8147_Shock Isolator Test Tower Tilt Carts Statement of Work Dated 31 August 2020.pdf

PDF 245 KB Posted

Attached to
Hill Air Force Base - Shock Isolator Test Tower Tilt Carts Federal contract opportunity
Solicitation number
FA822420R8147
Issued by
Department of the Air Force Materiel Command Air Force Sustainment Center

View the file

Other files for this federal contract opportunity

Other files attached to Hill Air Force Base - Shock Isolator Test Tower Tilt Carts, newest first.
File Type Posted
8147_Shock Isolator Test Tower Tilt Carts RFQ.pdf PDF
Blank DD2345 Military Critical Technical Data Agreement.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

(SOW)

For

Launch Control Center (LCC)

Shock Isolation Test Tower (SITT) Tilt Carts

In Shock Isolation (SI) Facility

309 Missile Maintenance Group (309 MMXG)

31 August 2020

Table of Contents

1. DESCRIPTION 2

2. BASIC SERVICES 2

3. REQUIREMENT LIST 3

4. GOVERNMENT FURNISHED PROPERTY AND FACILITES 4

5. GENERAL INFORMATION 4

6. APPENDICES 5

1. DESCRIPTION

The 309 Missile Maintenance Group (MMXG) requires the purchase of two (2) Launch

Control Center (LCC) Shock Isolation Test Tower (SITT) Tilt Carts. The LCC cart is a hydraulic maintenance stand for lifting and positioning heavy items being worked on in the

Shock Isolation (SI) Facility. The stand allows for 360 degree of movement that is vital for repairs and testing of assets on the SITT. The LCC carts will require testing be performed by the Contractor upon delivery.

2. BASIC SERVICE

2.1. The Contractor shall provide all management, tools, materials, services, transportation, and other items necessary to test the LCC carts once received by the Government to ensure functionality.

2.2. The Contractor shall submit a Military Critical Technical Data Agreement (DD 2345) for approval prior to the review of drawings.

2.3. Period of performance is within 24 weeks after award of contract. If there are delays in schedule, the contractor shall notify the Contracting Officer (CO) via email with the reason and justification for delay. Earlier delivery is acceptable.

3. REQUIREMENT LIST

3.1. The Contractor shall reference the following U.S. Air Force Drawings:

3.1.1. AF Form 1655 Drawing 201611045 – Tilt Cart / Tilt Station LCC Shock Isolator

Wing I, III & V. Note: Only certain sheets/details of this drawing apply.

3.1.2. AF Form 1655 Drawing 201716768 – Turnbuckle Assy, Inner Cylinder Adapter

LCC SI Tilt Cart

3.2. Equipment to be Purchased

3.2.1. Tilt Station LCC SI Tank Cradle Assembly (Item #1)

Qty: 2 EA

Drawing 201611045 (Drawing View 3)

3.2.1.1. All assemblies, sub-assemblies and components designated for this assembly in the drawing parts list, shall be included for each assembly, except for the Cylinder Cradle Optional Assy (-390, View 20).

(Reference Drawing 201611045, Sheet 6)

3.2.2. Cylinder Cradle Adapter Assembly (Item #2)

Qty: 8 EA

Drawing 201611045–370 (Drawing View 19)

3.2.2.1. All components designated for this assembly in the drawing parts list, shall be included for each assembly. (Reference Drawing 201611045, Sheet 43)

3.2.2.2. These items shall be installed on Item 1 using Items 4 (8 each only), 5, 6, and 7 (listed below) to create 390 assemblies. (Reference Drawing

201611045, Sheet 44)

3.2.3. SITT Top Swing Clamp Assembly (Item #3)

Qty: 4 EA

Drawing 201611045 (Drawing View 10)

3.2.3.1. All components designated for this assembly in the drawing parts list, shall be included for each assembly. (Reference Drawing 201611045, Sheet 36)

3.2.3.2. SIIT Top Swing Clamp Assembly (Item #3) along with 4 each of

Turnbuckle Inner Cylinder Clamp (Item #4) shall be used on a separate/existing tilt cart only

3.2.4. Turnbuckle Inner Cylinder Clamp (Item #4)

Qty: 12 EA

Drawing 201611045 (Drawing View 86)

3.2.4.1. Reference Drawing 201716768–10 Turnbuckle Assy

3.2.5. Push Button Quick Release Pin (Item #5)

Qty: 16 EA

Drawing 201611045 (Drawing View 124)

3.2.5.1. Reference Cage Code OKVE6 (McMaster-Carr) – Part #

90985A412

3.2.6. HEX HEAD SCREW (Item #6)

Drawing 201611045 (Drawing View 128)

3.2.6.1. Reference Cage Code OKVE6 (McMaster-Carr) – Part #

91257A851

3.2.7. HEX NUT (Item #7)

Drawing 201611045 (Drawing View 128)

3.2.7.1. Reference Cage Code OKVE6 (McMaster-Carr) – Part #

94895A036

4. GOVERNMENT FURNISHED PROPERTY AND FACILITIES

4.1. The Government will provide all required drawings for manufacturing needs to the contractor as government furnished property.

4.2. The Contractor shall be responsible for safeguarding all government components provided under this contract upon receipt of the LCC SI SITT Tilt Carts and until return shipment to Government facility is accepted.

4.3. Government Furnished Equipment will not be provided.

4.4. The Government will assist the contractor in processing the necessary forms to access government facilities and property.

5. GENERAL INFORMATION

5.1. Special Qualifications

5.1.1. The Contractor shall be familiar with, and have skilled technicians, who are trained to manufacture and service Hydraulic Carts.

5.2. Safety

5.2.1. The Contractor shall conform to safety requirements while on Government facilities.

5.3. Shipping

5.3.1. The Contractor shall provide all means of transportation to and from Hill AFB at no additional cost to the government.

Shipping address:

US Air Force

7653 Wardleigh Road Bldg. 850

Hill Air Force Base, Utah 84056

5.4. WARRANTY

5.4.1. The Contractor shall provide a one year warranty covering all parts and labor at no cost to the government.

6. APPENDICES

A. Acronyms & Abbreviations list

APPENDIX A

ACRONYMS AND ABREVIATIONS

CO Contract Officer

LCC Launch Control Center

SI Shock Isolator

SITT Shock Isolator Test Tower