About this file

This is a Project Manual and Invitation to Bid (ITB No. 26-2975-6JOK) issued by the County of Henrico, Virginia Department of Finance, Purchasing Office for the Tuckahoe Park Bond Project. The project involves new construction and extensive renovation at an existing Tuckahoe Little League facility located at 2400 Little League Drive, Henrico, VA 23233. The scope includes construction of two fully accessible restrooms with utility infrastructure, one new asphalt parking lot with accessible parking and associated amenities, renovation of two existing asphalt parking lots, a new dumpster enclosure, multi-use trails, sidewalks, a pedestrian bridge, and an accessible community playground. Additional work encompasses utility infrastructure installation (water and sanitary sewer), site lighting, earthwork, grading, stormwater piping, best management practice (BMP) installation, and concrete flatwork, along with supporting activities including DEQ/USACOE permit compliance, Henrico County Plan of Development compliance, tree clearing, stormwater improvements, and landscaping. Sealed bids must be submitted electronically through ProcureWare at https://henrico.procureware.com no later than 2:00 PM local time on August 3, 2026, with public opening and reading via Microsoft Teams immediately thereafter. A non-mandatory pre-bid conference is scheduled for 2:00 PM on July 13, 2026 at the project site. Substantial completion must be achieved within 515 calendar days after the Notice to Proceed, with final completion within 30 days thereafter.

Bidders must submit a 5% bid security via cashier's check, certified check, or bid bond payable to the County of Henrico, Virginia. The successful bidder must be a Virginia-registered contractor with a Class A contractor's license and possess relevant experience with comparable projects in nature, size, complexity, and cost. Performance and payment bonds for 100% of the contract amount are required within 15 days of the Notice of Award. Bidding Documents are available for download from the Portal, and all questions must be submitted in writing through the Questions function in ProcureWare at least eight days prior to the bid deadline. Liquidated damages are set at $1,000 per calendar day for failure to achieve substantial completion by the deadline. The bid form includes a base bid lump sum price plus ten unit price line items for earthwork materials and services, including undercut and disposal (3,000 and 6,000 cubic yards), offsite borrow material (5,000 cubic yards), various stone materials (VDOT No. 10, 57, 3, and 21A/B ranging from 1,500 to 4,500 cubic yards), geogrid (7,500 square yards), geotextile separation fabric (3,000 square yards), and lime stabilization (5,000 cubic yards). The Owner reserves the right to waive informalities and reject any or all bids. In the event of a tie bid, preference is given to businesses located in Henrico County or Virginia.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual Version 4.13.26

Project Manual for

ITB No. 26-2975-6JOK Tuckahoe Park Bond Project

Recreation & Parks

County of Henrico, Virginia

July 2, 2026

Architect of Record:

Vanasse Hangen Brustlin Inc 1021 E. Cary Street, Suite 200

Richmond, VA 23219 Phone: 804.343.7100

Recreation & Parks, County of Henrico, Virginia

TOC-1

TABLE OF CONTENTS

1 Table of Contents TOC 2 List of Drawings LOD 3 Invitation to Bid ITB 4 Bid Form BF 5 Standard Construction Administration Forms SF

AIA Documents 6 Instructions to Bidders: AIA Document A701, 2018 Electronic Edition 7 General Conditions of the Contract for Construction: AIA Document A201, 2017

Electronic Edition 8 Contractor’s Qualification Statement: AIA Document A305, 2020 Electronic

Edition 9 Standard Form of Agreement between Owner and Contractor: AIA Document

A101, 2017 Electronic Edition

County Documents 10 County of Henrico, Virginia Bid Bond 11 County of Henrico, Virginia Standard Performance Bond 12 County of Henrico, Virginia Standard Labor and

Material Payment Bond

Technical Specifications

DIVISION 01 - GENERAL REQUIREMENTS

010200 General Sitework Requirements 011000 Summary 012200 Unit Prices 012900 Payment Procedures 013000 Project Management and Coordination 013200 Construction Progress Documentation 013300 Submittal Procedures 014000 Quality Requirements 014100 Structural Tests and Special Inspections 014200 References 015000 Temporary Facilities and Controls 015639 Temporary Tree and Plant Protection 016000 Product Requirements 017300 Execution 017419 Construction Waste Management and Disposal 017700 Closeout Procedures 017826 Operation and Maintenance Data

TOC-2

017839 Project Record Documents

DIVISION 02 - EXISTING CONDITIONS

024113 Selective Site Demolition

DIVISION 03 – CONCRETE

033000 Cast-In-Place Concrete 033055 Cast-In-Place Concrete (Site)

DIVISION 04 – MASONRY

042000 Unit Masonry Assemblies

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

061000 Rough Carpentry 061600 Sheathing 062000 Finish Carpentry

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

071600 Bituminous Dampproofing 072100 Thermal Insulation 074113 Standing Seam Metal Roof Panels 074633 Vinyl Siding 076200 Sheet Metal Flashing and Trim 079200 Joint Sealants

DIVISION 08 – OPENINGS

081113 Hollow Metal Doors and Frames 083113 Access Doors and Frames 085200 Aluminum Windows 087100 Door Hardware (Restroom Building) 088000 Glazing

DIVISION 09 – FINISHES

092900 Gypsum Board Assemblies 093000 Tiling 095113 Acoustical Panel Ceilings 096513 Resilient Base and Accessories 096723 Resinous Flooring 099100 Painting

DIVISION 10 – SPECIALTIES

101400 Signage 102113 Solid Plastic Toilet Compartments

TOC-3

102800 Washroom Accessories 104400 Fire Protection Specialties

DIVISION 11 – EQUIPMENT

116800 Play Field Equipment and Structures

DIVISION 22 – PLUMBING

220000 General Requirements for Plumbing Systems 220500 Basic Plumbing Materials and Methods 220519 Meters and Gages 220523 Valves 220529 Hangers, Supports, and Anchors 220700 Plumbing Insulation 221116 Water Distribution Piping

