AIRPORT AND KESWICK 2018

SUBSTATION UPGRADES

Spec. No. xxx

SECTION C

DESCRIPTION/SPECIFICATIONS

CALIFORNIA

SECTION C

DESCRIPTION/SPECIFICATIONS

AIRPORT AND KESWICK 2018 SUBSTATION UPGRADES

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT

B. DESCRIPTION OF WORK

1. The Principal Components of Work

C. DESCRIPTION OF BIDDING SCHEDULE ITEM

1. Bidding Schedule item “Mobilization and preparatory work”

D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

1. Commencement, Prosecution, and Completion of the Work

2. Submittal Approval Time

3. Outage and Construction Schedule Restrictions

4. Protective Ground Leads

5. Maximum Available Fault Current

E. CONSTRUCTION SCHEDULE

1. Submittal Time

2. Format and Detail

F. MATERIAL

1. Points-of-Delivery

G. ELECTRIC POWER FOR CONSTRUCTION PURPOSES

H. WATER FOR CONSTRUCTION PURPOSES

I. EXPLOSIVES AND BLASTING

J. SUBMITTALS

1. General

2. Approval Time

3. Address

4. Project Protocol

DIVISION 9 – SUBSTATION - ELECTRICAL

A. GENERAL

1. For all Government-furnished Bidding Schedule items

2. For all Contractor-furnished Bidding Schedule items

3. Associated Support Structures Provided for each Electrical Equipment Rated Above 7-kV

4. Installation and Painting of Electrical Equipment and Material

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS

1. Bidding Schedule items “Motor operated disconnecting switch, 230-kV, 2,000 amps

(Government-furnished)” and “Motor operated selector switch with grounding blades, 230-kV, 2,000 amps (Government-furnished)”

2. Bidding Schedule item “Associated electrical equipment and material”

3. Bidding Schedule item “Existing outdoor electrical equipment and material”

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION

A. GENERAL

1. Bidding Schedule does not contain separate items

B. SPECIAL REQUIREMENTS

1. Coordination

2. Special Cultural Resources Requirements

3. Special Biological Requirements

4. Special Compliance Requirements

DIVISION 1 – GENERAL REQUIREMENTS

A. CONTRACT REQUIREMENT:

Construct and complete Airport and Keswick 2018 Substation Upgrades in accordance with the Construction Contract (Standard Form 1442); the Contract Clauses; Western’s Construction Standards (September 2016), including Standard 1 – General Requirements, Standard 9 – Substation

– Electrical, Standard 13 – Environmental Quality Protection, Standard 15 – Drawings; Standard Drawings; and these Project Specifications and Drawings.

If a conflict occurs between the Project Specifications and the Construction Standards, the Project Specifications shall govern. The Project Specifications and the Drawings are used to take exceptions or provide additions to the Construction Standards. Some paragraphs in the Construction Standards will not apply to this job.

Western’s Construction Standards, Standard Drawings, and Electrical Equipment Standards are available at https://www.wapa.gov/DoingBusiness/SellingToWestern/Pages/what-western-buys.aspx.

Western Project Specifications and Construction Standards are explained in Standard 1 – General Requirements, Section 1.1.1, “Standards and Project Specifications”.

B. DESCRIPTION OF WORK:

1. THE PRINCIPAL COMPONENTS OF WORK include the following:

a. Installing Government-furnished, 230-kV motor operated disconnecting switches.

b. Furnishing and installing aluminum conductor jumpers and miscellaneous bus work.

c. Removing and disposing of electrical equipment and aluminum and copper conductor jumpers and miscellaneous bus work.

Paragraphs “Description of Bidding Schedule Items” in Divisions – 1, 9 and 13 describe the work to be performed.

The work is located near Redding, California, as shown on Drawings AIR 0015 and KE 0015.

C. DESCRIPTION OF BIDDING SCHEDULE ITEM:

1. Bidding Schedule item “Mobilization and preparatory work” includes the following:

a. Performing mobilization and preparatory work in accordance with Section H of the contract clauses.

b. Prepare and submit a Construction Schedule and furnish a Safety and Health Program.

c. Providing jobsite office trailer and the items listed below. Prior to any jobsite work, the

Contractor shall provide the office trailer for the exclusive use of WAPA.

1. Relocation: If the Contractor changes the location of his office during the term of the contract, then the Contractor shall also move the mobile office trailer provided for WAPA, simultaneously with the transportation of his own unit.

a. Installation: Install anchors and tie-downs for the trailer complying with local, State and Federal regulations. The office trailer shall be grounded. Entry points to the trailer shall be provided with stairways complying with OSHA (29 CFR 1926.1052).

b. Office Space Requirements:

1) Size and Arrangement: At least 250-square feet (minimum) consisting of two (2) separate rooms (one (1) office and one (1) larger workroom).

2) Heating and Cooling: Heating and cooling unit sized to provide adequate heating and cooling.

3) Lighting and Electrical: Adequate lighting and 110 V electrical outlets.

4) Utilities: Make all arrangements and pay all costs for providing utilities, including potable drinking water, electrical power, and heating and cooling energy.

