About this file

This Invitation for Bids (IFB) is issued by King George County, Virginia for the complete design, permitting, fabrication, supply, delivery, and installation of prefabricated animal housing kennel systems at the King George Animal Control facility located at 11377 Citizens Way, King George, VA 22485. The project requires furnishing and installing a comprehensive kennel package including 24 indoor dog run stall-front assemblies (approximately 48"-49" wide by 75" high) with clear tempered glass gates, 22 side/division panels, 20 overhead braces, 24 flip-up rest benches, 24 document holders, plus additional components for dog isolation areas (2 stall-front assemblies, 2 side panels, 1 overhead brace, 3 document holders) and whelping areas (2 stall-front assemblies, 1 side panel, 2 document holders). Systems must be equal to or superior to Midmark Sani-Kennel specifications and include heavy-gauge stainless-steel framing, clear tempered safety glass, and non-porous chemical-resistant FRP infills. The mandatory pre-bid meeting and site visit is scheduled for November 30, 2026, at 10:00 a.m. Bids are due December 16, 2026, at 2:00 p.m. All work must be completed within 120 consecutive calendar days from the Notice to Proceed. The contract will be awarded to the lowest responsive and responsible bidder. Questions must be submitted in writing to Procurement Specialist Austin Wessel by 1:00 p.m. on December 4, 2026.

The bid must be submitted as a firm fixed price including all labor, design, engineering, permitting, materials, equipment, supervision, fabrication, delivery, installation, testing, disinfection, coordination, disposal, restoration, insurance, bonds, overhead, profit, and incidental work. Bidders must demonstrate a minimum of five years of comparable experience and provide three references from projects completed within the past three years. The contractor must obtain all required permits and approvals from King George County and other authorities having jurisdiction, with all permit fees included in the contract price. Warranty requirements include minimum five-year coverage for structural components, manufacturer's standard commercial warranty (minimum two years) for finishes and coatings, and one-year workmanship warranty from final acceptance. Contractors must provide Performance and Payment Bonds as required by Virginia law and submit bid security of five percent of the maximum bid price. General Liability insurance, Automobile Liability insurance, and Workers' Compensation insurance are required, with King George County listed as additional insured. The contractor is responsible for applicable taxes unless otherwise stated. Concrete bases, floor drains, plumbing, electrical, and HVAC modifications are excluded unless specifically added by change order.

View the file

Other files

File Type Posted
849651snowClarke.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

King George County – Animal Control Kennel Housing Furnish & Install | IFB # 26-1110

KING GEORGE COUNTY, VIRGINIA

INVITATION FOR BIDS

IFB # 26-1110

KING GEORGE COUNTY ANIMAL CONTROL

KENNEL HOUSING FURNISH & INSTALL

11377 Citizens Way, King George, VA 22485

ISSUE DATE: November 10, 2026 BID DUE DATE: December 16, 2026 AT 2:00

P.M.

PRE-BID MEETING / SITE VISIT: November 30, 2026 AT 10:00 A.M

PROCUREMENT CONTACT

Austin Wessel – Procurement Specialist King George County

10459 Courthouse Drive, Suite 201 King George, VA 22485

Phone: (540) 775-8525 | Fax: (540) 775-7692 E-mail: awessel@co.kinggeorge.state.va.us

BIDS MUST BE MARKED:

IFB # 26-1110 – KING GEORGE COUNTY ANIMAL CONTROL KENNEL HOUSING FURNISH & INSTALL

BIDDER'S NAME AND ADDRESS MUST BE VISIBLE ON THE OUTER DELIVERY PACKAGE.

Name and Address of Firm/Individual Submitting Bid:

Date: By: (Signature in Ink) Virginia State Contractor's #: Telephone:

E-mail: Tax ID #:

Virginia State Corporation Commission No.:

Questions: All questions must be submitted in writing directly to the King George County Procurement Specialist at the address referenced above. Questions will be accepted until 1:00 PM, December 4, 2026.

Questions may be sent by fax or email.