221119.1 Plumbing Specialties

221123 Water Distribution Pumps 221316 Drainage and Vent Systems 223300 Electric Water Heaters 224000 Plumbing Fixtures

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

230000 General Requirements for HVAC Systems 230500 Basic Mechanical Materials and Methods 230529 Supports and Anchors 230593 Testing, Adjusting, and Balancing 230700 Mechanical Insulation 230993 Sequence of Operation 233113 Metal Ducts 233300 Duct Accessories 233400 Fans 233713 Diffusers, Registers, and Grilles 236200 Condensing Units 237200 Air-To-Air Energy Recovery Ventilators 237300 Split System Air-Handling Units 238200 Terminal Units

DIVISION 26 – ELECTRICAL

260500 Basic Electrical Requirements 260501 Basic Electrical Materials and Methods 260510 Temporary Power and Lighting 260519 Building Wire and Cable 260526 Grounding and Bonding for Electrical Systems 260529 Hangers and Supports for Electrical Systems

TOC-4

260533 Raceways and Boxes for Electrical Systems 260553 Electrical Identification

260573.16 Overcurrent Protective Device Coordination Study

260573.19 Overcurrent Protective Devise Arc-Flash Study

260583 Equipment Connections 260923 Lighting Control Equipment 262100 Electrical Service-Utility 262200 Dry-Type Transformers 262416 Panelboards and Circuit Breakers 262726 Wiring Devices 262816 Safety Switches 262900 Motor Controllers 265100 Interior Lighting Fixtures 265600 Exterior Lighting 265668 Sport Field Lighting System

DIVISION 31 – EARTHWORK

310000 Earthwork 311000 Site Clearing 312300 Excavation and Fill 312333 Trenching and Backfilling 312500 Erosion and Sedimentation Controls

DIVISION 32 - EXTERIOR IMPROVEMENTS

321100 Base Courses (Pavements) 321215 Asphalt Paving 321313 Concrete Paving 321723 Pavement Markings 321813 Synthetic Grass Surfacing

321816.13 Playground Protective Surfacing

323113 Chain Link Gates 323219 Masonry Site Walls 323300 Site Furnishings 328000 Irrigation System 329113 Soil Preparation 329119 Landscape Grading 329200 Turf and Grasses 329300 Planting