5) Toilet Facilities: Toilet facilities shall be provided in the immediate vicinity of the office and shall be maintained.

2. Emergency Equipment: Provide and maintain the following emergency equipment:

a. First aid kit that meets or exceeds ANSI Z308.1 (latest version) Class B, Type IV.

Mount to the wall inside the workroom.

b. Dry chemical fire extinguishers, classified 4-A:60-B:C, one to be located inside each entrance to the trailer.

3. Window Coverings: Provide adjustable mini-blinds.

4. Office Furniture: Provide good quality, fully functional, office furniture as follows:

QUANTITY DESCRIPTION

5 Folding Office Chairs 1 Office desk (30-inches by 60-inches minimum) 2 Office tables (30-inches by 60-inches minimum) 1 Five-drawer file cabinet 1 Bookcase (30-inches by 13-inches by 48-inches) 12 “Plan Hold” binders No. 1CB-24 (including one (1) plan rack)

D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:

1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF THE WORK. See FAR 52.211-10 in Section F of the solicitation/contract.

2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, Western will require 20-calendar days for review of drawings or data submitted for approval.

3. OUTAGE AND CONSTRUCTION SCHEDULE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following outage and schedule restrictions shall apply:

a. Outage Restrictions

i. General:

(1) All bus work shall be performed in a manner such that the bus can be returned to service within 48-hrs of notification by Western.

(2) All outages are subject to system restrictions and conditions. This may require work be performed on weekends and/or evenings.

ii. Keswick

(1) No concurrent outages of the main and transfer bus are allowed.

(2) Only two outages are allowed on the transfer bus. Outages shall be from October 1, 2019, through May 1, 2020.

(3) Only two outages are allowed on the main bus. Outages shall be from October 1, 2019, through May 1, 2020.

(4) Only one outage on the Flanagan-Keswick Line is allowed. Outages shall be from October 1, 2019, through May 1, 2020.

iii. Airport

(1) No concurrent outages of the ring bus are allowed. Service to at least one line and one transformer shall be maintained at all times.

(2) Only one outage on the Keswick-Airport 230kv line is allowed. Outages shall be from October 1, 2019, through May 1, 2020.

(3) Only one outage on the Airport-Cottonwood 230kv line is allowed. Outages shall be from October 1, 2019, through May 1, 2020.

b. CONSTRUCTION RESTRICTIONS: The following construction restrictions shall apply:

i. Keswick

(1) The Flanagan-Keswick Line bay work shall be completed by May 1, 2020.

(2) The main bus work shall be completed by May 1, 2020.

(3) The Transfer bus work shall be completed by May 1, 2020.

ii. Airport

(1) The Airport-Cottonwood 230kv line bay work shall be completed by May 1, 2020.

(2) The Keswick-Airport 230kv line bay work shall be completed by May 1, 2020.

(3) Airport ring bus work shall be completed by May 1, 2020.

4. PROTECTIVE GROUND LEADS: See Western Construction Standards, Standard 1 “General Requirements”, Section 1.4.14.3(1).

5. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the following:

a. The maximum available fault current at Airport Substation in the 230-kV area is

17,815 amps. The maximum available fault current at Keswick Substation in the 230-kV area is 22,718 amps.

b. A minimum of one (1) 1/0 ground is required in the 230-kV area at Airport Substation and a minimum of two (2) 1/0 grounds is required in the 230-kV area at Keswick Substation.

E. CONSTRUCTION SCHEDULE:

1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer’s Representative (COR) within 45-calendar days after date of Notice to Proceed.

2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.

F. MATERIAL: Furnish all material for completing the work, except material furnished by Western as listed below:

ITEM

ESTIMATED

WEIGHT

(LBS)

ESTIMATED

DELIVERY

DATE

ESTIMATED

COST

1. Five (5), three-phase, 230-kV, 2,000 amp motor operated disconnecting switches

6,000 ea NST-Sept 1, 2019 NLT-Oct 1, 2019 $32,000 ea

2. One (1), three-phase, 230-kV, 2,000 amp motor operated disconnecting switch

6,000 On Site at Elverta Substation $32,000

3. One (1), three-phase, 230-kV, 2,000 amp motor operated selector switch with grounding blades

12,000 NST-Sept 1, 2019 NLT-Oct 1, 2019 $52,000

NST – No sooner than.

NLT – No later than.

1. POINTS-OF-DELIVERY: The disconnecting switches will be delivered to Keswick Substation

(except as noted). The Contractor shall load, transport and unload the material to the jobsite.

The Contractor shall inspect the equipment and report any damages to the COR. Elverta Substation is located in Elverta, California as shown on Drawing ELV 0015.

G. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:

The Contractor shall furnish power for his operations by own means.

H. WATER FOR CONSTRUCTION PURPOSES:

The Contractor shall provide water needed for construction purposes and potable water for employees. The contractor must make arrangements for obtaining and conveying water to points of use.

I. EXPLOSIVES AND BLASTING:

Explosives shall not be used.

J. SUBMITTALS:

1. GENERAL: Submittals must be provided in accordance with the Construction Standards and Project Specifications. The Contractor shall furnish submittals electronically (i.e. e-mail), unless otherwise specified by the COR. Submittals shall be sent to DSW-G5600- CS@wapa.gov in standard PDF or electronic CAD “*.dwg” (AutoCAD 2010) formats. All submittals shall include WAPA's Contract No., Project Title, Transmittal/Submittal No., and corresponding Item No. as shown in the examples in Division 1.J.6. Refer to the Submittal Log for the list of required submittals. This list may not be all-inclusive, and it remains the Contractor's responsibility to ensure conformance to the individual Specifications for possible additional submittal requirements. All submittals must be submitted with the attached cover sheet “CM-16 Transmittal Form Appendix A” in Microsoft Excel or PDF. Submittals will be rejected if CM-16 Form is not attached.

In addition to required submittals, the Contractor shall submit the following information electronically to DSW-G5600-CS@wapa.gov:

a) Payrolls.

mailto:DSW-G5600-CS@wapa.gov mailto:DSW-G5600-CS@wapa.gov

b) Sub-Contractor List/Forms.

c) Citizenship Forms.

d) Erosion Control Plan.

e) Environmental Submittals.

f) Request For Information (RFI).

g) Request for Equitable Adjustment (REA).

h) Any questions, comments, correspondence relevant to this project.

A submittal is required if the item is used in the performance of the contract.

2. APPROVAL TIME: Approval time for submittals shall be in accordance with the

“Commencement, Prosecution, and Completion of Work” paragraph.

3. ADDRESS: The Contractor shall transmit specified non-electronic submittals to the following address:

Western Area Power Administration

ATTN: G5600

P.O. Box 6457 Phoenix, AZ 85005-5313

4. PROJECT PROTOCOL:

a. Electronic Correspondence:

EMAIL SUBMITTAL FORMAT:

Subject Line in Email Submittal number, Subject, Applicable Standard Number, Project Name/Number, and Contract Number Example: Submittal 017, Steel Compression Dead Heads-Std 10, Substation Stage 06, SD-

17WC120498-878, DE-WA000xxxx

b. Payment Requests:

EMAIL PAYMENT REQUEST FORMAT:

Invoice number and Project Name/Number and Contract Number Example: Invoice 01, Substation Stage 06, SD-17WC120498-878, DE-WA000xxxx

c. Certified Payrolls-Prime and Sub-Contractors:

EMAIL CERTIFIED PAYROLL FORMAT:

Certified Payroll (CP), Contractor’s names, Week ending (WE), and Project Name/Number, and Contract Number Example: CP-(Smith Inc., Bob’s Electrical), WE 09/12/15 & 09/19/15, Substation Stage 06, SD-

17WC120498-878, DE-WA000xxx

d. Request for Information:

EMAIL (REQUEST FOR INFORMATION) FORMAT:

Request for Information (RFI), Project Name/Number, and Contract Number Example: RFI-003, Labeling Info, Substation Stage 06, SD-17WC120498-878, DE-WA000xxxx

DIVISION 9 – SUBSTATION - ELECTRICAL

A. GENERAL: Electrical equipment and material shall be as specified in Western’s “WAPA ES”

Standard Equipment Specifications, as shown on project drawings, and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL, and Federal specifications and standards as applicable.

Applicable requirements shall be met under the following service conditions:

Ambient Temperatures:

Maximum ........................................................................................... +50°C Minimum ............................................................................................. -10°C

Airport Elevation:

Above Mean Sea Level ................................................................. 490 Feet

Keswick Elevation:

Above Mean Sea Level ................................................................. 600 Feet

*ASCE-7 Wind Load:

Minimum Basic Wind Speed .......................................................... 90 MPH Importance Factor ................................................................................ 1.15

*IEEE Seismic Qualification:

Performance Level ....................................................................... Moderate

*Wind and seismic loads are nonsimultaneous.

1. For all Government-furnished Bidding Schedule items, the Contractor shall:

a. Unless otherwise indicated, unload and inspect Government-furnished items.

b. Install associated support structures when furnished.

c. Install Government-furnished items as shown on drawings.

2. For all Contractor-furnished Bidding Schedule items, the Contractor shall:

a. Provide (furnish and install) Bidding Schedule items, equipment, and material not furnished by the Government.

3. Unless otherwise specified, associated support structures provided for each electrical equipment rated above 7-kV shall be 102-inches in height and hot-dip galvanized, if made of steel.

Instrument transformers that are seismically qualified shall be 96-inches in height. If tubular steel supports are furnished, they shall be galvanized internally and externally.

4. Installation and painting of electrical equipment and material shall be provided in accordance with

Standards 9 and 12 respectively.

