, which in his opinion, must be judged in conjunction with related information until such related information has been submitted.
If any of the information is in variance with the detailed contract requirements because of standard shop practice or other reason, the contractor shall make specific mention of and give the reasons for such variation in his/her letter of transmittal in order that, if acceptable, suitable action may be taken for proper adjustment: otherwise the contractor will not be relieved of his/her responsibility for executing the work in strict accordance with the detailed contract requirements even though the information has been approved by the City Representative. It shall not be implied or interpreted that the provision of this paragraph permits or invites general variance from the detailed requirements of the contract.
2. City Representative’s Check:
The City Representative will check the information submitted for compliance with the contract requirements. If any of the information submitted by the contractor is found by the City Representative to not meet the contract requirements, the City Representative will return one copy, marked with the notations, corrections, or changes that are required. Returned, unapproved
GENERAL SPECIFICATIONS 6
information shall be promptly revised or corrected by the contractor and resubmitted to the City Representative.
3. City Representative’s Approval:
When the information is found to meet the contract requirements, the City Representative will place his approval on each copy and return three copies bearing his approval to the contractor. The work shall thereafter be performed in conformity with such approved information.
Where the information as submitted indicates a variation from the detailed contract requirements, and the contractor has made specific mention and has given reasons for such variation, the City Representative, if he/she determines the variation to be minor adjustment in the interest of the City, may approve “as noted” information, but the as noted approval will contain in substance, the following:
“The modification contained herein is approved in the interest of the City of Detroit with the understanding that all other contract terms and conditions remain unchanged.”
7. SAMPLES, CERTIFICATES, AND TESTS
The contractor should, in general, request approval by the City Representative, of the various materials proposed for use in the work before they are delivered to the site. No materials, however, for which samples are specifically required for test and approval shall be delivered to the site until representative samples have been tested and approved, unless such requirement is expressly waived by the City Representative, and then only the contractor’s risk of subsequent rejection. Samples of materials and certificates relating to the materials shall be submitted as stipulated in the Detailed Specifications or as directed by the City Representative.
A. TESTING:
The contractor shall employee the services of a Testing Laboratory prior to the start of the work. The contractor shall submit to the City Representative the name of a qualified testing facility they intend to use for the City’s review and approval. The contractor shall furnish all items that the Laboratory representatives may require for collecting, obtaining, storing, conducting and forwarding samples to the Laboratory for testing, that can not otherwise be tested in the field, as maybe per customary and standard practice for such tests. All test results shall be forwarded to the City and contractor directly without costs to the City. The contractor shall pay for all testing costs.
B. SAMPLES:
All materials to be incorporated into the Work shall meet the requirements of the Contract Documents. All samples shall be taken in such manner as to be truly representative of the entire lot and shall not be worked on in any way as to alter the quality or appearance. The samples shall be of such size, quantity or number as to permit the City Representative or testing laboratory to properly judge their acceptability and make such tests as maybe required
1. The City Representative shall at all times have access to all materials intended for use in the work as well as to the plants where such materials are produced. Plant material inspection may be made if the quantities are sufficient to warrant such inspection prior to digging, if it
GENERAL SPECIFICATIONS 7
is to the best interest of the City, or as specified within the pertinent specification section. In any case materials may be either inspected or tested when received on the Project site. Materials shall not be used until approval has been received from the City. Approval of materials at the producing plant or product source does not constitute a waiver of the City’s right for re-examination at the project site.
2. Samples shall be packed that they will reach their destination in good condition and samples of liquid or viscous materials shall be shipped in tight metal containers. All samples shall be properly labeled, or otherwise marked, to show the material or product represented, its place of origin, the name of the producer, the name of the contractor, and the contract number for which it is intended. The samples shall be delivered with all transportation charges prepaid by the contractor to the location designated by the City Representative.
3. The standards for testing materials unless otherwise specified, shall be as established by the American Society for Testing and Materials (ASTM) or other authoritive agency. All tests of materials will be made in accordance with the methods described or designated in the specifications. The sampling and testing of all materials not specifically mentioned shall be done by generally accepted methods, unless otherwise specified by the City Representative.
C. CERTIFICATES
When stipulated in the detailed specifications or required by the City Representative, a certificate shall be submitted to the City Representative, in triplicate, attesting that the material, equipment, or accessory submitted complies with the Contract Document requirements. The certificates shall include the following information:
1. Name and brand of the product, name of manufacturer, location of the plant or plant materials.
2. An outline giving the chemical and physical properties of the material represented by the sample submitted, and giving the name of the testing laboratory, which made the test, and the dates of the tests. This information may be omitted in the case of materials required to conform to Federal Specifications or A.S.T.M. Standards, provided a certified statement by an acceptable testing laboratory is furnished in lieu thereof.