DIVISION 33 – UTILITIES

331000 Water Utilities 333900 Sanitary Utility Sewerage Structures 334000 Storm Drainage Utilities

TOC-5

334020 Warning and Tracer Tape

- END OF TABLE OF CONTENTS -

LOD-1

LIST OF DRAWINGS

Sheet Title

C0.00 COVER SHEET

C0.01 ILLUSTRATIVE MASTER PLAN

C1.00 EXISTING CONDITIONS PLAN

C1.10 OVERALL DEMOLITION PLAN

C1.30 POLLUTION PREVENTION PLAN

C1.40 GENERAL FLOODPLAIN DEVELOPMENT PERMIT

C2.00 OVERALL E&SC PHASE 1 PLAN

C2.01 E&SC PHASE 1 PLAN

C2.02 E&SC PHASE 1 PLAN

C2.03 E&SC PHASE 1 PLAN

C2.04 E&SC PHASE 1 PLAN

C2.05 E&SC PHASE 1 PLAN

C2.10 OVERALL E&SC PHASE 2 PLAN

C2.11 E&SC PHASE 2 PLAN

C2.12 E&SC PHASE 2 PLAN

C2.13 E&SC PHASE 2 PLAN

C2.14 E&SC PHASE 2 PLAN

C2.15 E&SC PHASE 2 PLAN

C2.20 HENRICO CO. STD. ESC NOTES AND DETAILS

C2.21 HENRICO CO. STD. ESC NOTES AND DETAILS

C2.22 EROSION & SEDIMENT CONTROL STANDARD DETAILS

C3.00 OVERALL KEY PLAN

C3.01 LAYOUT AND MATERIALS PLAN

C3.02 LAYOUT AND MATERIALS PLAN

C3.03 LAYOUT AND MATERIALS PLAN

C3.04 LAYOUT AND MATERIALS PLAN

C3.05 LAYOUT AND MATERIALS PLAN

C3.10 FIRE LANE PLAN

C4.00 OVERALL UTILITY PLAN

C4.01 UTILITY PLAN

C4.02 UTILITY PLAN

C4.03 WATER SERVICE LINE PLAN

C4.10 UTILITY PROFILES

C4.11 UTILITY PROFILES

C4.12 UTILITY PROFILES

C4.20 WATER MODEL

C5.00 OVERALL GRADING & DRAINAGE PLAN

C5.01 GRADING & DRAINAGE PLAN

C5.02 GRADING & DRAINAGE PLAN

C5.03 GRADING & DRAINAGE PLAN

C5.04 GRADING & DRAINAGE PLAN

C5.05 GRADING & DRAINAGE PLAN

C5.10 DRAINAGE PROFILES

LOD-2

C5.11 DRAINAGE PROFILES

C5.12 DRAINAGE PROFILES

C5.13 DRAINAGE PROFILES

C5.20 DRAINAGE STRUCTURE AND PIPE TABLES

C7.00 HENRICO CO STD. DETAILS

C7.01 SITE DETAILS

C7.02 SITE DETAILS

C7.03 SITE DETAILS

C7.04 SITE DETAILS

C7.10 UTILITY DETAILS

C7.11 UTILITY DETAILS

C7.12 UTILITY DETAILS

C7.13 UTILITY DETAILS

C7.20 BMP & DRAINAGE DETAILS

C7.21 BMP 2 DETAILS

C8.01 DRAINAGE AREA MAP - PREDEVELOPMENT

C8.02 DRAINAGE AREA MAP - POSTDEVELOPMENT

C8.04 WATER QUALITY - PLAN VIEWS

C8.05 WATER QUALITY - CALCULATIONS

C8.06 WATER QUALITY - CALCULATIONS

C8.07 STORM DRAIN INLET AREA MAP

C8.08 STORM SEWER CAPACITY CALCULATIONS

C8.09 HYDRAULIC GRADE LINE ANALYSIS CALCULATIONS

C8.10 EX. HGL ANALYSIS & CURB INLET SPREAD CACLULATIONS

C8.11 FLOOD PLAIN ANALYSIS

C8.12 FLOOD PLAIN APPROVAL LETTERS

C8.13 CONSTRUCTION GENERAL PERMIT

C8.14 SEDIMENT TRAP ADEQUATE OUTFALL ANALYSIS

L0.00 HENRICO COUNTY LANDSCAPE CALCULATIONS

L0.01 PLANTING PLAN

L0.02 PLANTING PLAN

L0.03 PLANTING PLAN

L0.10 PLANT SCHEDULE, NOTES AND DETAILS

E-001 ELECTRICAL LEGEND, ABBREVIATIONS & SYMBOLS

E-002 ELECTRICAL OVERALL SITE PLAN

E-101 ELECTRICAL SITE PLAN - SECTION A

E-102 ELECTRICAL SITE PLAN - SECTION B

E-103 ELECTRICAL SITE PLAN - SECTION C

E-104 ELECTRICAL SITE PLAN - SECTION D

E-105 ELECTRICAL SITE PLAN - SECTION E

E-106 ELECTRICAL SITE PLAN - SECTION F

E-151 ELECTRICAL RESTROOM POWER PLAN

E-152 ELECTRICAL RESTROOM LIGHTING PLAN

E-501 ELECTRICAL LIGHTING SCHEDULES

LOD-3

E-601 ELECTRICAL SCHEDULES

E-602 ELECTRICAL ONE-LINE DIAGRAM - NORTH SERVICE

E-603 ELECTRICAL ONE-LINE DIAGRAM - SOUTH SERVICE

E-701 ELECTRICAL DETAILS

P-001 LEGEND, ABBREVIATIONS AND SYMBOLS

P-101 PLUMBING PLANS

P-700 PLUMBING DETAILS AND SCHEDULES

M-001 LEGEND, ABBREVIATIONS AND SYMBOLS

M-101 MECHANICAL PLAN

S001 STRUCTURAL GENERAL NOTES

S101 STRUCTURAL PLANS

S201 SECTIONS & DETAILS

S301 TYPICAL CONCRETE SECTIONS & DETAILS

S302 TYPICAL WOOD & LIGHT GAGE SECTIONS & DETAILS

L1.00 OVERALL SITE PLAN

L2.00 OVERALL MATERIALS PLAN

L2.01 MATERIALS PLAN

L2.10 SITE DETAILS

L2.11 SITE DETAILS

L2.20 CUT SHEETS

L2.21 CUT SHEETS

L3.00 OVERALL LAYOUT PLAN

L3.01 LAYOUT PLAN

L4.00 OVERALL GRADING PLAN

L4.01 GRADING PLAN

L5.00 OVERALL PLANTING PLAN

L5.01 PLANTING PLAN

L5.10 PLANTING DETAILS

L6.00 OVERALL PHOTOMETRIC PLAN

L6.01 PHOTOMETRIC PLAN

L6.10 LIGHTING CUT SHEETS

S1.00 STRUCTURAL NOTES

S2.00 RETAINING WALL PLAN VIEW

S3.00 STRUCTURAL DETAILS

IRR-100 IRRIGATION PLAN

IRR-101 IRRIGATION PLAN

IRR-102 IRRIGATION PLAN

IRR-200 IRRIGATION DETAILS

IRR-201 IRRIGATION DETAILS

LOD-4

A001 PROJECT DATA, SYMBOLS AND ABBREVIATIONS

A002 CODE ANALYSIS

A003 LIFE SAFETY PLAN

A101 FLOOR PLAN

A102 REFLECTED CEILING AND ROOF PLAN

A201 RESTROOM ELEVATIONS

A301 RESTROOM SECTIONS

A302 RESTROOM WALL SECTIONS

A303 WALL SECTION DETAILS

A401 RESTROOM INTERIOR ELEVATIONS

A601 ACCESSIBILITY AND TOILET DETAILS

A801 DOOR AND WINDOW SCHEDULE

A802 ROOM AND SIGNAGE SCHEDULES

- END OF LIST OF DRAWINGS -

ITB-1

INVITATION TO BID

ITB No. 26-2975-6JOK

County of Henrico, Virginia

Sealed bids for Tuckahoe Park Bond Project, in accordance with the conditions, specifications, and instructions below and on the attached sheets hereto, will be received no later than 2:00 PM, local prevailing time, August 3, 2026 and then publicly opened and read immediately thereafter through a Microsoft Teams meeting. Sealed bids shall be submitted through Henrico County’s Electronic Documents Web Portal, ProcureWare, at https://henrico.procureware.com. Bidders interested in participating in the bid opening shall send a request to be added to the meeting invitation to Oscar Knott via email at kno008@henrico.gov.

Time is of the essence, and any bidder that attempts to submit a bid after the appointed hour for submission, will be unable to, as ProcureWare automatically closes the bid. The time of receipt shall be determined by the time clock in ProcureWare. Bidders are responsible for ensuring that their bid is submitted in ProcureWare by the deadline indicated.

The Work consists of new construction and renovation to an existing site that hosts Tuckahoe Little League. The project will include the construction of two (2) new fully accessible restrooms and associated utility infrastructure; one (1) newly constructed asphalt parking lot with accessible parking, curb and gutter, storm sewer, site lighting, and landscaping; two (2) renovated asphalt parking lots with new paving, storm sewer, curb and gutter, site lighting, and landscape; construction of a new dumpster enclosure; new asphalt multi-use trails, sidewalks, and pedestrian bridge; and the construction of a new accessible community playground. Project scope will also include utility infrastructure (water and sanitary sewer installation), trail, parking lot, and playground site lighting, earthwork and site grading, stormwater piping and BMP installation, and concrete flat work. All supporting activities required to complete the project will be included, such as DEQ/USACOE permit compliance, Henrico County POD compliance, tree clearing, stormwater improvements, landscaping, landscape architectural components, and site lighting. The project is located at 2400 Little League Drive, Henrico, VA 23233.

This project is located at a County Park that is also utilized as a local little league. Scheduled phases and times of construction shall be agreed upon between the Contractor and the Owner prior to the commencement of any work performed on the site that impacts access to the Little League fields, Tuckahoe Sports Inc, and the County maintenance facility on-site.