DO NOT RETURN ALL PAGES OF THIS IFB PACKAGE – SEE SECTION

17.0 mailto:awessel@co.kinggeorge.state.va.us

TABLE OF CONTENTS

1.0 PURPOSE

2.0 COMPETITION INTENDED

3.0 PERIOD OF CONTRACT

4.0 PRE-BID MEETING / SITE VISIT

5.0 EXAMINATION OF IFB DOCUMENTS AND WORK SITE

6.0 SPECIFICATIONS / SCOPE OF WORK

7.0 AWARD

7.1 NEGOTIATION WITH LOWEST RESPONSIBLE BIDDER

8.0 WARRANTY

9.0 DELIVERY / PROJECT COMPLETION

9.1 FAILURE TO PERFORM / RIGHT OF COUNTY TO CURE

10.0 IFB AND BID CLARIFICATION

11.0 QUALIFICATIONS

12.0 INSURANCE

13.0 TAXES

14.0 PERFORMANCE, PAYMENT, AND BID BONDS

15.0 REFERENCES

16.0 COOPERATIVE PROCUREMENT

17.0 BID SUBMISSION REQUIREMENTS

18.0 LATE BIDS

19.0 FACILITY CLOSURE

20.0 BID FORM – COVER SHEET

20.1 CERTIFICATION OF AUTHORITY TO TRANSACT BUSINESS

21.0 BID FORM / BID SCHEDULE

ATTACHMENTS / CONTRACT DOCUMENTS

Attachment A – King George County General Terms and Conditions.

Attachment B – Contractor Certification Relating to Background Checks, if applicable.

Attachment C – Sample Construction Services Agreement.

Attachment D – Davis Bacon Prevailing Wages

KING GEORGE COUNTY, VIRGINIA

Animal Control Kennel Housing Furnish & Install

INVITATION FOR BIDS

This Invitation for Bids, together with the resulting contract, shall be consistent with and governed by the King George County Purchasing Ordinance and applicable provisions of the Virginia Public Procurement Act. Each individual or firm submitting a response is a “Bidder.” A Bidder whose bid results in an award is a “Contractor.”

1.0 PURPOSE

The purpose and intent of this IFB is to obtain a firm fixed price from a qualified Contractor for the complete design, permitting, fabrication, supply, delivery, and installation of prefabricated animal housing kennel systems equal or superior in quality, quantity, and performance to the Mid-Mark Sani-Kennel systems and the specifications described below. The contractor may work directly with a manufacturer of the housing system.

The Contractor shall provide all labor, design, engineering, permitting, materials, equipment, supervision, and incidentals necessary to deliver a complete, fully installed, and operational kennel system for the King George Animal Control facility.

2.0 COMPETITION INTENDED

It is KGC's intent that this IFB permit full and open competition. It shall be the Bidder's responsibility to advise the Procurement Specialist, in writing, if any language, requirement, specification, or combination thereof inadvertently restricts or limits competition. Written notice shall be received no later than five (5) business days prior to the date set for bids to close. King George County does not discriminate against faith-based organizations in accordance with the Code of Virginia, § 2.2-4343.1 or against any Bidder because of race, religion, color, sex, national origin, age, disability, or any other basis prohibited by law relating to discrimination in employment.

3.0 PERIOD OF CONTRACT

All Work shall be completed within 120 consecutive calendar days from the date of the Notice to Proceed, unless a written change or extension is authorized by the County.

4.0 PRE-BID MEETING / SITE VISIT

A mandatory pre-bid meeting/site visit is scheduled for November 30, 2026, at 10:00 am. The meeting will be held at 11377 Citizens Way, King George, VA 22485, unless otherwise stated by written addendum. The purpose is to acquaint interested firms with site conditions and the requirements of the IFB.

If attendance is designated mandatory by the County, attendance shall be a prerequisite to submitting a bid. The selected Contractor will not be relieved from responsibility for properly estimating the difficulty and cost of performing the Work because of failure to become acquainted with site conditions.

5.0 EXAMINATION OF IFB DOCUMENTS AND WORK SITE

Before submitting a Bid, each Bidder shall examine the IFB Documents thoroughly; visit the site; familiarize itself with federal, state, and local requirements; correlate its observations with the IFB Documents; and notify the Procurement Specialist of conflicts, errors, omissions, or discrepancies.