3. If the statement originates with the producer, the contractor shall endorse all claims and submit the statement in his own name. The contractor shall also guarantee that all materials furnished for use under the contract will be in compliance with the samples and certificates.
D. TESTS
1. Tests will be made by such methods and in such numbers as the City
Representative shall determine to be adequate and equitable.
Whenever materials are required to conform to Federal Specifications or A.S.T.M. Standards, and such specifications are accepted as establishing the technical qualities and testing methods, they shall not necessarily govern the number of tests required to be made. The City Representative may require laboratory tests on samples submitted or
GENERAL SPECIFICATIONS 8
may approve materials on the basis of data submitted in certificates with the samples.
2. If the tests of the samples submitted indicate that the proposed material will not conform to the contract requirements, the City Representative will notify the contractor that the proposed material is unacceptable and rejected, and will furnish the contractor the basic reasons for such rejection. However, the City Representative shall not be required to furnish the contractor with copies of all the test data and results.
E. CITY REPRESENATIVE’S APPROVAL
Approval by the City Representative will be general only and shall not of the City’s right to demand full compliance with the Contract requirements. When a material test or sample has been approved no change in brand or make will be permitted unless:
1. The Manufacturer cannot make satisfactory delivery; or
2. The material as delivered fails to comply with the contract requirements.
F. FIELD CHECK TESTS
After actual deliveries of materials to the site, the City Representative will make such tests, as deemed necessary, to insure compliance of the materials delivered or used to complete the contract requirements. The City Representative may reject such materials for cause even though such materials have previously been given general approval. If materials, which fail to meet field check tests, have been incorporated in the work, the City Representative shall have the authority to require their removal and replacement with proper materials conforming to the contract requirements.
8. MATERIALS, DELIVERY, STORAGE, AND HANDLING
A. The contractor shall provide for expeditious transportation and delivery of materials and equipment to the project site in an undamaged condition and on a schedule to avoid delay of the work. Materials and equipment shall be delivered in original containers or packaging with identifying labels intact and legible.
B. All materials shall be so delivered, stored, and handled as to prevent the inclusion of foreign matter or damage by water, breakage, exposure or other means. Packaged materials shall be delivered in original, unopened packages, and properly stored until ready for use. Packages showing evidence of water or other damage shall be rejected unless the contents are specifically approved for use by the City Representative. Any material showing evidence of water or other damage shall be rejected.
C. The Contractor shall store materials and equipment immediately on delivery, and protect it until installed in the work.
D. Products subject to damage by elements shall be stored in weather tight enclosures with temperature and humidity ranges as required by manufacturer's instructions. Loose granular materials shall be stored on solid surfaces to prevent mixing with foreign matter.
GENERAL SPECIFICATIONS 9
E. The place of storage shall be located so as to minimize interference with traffic and to provide easy access for inspection. No material shall be stored closer than five (5) feet to the edge of a pavement or traveled way open to the public.
F. Materials that have been stored shall be subject to retest and shall meet the requirements of their respective specifications at the time they are to be used in the Work. The Contractor shall provide protection of stored or installed materials and equipment as necessary to prevent damage from traffic, vandalism and subsequent operations.
G. All materials that have been stored shall be subject to re-examination or retest and must meet the requirement of their respective specifications at the time they are to be used in the work regardless of any prior test or approval by the City Representative.
9. WATER FOR CONSTRUCTION
All water used in connection with the work shall be City of Detroit water. The contractor shall make all arrangements for obtaining the required water and he/she shall obtain the necessary authorization and permit from the Detroit Water & Sewerage Department (DWSD) and shall strictly comply with all regulations and restrictions for such use and shall bear all expense for the permit and the water used.
If connections are made to a fire hydrant, the Contractor shall in addition, obtain authorization from the Detroit Fire Department (DFD). The DFD standard hydrants shall be pumped out and left dry after each use regardless of the season of the year.
10. TEMPORARY POWER AND LIGHT
Electric lights shall be used and power-driven construction equipment shall be electrically operated throughout the work insofar as possible. The contractor shall furnish all wiring, switches, fuses, receptacles, lamps, etc., as may be required for the work.