Pursuant to Henrico County Code Section 16-43, the Board of Supervisors of Henrico County, Virginia shall be the awarding authority when the contract amount is over $200,000. Otherwise, the award will be made by the Purchasing Director.

Normal working hours shall be between 7:00 AM to 6:00 PM Monday through Friday. Work after normal working hours and may be scheduled only with the County’s approval.

Bidding Documents consisting of Contract Drawings and Project Manuals may be obtained by visiting the Henrico County Electronic Document’s Web portal at https://henrico.procureware.com/home. Options are provided for downloading a complete set of documents or selected files from this web portal. The Contract Drawings and Project Manuals are provided in PDF Format, which may be shared electronically with your https://henrico.procureware.com/ mailto:kno008@henrico.gov https://henrico.procureware.com/home

ITB-2

subcontractors, employees, and suppliers. The failure or omission of any bidder to download, receive or examine any form, instrument, addendum or other documents, or to acquaint itself with conditions existing at the site(s), shall in no way relieve any bidder from any obligations with respect to its bid or to the contract.

A non-mandatory pre-bid conference will be held at 2:00 PM on July 13, 2026 at Tuckahoe Park, 2400 Little League Drive, Henrico, VA 23233, to review the scope of work and clarify any aspects of the work that may be in question. Direct any questions, concerning the Project Manual and Drawings in writing through the Questions function in ProcureWare.

Bids must be accompanied by either a cashier’s check or certified check or bid bond in the amount of 5% of the Total Bid and made payable to the County of Henrico, Virginia.

A bid may not be modified, withdrawn or cancelled by the bidder after the time and date designated for the receipt of bids and for 90 days thereafter except as provided by Va. Code § 2.2-4330. The following is the procedure for withdrawal of a bid: Va. Code § 2.2-4330(B)(1), as may be amended from time to time.

Nothing herein is intended to exclude any responsible bidder, its product or service or in any way restrain or restrict competition. Comments as to how bid documents, specifications or drawings can be improved are welcome.

If a contract is awarded, a separate performance bond and a payment bond, County of Henrico, Virginia Standard Performance Bond and County of Henrico, Virginia Standard Labor and Material Payment Bond, for 100% of the contract amount shall be provided by the Successful Bidder.

The Owner reserves the right to waive informalities and/or reject all bids. In accordance with Va. Code, Section 2.2-4319, the Owner shall not reject all bids solely to avoid awarding a contract to a particular responsive and responsible bidder.

The Bidder must be a registered contractor in the Commonwealth of Virginia in accordance with Title 54.1, Chapter 11 of the Code of Virginia, as amended, at the time of bid submission, and shall possess a Virginia Contractor’s License Class A. The Bidder shall have bid and completed projects of comparable nature, size, complexity and construction cost. The Bidder should submit with its bid a completed AIA Document A305, Contractor’s Qualifications Statement, which shall document how the applicable projects meet or exceeds the size, complexity, and nature of this project; and includes details of the management staff and self-performed activities associated with the referenced projects. Only those projects which the Bidder performed the work as the General Contractor should be included in the AIA Document A305. Bidders are not required to submit AIA Document A305, Contractor’s Qualification Statement if they have submitted one within the last twelve (12) months as of the date of this bid.

- END OF INVITATION TO BID -

BF-1

BID FORM

FIXED PRICE CONTRACT

ITB No. 26-2975-6JOK

Date: ____________________________

To: County of Henrico Department of Finance, Purchasing Office

8600 Staples Mill Road, Henrico, VA 23228-2360 PO Box 90775, Henrico, VA 23273-0775

Project: Tuckahoe Park Bond Project

From (full name): __________________________________

(full address) __________________________________

Having carefully examined the site, the drawings, specifications and other documents, and in compliance with your "Invitation to Bid", Instructions to Bidders AIA701-2018 Edition, and this “Bid Form”, the undersigned proposes to furnish all labor, materials, supplies and equipment necessary for Tuckahoe Park Bond Project. All shall be in accordance with Drawings prepared by Vanasse Hangen Brustlin Inc dated June 9, 2026 and the Project Manual, dated July 2, 2026.

The Bidder must be a registered contractor in the Commonwealth of Virginia in accordance with Title 54.1, Chapter 11 of the Code of Virginia, as amended, at the time of bid submission, and shall possess a Virginia Contractor’s License Class A. The Bidder shall have bid and completed projects of comparable nature, size, complexity and construction cost. The Bidder should submit with its bid a completed AIA Document A305, Contractor’s Qualifications Statement, which shall document how the applicable projects meet or exceeds the size, complexity, and nature of this project; and includes details of the management staff and self-performed activities associated with the referenced projects. Only those projects which the Bidder performed the work as the General Contractor should be included in the AIA Document A305. Bidders are not required to submit AIA Document A305, Contractor’s Qualification Statement if they have submitted one within the last twelve (12) months as of the date of this bid.

The Work consists of new construction and renovation to an existing site that hosts Tuckahoe Little League. The project will include the construction of two (2) new fully accessible restrooms and associated utility infrastructure; one (1) newly constructed asphalt parking lot with accessible parking, curb and gutter, storm sewer, site lighting, and landscaping; two (2) renovated asphalt parking lots with new paving, storm sewer, curb and gutter, site lighting, and landscape; construction of a new dumpster enclosure; new asphalt multi-use trails, sidewalks, and pedestrian bridge; and the construction of a new accessible community playground. Project scope will also include utility infrastructure (water and sanitary sewer installation), trail, parking lot, and playground site lighting, earthwork and site grading, stormwater piping and BMP installation, and concrete flat work. All supporting activities required to complete the project will be included, such as DEQ/USACOE permit compliance, Henrico County POD compliance, tree clearing, stormwater improvements, landscaping, landscape architectural components, and site lighting. The project is located at 2400 Little League Drive, Henrico, VA 23233.

BF-2

It shall be the responsibility of the Contractor to apply for and diligently pursue the applicable Building Permits from the County of Henrico. It shall be the responsibility of the Owner to pay for the Building Permits. However, in a cooperative and expedient effort, the Owner may apply and pay for the Building Permits prior to receipt of bids and should not be included in the bid amount. The Contractor will be responsible for obtaining and bearing the cost of all subcontractors permits.