The County has not performed work or investigations associated with the location of all existing utilities. The Bidder shall independently verify existing conditions, utility locations, access, grades, drainage, soil conditions, and other conditions affecting the Work. Utility locating shall be coordinated through Virginia 811 and applicable utility owners.

Bidders may, at their own expense and under County coordination, conduct additional examinations, investigations, tests, and studies necessary to establish their Bid.

6.0 SPECIFICATIONS / SCOPE OF WORK

This is a design-build solicitation under the Virginia Public Procurement Act. The County seeks a single firm fixed-price proposal for the complete design, permitting, fabrication, supply, delivery, and installation of prefabricated animal housing kennel systems equal or superior in quality, quantity, and performance to the Midmark Sani- Kennel product line and the specifications described below. The contractor may work directly with a manufacturer of the housing system.

6.1 DESIGN-BUILD SCOPE

The Contractor shall provide all design, engineering, permitting, materials, labor, equipment, supervision, and incidentals necessary to deliver a complete, fully installed, and operational kennel system. Work includes:

• Final design and layout coordinated with existing room dimensions and County requirements

• Preparation and submission of all design submittals, shop drawings, and product data to the County for review and approval prior to fabrication

• Obtaining all required permits and approvals from King George County and any other authority having jurisdiction

• Fabrication, delivery, and complete installation of all kennel components

• Final cleanup and turnover of a fully functional system

6.2 DESIGN SUBMITTALS

Prior to fabrication and installation, the Contractor shall submit the following to the County for review and written approval:

• Complete product data and catalog cuts

• Shop drawings showing dimensions, hinge orientation, panel layout, hardware, and room fit

• Material certifications (stainless steel grade, glass type, FRP specifications)

• Color samples for FRP infill and any coated components

• Installation plan and schedule coordinated with County operations

• Point-by-point equivalency comparison if proposing an alternate manufacturer

No fabrication or installation shall proceed until the County has approved the design submittals in writing.

6.3 PERMITTING

• The Contractor shall be responsible for preparing, submitting, and obtaining all permits and approvals required for the work, including building, trade, or other permits issued by King George County or other authorities having jurisdiction. All permit fees shall be included in the contract price. The Contractor shall coordinate inspections and close out all permits upon completion.

6.4 KENNEL SYSTEMS TO BE PROVIDED

Furnish and install a complete kennel package including all stall fronts, side panels, overhead braces, flip-up rest benches, document holders, and hardware for the following areas:

Indoor Dog Runs

• 24 stall-front assemblies (approx. 48"–49" wide × 75" high) with clear tempered glass gates and fixed fronts, double bowl brackets, mixed left- and right-hinged

• 22 side/division panels (72" × 75") with wire-over-stainless-steel infill

• 20 overhead braces (48" × 72")

• 24 flip-up rest benches with FRP infill

• 24 document holders (8.5" × 11") and complete hardware kit

Dog Isolation

• 2 stall-front assemblies (48" × 75") with narrow gates, clear glass, double bowl brackets

• 2 side panels (72" × 75") with full stainless-steel infill

• 1 overhead brace, 3 document holders, and complete hardware kit

Whelping

• 2 stall-front assemblies (approx. 60"–61" wide × 75" high) with clear glass, double bowl brackets

• 1 side panel (72" × 75") with full stainless-steel infill

• 2 document holders and complete hardware kit

6.5 MATERIALS & PERFORMANCE

• Heavy-gauge stainless-steel or equivalent corrosion-resistant framing suitable for wet service and chemical cleaning

• Clear tempered safety glass for gates and fixed fronts

• Non-porous, chemical-resistant FRP (or equal) rest-bench infills

• Systems designed for commercial veterinary / animal-shelter use and independent run cleaning

6.6 INSTALLATION & EXCLUSIONS

The Contractor shall furnish all labor, tools, equipment, and supervision to fully install the kennel systems in the designated rooms. Installation includes assembly, anchoring as required, adjustment of gates and hardware, and verification that all components operate properly. The Contractor shall protect existing finishes and repair any damage caused by its operations. Work shall be coordinated with County staff to minimize disruption to facility operations and done based on a mutually agreed upon phased schedule.

