This is the 2016 Western Area Power Administration (WAPA) Equipment Standard Specification for Surge Arresters (WAPA ES 9.1), which establishes technical requirements for metal-oxide type surge arresters used in electrical substations.

Surge arresters must comply with IEEE C62.11 standards, with WAPA specifications taking precedence in case of conflicting requirements. Equipment must be new and of current manufacture. Each arrester must include a pressure-relief diaphragm to prevent explosive shattering of the porcelain housing under excessive current; a gray porcelain housing; corona rings (required for systems rated above 121 kV); NEMA CC1 standard 4-hole line terminal pads; and grounding terminal connectors suitable for No. 2 AWG to 400-kcmil copper cable. Testing and retesting must verify arrester ratings per IEEE C62.11. When seismic qualification is required, data must comply with IEEE 693; a seismic report is not required for the low seismic performance level. The contractor must provide drawings and technical data in English with dimensions in feet and inches, weights in pounds, and volumes in cubic feet or cubic inches. Acceptable formats include PDF, AutoCAD 2010 or 2014 (.dwg), Microsoft Word (.doc/.docx), or Microsoft Excel (.xls/.xlsx); freehand sketches or skewed scans are not accepted. Installation drawings and data, including seismic qualification reports if applicable, must be delivered within 60 days after contract award (up to 150 days for seismic reports if equipment is not previously qualified). Informational drawings and final drawings, parts identification lists, and manufacturer's operation and maintenance instructions must be delivered 21 days prior to shipment. WAPA reserves the right to use, reproduce, distribute, and reuse all contractor drawings for installation, maintenance, replacement, repair, and provision to subsequent bidders and contractors.

View the file

Other files

File Type Posted
Sol_89503127QWA000433.pdf PDF
Attach_B_Additional_Info.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUBSTATION - ELECTRICAL

EQUIPMENT SPECIFICATIONS

WAPA ES 9.1

SURGE ARRESTERS

WESTERN AREA POWER ADMINISTRATION

WAPA ES 9.1 STANDARD SPECIFICATIONS

9.1 - i

TABLE OF CONTENTS

Subject Page

9.1.1 General .................................................................................................................................... 9.1 - 1

9.1.2 Material .................................................................................................................................... 9.1 - 1

1. Pressure-Relief Diaphragm ............................................................................................... 9.1 - 1

2. Porcelain Housing ............................................................................................................. 9.1 - 1

3. Corona Rings. .................................................................................................................... 9.1 - 1

4. Line Terminal Pads ............................................................................................................ 9.1 - 1

5. Grounding Terminal Connectors ....................................................................................... 9.1 - 1

9.1.3 Tests ........................................................................................................................................ 9.1 - 1

9.1.4 Seismic Qualification ............................................................................................................. 9.1 - 1

9.1.5 Drawings And Data ................................................................................................................ 9.1 - 1

1. General .............................................................................................................................. 9.1 - 1

Table-A Drawings And Data Schedule .............................................................................. 9.1 - 2

2. Installation Drawings And Data ......................................................................................... 9.1 - 2

3. Informational Drawings And Data ...................................................................................... 9.1 - 2

4. Final Drawings And Data ................................................................................................... 9.1 - 3

5. Right To Use Contractor’s Drawings ................................................................................. 9.1 - 3

9.1 - 1

9.1.1 GENERAL: Surge arresters shall be metal-oxide type and meet the requirements of these specifications and applicable requirements of IEEE C62.11. In the event of contradictory requirements, the requirements of these specifications shall prevail. Only new equipment of current manufacture shall be furnished.

9.1.2 MATERIAL: Each surge arrester shall have the following features:

1. PRESSURE-RELIEF DIAPHRAGM: Pressure-relief diaphragm shall rupture to prevent explosive shattering of porcelain housing in the event of excessive current causing high internal pressure.

2. PORCELAIN HOUSING: Porcelain housing color shall be gray.

3. CORONA RINGS: Corona rings may be furnished at any voltage but are required for systems with rated maximum voltages above 121 kV.

4. LINE TERMINAL PADS: Line terminal pads shall be NEMA CC1 standard 4-hole pads.

5. GROUNDING TERMINAL CONNECTORS: Grounding terminal connectors shall be suitable for

No. 2 AWG to 400-kcmil copper cable.

9.1.3 TESTS: Testing and retesting in accordance with IEEE C62.11 to verify arrester ratings.

9.1.4 SEISMIC QUALIFICATION: When seismic qualification is required, data and requirements shall be provided in accordance with the latest IEEE 693. The data required for metal tag to be attached to equipment may be provided on the nameplate. A seismic report is not required for the low seismic performance level.

9.1.5 DRAWINGS AND DATA:

1. GENERAL: Drawings and technical data required to be furnished by the Contractor shall be in English, with dimensions in feet and inches, weight in pounds, and volume in cubic feet or cubic inches.