The Bid Form must be completed in blue or black ink or by typewriter. The bid amounts shall be expressed in figures, only. The unit price of each item on the form, if requested, must be stated in figures. Discrepancies in the multiplication of units of work and the unit prices will be resolved in favor of the correct multiplication of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. My/Our lump sum price is as follows:

PRICES QUOTED SHALL BE FOB DESTINATION

TOTAL BID AMOUNT:

TOTAL BID: The Total Bid includes all Work required by the Bidding Documents for Tuckahoe Park Bond Project in strict accordance with the Bidding Documents including the Drawings and Project Manual for the lump sum of:

$[Enter pricing electronically in ProcureWare] (Figure Only)

Price Schedule Base Bid Item

Description Lump Sum Price Base Bid includes all Work required by the Bidding Documents for Tuckahoe Park Bond Project in strict accordance with the Bidding Documents including the Drawings and Project Manual.

[Enter pricing electronically in ProcureWare]

Unit Price Items (Reference Section 012200 – Unit Prices)

Description Quantity Unit Unit Price Extended Price

Unit Price Item No. 1: Undercut and disposal offsite 3,000 CY

[Enter pricing

Pricing will automatically calculate in ProcureWare

Unit Price Item No. 2: Undercut and disposal on site 6,000 CY

[Enter pricing

Unit Price Item No. 3: Offsite Borrow Material 5,000 CY

[Enter pricing

BF-3

Unit Price Item No. 4: VDOT No. 10 Stone 4,500 CY

[Enter pricing

Unit Price Item No. 5: VDOT No. 57 Stone 1,500 CY

[Enter pricing

Unit Price Item No. 6: VDOT No. 3 Stone 1,500 CY

[Enter pricing

Unit Price Item No. 7: VDOT 21A/B Stone 1,500 CY

[Enter pricing

Unit Price Item No. 8: Geogrid 7,500 SY

[Enter pricing

Unit Price Item No. 9:

Geotextile Separation Fabric 3,000 SY

[Enter pricing

Unit Price Item No. 10: Lime Stabilization 5,000 CY

[Enter pricing

Total Bid Amount (equals the sum of Base Bid + Unit Price Items No. 1 – 10)

Pricing will automatically

BID SECURITY:

Attached hereto is my bid security for five percent (5%) of the Total Bid, made payable to the County of Henrico, Virginia.

GENERAL:

BF-4

It is the intent of the County of Henrico to recommend the award of this contract to the lowest responsive and responsible bidder based upon the Total Bid, provided the bid does not exceed the funds available for the contract.

If a contract is awarded, a separate performance bond and a payment bond County of Henrico, Virginia Standard Performance Bond and County of Henrico, Virginia Standard Labor and Material Payment Bond, for 100% of the contract amount, including any additions and/or deductions, shall be provided by the Successful Bidder.

The Successful Bidder agrees to use unit prices to determine changes to the Contract Sum when authorized changes are directed. Unit prices shall include all labor and materials, in place and complete. The source of the unit prices (other than those listed herein) shall be Means Open Shop Building Construction Cost Data, latest edition, R. S. Means Company, Inc., adjusted for Richmond, Virginia. The unit prices will be used as maximum limiting charges and minimum credits allowable for any change in the Work.

TIME OF COMPLETION:

The Work shall be Substantially Complete and certified by the Architect within 515 calendar days after the date of the written Notice to Proceed from the Owner to the Contractor. Final Completion of all Work shall be within 30 calendar days after the date of Substantial Completion.

The Owner and the Contractor recognize that time is of the essence and that the Owner will suffer financial loss if the Work is not completed by the deadline for Substantial Completion. Both parties recognize the delays, expense, and damages involved in proving in a legal proceeding the actual loss suffered by the Owner if the Work is not completed on time. Accordingly, notwithstanding any other provisions of this Contract, the Owner and the Contractor agree, stipulate and fix as liquidated damages, but not as a penalty, the sum of One Thousand Dollars ($1,000.00) per day, which the Contractor together with the Contractor's surety shall pay the Owner for each calendar day or part thereof after the Substantial Completion deadline until the Contractor achieves Substantial Completion of the entire Work. The Contractor hereby waives any defense as to the validity of liquidated damages stated in this Agreement on the grounds that such liquidated damages are void as penalties or are not reasonably related to actual damages, and the parties agree that the Owner's entitlement to liquidated damages shall be determined at the time of Substantial Completion.

(BID SIGNATURE SHEET FOLLOWS)

BF-5

BID SIGNATURE SHEET

My signature certifies that the bid as submitted complies with all requirements specified in this Invitation to Bid (“ITB”) No. 26-2975-6JOK – Tuckahoe Park Bond Project.

My signature also certifies that by submitting a bid in response to this ITB, the Bidder represents that in the preparation and submission of this bid, the Bidder did not, either directly or indirectly, enter into any combination or arrangement with any person or business entity, or enter into any agreement, participate in any collusion, or otherwise take any action in the restraining of free, competitive bidding in violation of the Sherman Act (15 U.S.C.

Section 1) or Sections 59.1-9.1 through 59.1-9.17 or Sections 59.1-68.6 through 59.1-68.8 of the Code of Virginia.

I hereby certify that I am authorized to sign as a legal representative for the business entity submitting this bid.