The contractor shall provide all temporary electric power and light. He shall make all necessary application, obtain and pay for required permits for the temporary service, and pay all fees and charges for the electrical energy used. This shall include charges for energy used during construction from all permanent building service sources, until the completed project is turned over to the City.
11. HOURS OF WORK
A. From a construction standpoint alone, the contractor may normally prosecute the work during the entire 24 hours of any weekday, providing that he/she so conducts his/her operations as to not create a public nuisance or disturb the peace. However, should the contractor be stopped by order of public authority from working at such times that are contrary to or in violation of any law, ordinance, permit or license, the contractor shall not be entitled to an extension of time due to such a work stoppage.
B. At the beginning of work this contract, the contractor shall notify the City
Representative in writing the days and hours thereof, which shall be
GENERAL SPECIFICATIONS 10
considered the normal workweek. Whenever the contractor intends to depart from his/her normal workweek or normal daily work hours, he/she shall notify the City Representative at least 24 hours in advance of the contemplated change so that the City Representative may make the necessary arrangements to have required inspectors assigned to the work. Failure of the Contractor to give such timely advance notice may be cause for the City Representative requiring the removal or uncovering of the work performed during such time without the City Representative’s knowledge.
C. In an emergency, requiring work to be performed outside the normal working hours of the normal work week schedule to save or protect life or property, the requirements for the 24 - hour notification will be waived. The contractor exists necessitating the change in or extension of the normal hours of work.
However, the contractor’s determination of the existence of the emergency is subject to review and revision by the City Representative.
D. The normal work week schedule and/or daily hours of work shall be altered at such times as directed by the City Representative when, in his judgment, such alteration is necessary to maintain the required progress of the work.
12 CONSTRUCTION PROGRESS SCHEDULE
Within ten days after the date stipulated in the written “Notice to Proceed” work, unless otherwise directed or authorized by the City Representative, the contractor shall submit to the City Representative five copies of a proposed Construction Schedule, in a form satisfactory to the City Representative, showing in a clear, graphical manner:
A. The anticipated date of commencement and completion of the various operations to be performed under the contact, including submission of shop drawings and other information requiring approval of the City Representative, which directly control the key operations.
B. The sequence and inter-relationship of each of these operations with the others and, when applicable, with those of other related contracts; and
C. The estimated time required for fabrication of delivery, or both, of controlling materials and equipment required for the work.
D. The Construction Progress Schedule shall be predicated on the completion of all work on or before the date specified herein.
E. After being accepted as satisfactory by the City Representative, the Construction Progress Schedule shall be strictly adhered to by the contractor, subject however, to the provisions next below relating to revisions.
REVISIONS OF SCHEDULE
The accepted Construction Progress Schedule shall be revised by the contractor and five copies submitted to the City Representative when any of the following occurs:
A. If the time allowed for completion is extended by the City;
GENERAL SPECIFICATIONS 11
B. If extra work was ordered by the City which is not included in operations originally shown;
C. If the actual progress of the work is such that, in the judgement of the City
Representative, the remaining work to be performed will not be started or completed, or both, as indicated by the Construction Progress Schedule.
The revisions shall be made in such manner as to not obliterate the original schedule but will show were and to what extent the Construction Progress Schedule has been revised. Such revised schedule shall be acceptable to the City Representative and thereafter shall be strictly adhered to by the contractor.
13. WORKING AREA AND MAINTENANCE OF TRAFFIC
A. General:
Construction equipment, storage of materials, and construction operations shall be restricted to the area shown on the drawings.
Trucking routes selected by the contractor shall be subject to regulations of the Detroit Department of Transportation DDOT or MDOT as the case and route chosen may apply. The contractor shall strictly observe the spring “Frost Laws” issued by the above agencies.
The contractor shall properly protect all curbs sidewalks, lawn, and streets.
Any curbs, walks or other surfaces or park items damaged by contractors operations shall be replaced at no cost to the City.
B. Manhole and Minor Street Openings
The working site at a manhole, sewer connection, and minor street openings shall be kept as small as practicable. The site need not be fenced, but shall be well protected by substantial barricades and adequate warning flags, signs and lights. The work at such location shall be completed without undue delay so that the opening may be filled in as soon as possible. Whenever work is not underway, a small street opening shall be covered at pavement level with a securely anchored substantial steel plate sufficiently strong to carry truck traffic.
C. Open-Cut Work
All operations necessary for the open-cut work, including the temporary storage of construction materials and equipment, shall be restricted to the City streets and alleys adjacent to the work, or the area shown on the drawings.