Concrete bases, floor drains, plumbing, electrical, and HVAC modifications are excluded unless specifically added by change order.

6.7 WARRANTY

• Structural components: minimum five (5) years

• Finish, coating, and glass: manufacturer’s standard commercial warranty (minimum two years)

• Workmanship: one (1) year from final acceptance

• All warranties shall run to the benefit of King George County

7.0 AWARD

Award will be made to the lowest responsive and responsible Bidder meeting the specifications. KGC reserves the right to reject any or all bids, waive informality, delete items before award, and determine whether proposed

Work is acceptable. KGC intends to enter into a construction services agreement and issue a Notice to Proceed.

7.1 NEGOTIATION WITH LOWEST RESPONSIBLE BIDDER

If the low responsive and responsible bid exceeds available funds, KGC may negotiate with the low Bidder to obtain a contract price within available funds, consistent with applicable law.

8.0 WARRANTY

All materials and workmanship shall be warranted for one year following completion and acceptance unless a longer warranty is required by the plans, specifications, manufacturer or law. Defective or nonconforming Work shall be corrected at no additional cost.

9.0 DELIVERY / PROJECT COMPLETION

All Work shall be performed at 11377 Citizens Way, King George, VA 22485. The Contractor shall furnish all tools, equipment, labor, materials, transportation, supervision, testing, permits and incidentals. Completion shall occur within the period stated in Section 3.0.

9.1 FAILURE TO PERFORM / RIGHT OF COUNTY TO CURE

Failure to comply with the IFB or resulting contract may constitute default. If the Contractor is found in default, KGC may obtain required goods/services on the open market and the Contractor may be responsible for resulting costs to the extent permitted by law and contract.

10.0 IFB AND BID CLARIFICATION

All inquiries must be submitted in writing to the Procurement Specialist. Oral interpretations are not binding. A written addendum issued by the Procurement Specialist is the only official method for changing or clarifying this

IFB.

11.0 QUALIFICATIONS

Bidders shall have a minimum of five (5) years of demonstrated experience performing comparable site-development, earthwork, utility, concrete and paving work, unless otherwise approved by the County. Bidders must be authorized as required by law to transact business in Virginia and shall provide applicable SCC information or exemption and comply with King George County business licensing requirements.

11.1 BUSINESS LICENSE:

All firms doing business in King George County shall be licensed in accordance with the KGC’s Business Licensing regulations.

The King George County Business License requirements are as follows:

If a Contractor holds a Business License in the jurisdiction it’s home office is located, then a King George County Business License is not required unless the amount earned in King George County during a calendar year is $25,000 or greater.

If a Contractor does not hold a Business License from its home jurisdiction, then a King George County Business License is required when any calendar year’s earnings within King George County are expected to meet or exceed $2,500.

12.0 INSURANCE

The Contractor shall comply with the insurance requirements set forth in the following numbered paragraphs and those required under the Commonwealth of Virginia statutory requirements. The Contractor shall provide KGC a certified Certificate of Insurance, with King George County listed as additional insured before a contract is executed and any work is started. These certified copies shall be sent to the KGC Procurement Manager from the Contractor’s insurance agent or representative. Certificates of Insurance submitted to KGC shall have the corresponding Contract/Agreement number noted on them.

12.1 The Contractor shall be responsible for its work and every part thereof, and for all materials, equipment, and property of any and all description used in connection therewith. The Contractor assumes all risks of direct and indirect damage or injury to any person or property wherever located, resulting from any action, omission, commission, or operation under the contract, or in connection in any way whatsoever with contracted work.

12.2 The Contractor shall, during the continuance of all work under the contract, provide and agree to maintain the following:

12.2.1 Worker’s Compensation and Employees insurance under the Commonwealth of Virginia statutory requirements, to protect the Contractor from any liability or damages for any injuries (including death and disability) to any and all of its employees, or subcontractors, including any and all liability or damage which may arise by virtue of any statute or law in force with the Commonwealth of Virginia, or which may be hereinafter enacted.