LEGAL NAME OF BIDDER (DO NOT USE TRADE NAME): ________________________________

ADDRESS: __________________________________________________________________________

SIGNATURE: ________________________________________________________________________

NAME OF PERSON SIGNING (PRINT): __________________________________________________

TITLE: ______________________________________________________________________________

TELEPHONE: ________________________________________________________________________

EMAIL ADDRESS: ____________________________________________________________________

DATE: ______________________________________________________________________________

VIRGINIA CONTRACTOR’S REGISTRATION NUMBER:______________________ CLASS: _____

Surety2000 Bond Number for Bid Bond (if applicable): _______________________________________

Bidder _____ is or ____ is not located in Henrico County? If so, have you obtained a County license to conduct or engage in business, trade or occupation in the County? _____ Yes _____ No

RECEIPT OF ADDENDA:

We acknowledge the receipt of the following Addenda:

Addendum No. Dated

Addendum No. Dated

Addendum No. Dated

Addendum No. Dated

BF-6

BUSINESS CATEGORY CLASSIFICATION FORM

Company Name: _______________________________________________________________

This form has been completed by:

Signature: _____________________________________________ Date: _________________

Title: _____________________________________________

Specify your Business Category by checking the appropriate business category classification below (check all that apply):

_____ Small Business

_____ Women-Owned Business

_____ Minority-Owned Business

_____ Military Family-Owned Business

_____ Service-Disabled Veteran Business

_____ Employment Services Organization

_____ Non-SWaM Business (if none of the above)

If certified by the Virginia Department of Small Business and Supplier Diversity (SBSD), provide your certification number and expiration date below:

Number: _________________________ Date: _________________________

For the purpose of determining the appropriate business category, please review the definitions provided by SBSD at: https://sbsd.virginia.gov/certification-division/swam/. “Employee services organization” is defined as s an organization that provides community-based employment services to individuals with disabilities that is an approved Commission on Accreditation of Rehabilitation Facilities (CARF) accredited vendor of the Department of Aging and Rehabilitative Services.

https://sbsd.virginia.gov/certification-division/swam/

BF-7

VIRGINIA STATE CORPORATION COMMISSION (SCC)

REGISTRATION INFORMATION

The Bidder:

is a corporation or other business entity with the following SCC identification number:

________________________________ -OR-

is not a corporation, limited liability company, limited partnership, registered limited liability partnership, or business trust -OR-is an out-of-state business entity that does not regularly and continuously maintain as part of its ordinary and customary business any employees, agents, offices, facilities, or inventories in Virginia (not counting any employees or agents in Virginia who merely solicit orders that require acceptance outside Virginia before they become contracts, and not counting any incidental presence of the Bidder in Virginia that is needed in order to assemble, maintain, and repair goods in accordance with the contracts by which such goods were sold and shipped into Virginia from Bidder’s out-of-state location) -OR-is an out-of-state business entity that is including with this bid/proposal an opinion of legal counsel which accurately and completely discloses the undersigned Bidder’s current contracts with Virginia and describes why those contracts do not constitute the transaction of business in Virginia within the meaning of §13.1-757 or other similar provisions in Titles 13.1 or 50 of the Code of Virginia.

Please check the following box if you have not checked any of the foregoing options but currently have pending before the SCC an application for authority to transact business in the Commonwealth of Virginia and wish to be considered for a waiver to allow you to submit the SCC identification number after the due date for bids:

BF-8

RESPONSIBLE BIDDER CERTIFICATION

Name of Bidder: __________________________________

“Responsible bidder” means a person who has the capability, in all respects, to perform fully the contract requirements and the moral and business integrity and reliability that will assure good faith performance, and who has been prequalified, if required.

In determining whether a Bidder is responsible, the County will consider whether the Bidder has defaulted on any government contract in the last five years; whether any government has terminated a contract with the Bidder for cause in the last five years; and whether the Bidder or any of its officers, directors, partners, or owners is currently barred from bidding on contracts by any federal, state, or local government agency.

As part of this submission, the Bidder certifies that:

It has not defaulted on any government contract in the last five years.

No government has terminated a contract with the Bidder for cause in the last five years.

Neither it nor any of its officers, directors, partners, or owners are barred from bidding on contracts by any federal, state, or local government agency.

If the Bidder cannot make any of the certifications required above, the Bidder must indicate the reason by selecting the appropriate box below.

It has defaulted on one or more government contract(s) in the last five years.

A government has terminated a contract with the Bidder for cause in the last five years.

It or one or more of its officers, directors, partners, or owners are barred from bidding on contracts by a federal, state, or local government agency.

If any of the above three boxes are checked, the Bidder must explain all defaults, terminations, and/or bars in reasonable detail and include the contact information for the government agency on whose contract the Bidder has defaulted, been terminated, or been barred from bidding.

Signature of Authorized Representative

Printed Name of Authorized Representative

SF-1

STANDARD CONSTRUCTION ADMINISTRATION FORMS

The AIA Documents normally required, though not necessarily all-inclusive, are listed below for your information. These Documents may be obtained directly from American Institute of Architects, Washington, D.C. (www.aia.org)

In all cases, the latest edition of the document must be used.

AIA Document Title

G701 Change Order G702 Application and Certificate for Payment G703 Application and Certificate for Payment, Continuation Sheet G704 Certificate of Substantial Completion G706 Contractor's Affidavit of Payment of Debts and Claims G706A Contractor's Affidavit of Release of Liens G707 Consent of Surety to Final Payment G709 Proposal Request G714 Construction Change Directive

The Owner Documents (Forms) are as noted below and will be provided to the Contractor in Microsoft Excel format

OWNER Documents Title

Estimate for Proposed Change Order (PCO):

GC-1 Henrico County Form - General Contractor Estimate SC-1 Henrico County Form - Sub-Contractor Estimate SS-1 Henrico County Form - Sub-Subcontractor Estimate

- END OF STANDARD CONSTRUCTION ADMINISTRATION FORMS –

http://www.aia.org/

Document A701® – 2018 Instructions to Bidders

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:48:12 ET on 06/29/2026 under Order No.3104239353 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA4B)

ADDITIONS AND DELETIONS:

The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed. A vertical line in the left margin of this document indicates where the author has added necessary information and where the author has added to or deleted from the original AIA text.

This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.

FEDERAL, STATE, AND LOCAL

LAWS MAY IMPOSE

REQUIREMENTS ON PUBLIC

PROCUREMENT CONTRACTS.

CONSULT LOCAL AUTHORITIES

OR AN ATTORNEY TO VERIFY

REQUIREMENTS APPLICABLE TO

THIS PROCUREMENT BEFORE

COMPLETING THIS FORM.