Where work is required to be done under existing sidewalks, as much of the existing sidewalk area may be occupied at one time as may be necessary, but safe pedestrian passageways shall be provided and maintained until the sidewalk is replaced permanently.
Safety precautions shall be taken at all open-cut excavations. Substantial barricades shall be erected and maintained as necessary to prevent accidents to vehicular and pedestrian traffic. Red flags by day and red lights by night shall be diligently posted and maintained at all points of possible danger.
GENERAL SPECIFICATIONS 12
14. SIGNS
A. Advertising Signs of any kind shall not be erected or displayed on site.
B. Job Instruction Signs, such as “Danger,” “Keep Out,” etc., shall be furnished, erected, and maintained by the contractor as may be required to safely conduct and protect the work. Such signs shall be neat appearing, substantially erected, kept in good condition, and promptly removed when their usefulness has ended.
C. The contractor shall erect all appropriate safety, warning and other types of construction signage deemed appropriate or as maybe required by code, M- OSHA, or the City of Detroit. The signs shall be maintained in good condition for as long as they shall be needed. Once a sign is no longer needed it shall be promptly removed. Any post holes shall be immediately backfilled and compacted in 6” layers of sand. At finish grade the top lift of soil shall be 4” of Topsoil and sod installed at the required finish adjacent grade.
D. Project Sign
Prior to the start of work at the project site, the contractor shall furnish and erect, and then maintain on the site were directed by the City Representative, one (1) Project Sign. The temporary (4’ x 8’ x ¾”) Project Sign in color on corrugated chloroplast (Attachment A) shall remain in place until near the end of the warranty period (one year) generally, or as directed by the City Representative, at which point the contractor shall remove the sign and any post holes shall be filled with compacted sand, 4” of Topsoil and sod installed at the required finish adjacent grade.
1. Attached herewith or contact the City Representative for Project Sign artwork.
2. The project sign shall be installed on two 4x4 posts set into the ground not less than 36-inches deep and the bottom of the project sign shall be set approximately 42-inches above grade and set plumb.
15. FIELD OFFICE
NOT USED Note: Construction Superintendent must have a working cell phone.
GENERAL SPECIFICATIONS 13
16. TEMPORARY CONSTRUCTION FACILITIES, CONTROLS & FENCING
All temporary construction facilities used by the contractor and his subcontractors shall be neatly constructed and arranged on the site in an orderly manner. The general arrangement of such facilities shall be subject to approval by the City Representative. When so required by the City Representative, the Contractor shall prepare and submit to the City Representative, for approval prior to starting work, a construction plan layout, showing arrangement of storage areas, temporary buildings, construction equipment, and storage and work areas. Temporary facilities include but are not limited to the following items:
The contractor and all workers shall park their vehicles at curbside in the street ROW and NOT upon the lawn turf of park property.
A. Temporary facilities such as fencing, B. Temporary security protection (see Concrete Work, Protective Surfacing, etc.), ALL SITE SECURITY COSTS ARE AT THE CONTRACTORS EXPENSE
FOR WHATEVER REASON OR NEED AND SHALL BE PROVIDED FOR IN THE
BID PROPOSAL.
C. Project Sign (see # 14C above) and any other construction signage deemed necessary, D. Temporary portable toilet, E. Protection around existing trees at their drip lines, F. Existing drainage structure protection, G. Any other miscellaneous temporary facilities or equipment necessary to complete the work in a safe and secure manner and as further indicated within these General Specifications and Contract Documents, H. Suitable temporary, weather tight storage shed (s), with raised floor (s), shall be provided of capacity required to contain all materials, which might be damaged by storage in the open.
I. Construction equipment and other facilities such as tarps, bracing, barricades, canopies, warning lights, flashers, steps, platforms, ladders, scaffolds, ramps, etc. shall be strong, substantial, and safe, and suitable for the purpose intended and shall meet all the applicable requirements of the State of Michigan, OSHA, the Department of Building and Safety Engineering, and shall also be subject to the City Representative’s approval.
J. Whenever practical and as soon as possible, permanent parts of the work shall be used in place of temporary facilities when authorized by the City Representative. Adequate precautions, however, shall be used to prevent damage to such parts of the permanent work used during construction.
K. When temporary buildings, construction equipment, and other facilities are no longer needed for the work they shall be promptly dismantled.