12.2.2 General Liability insurance sufficient to protect the Contractor, its subcontractors, and the interest of KGC, against any or all injuries to third parties, including bodily injury and personal injury, wherever located, resulting from any action or operation under the Contract or in connection with the contracted work. The General Liability insurance shall also include the Broad Form General Liability endorsement, in addition to coverages for explosion, collapse, and underground hazards, where required. Completed Operations Liability coverage shall continue in force for one year after completion of work.

12.2.3 Automobile liability insurance, including property damage, covering all owned, non-owned, borrowed, leased, or rented vehicles operated by the Contractor and/or his/her subcontractors in the performance of the work. In addition, all mobile equipment used by the Contractor in connection with the contracted work, will be insured under either a standard Automobile Liability Policy, or a Commercial General Liability policy.

12.2.4 Liability insurance may be arranged by General Liability and Automobile Liability policies for the full limits required, or by a combination of underlying liability policies for lesser limits with the remaining limits provided by an Excess or Umbrella Liability policy.

12.2.5 The Contractor shall secure and maintain all insurance policies of its subcontractors. Those policies shall be made available to KGC on request.

12.2.6 No change, cancellation, or non-renewal shall be made to any insurance coverage without a thirty (30) day written notice to KGC Procurement Manager. The Contractor shall furnish the KGC Procurement Manager a new prior to any change or cancellation date. The failure of the Contractor to deliver a new and valid certificate will result in suspension of all payments until the new certificate is furnished to KGC Procurement Manager.

12.2.7 Insurance coverage required in these specifications shall be in force throughout the contract term.

Should the Contractor fail to provide acceptable evidence of current insurance within five (5) days of written notice at any time during the contract term, KGC shall have the absolute right to terminate the contract without any further obligation to the Contractor, and the Contractor shall be liable to KGC for the entire additional cost of procuring the incomplete portion of the Contract at time of termination.

12.2.8 Compliance by the Contractor and all subcontractors with the foregoing requirements shall not relieve the Contractor and all subcontractors of their liabilities and obligations under this heading or under any other section or provisions of this contract.

12.2.9 Contractual and other Liability insurance provided under the Contract shall not contain a supervision, inspection, or services exclusion that would preclude KGC from supervising and/or inspecting the work as the end result. The Contractor shall assume all on-the-job responsibilities for the control of persons directly employed by it, the subcontractors, any person employed by the subcontractor.

12.2.10 Nothing contained herein shall be construed as creating any contractual relationship between any subcontractor and KGC. The Contractor shall be as fully responsible to KGC for the acts and omissions of the subcontractors and of persons employed by them as it is for the acts and omissions of persons directly employed by it.

12.2.11 Precaution shall be exercised at all times for the protection of persons (including employees) and property.

The Contractor, and all subcontractors, are to comply with the Occupational Safety and Health Act of 1970, Public Law 91-956, as it may apply to the Contract.

13.0 TAXES

Contractor and subcontractors are responsible for applicable taxes associated with the Work unless otherwise stated in the Agreement. County tax-exempt status shall be applied where legally applicable.

14.0 PERFORMANCE, PAYMENT, AND BID BONDS

The Contractor shall provide Performance and Payment Bonds as required by the General Conditions and applicable Virginia law. Each Bid shall be accompanied by Bid Security in the amount of five percent (5%) of the maximum Bid price in an acceptable form. The Successful Bidder shall execute the Agreement and furnish required contract security within fifteen (15) days after Notice of Award unless otherwise specified.

15.0 REFERENCES

Provide at least three (3) references from the past three years for comparable site-development, earthwork, utility, concrete and paving projects, including contact name, address and telephone number.

16.0 COOPERATIVE PROCUREMENT

As authorized by the Code of Virginia, this procurement may be used by other public bodies, agencies, institutions and localities with the consent of the Contractor and subject to the resulting contract.

17.0 BID SUBMISSION REQUIREMENTS

Submit the pages 1, 12, 13, 14 the required references, IRS Form W-9, proof of authorization to transact business in Virginia when applicable, Bid Security and all other required documents. Acknowledge all addenda.

Bid prices shall include permitting, excavation, grading, materials, delivery, installation, testing, disinfection, coordination, disposal, restoration, insurance, bonds, overhead, profit and incidental work necessary for complete performance. Prices shall remain fixed unless changed by authorized written change order. Bids shall remain valid for ninety (90) days after opening.

18.0 LATE BIDS

Late Bids will be rejected and returned unopened. It is the Bidder's responsibility to ensure receipt before the deadline.

19.0 FACILITY CLOSURE

If County offices are closed due to inclement weather or emergency conditions on the bid due date, Bids will be due at the same time on the next business day the County office is open, unless otherwise announced.

20.0 BID FORM – COVER SHEET

The Bidder agrees to furnish all labor, materials, equipment, services and incidentals required to complete the Kennel Housing System for King George County Animal Control at 11377 Citizens Way, King George, VA 22485, in accordance with this IFB, attached plans, addenda and resulting contract.

20.1 CERTIFICATION OF AUTHORITY TO TRANSACT BUSINESS

Is Contractor organized or authorized to transact business in the Commonwealth pursuant to Title 13.1 or Title 50 of the Code of Virginia? YES NO

SCC identification number:

If exempt, explain:

Date:

Firm/Individual Submitting Bid (Signature):

Firm/Individual Submitting Bid (Print):

Title:

An IRS Form W-9, references, Bid Security and proof of Authorization to Conduct Business in the Commonwealth (if applicable) must be submitted with the Bid.

21.0 BID FORM / BID SCHEDULE

Each lump-sum price shall include all labor, materials, equipment, mobilization, demobilization, permits, testing, coordination, disposal, restoration, insurance, bonds, overhead, profit and incidentals necessary to complete the item.

TOTAL BASE BID PRICE (numbers): $

TOTAL BASE BID PRICE (in words):

The undersigned agrees to complete all required Work within 120 consecutive calendar days from the Notice to Proceed.

Addendum No. Date: Addendum No. Date: Addendum No. Date:

Authorized Agent: Title:

Signature: Date:

Company: Virginia Contractor License No.:

CONTRACTOR ACKNOWLEDGMENT

The Bidder acknowledges that it has examined the IFB, visited or had the opportunity to visit the site, reviewed the complete attached plan set, and included all labor, materials, equipment, permits, testing, coordination and incidental work necessary to complete the Work.

Firm:

Authorized Representative:

Signature:

Date:

TABLE OF CONTENTS
ATTACHMENTS / CONTRACT DOCUMENTS
1.0 PURPOSE
2.0 COMPETITION INTENDED
3.0 PERIOD OF CONTRACT
4.0 PRE-BID MEETING / SITE VISIT
5.0 EXAMINATION OF IFB DOCUMENTS AND WORK SITE
6.0 SPECIFICATIONS / SCOPE OF WORK
6.1 DESIGN-BUILD SCOPE
6.2 DESIGN SUBMITTALS
6.3 PERMITTING
6.4 KENNEL SYSTEMS TO BE PROVIDED
6.5 MATERIALS & PERFORMANCE
6.6 INSTALLATION & EXCLUSIONS
6.7 WARRANTY
7.0 AWARD
7.1 NEGOTIATION WITH LOWEST RESPONSIBLE BIDDER
8.0 WARRANTY
9.0 DELIVERY / PROJECT COMPLETION
9.1 FAILURE TO PERFORM / RIGHT OF COUNTY TO CURE
10.0 IFB AND BID CLARIFICATION
11.0 QUALIFICATIONS
11.1 BUSINESS LICENSE:
12.0 INSURANCE
13.0 TAXES
14.0 PERFORMANCE, PAYMENT, AND BID BONDS
15.0 REFERENCES
16.0 COOPERATIVE PROCUREMENT
17.0 BID SUBMISSION REQUIREMENTS
18.0 LATE BIDS
19.0 FACILITY CLOSURE
20.0 BID FORM – COVER SHEET
20.1 CERTIFICATION OF AUTHORITY TO TRANSACT BUSINESS
21.0 BID FORM / BID SCHEDULE
CONTRACTOR ACKNOWLEDGMENT

File details come from the government source that posted it. Updated .