It is intended that AIA Document G612™–2017, Owner’s Instructions to the Architect, Parts A and B will be completed prior to using this document.

for the following Project:

(Name, location, and detailed description)

ITB No. 26-2975-6JOK - Tuckahoe Park Bond Project

THE OWNER:

(Name, legal status, address, and other information)

County of Henrico, VA PO Box 90775 Henrico, VA 23228

THE ARCHITECT:

(Name, legal status, address, and other information)

Vanasse Hangen Brustlin Inc

TABLE OF ARTICLES

1 DEFINITIONS

2 BIDDER’S REPRESENTATIONS

3 BIDDING DOCUMENTS

4 BIDDING PROCEDURES

5 CONSIDERATION OF BIDS

6 POST-BID INFORMATION

7 PERFORMANCE BOND AND PAYMENT BOND

8 FORM OF AGREEMENT BETWEEN OWNER AND CONTRACTOR AND ADDITIONAL

TERMS

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:48:12 ET on 06/29/2026 under Order No.3104239353 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA4B)

ARTICLE 1 DEFINITIONS

§ 1.1 Bidding Documents include the Bidding Requirements and the Proposed Contract Documents. The Bidding Requirements consist of the advertisement or Invitation to Bid, Instructions to Bidders, supplementary instructions to bidders, the bid form, and any other bidding forms. The Proposed Contract Documents consist of the unexecuted form of Agreement between the Owner and Contractor and that Agreement’s Exhibits, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, all Addenda, and all other documents enumerated in Article 8 of these Instructions.

§ 1.2 Definitions set forth in the General Conditions of the Contract for Construction, or in other Proposed Contract Documents apply to the Bidding Documents.

§ 1.3 Addenda are written or graphic instruments issued by the Owner or Architect, which, by additions, deletions, clarifications, or corrections, modify or interpret the Bidding Documents.

§ 1.4 A Bid is a complete and properly executed proposal to do the Work for the sums stipulated therein, submitted in accordance with the Bidding Documents.

§ 1.5 The Base Bid is the sum stated in the Bid for which the Bidder offers to perform the Work described in the Bidding Documents, to which Work may be added or deleted by sums stated in Additive Bids.

§ 1.6 An Additive Bid (or Additive) is an amount stated in the Bid to be added to, or that does not change, the Base Bid if the corresponding change in the Work, as described in the Bidding Documents, is accepted.

§ 1.7 A Unit Price is an amount stated in the Bid as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, as described in the Bidding Documents.

§ 1.8 A Bidder is a person or entity who submits a Bid.

§ 1.9 A Sub-bidder is a person or entity who submits a bid to a Bidder for materials, equipment, or labor for a portion of the Work.

§ 1.10 A Responsible Bidder means a person who has the capability, in all respects, to perform fully the contract requirements and the moral and business integrity and reliability which will assure good faith performance, and who has been pre-qualified, if required (Code of Virginia, Section 2.2-4301).

§ 1.11 A Responsive Bidder means a person who has submitted a Bid, which conforms in all material respects to the Invitation to Bid (Code of Virginia, Section 2.2-4301).

§ 1.12 A Successful Bidder means the Responsible and Responsive Bidder to whom the Owner awards the Contract.

§ 1.13 An Informality means a minor defect or variation of a Bid from the exact requirements of the Invitation to Bid which does not affect the price, quality, quantity or delivery schedule for the goods, services or construction being procured (Code of Virginia, Section 2.2-4301).

§ 1.14 The Invitation to Bid (or ITB) is the Owner’s solicitation containing or incorporating by reference the specifications and other terms and conditions related to the Project that invites Bidders to submit Bids.

§ 1.15 The Portal is the Owner’s construction bid postings web portal where Bidding Documents are publicly posted and available for download and where electronic bid submissions must be submitted. The web address for the Portal is https://henrico.procureware.com/.

ARTICLE 2 BIDDER’S REPRESENTATIONS

§ 2.1 By submitting a Bid, the Bidder represents that:

.1 the Bidder has read and understands the Bidding Documents, has carefully reviewed the Bidding Documents, and has verified that all sets of the Bidding Documents received are complete;

.2 the Bidder understands how the Bidding Documents relate to other portions of the Project, if any, being bid concurrently or presently under construction;

.3 the Bid complies with the Bidding Documents;

.4 the Bidder has visited the site, become familiar with local conditions under which the Work is to be performed, and has correlated the Bidder’s observations with the requirements of the Proposed Contract Documents;

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:48:12 ET on 06/29/2026 under Order No.3104239353 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA4B)

.5 the Bid is based upon the materials, equipment, and systems required by the Bidding Documents without exception; and

.6 the Bidder has read and understands the provisions for liquidated damages, if any, set forth in the form of Agreement between the Owner and Contractor.

.7 The Bidder has familiarized himself with all federal, state and local laws, ordinances, rules and regulations that in any manner may affect cost, progress or performance of the Work; the Bidder has obtained the proper County license, if applicable, and is licensed or certified to perform the Work in the Commonwealth of Virginia in accordance with Title 2.2, Chapter 43 of the Code of Virginia, as amended. If you have any questions, contact the Business Section, Department of Finance, County of Henrico, telephone (804) 501-4729.

(Paragraphs Deleted)

.8 The Bidder shall pay all County, city, state and federal taxes required by laws in effect at the time the Bids are received and resulting from the Work or traceable thereto, under whatever name levied. Said taxes shall not be in addition to the Contract price between the Owner and the Bidder, as the taxes shall be an obligation of the Bidder and not of the Owner, and the Owner shall be held harmless for the same by the Bidder.

.9 The Bidder shall secure and pay for all permits, governmental fees and licenses necessary for the proper execution and completion of the Work which are applicable at the time that the Bids are received, except as expressly provided hereafter. The Bidder shall not pay for the following, however the Bidder shall be responsible to secure these:

.1 Any permits issued by the Department of Building Construction and Inspections of the County of Henrico.

.2 Water and/or sewer connection fees charged by the Department of Public Utilities of the County of Henrico.

The Owner shall arrange for payment of all such permits and fees and the cost of such permits and fees listed in “.1” and “.2” above shall not be included in the amount of the Bidder's Bid on the Work.

.10 The failure or omission of any Bidder to receive or examine any form, instrument, addendum or other documents, or to acquaint itself with conditions existing at the site(s), shall in no way relieve any Bidder from any obligations with respect to its Bid or to the Contract.