GENERAL SPECIFICATIONS 14
FENCING:
A. The contractor is responsible and legally libel to provide a safe working environment to protect both the construction operations and the public. The contractor shall maintain existing fencing and /or temporary fencing as necessary to close off the actual construction site to the public. All appropriate warning signage shall be posted and maintained as long as necessary.
B. All temporary fencing shall be kept in a safe secure condition as long as it is installed on the site. Once the need no longer exists for temporary fencing it shall be promptly removed and taken from the site. All cost associated with temporary fencing are considered incidental to the completion of the work, and are at the contractor’s expense.
C All adjoining property shall be carefully protected from damage. If the contractor damages any adjacent property, he shall be responsible for replacement or restoration to original condition at no additional cost to the City.
1. Where the existing Park property lines abut private residential property, the property shall be protected by the installation of temporary fencing until the new fence posts and fabric are installed, at which point it shall be promptly removed.
2. Temporary fencing shall be well installed and maintained during its usage along private property.
D. The contractor shall erect and maintain snow fencing installed in a circle around the outer edge (drip line) of all existing trees. Such protective fencing shall remain in place until near the completion of the work.
17. CLEANLINESS OF WORK AND STREETS
The work and all public or private property used in connection with the work shall be kept in a neat, safe and orderly condition at all times. Waste materials, rubbish, and debris shall not be allowed to accumulate. Construction equipment, temporary buildings and excess materials shall be promptly removed from the site, as they become no longer needed for the progress of the work. At the completion of the work, the premises shall be left broom and rake clean.
Trucks hauling loose materials to and from the site shall be tight and their loads trimmed to prevent spillage on the public streets, and covered if so required. This requirement likewise applies to suppliers making deliveries to the site and the contractor will be held responsible for compliance to these specifications, by his/her suppliers. The contractor shall promptly clean streets dirtied by any cause arising from his/her operations. Should he fail to maintain proper street cleanliness, the City will clean such streets and charge all costs to the contractor.
GENERAL SPECIFICATIONS 15
18. SANITARY REQUIRMENTS
Committing of nuisance, either general or related to sanitary requirements, on the site is prohibited. Any employee who violates such provisions shall be promptly removed form the work and shall not again be employed on the work without the written consent of the City Representative.
At the start of the work at the site, suitable and adequate toilet facilities shall be provided for all persons employed on the site subject to the approval of the City Representative as to the number, type, size, and location. The facilities shall be maintained in a sanitary condition, frequently cleaned and disinfected, and shall be promptly removed from the site when no longer needed or as directed by the City Representative.
19. FIRST AID
A completely equipped first-aid kit shall be provided and maintained at the site in a clean orderly condition, and shall be readily accessible at all times to all of the contractor’s employees. The contractor shall designate certain employees who are properly instructed to be in charge of first aid. At least one such employee shall be available whenever work is being carried out.
20. BARRICADES AND LIGHTS
The City Ordinance (Article 58-1-7, Municipal code) relative to barricades and colored lights around excavated areas shall be observed by the contractor. Further, the contractor shall furnish and maintain sufficient and suitable barricades, guard fences, and transistorized lights, as approved by the City Representative, to clearly indicate all equipment, materials, or any other hazards that might cause an accident.
21. CLEANOUT OF MANHOLES, HANDHOLES, AND CATCH BASINS
Care shall be taken to prevent the dropping of construction materials into manhole, handhole and catch basin structures. Prior to final acceptance of the complete work, all existing and new manholes, hand holes, and catch basins within the contract limits, and that have in anyway been affected by the operations of the contractor, shall be thoroughly cleaned of debris resulting from the contractor’s operation. To facilitate the inspection of the manholes, handholes, and catch basin the contractor shall provide the labor and tools to remove all manhole, handhole, and catch basin covers, within the contract limits, so that the City Representative can make a thorough investigation of the condition of the manholes, handholes, and catch basins.
The City Representative will make an inspection of existing structures with the contractor prior to construction, if the contractor requests such an inspection.
22. TEMPORARY ENCLOSURES
Temporary, secure, weather-tight enclosures for all exterior building openings shall be provided and maintained as soon as the exterior walls and roof have been built, as may be necessary to protect the interior of the structure from the weather, to prevent entrance of unauthorized persons, and to permit the continuation of interior work. The adequacy and timeliness of such enclosures shall be subject to the City Representative’s approval.
GENERAL SPECIFICATIONS 16
23. TEMPORARY HEAT
Adequate temporary heat necessary for proper protection and drying of all work shall be provided until the City accepts the structure or work. Until the structure is enclosed, heavy tarpaulins, or other suitable means shall be provided to enclose the space requiring heating or protection from the weather during construction operations. All temporary heating devices shall meet the requirements of the Detroit Official Building Code and shall be subject to the City Representative’s approval. In no case shall any heating devices or means be used which may in any way damage or impair the competed work.
After the permanent heating system is in operating condition and the structure is enclosed, heat may be provided from the permanent heating plant if and as approved by the City Representative. In such case, the contractor shall arrange to operate the plant, connecting permanent or temporary space heating devices, and so maintain the plant during operation that it will be turned over to the City undamaged at the completion and final acceptance of the work. The contractor shall provide all labor and fuels required and pay all other costs.
Temperatures not less than those specified below shall be maintained during the following operations unless specified differently elsewhere in the technical specifications Operation Minimum Degrees (F) Plastering 60 Resilient & Wood Floor Installation 70 Finished Carpentry 60 Painting 70 Safety Surface Installation 60 Asphalt Paving 50 Concrete Work 40
All other trade work not mentioned above shall be done within temperature ranges as stated within and in strict accordance to the material/manufactures specifications, or as otherwise specifically stated within these contract technical specification sections.
24. FINAL CLEANING AND BUILDING
Upon completion of the construction and prior to final acceptance, all work shall be left free of stains, paint splatters, marks, fingerprints, dust, dirt, trash or other debris.
25. BUILDING & EQUIPMENT SYSTEM STARTUP AND TESTING
The Contractor shall perform a comprehensive startup and demonstration of equipment performance and compliance with the design requirements. When there is more than one mode of operation, the equipment shall be operated in every mode to verify proper operation.
When equipment is to operate in conjunction with other equipment as a system, each piece of equipment shall be operated both by itself and automatically as a system to verify its proper operation.
The contractor shall provide to the City Representative, in advance of startup, a schedule and listing of startup and testing procedures for review by the City. Checklists and diagrams may be required to ensure adequate startup and testing. The City Representative may recommend changes to the startup procedure as necessary.
GENERAL SPECIFICATIONS 17
All equipment is to be inspected prior to operation for debris or other obstructions.
Equipment is to be properly lubricated and calibrated prior to operation. The contractor shall make all adjustments necessary to assure correct operation. When required, the equipment installation and operation is to be witnessed and checked by manufacturer.
When required, the contractor shall train the City’s operation and maintenance personnel in the proper operation and maintenance of each piece of equipment and the system as a whole.
All equipment startup is to be witnessed by the City Representative.
26. SOIL CONDITIONS
The contractor shall assume all risks and responsibility because of existing soil conditions and shall complete the work in whatever ground conditions he may encounter or create, without additional cost to the City.
27. VENTILATION
Prior to entry in to entry in any structure, qualified personnel shall check it for air quality and safety for humans. If gas is present in existing sewers, where it is necessary for the contractor to work, the sewer shall be cleared of gas before entering. If the gas cannot be removed by natural ventilation, that is, by removal of manhole covers, the contractor shall maintain forced draft ventilation, so as to render the sewers safe as determined by gas test.
No employee of the Contractor shall enter any existing sewer until a gas test has been performed and safe access has been certified by said test.
28. EXISTING UTILITIES
All existing drainage structures and sewer lines shall remain at the locations shown on the drawings, and shall be protected from damage. Contractor shall exercise extreme caution not to disturb drainage structures that are to remain.
A. Public utilities of all types have been shown on the drawings, when known.
The locations of these utilities are shown using the best information available.
No guarantee is given that the locations are absolutely accurate or that other utilities than those shown are not present. Before starting construction, the contractor shall check the City departments and Public Service Organizations to ascertain for himself the location of all utilities which might interfere with the work and shall give due notice to all organizations whose utilities will be affected by his operations.
B. All public utilities, including building connections, whether or not indicated on the drawings, which are adjacent to the construction but which, in the judgment of the City Representative may be left in place, shall be maintained in accordance with the standard method employed by the utility involved and in such a manner as to secure the safety of the public and of adjacent structures or utilities. Such maintenance shall be by the contractor or at his instance and expense.
C. When the contractor deems it unsafe, impractical, or impossible to construct the work without moving a utility, he shall so notify the City Representative.
Should the City Representative concur with the contractor’s opinion, the City
GENERAL SPECIFICATIONS 18
Represe…