The drawings and data shall be complete and accurate in their content, and legible. Drawings shall be prepared using CAD or drafting equipment, shall be drawn to scale, and shall have neat lettering. Drawings or informational data shall be provided as a standard PDF file, Electronic CAD “*.dwg” (AutoCAD 2010 or 2014 formats), Microsoft Word (.doc/.docx) or Microsoft Excel .xls/.xlsx formats. Freehand sketches or skewed scans will not be accepted. Western will require 40 calendar days to answer correspondence pertaining to each submittal of data or drawings.

Reproducible prints shall be of such quality as to permit clear, sharp, legible prints or other reproductions to be made by direct contact methods.

Western shall have the right to require the Contractor to make any changes in the drawings and data that may be necessary to show the equipment furnished conforms to the requirements of the specifications and these standards. The design and coordination of this electrical equipment shall be the responsibility of the Contractor and Western assumes no responsibility to approve or review drawings and data that are submitted. Western's review of the Contractor's drawings shall not relieve the Contractor of meeting all requirements of these specifications or for the correctness of his drawings. Revised drawings shall show revision dates and all changes and revisions circled on the drawings. Drawings shall not exceed 22 inches in height by 36 inches in width.

Procurement and construction specifications include the delivery times, quantities, and destinations for drawings and data submittals. The following Table – A shows the normal delivery time and quality requirements.

9.1 - 2

TABLE-A

DRAWINGS AND DATA SCHEDULE

TYPE OF DRAWINGS

AND DATA

SECTION

9.1.6

PARAGRAPH

DELIVERY TIME

(CALENDAR DAYS)

TYPE OF

MATERIAL

Installation drawings and data including seismic qualification report

2.

† Within 60 days after date of contract award

Blackline Prints/Data Reports or CAD Drawings

Informational drawings and data

3.

Within 60 days after date of contract award

Blackline PDF or CAD Drawings

Final drawings 4.a.

21 days prior to shipment

Blackline PDF or CAD Drawings

Parts identification lists and bills of material

4.b.

21 days prior to shipment

Lists in Excel, Word or PDF

* Manufacturer’s operation and maintenance instructions

4.c.

21 days prior to shipment

Books or PDF

* Furnish one print of each final drawing with each copy of instructions.

† Seismic qualification report may be submitted within 150 calendar days after date of contract award, if equipment not previously qualified per latest IEEE 693. A seismic report is not required for the low seismic performance level.

2. INSTALLATION DRAWINGS AND DATA: The required delivery time and quantity of installation drawings and data are listed in Table-A. The installation drawings and data are required to prepare final design of foundations and, when applicable, support structures. Drawings and data required include all of the following that are applicable:

a. Outlines, dimensions and weights of equipment and, when applicable, associated support structure.

b. Base type, dimensions, and mounting details.

c. Location, types, sizes, and projections of required embedded anchor bolts or material. The Government will furnish the foundations, anchor bolts, and embedded material.

d. Orientation of all equipment and a complete anchor bolt setting plan.

e. Seismic qualification report.

3. INFORMATIONAL DRAWINGS AND DATA: The required delivery time and quantity of informational drawings and data are listed in Table-A. The drawings and data shall:

a. Include outlines, catalog data, and instructions.

b. Specifically verify conformance with equipment requirements.

c. Be sufficiently complete to allow preparation of final design and installation drawings.

9.1 - 3

4. FINAL DRAWINGS AND DATA: The minimum delivery time and quantity of final drawings and data are listed in Table-A. The drawings and data shall include the following:

a. Final Drawings: Final drawings shall show all changes and revision dates therefor, made up to the time the drawings are furnished. Final drawings shall be furnished rolled or flat, not folded, be printed on quality bond paper, be full size, and be clear, sharp, and legible.

Final drawings shall include the following:

Outlines of associated support structures, when applicable.

Outlines of arresters.

Nameplate drawing.

b. Sets of Parts Identification Lists or Bills of Materials for the Equipment: Each part shall be assigned an identifying number which can be used for ordering replacements, and a reference number that locates the part on the appropriate outline drawing. Separate lists are not required if data is shown on outline drawings.

c. Sets of manufacturer's instructions covering installation, operation, and maintenance repair for the equipment. A print of each final drawing as required above shall be included with the instructions.

5. RIGHT TO USE CONTRACTOR’S DRAWINGS: Western expressly reserves the right to use, to reproduce in whole or in part, to distribute, and to reuse any and all such drawings, whether copyrighted or not, in connection with the following:

a. Installation, maintenance, replacement, and repair of the articles to be furnished under this contract.

b. Making any and all such drawings and reproductions thereof available to subsequent bidders and the Contractors, where necessary, for fabricating and furnishing articles connected with or dependent upon information shown on the drawings and duplicating the drawings to be furnished hereunder.

The depositing of all such drawings with Western shall constitute a license to Western to use said drawings in the manner hereinabove stated.