ARTICLE 3 BIDDING DOCUMENTS

§ 3.1 Distribution § 3.1.1 Bidding Documents may be obtained by visiting the Portal. Options are provided for downloading a complete set of documents or selected files. The failure or omission of Bidders to download, receive or examine any form, instrument, addendum or other documents, or to acquaint itself with conditions existing at the site(s), shall in no way relieve Bidders from any obligations with respect to its Bid or to the Contract.

§ 3.1.2 Bidders shall use complete Bidding Documents in preparing Bids. Neither the Owner nor Architect assumes responsibility for errors or misinterpretations resulting from the use of incomplete Bidding Documents. Every Bidder is responsible to review all Bidding Documents obtained from the Portal to verify that Bidding Documents are complete. Bidders shall notify the Architect or Owner if Bidding Documents are found to be incomplete.

§ 3.1.3 The Bidding Documents will be available for the sole purpose of obtaining Bids on the Work. No license or grant of use is conferred by distribution of the Bidding Documents.

§ 3.2 Modification or Interpretation of Bidding Documents § 3.2.1 The Bidder shall carefully study the Bidding Documents, shall examine the site and local conditions, and shall notify the Architect of errors, inconsistencies, or ambiguities discovered and request clarification or interpretation pursuant to Section 3.2.2.

§ 3.2.2 Requests for clarification or interpretation of the Bidding Documents shall be submitted by the Bidder in writing and shall be received by the Architect at least eight days prior to the date for receipt of Bids as

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:48:12 ET on 06/29/2026 under Order No.3104239353 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA4B) provided in the Invitation To Bid.

§ 3.2.3 Modifications and interpretations of the Bidding Documents shall be made by Addendum. Modifications and interpretations of the Bidding Documents made in any other manner shall not be binding, and Bidders shall not rely upon them.

§ 3.3 Substitutions § 3.3.1

(Paragraph Deleted)

No substitutions shall be approved prior to the time and date designated for the receipt of Bids.

§ 3.3.2 Unless the Bidding Documents specifically indicate that substitutions are not permitted, whenever the Bidding

Documents require a particular brand, make of material, manufacturer, device, or equipment, such brand, make of material, manufacturer, device or equipment shall denote the general style, type, character and quality standard of article desired and does not restrict Bidders to the specific brand, make, manufacturer, device or equipment named. Any other brand, make of material, manufacturer, device or equipment, which in the opinion of the Architect is recognized the equivalent of that indicated considering quality, workmanship and economy of operation and is suitable for the purpose intended, shall be accepted. Division 1 of the Specifications will include requirements for “design standard” designations and information required of Successful Bidder, if any.

§ 3.3.3 The Bidder agrees that its Bid shall be based on products and work indicated in the Bidding Documents. The Bidder assumes all risks using a price or bid proposal representing a product/material that is not indicated in the Bidding Documents and if the Bidder elects to use that product/material, he shall submit it in accordance with Division 1 of the Specifications and as stated herein. If that product/material is rejected, the Bidder shall provide a product/material indicated in the Bidding Documents at no additional cost to the Owner.

§ 3.4 Addenda § 3.4.1 Each Addendum will be transmitted as stated in the Invitation to Bid. When Bidding Documents are made available via the Portal, a notice of each Addendum will be sent to the email address for each Bidder included on the list of Bidders for the Project on the Portal and Bidders may download the Addendum from the Portal.

§ 3.4.2 Addenda will be available where Bidding Documents are on file.

§ 3.4.3 Addenda will be issued no later than six days prior to the date for receipt of Bids, except an Addendum withdrawing the request for Bids or one which includes postponement of the date for receipt of Bids.

§ 3.4.4 Prior to submitting a Bid, each Bidder shall ascertain that the Bidder has received all Addenda issued, and the Bidder shall acknowledge their receipt in the Bid.

ARTICLE 4 BIDDING PROCEDURES

§ 4.0 Electronic

AIA Document A701 – 2018. Copyright © 1970, 1974, 1978, 1987, 1997 and 2018. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This document was produced at 13:48:12 ET on 06/29/2026 under Order No.3104239353 which expires on 12/31/2026, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (3B9ADA4B)

Bids Reserved.

§ 4.1 Preparation of Bids § 4.1.1 Bids shall be submitted on the forms included with or identified in the Bidding Documents.

§ 4.1.2 All blanks on the bid form shall be legibly executed.

§ 4.1.3 Where so indicated by the markup of the bid form, the Unit Prices, the Base Bid Amount, and any other pricing the bid form requests shall be expressed in figures only. Discrepancies in the multiplication of units of Work and the Unit Prices will be resolved in the favor of the correct multiplication of the Unit Prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Discrepancies between the completed Bid Form, or the pricing submitted electronically in ProcureWare shall be resolved in the favor of the pricing submitted electronically in ProcureWare.

§ 4.1.4 All changes made by the Bidder to the bid form shall be signed or initialed by the Bidder. Bids containing any conditions, omissions, erasures, alterations, or items not called for in the Bid, may be rejected by the Owner as being incomplete or non-responsive.

§ 4.1.5 Bidders must submit a Bid for all Additives listed on the bid form. If a Bidder fails to submit a Bid for each Additive, the Owner may declare the Bid to be non-responsive.

§ 4.1.6 Omitted.

§ 4.1.7 Each Bid shall state the legal name and legal status of the Bidder. As part of the documentation submitted with the Bid, the Bidder shall provide evidence of its legal authority to perform the Work in the jurisdiction where the Project is located. Each copy of the Bid shall be signed by the person or persons legally authorized to bind the Bidder to a contract. A Bid by a corporation shall further name the state of incorporation and have the corporate seal affixed. A Bid submitted by an agent shall have a current power of attorney attached, certifying the agent’s authority to bind the Bidder. Each Bid shall include the Bidder’s Virginia Contractor registration number and classification (A, B or C).

§ 4.1.8 Authorization to Transact Business in the Commonwealth:

1. Any business entity that enters into a written contract with the Owner that is organized as a stock or nonstock corporation, limited liability company, business trust, or limited partnership or registered as a registered limited liability partnership must be authorized to transact business in the Commonwealth of Virginia as a domestic or foreign business entity if so required by Title 13.1 or Title 50…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .