Clarification Questions W9128F21Q0076 Zorinsky Tree Clearing.docx
DOCX document 20 KB Posted
- Attached to
- W9128F21Q0076 - Zorinsky Tree Removal Phase 2 Federal contract opportunity
- Solicitation number
- 8587
About this file
This document contains clarification questions and responses regarding a solicitation for tree removal services. The solicitation is for Phase 2 of the Zorinsky Tree Removal project located at Papio Creek Site 18 - Lake Zorinsky and requires creating a 30-foot wide firebreak zone by removing all trees 6 inches in diameter or larger a minimum of 6 inches below ground along the property line. The clarification responses specify that progress payments may be allowed if requirements are met, 20% retainage will be held until final inspection for each line item, and the contractor is responsible for repairing any failed seed establishment areas over 50 square feet during the one-year warranty period. The contractor must control weeds during all phases and till all disturbed areas, including near the fence line, to a depth of 6 inches. A temporary creek crossing may be allowed pending regulatory approval but would not extend the 365-day period of performance. The site visit will be on September 1, 2021 at 10:00 a.m. at a location provided by contacting the specified Corps representative.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 1 Project Maps Rev 002.pdf | ||
| Site Visit Sign In Sheet 1 Sep 2021 .pdf | ||
| Amendment 0002 W9128F21Q0076 Zorinsky Tree Removal.pdf | ||
| Amendment 0001 W9128F21Q0076 Zorinsky Tree Removal.pdf | ||
| Attachment 1 - Project Maps Areas 00-09 Revised.pdf | ||
| Zorinsky Site Visit Location Map.pdf | ||
| Attachment 1 - Project Maps.pdf | ||
| W9128F21Q0076 Zorinsky Tree Removal Phase 2- 8587.pdf | ||
| Attachment 2 - PesticideAppRecord.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Clarification Questions for W9122F21Q0076, Zorinsky Tree Clearing
1. Would progress payments be approved during performance of this project? If so what requirements would need to be meet to allow contractor to submit a request for progress payment. What would be the frequency of progress payments?
USACE RESPONSE: See Amendment 002
2. Would there be any retainage held back after final inspection for the 1 year seed growth warranty period? If so, what would be the percentage of retainage for each line item?
USACE RESPONSE: See Amendment 002. 20% is retained until the final inspection and all work is completed and accepted for each CLIN item. The contractor shall be responsible to repair any areas greater than 50 square feet that did not establish during the 1 year warranty period after final acceptance.
3. Would maintenance during the 1 year seed growth warranty period be required such as mowing, trimming of fence lines, control of weeds, and control of any regrowth of trees be required? If the newly seeded areas are damaged due to vehicle traffic, weather, flooding or any other means would the contractor be required to repair or reseed affected areas if greater than 50 square feet in size?
USACE RESPONSE: Contractor shall ensure all weed plants are controlled and killed during all phases of the work as stated in the PWS. The contractor shall guarantee the seed to be established for one full year after the final inspection and acceptance. The contractor shall reseed any areas greater than 50 square feet of failed seed establishment as determined by the COR.
4. Referencing paragraph 17 of the Performance Work Statement please clarify if all areas will need to be tilled to a depth of at least 6" or just the areas that were compacted by heavy equipment. Would the areas close to and inside the woven wire fence need to be tilled to a depth of at least 6"?
USACE RESPONSE: Contractor shall prepare ground surfaces, fertilize, seed, provide erosion control and mulch all disturbed ground surfaces as shown on the drawings or in all areas disturbed as a part of the work in this PWS. All areas including the areas around the wire fence and disturbed as a part of the work in this PWS shall be tilled to a depth of 6 inches to allow root penetration and prepared.
5. Referencing Map Area 00 would a temporary creek crossing be allowed? If so, what requirements would need to be meet? Could a temporary culvert be installed?
USACE RESPONSE: Temporary creek crossing would have to be submitted for approval through the USACE regulatory office. Time for the approval would not be added to the period of performance.
6. Would weather delay days, or work restriction days imposed as a result of bird surveys conducted according to the Bald and Golden Eagle Protection Act and Migratory Bird Treaty Act, be added onto the performance period?
USACE RESPONSE: No, the period of performance is 365 days and unless unusual Midwest weather is encountered the contractor shall prepare for normal Midwest weather year when preparing his work plan and work schedule. All trees identified in this Performance Work Statement (PWS) shall be felled between September 1 and April 1 and the Contractor shall follow all Local, State, and Federal wildlife laws and regulations regarding the Bald and Golden Eagle Protection Act, Migratory Bird Treaty Act, and the Endangered Species Act.