B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:

1. Bidding Schedule items “Motor operated disconnecting switch, 230-kV, 2,000 amps (Government-furnished)” and “Motor operated selector switch with grounding blades, 230-kV, 2,000 amps (Government-furnished)” includes furnishing all equipment and material not furnished by WAPA and installing the Government-furnished switches onto existing lattice support structures at Keswick Substation:

Designation WY2E, WY2W, WY3W, WY8E, WY8W WY5W YY8E-YY8W-ZY8G

Type 3-pole, single throw, outdoor, motor group operated, vertical break, rotating insulator

3-pole, single throw, outdoor, motor group operated, vertical break, rotating insulator

3-pole, single throw, outdoor, motor group operated, vertical break, rotating insulator, selector type with grounding blades Manufacturer TBD Southern States TBD System Nominal Voltage Rating (kV) 230 230 230

Rated Maximum Voltage (kV) 245 245 245 Basic Impulse Insulation Level (kV) 900 900 900

Continuous Current Rating (Amps) 2,000 2,000 2,000 Short-time(3 second) Withstand Current Rating (kA) 63 63 63

Phase Spacing 13’-0” 13’-0” 13’-0”

Control Circuit Voltage (VDC) 125 125 125

Mounting Position Horizontal Horizontal Horizontal

The Contractor shall load and haul the disconnecting switch designated WY5W from Elverta Substation and off-load the switch at Keswick Substation, as directed by the COR. Contractor personnel shall inspect the switch for possible damage during transportation and report any damage to the CO.

New motor operator cabinets shall be installed in the same locations as the existing cabinets.

The Contractor shall re-terminate the existing power and control cables in the new motor operator cabinets.

2. Bidding Schedule item “Associated electrical equipment and material” includes providing equipment, material, and services required to complete the following substation installations as shown on the Drawings:

a. Electrical Testing: Includes providing electrical testing in accordance with Standard 9, paragraph 9.1.2 Acceptance Tests - Method B, except for the following which will be performed by Western personnel:

(1) Control, Metering and Relaying Equipment Test.

(2) Testing of Protective Relays.

(3) Operational Tests.

(4) Energization Tests.

(5) Infrared Inspection.

b. Outdoor Bus System: Includes providing material and services required to complete the outdoor jumper bus installations. Unless otherwise specified on the Drawings, splices, elbows, pad type terminal connectors, and other fittings used on rigid or cable may be 360 degree radial swaged type. If swaged type fittings are used, the fittings and installation tooling shall be furnished by the same manufacturer. Furnish corona shields for all 230-kV pad to pad connections.

c. Substation signs:

(1) Equipment Identification Signs (31 1000) – Lettering on the sign shall be as follows:

(a) NORTH BUS TIE

KE 1393

DISC SW WY2W 230KV

(b) TRANSFER BUS

KE 1397

DISC SW WY2E 230KV

(c) NORTH BUS

KE 593

DISC SW WY3W 230KV

(d) SOUTH BUS

KE 793

DISC SW WY5W 230KV

(e) SOUTH BUS TIE

KE 1093

DISC SW WY8W 230KV

(f) TRANSFER BUS

KE 1097

DISC SW WY8E 230KV

(g) GENERATOR BUS

KE 1091

DISC SW YY8W 230KV

(h) GENERATOR BUS

KE 1095

DISC SW YY8E 230KV

(i) GENERATOR BUS

KE 1090

GND SW ZY8G 230KV

3. Bidding Schedule item “Existing outdoor electrical equipment and material” includes removal and disposal of existing electrical equipment and material.

a. Material to be removed and disposed of is as follows:

(1) Six (6), three-phase, 230-kV, motor operated disconnecting switches designated WY2E, WY2W, WY3W, WY5W, WY8E and WY8W, including motor-operators.

(2) One (1), three-phase, 230-kV, motor operated selector switch designated YY8E-

YY8W-ZY8G.

(3) One (1), single-phase, 230-kV, wave trap designated TY5E2.

(4) Porcelain insulator bells and associated hardware.

(5) Aluminum and copper conductor and associated fittings.

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION

A. GENERAL:

1. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items:

a. Contractor Furnished Data: Submit quantities of all recycled materials to the COR prior to submittal of final invoice.

b. Environmental Requirements (See Section 13.3 of Standard): Comply with all appropriate Federal, State, and local environmental laws and regulations.

c. Landscape Preservation (See Section 13.4 of Standard).

d. Preservation of Cultural Resources (See Section 13.5 of Standard): Do not remove or alter cultural artifacts or paleontological resources (fossils). Cultural artifacts may be of scientific or cultural importance and includes, but is not limited to bones, pottery, glass, projectile points (arrowheads), other stone or metal tools, historic buildings, and features.

Paleontological resources can be of scientific importance and include mineralized animals and plants or trace fossils such as footprints. Both cultural and paleontological resources are protected by Federal Regulations during Federal construction projects. The Contractor shall restrict all ground disturbing activities to areas that have been surveyed by Western for cultural or paleontological resources.

e. Noxious Weed Control (See Section 13.6 of Standard): Comply with Federal, State, and local noxious weed control regulations. Provide a “clean vehicle policy” while entering and leaving construction areas to prevent transport of noxious weed plants and/or seed.

Transport only construction vehicles that are free of mud and vegetation debris to staging areas and the project right of-way.

f. Recycled Material Quantities (See Section 13.7 of Standard): If the products listed below or other products listed are obtained as part of this project, purchase the items with the highest recovered material content possible unless recovered material products are not available: 1) competitively within a reasonable time frame, 2) meeting reasonable performance standards as defined in the Standards or Project Specifications, or 3) at a reasonable price. All recycling proceeds from the project shall be paid to the Western Area Power Administration in check form from the recycler prior to final submittal of the final invoice.

g. Use of Products Containing Recovered Materials (See Section 13.8 of Standard): If the products listed at: http://www.biobased.oce.usda.gov are obtained as part of this project, purchase the items with the highest biobased content possible and no less than the percent indicated for each product unless biobased material products are not available: 1) competitively within a reasonable time frame, 2) meeting reasonable performance standards as defined in the Standards or Project Specifications, or 3) at a reasonable price.

h. Disposal of Waste Material (See Section 13.9 of Standard): Dispose or recycle waste material in accordance with applicable Federal, State and local regulations and ordinances.

In addition to the requirements of the Contract Clause “Cleaning Up”, remove all waste material from the construction site. No waste shall be left on Western property, right-of-way, or easement. Burning or burying of waste material is not permitted.

i. The Contractor’s Liability for Regulated Material Incidents (See Section 13.10 of Standard):

The Contractor is solely liable for all expenses related to spills, mishandling, or incidents of regulated material attributable to his actions or the actions of his subcontractors. This includes all response, investigation, cleanup, disposal, permitting, reporting, and requirements from applicable environmental regulation agencies. The actions of the Contractor employees, agents, and subcontractors shall be properly managed at all times on Western property or while transporting Western’s (or previously owned by Western) regulated material and equipment.

j. Pollutant Spill Prevention, Notification, and Cleanup (See Section 13.11 of Standard).

k. Pesticides (See Section 13.12 of Standard).

l. Treated Wood Poles and Members Recycling or Disposal (See Section 13.13 of Standard).

m. Prevention of Air Pollution (See Section 13.14 of Standard).

n. Handling and Management of Asbestos Containing Material (See Section 13.15 of Standard): In the event asbestos is encountered during demolition or construction notify the COR. The Contractor is responsible for meeting all Federal, State, or local agency requirements regarding the handling and disposal of asbestos.

o. Materials with Lead-Based Paint (See Section 13.16 of Standard): The Contractor is responsible for meeting all Federal, State, or local agency requirements regarding the handling and disposal of lead-based paint used during construction or removed during demolition.

p. Prevention of Water Pollution (See Section 13.17 of Standard): Ensure that surface and ground water is protected from pollution caused by construction activities and comply with applicable regulations and requirements. Ensure that streams, waterways and other courses are not obstructed or impaired unless the appropriate Federal, State or local permits have been obtained. The Contractor is responsible for development and implementation of a Storm Water Pollution Prevention Plan (SWPPP) for the project, if applicable.

q. Testing, Draining, Removal, and Disposal of Oil-Filled Electrical Equipment

(See Section 13.18 of Standard).

r. Removal of Oil-Contaminated Materials (See Section 13.19 of Standard).

s. Conservation of Biological Resources (See Section 13.20 of Standard): Federal law prohibits the “take” of endangered, threatened, proposed or candidate wildlife and plants, and destruction or adverse modification of designated Critical Habitat. Federal law also prohibits the “take” of birds protected by the Migratory Bird Treaty Act, and the Bald and Golden Eagle Protection Act. “Take” means to pursue, hunt, shoot, wound, kill, trap, capture or collect a protected animal or any part thereof, or attempt to do any of those things without a permit from U.S. Fish and Wildlife Service. The Contractor will take precautions to avoid harming other wildlife species. Contractor shall restrict all ground disturbing activities to areas that have been surveyed by Western for natural resources.

t. Known Occurrence of Protected Species or Habitat: Following issuance of the notice to proceed, and prior to the start of construction, Western will provide training to all Contractor and subcontractor personnel and others involved in the construction activity if there is a known occurrence of protected species or habitat in or around the construction area.

Untrained personnel shall not be allowed in the construction area. Western will provide drawings or maps showing sensitive areas located on or immediately adjacent to the construction area. These sensitive areas shall be considered avoidance areas. Prior to any construction activity, the avoidance areas shall be marked on the ground by Western, if necessary.

u. Unknown Occurrence of Protected Species or Habitat: If evidence of a protected species is found in or around the construction area, the Contractor shall immediately notify the COR and provide the location and nature of the findings. The Contractor shall stop all activity within 200-feet of the protected species or habitat and not proceed until directed to do so by the COR.

v. Fueling Vehicles and Equipment: Fueling operations where the potential exists to contaminate the soil, water, or air (not including commercial or approved gas stations), the Contractor will have a spill plan (to identify fuels and its hazards, safe fueling practices, and the safe handling of such material), emergency response plan (with emergency phone numbers, actions taken by specific individuals, and the phone number of a spill “clean up” team), drip pans below the fueling operation to catch fuel leaks, secondary containment for fuel can storage, a policy of all fuel storage containers are sealed tight (except during fueling) to prevent leaks, and a spill kit adequate to stop potential spills.

w. Petroleum Products used in Engines, Transmissions, and Gear Boxes: The Contractor will inspect daily the equipment engines, transmissions, and gear boxes for oil, transmission fluid, and gear oil leaks. The Contractor will repair the leaks prior to operating the equipment except in the case the equipment is being operated solely to move it offsite to minimize environmental damage.

B. SPECIAL REQUIREMENTS:

1. COORDINATION:

a. The Contractor shall perform work only in locations within the Folsom Substation and Elverta Maintenance Facility as defined by Western Biologists and Archaeologists, and Environmental Protection Specialist in order to ensure avoidance of any potential affected sensitive resources.

b. All Contract employees shall attend the one-time environmental awareness training prior to the start of work. Any persons that do not attend the originally scheduled training shall complete the training and have an understanding of the required minimization measures prior to construction and staging activities.

2. SPECIAL CULTURAL RESOURCES REQUIREMENTS

a. In the event of any inadvertent (unanticipated) discovery of a cultural resource, the

Contractor shall stop work within 100-feet and immediately notify the COR and/or the Western SNR Natural Resources Supervisor. Western will have a qualified archaeologist, who meets the Secretary of the Interior’s Standard, evaluate and assess the find (in consultation with the SHPO and local tribes) if the site is prehistoric in nature.

3. SPECIAL BIOLOGICAL REQUIREMENTS:

a. The following are avoidance measures that the Contractor must adhere to in order to avoid impacts to sensitive plant and animal species in and around the construction area. The Contractor must meet with Westerns environmental team (including Westerns biologist and cultural resources specialist) at least 30-days prior to the start of project activities to review impact and avoidance areas.

b. Prior to the start of project activities, all personnel will participate in environmental awareness training which will inform them of the sensitive habitats within the vicinity of the construction area, species that have the potential to occur in or around the construction area and the avoidance and minimization measures that are to be adhered to during construction activities. Any new crew members that start after project activities have commenced will be given the environmental awareness training prior to working onsite.

(1) MIGRATORY BIRDS AND RAPTORS:

(a) Under the Migratory Bird Treaty Act of 1918, migratory bird species and their nests and eggs are protected from injury or death. Impacts to migratory bird nests shall be avoided during the nesting season (March 1 to August 15). If construction activities occur during the nesting season, Western will survey the construction area for migratory bird nests prior to construction activities and establish appropriate buffers around any nests that may potentially be disturbed. If work must be conducted within these buffers, a Western supplied biological monitor will be on site for construction activities within the buffers. If the biological monitor determines that activities are likely to cause nest impacts or nest abandonment, then construction activities in the area shall be postponed until nestlings have fledged or the nest is no longer active.

(2) BURROWING OWL

(a) From February 1 to August 31 activity will be prohibited within 250 feet of potential burrowing owl nesting dens. From September 1 through January 31, disturbance will be prohibited within 160 feet of potential burrowing owl dens.

Or a qualified biologist will conduct nesting and wintering surveys. If nesting or wintering activity is detected, a qualified biologist will mark and monitor an appropriate non-disturbance buffer in the vicinity of burrows that have been active within the last three years. Within the buffer zone, all activities will be prohibited from February 1 to August 31.

(3) VALLEY ELDERBERRY LONGHORN BEETLE (VELB)

(a) If any activities occur outside the Folsom substation fence, prior to project activities, a qualified biologist will flag elderberry shrubs within 100 feet of the project activities. A minimum buffer zone of 20 feet outside of the dripline of each elderberry plant will be provided during all activities.

(4) SEASONAL WETLAND HABITAT (INCLUDING VERNAL POOLS): Although construction activities will be inside the substation, there are sensitive wetland habitats south and southeast of the Elverta Substation where the transformer shell will be placed. The Contractor will adhere to the following measures:

(a) Vehicle access will only be permitted on well-established roads unless soils are dry. Soils will be considered sufficiently dry for vehicle access when they resist compaction, and after annual plants have set seed (generally June 1 to September 30, or as determined by a qualified biologist based on personal observation of the soils).

(b) When feasible, all maintenance activities will be routed around wet areas while ensuring that the route does not cross sensitive resource areas.

(c) If activities are proposed within 250 feet of a seasonal wetland a biological monitor will be present and/or a qualified biologist will clearly mark the limits of the feature(s) or appropriate buffers. A qualified biologist will clearly flag a 50 foot buffer around all seasonal wetland features if work is proposed during the wet season (generally October 1 to May 31) or flag the feature if work is proposed during the dry season (generally June 1 to September 30).

(d) All equipment will be stored, fueled, and maintained in a vehicle staging area

300-feet or the maximum distance possible from any vernal pool, vernal pool grassland, or seasonal wetland, and no closer than 200-feet unless a bermed

(no ground disturbance) and lined refueling area is constructed and hazardous material absorbent pads are available in the event of a spill.

(e) Vehicles will be inspected daily for fluid leaks before leaving the staging area.

