About this file

This is a Statement of Work (SOW) for the removal, refurbishment, and reinstallation of two 200-horsepower General Electric induction motors at NASA Ames Research Center's Unitary Plan Wind Tunnel facility in Moffett Field, California. The motors serve as blower fan motors for cooling the windings of the main drive motor #1 in the wind tunnel compressor system. The contract requires a fixed-price quote covering all specified refurbishment tasks, with any additional motor repair work to be addressed via separate change order. Prevailing wage requirements do not apply. Work is scheduled to begin on or near April 12, 2027, with a maximum duration of 40 days, completing by May 21, 2027. The NASA Project Manager is Carl Kruger.

The scope encompasses pre-removal vibration analysis, electrical disconnection following OSHA and NEC standards, rigging and removal of approximately 2,100-pound motors from a basement location, transportation to the contractor's facility, comprehensive refurbishment including disassembly, cleaning, electrical testing, stator rewinding with double dip and bake, hipot and surge testing, bearing replacement, dynamic balancing, assembly and test run, return transportation, and reinstallation with precise alignment verification. Post-installation deliverables include vibration analysis reports, detailed motor condition assessments, before/after photographs, parts replacement documentation, and alignment data. The contractor must provide a one-year warranty on refurbished motors and installation work covering defects in materials, workmanship, and performance. All personnel on-site must be U.S. persons with Real ID driver's licenses; confined space certification is required for basement work. The lift plan must be submitted by March 1, 2027, and approved by the Owner's Safety Department prior to work commencement.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work for

Drive Motor #1 Blower Fan Motors Refurbishment

Rev. 1

Project Overview: The drive for the wind tunnel compressor consists of four motors which can be coupled together or run separately. To cool the windings of the drive motors, each drive motor has a pair of blowers mounted in the basement beneath the drive motor.

motors. See Figure 1 below.

Figure 1: Main Drive Blower Motors two (2) , NASA Ames Research

Center at . The two blower motors to be refurbished are the two blower motors associated with main drive motor #1. Removal of the motors will be the switchgear room. A job walk is required to understand the complexity of the motor removal.

Figure 2: Motor Nameplate

The period of performance will begin on or near April 12, 2027, or as determined by the Branch Chief, Facility Chief, and Facility Managers so long as there are no hindrances to . The scope includes of the refurbished motors. The a 40-

The work will be performed by [Contractor Name], herei Contractor [NASA Ames Owner.” The NASA Project Manager is Carl Kruger.

The base quote should price the scope of work and the motor repair work required will be paid for via a separate change order. Prevailing wage requirements do not apply.

Access to Site:

Note:

Real ID driver’s license is required to enter the center.

A NASA badge or visitor’s pass is required to enter the NASA Ames Research Center. The names of each worker needing a visitor pass shall be sent to the Amentum/NASA Project Manager (Electrical Craft Supervisor) at least three business days prior to any work date on site. Each worker will be sent an automated email with a pre-denied entry to the center. The Badging office opens at 6 a.m.

Personnel on site for 29 days or less in a 365-day period shall be badged using the visitor badge process, which -day period shall be badged via the via the NASA IdMAX system as either short-term (NASA non-PIV temporary -day period) or long- -day period) employees.

- on includes a. Name of the applicant.

b. Date of birth of the applicant. c. Home

Safety

Confined Space Training The basement beneath the drive motors is considered a non-permit confined space. Personnel who enter the basement by the NASA Safety Manager.

Chemicals – Cleaning Supplies Any chemicals, solvents, or other hazardous material to be used on site must be approved by the Jacobs

An estimated quantity of use shall be provided, in addition to SDS’ for each material. SDS for each material must be always on site and available to workers.

Use Of Ladders Portable ladders are to be inspected before initial use in each work shift, and more frequently as necessary to identify any visible defects that could cause employee injury. Ladders with defects are not to be used and shall be immediately removed from service. All ladders shall be of a type, size, and rating appropriate for the task, and used in accordance with manufacturer requirements.

Rigging Equipment

All rigging equipment used for the job

The Contractor shall submit a Plan detailing motor removal by March 1, 2027 prior to the commencement of work.

Fire Permits/Hot Work Permits

Safety clearance permits shall be obtained with the support of the Amentum’s Project Manager prior to performing any of the following:

Hot Work Permits - The Amentum Project Manager will coordinate with the Fire Prevention Program Supervisor to procure a hot work permit. Permits shall be requested 24 hours prior to commencing hot work and are posted at the jobsite for the duration of the work. Hot work consists of open flame heating devices, cutting torches, welding, welding pre-heat devices, or any other processes that create a potential fire hazard.

Energized Electrical Work Permits - The Amentum Project Manager will coordinate issuance of Energized Electrical Work Permits. These permits must be issued prior to work on live circuits >50 volts to ground.

Permits will only be issued if the de-energization introduces additional or increased hazards, or is infeasible due to equipment design or operational limitations. Permit approval is dependent upon approval from the associated NASA directorate. Energized Electrical Work Permits are not required if only performing diagnostic checks (i.e. voltage or amperage readings)

Safety Clearance Permit - The Amentum Project Manager shall arrange for issuance of a Safety Clearance Permit (from Branch JCM) prior to construction activities that include excavations, high-noise levels, open flame, welding/flame cutting, confined space, radiation, explosives, or facility closures.

Scope of work:

1. Pre-a.

associated with drive motor #1 prior to removal.

i. Motors will be running. Analysis equipment to be installed and able to record with no personnel inside basement area.

b.

c. A report summarizing these , to the motor rebuild on one, or both, motors.

2.

a.

NEC standards.

b. perform the of ontractor prior to commencement of work.

c. Contractor shall verify de- removal, and each worker shall place their personal locks on the designated Lock Box.

3. Rigging and Removal:

a. Contractor shall supply all necessary rigging equipment, tools, and personnel to safely remove each motor.

b. Each motor, weighing approximately 2100 lbs., shall be removed through the designated opening to the main switchgear room. Motors may also be removed via the staircase out of the basement to the barn.

Figure 3: Staircase out of Basement (alternate removal path)

c. wner will open the access door between the switchgear room and basement and clear any

Figure 4: Access door between the switchgear room and basement (view from basement)

Figure 5: Access door between the switchgear room and basement (view from switchgear room) d.

4.

a.

refurbishment.

b. Motors shall be refurbished to meet or exceed original manufacturer or damaged components replaced.

i. Dismantle, clean and inspect.

ii. Electrically test windings (grounded / shorted).

iii. Rewind, double dip and bake stator.

iv. Hipot and surge test stator windings.

v.

vi.

vii. Install new bearings.

viii. Assemble, test run, paint.

c. Contractor shall provide a detailed report on state of the motor within 5 business days and report if any work (such as rewinding, resurfacing) is needed beyond the stated refurbishment criteria above.

d. Contractor shall provide a report for each motor, including parts, list of parts replaced, and tests performed .

e.

f. and protected to prevent damage.

5.

a.

i.

systems.

b. Alignment shall be performed (e.g., using laser alignment tools ) to or deviate from eccentricity/unbalance.

i.

c.

d. Contractor shall perform post-alignment.

6. mmissioning:

a.

for fasteners.

b.

c.

d. The NASA Project Manager will be present to completed

7. Res

a. Contractor:

i. lts, and transport to complete the scope of work.

ii. Ensure all work complies with applicable , ASME, ANSI and Ames Research Center

iii. Coordinate sche b.

i. Provide access to the work area, including opening the switchgear room door and removing This will include removal of the blower inlet screens.

ii. any chemicals needed to complete the work onsite.

iii. -removal .

with contractor.

iv. Provide necessary facility- ety training or permits, if required.

Schedule: Work is to be performed within the dates shown in the schedule below. Contractor shall submit a proposed schedule within 15 business days of contract award. Work shall be completed within 40 days from the agreed start date, barring unforeseen delays. Work shall be completed during normal working hours Monday – Friday, 6 a.m. – 6 p.m.

9. Deliverables:

a. Due: 03/01/2027

b. Safety Data Sheet’s (SDS) for any hazardous materials shall be provided to the owner by contractor prior to start of work for approval.

c.

d. -removal) and refurbished motors (post-e.

f. removed motor within beyond the stated refurbishment criteria .

g.

h. and s of vane / shroud clearances .

i. has been completed to

10. Warranty:

a. Contractor shall provide a 1-

b. Warranty shall cover defects in materials, workmanship, and performance, with Contractor

11.

a. Contractors shall dispose of any replaced components (e.g., old bolts, worn parts) per local b.

refurbishment within Ames Research Center shall be handled and disposed of by the owner process. Form ARC749, Form A by a trained Hazardous Waste Generator via Satern Training who will then contact the Centers Hazardous Waste Disposal, Code JQ.

Date 1 Bids due TBD 2 Contract Award 12/11/2026 3 03/01/2027 4 Work Start 04/12/2027 5 Work Complete 05/21/2027 c.

d. cause the work to exceed the 40-

12. Approval:

a.