4. SPECIAL COMPLIANCE REQUIREMENTS: In addition to items in Section A of this Division 13, the Contractor shall adhere to the following:

a. Prevention of Air Pollution: Folsom Substation is located in Sacramento County, which is under the jurisdiction of the Sacramento Metropolitan Air Quality Management District (SMAQMD). Sacramento County has been designated as non-attainment for Federal ozone and PM 2.5 standards. If an air permit is required, the Contractor is responsible to provide a copy of the Authority to Construct to the COR 14-days prior to the start of work, and to remit a copy of the Permit to Operate to the COR prior to submittal of the final invoice.

For this project, an emergency backup generator will be required to provide power for the substation during the outage. This generator must be permitted by the local air district.

The Contractor will prevent emissions of fugitive dust from becoming airborne and leaving the property during construction operations in accordance with SMAQMD Rule 403, Fugitive Dust by employing Reasonably Available Control Measures to minimize dust. The Contractor will ensure industrial coatings are compliant under SMAQMD Rule 442, Architectural Coatings, and Rule 460, Adhesives and Sealants. All SMAQMD rules may be found here: http://www.airquality.org/businesses/rules-regulations.

Machinery Air Emissions: Diesel and large spark ignition equipment, including machinery, trucks, and all construction equipment used on the project shall be compliant with Federal, State, and local regulations, including those of the California Air Resources Board and SMAQMD. Diesel equipment shall be registered and/or permitted as required. If emissions control devices are required, they shall be installed on the equipment, maintained properly, and used in accordance with the regulations.

b. Prevention of Water Pollution: All projects shall be managed in accordance with Federal, State and local regulations. The Contractor shall utilize best management practices (BMPs) to protect surface and ground water from pollution caused by construction activities. Runoff from excavated areas and piles of excavated material, wastes, or chemical products shall be controlled. Concrete washing shall not be permitted at any source of surface water.

c. Waste Management: All materials generated from the project that can be recycled, shall be recycled. Quantities of recycled and waste materials shall be reported to the COR according to the provisions of Western’s Construction Standards document, section 13.7. Manage hazardous, universal (i.e., fluorescent lamps, aerosol cans, etc.), and non-hazardous wastes in accordance with State and Federal regulations, and in accordance with Western’s Construction Standards document, section 13.7 Disposal of Waste Material. Coordinate all disposals with the COR and disposals of hazardous waste, including oil with Environment.

Environment staff must be on-site to sign hazardous waste manifests generated from the project.

d. Spill Prevention Notification and Cleanup Plan: The project involves the use of pollutants including oil, etc., therefore a spill prevention and notification plan must be submitted to the COR for review and comment at least 14-days prior to the start of work. Pollutants include any hazardous or non-hazardous substance, that when spilled, will contaminate soil, surface water or ground water. This includes any solvent, oil, paint, pesticide, engine coolants, and similar substances. The plan shall be prepared in accordance with Section 13.11:

This plan shall describe spill prevention measures used at the jobsite to prevent spills.

The plan shall describe the procedures for notification in the event of a spill.

If a hazardous substance spill exceeds 10 gallons or if any amount has been released to surface water, or storm drains, the COR and WAPA Environmental Compliance staff shall be notified.

(1) WAPA COR or Technical Representative: To be determined.

(2) WAPA Environmental Compliance: Kristen Dalldorf, (916)397-9186.

WAPA Environmental Compliance staff shall be responsible to make notifications to state agencies including the Cal OES State Warning Center (800) 852-7550, the National Response Center (800) 424-8802 (if the spill >42 gallons on land), and respective local agencies.

The plan shall describe awareness training procedures implemented to ensure personnel are knowledgeable about the contents of the Plan and the need for notification.

The plan shall identify a commitment of manpower including equipment and materials.

Message from the Administrator

At Western, we show our commitment to safety every day through the actions we take, the training we offer and the work conditions we provide. We expect the same commitment to safety from each of our contractors who provide products or services to Western. In performing work for Western, all contractors must make the right decisions to ensure that the work environment is as safe as possible.

Our safety program is based on four points:

Safety procedures or common sense must be applied by each Federal and contract employee. Safety should not be set aside to meet a project schedule or for personal convenience.

Employees and contractors must believe that they have the right and the responsibility to identify and take action to reduce, if not eliminate, hazardous work environments and hazardous work practices.

Managers and supervisors must lead by example and execute their responsibility to ensure each job is accomplished in a safe and healthy way.

Safety is a personal responsibility. Each individual makes the decision on what action to take to accomplish a task.

By integrating these principles into every task we take, together we can ensure Western is a safe place to work.

Mark A. Gabriel Administrator

DIVISION 1 – GENERAL REQUIREMENTS
A. CONTRACT REQUIREMENT:
B. DESCRIPTION OF WORK:
1. THE PRINCIPAL COMPONENTS OF WORK include the following:
C. DESCRIPTION OF BIDDING SCHEDULE ITEM:
1. Bidding Schedule item “Mobilization and preparatory work” includes the following:
1) Size and Arrangement: At least 250-square feet (minimum) consisting of two (2) separate rooms (one (1) office and one (1) larger workroom).
2) Heating and Cooling: Heating and cooling unit sized to provide adequate heating and cooling.
3) Lighting and Electrical: Adequate lighting and 110 V electrical outlets.
4) Utilities: Make all arrangements and pay all costs for providing utilities, including potable drinking water, electrical power, and heating and cooling energy.
5) Toilet Facilities: Toilet facilities shall be provided in the immediate vicinity of the office and shall be maintained.
D. COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK:
1. COMMENCEMENT, PROSECUTION, AND COMPLETION OF THE WORK. See FAR 52.211-10 in Section F of the solicitation/contract.
2. SUBMITTAL APPROVAL TIME: Except as otherwise provided for specific submittals, Western will require 20-calendar days for review of drawings or data submitted for approval.
3. OUTAGE AND CONSTRUCTION SCHEDULE RESTRICTIONS: In addition to the restrictions listed in Construction Standard 1, the following outage and schedule restrictions shall apply:
a. Outage Restrictions
i. General:
(1) All bus work shall be performed in a manner such that the bus can be returned to service within 48-hrs of notification by Western.
(2) All outages are subject to system restrictions and conditions. This may require work be performed on weekends and/or evenings.
ii. Keswick
4. PROTECTIVE GROUND LEADS: See Western Construction Standards, Standard 1 “General Requirements”, Section 1.4.14.3(1).
5. MAXIMUM AVAILABLE FAULT CURRENT: When protective ground leads are required, the protective ground leads shall be sized as defined below and shall meet the requirements of Standard 1 – General Requirements, Section 1.4 “Safety and Health” and the f...
E. CONSTRUCTION SCHEDULE:
1. SUBMITTAL TIME: Prepare and Submit a Construction Schedule to the Contracting Officer’s Representative (COR) within 45-calendar days after date of Notice to Proceed.
2. FORMAT AND DETAIL: Dates for each item of Government-furnished material shall be provided. Do not program dates earlier than the estimated delivery dates shown in the “Material” paragraph.
F. MATERIAL: Furnish all material for completing the work, except material furnished by Western as listed below:
1. POINTS-OF-DELIVERY: The disconnecting switches will be delivered to Keswick Substation (except as noted). The Contractor shall load, transport and unload the material to the jobsite. The Contractor shall inspect the equipment and report any dama...
G. ELECTRIC POWER FOR CONSTRUCTION PURPOSES:
H. WATER FOR CONSTRUCTION PURPOSES:
I. EXPLOSIVES AND BLASTING:
J. SUBMITTALS:
1. GENERAL: Submittals must be provided in accordance with the Construction Standards and Project Specifications. The Contractor shall furnish submittals electronically (i.e. e-mail), unless otherwise specified by the COR. Submittals shall be sent ...
2. APPROVAL TIME: Approval time for submittals shall be in accordance with the “Commencement, Prosecution, and Completion of Work” paragraph.
3. ADDRESS: The Contractor shall transmit specified non-electronic submittals to the following address:
4. PROJECT PROTOCOL:
DIVISION 9 – SUBSTATION - ELECTRICAL
A. GENERAL: Electrical equipment and material shall be as specified in Western’s “WAPA ES” Standard Equipment Specifications, as shown on project drawings, and in accordance with NEMA, ANSI, IEEE, ICEA, ASTM, NEC, NESC, UL, and Federal specifications...
1. For all Government-furnished Bidding Schedule items, the Contractor shall:
2. For all Contractor-furnished Bidding Schedule items, the Contractor shall:
3. Unless otherwise specified, associated support structures provided for each electrical equipment rated above 7-kV shall be 102-inches in height and hot-dip galvanized, if made of steel. Instrument transformers that are seismically qualified shall ...
4. Installation and painting of electrical equipment and material shall be provided in accordance with Standards 9 and 12 respectively.
B. DESCRIPTION OF BIDDING SCHEDULE ITEMS:
1. Bidding Schedule items “Motor operated disconnecting switch, 230-kV, 2,000 amps (Government-furnished)” and “Motor operated selector switch with grounding blades, 230-kV, 2,000 amps (Government-furnished)” includes furnishing all equipment and mate...
2. Bidding Schedule item “Associated electrical equipment and material” includes providing equipment, material, and services required to complete the following substation installations as shown on the Drawings:
KE 1393
DISC SW WY2W 230KV

3. Bidding Schedule item “Existing outdoor electrical equipment and material” includes removal and disposal of existing electrical equipment and material.

DIVISION 13 – ENVIRONMENTAL QUALITY PROTECTION
A. GENERAL:
1. Bidding Schedule does not contain separate items for the following. Include these items in applicable Bidding Schedule items:
B. SPECIAL REQUIREMENTS:
1. COORDINATION:
2. SPECIAL CULTURAL RESOURCES REQUIREMENTS
3. SPECIAL BIOLOGICAL REQUIREMENTS:
4. SPECIAL COMPLIANCE REQUIREMENTS: In addition to items in Section A of this Division 13, the Contractor shall adhere to the following: