About this file

Statement of Work Summary

This is a Statement of Work (SOW) for the removal, refurbishment, and reinstallation of two 200 HP General Electric induction blower motors at NASA Ames Research Center's Unitary Plan Wind Tunnel facility in Moffett Field, California. The motors cool the windings of drive motor #1 and are located in the basement beneath the switchgear room. The NASA Project Manager is Carl Kruger. Contractors must provide a fixed price quote; prevailing wage requirements do not apply. The period of performance begins on or near April 12, 2027, with work scheduled to complete by May 21, 2027, not exceeding 40 days duration. Work must be completed during normal business hours, Monday through Friday, 6 a.m. to 6 p.m.

The scope encompasses seven major phases: (1) pre-removal vibration analysis on operating motors with a report due within 5 business days; (2) electrical disconnection adhering to OSHA and NEC standards, with the Owner performing lock-out/tag-out procedures; (3) rigging and removal of the approximately 2,100-pound motors through a designated opening; (4) transportation to the contractor's facility and comprehensive refurbishment including disassembly, inspection, electrical testing, stator rewinding with double dip and bake, hipot and surge testing, bearing replacement, dynamic balancing, assembly, test run, and painting, with a detailed report due within 5 business days; (5) reinstallation with laser alignment verification and new Grade 8 or equivalent mounting bolts torqued to ASME standards; (6) post-installation vibration analysis and functional testing confirming no vane-to-shroud interference; and (7) one-year warranty covering defects in materials, workmanship, and performance. Key deliverables include a lift plan due March 1, 2027; Safety Data Sheets for hazardous materials; proof of insurance and certifications; vibration analysis reports; before/after photographs with parts lists; and PM sign-off of completed work. The contractor must supply all labor, materials, tools, rigging equipment, and transportation, ensuring compliance with OSHA, NEC, ASME, and ANSI standards. All personnel must be U.S. persons with Real ID driver's licenses; visitor badges or NASA credentials are required, with names submitted at least three business days prior to work dates.

View the file

Other files

File Type Posted
SATPC0043179 Tab 10 RFQ Open Market.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6/2026 11/16/2026

Statement of Work for

Drive Motor #1 Blower Fan Motors Refurbishment

6/2026 11/16/2026

Project Overview: The drive for the wind tunnel compressor consists of four motors which can be coupled together or run separately. To cool the windings of the drive motors, each drive motor has a pair of blowers mounted in the basement beneath the drive motor. The blower wheels are overhung on dual shaft 200hp motors. See Figure 1 below.

Figure 1: Main Drive Blower Motors

This Statement of Work outlines the requirements for the removal, refurbishment, and reinstallation of two (2) 200 HP General Electric (GE) induction motor at the Unitary Plan Wind Tunnel facility in Moffett Field, CA. The two blower motors to be refurbished are the two blower motors associated with main drive motor #1. Removal of the motors will be difficult because of their position in the basement of the switchgear room. A job walk is required to understand the complexity of the motor removal.

The period of performance will begin on or near April 12, 2027 or as determined by the Branch Chief, Facility Chief, and Facility Managers so long as there are no hindrances to wind tunnel operations. The scope includes vibration analysis, electrical disconnection, rigging, transportation, refurbishment, and reinstallation of the refurbished motors. The project duration should not exceed a 40-day duration.

6/2026 11/16/2026

The work will be performed by [Contractor Name], hereinafter referred to as “Contractor,” in coordination with [NASA Ames Unitary Plan Wind Tunnel], hereinafter referred to as “Owner.” The NASA Project Manager is Carl Kruger.

Contractors shall provide a fixed price quote. Prevailing wage requirements do not apply.

Access to Site:

Note: All personnel on site shall be a “US Person”. A “US Person” is defined as any individual who is granted U.S.

citizenship; or any individual who is granted U.S. permanent residence ("Green Card" holder); or any individual who is granted status as a "protected person" under 8 U.S.C. 1324b(a)(3). Real ID driver’s license is required to enter the center.

A NASA badge or visitor’s pass is required to enter the NASA Ames Research Center. The names of each worker needing a visitor pass shall be sent to the Amentum/NASA Project Manager (Electrical Craft Supervisor) at least three business days prior to any work date on site. Each worker will be sent an automated email with a pre-screening questionnaire. If they fail to provide the requested information 48 hours in advance, they may be denied entry to the center. The Badging office opens at 6 a.m.

Personnel on site for 29 days or less in a 365-day period shall be badged using the visitor badge process, which requires only name, citizenship, and company affiliation. Personnel on site for more than 29 days in a 365-day period shall be badged via the via the NASA IdMAX system as either short-term (NASA non-PIV temporary credentials; 30 to 179 days in a 365-day period) or long-term (180 days or more in a 365-day period) employees.

The basic information needed from visitors for a non-PIV badge application includes a. Name of the applicant.

b. Date of birth of the applicant. c. Home address. d. Social Security Number (SSN). e. Position of the applicant.

f. Contact information for the applicant. g. Name of the requester. h. Organization of the requester. i. Contact information for the requester.

Safety

Chemicals – Cleaning Supplies Any chemicals, solvents, or other hazardous material to be used on site must be approved by the Jacobs Project Manager prior to use. The approval process shall be through the Wind Tunnel Division Safety Office.

An estimated quantity of use shall be provided, in addition to SDS’ for each material. SDS for each material must be always on site and available to workers.

Use Of Ladders Portable ladders are to be inspected before initial use in each work shift, and more frequently as necessary to identify any visible defects that could cause employee injury. Ladders with defects are not to be used and shall be immediately removed from service. All ladders shall be of a type, size, and rating appropriate for the task, and used in accordance with manufacturer requirements.

Rigging Equipment

All rigging equipment used for the job must have been load tested within a year and tagged with certification (100% rating).

11/16/2026

The Contractor shall submit a Lift Plan detailing motor removal & installation by February 2027. This Lift Plan must be approved by the Owner’s Safety Department prior to the commencement of work.

Fire Permits/Hot Work Permits

Safety clearance permits shall be obtained with the support of the Amentum’s Project Manager prior to performing any of the following:

• Hot Work Permits - The Amentum Project Manager will coordinate with the Fire Prevention Program Supervisor to procure a hot work permit. Permits shall be requested 24 hours prior to commencing hot work and are posted at the jobsite for the duration of the work. Hot work consists of open flame heating devices, cutting torches, welding, welding preheat devices, or any other processes that create a potential fire hazard.

• Energized Electrical Work Permits - The Amentum Project Manager will coordinate issuance of Energized Electrical Work Permits. These permits must be issued prior to work on live circuits >50 volts to ground.

Permits will only be issued if the de-energization introduces additional or increased hazards,or is infeasible due to equipment design or operational limitations. Permit approval is dependent upon approval from the associated NASA directorate. Energized Electrical Work Permits are not required if only performing diagnostic checks (i.e. voltage or amperage readings)

• Safety Clearance Permit - The Amentum Project Manager shall arrange for issuance of a Safety Clearance Permit (from Branch JCM) prior to construction activities that include excavations, high-noise levels, open flame, welding/flame cutting, confined space, radiation, explosives, or facility closures.

11/16/2026

Scope of work:

1. Pre-Removal Vibration Analysis:

a. Contractor shall perform a detailed vibration analysis on each of the two existing 200HP GE induction motors associated with drive motor #1 prior to removal.

i. Motors will be running. Analysis equipment to be installed and able to record with no personnel inside basement area.

b. Analysis shall include baseline measurements of vibration levels, frequency spectra, and any identified anomalies.

c. A report summarizing these initial findings for each motor shall be provided to Owner within 5 business days of analysis completion, to determine if additional funds are necessary to complete the motor rebuild on one, or both, motors.

2. Electrical Disconnection:

a. Contractor shall safely disconnect all electrical connections to each motor, adhering to OSHA and

NEC standards.

b. The Owner will perform the LOTO of applicable equipment, provide associated schematic drawings and walkthrough the LOTO with the Contractor prior to commencement of work.

c. Contractor shall verify de-energization of each motor prior to removal, and each worker shall place their personal locks on the designated Lock Box.

3. Rigging and Removal:

a. Contractor shall supply all necessary rigging equipment, tools, and personnel to safely remove each motor.

b. Each motor, weighing approximately 2100 lbs., shall be removed through the designated opening to the main switchgear room.

c. Owner will remove the access cover between the switchgear room and basement and clear any obstructions in the removal path.

d. Contractor shall ensure protection of the facility floors, walls, and equipment during removal.

4. Transportation and Refurbishment:

a. Contractor shall transport the motors from Owner’s facility to Contractor’s facility for refurbishment.

b. Motors shall be refurbished to meet or exceed original manufacturer specifications, with all worn or damaged components replaced.

i. Dismantle, clean and inspect.

ii. Electrically test windings (grounded / shorted).

iii. Rewind, double dip and bake stator.

iv. Hipot and surge test stator windings.

v. Check mechanical fit.

vi. Dynamically balance all rotating parts.

vii. Install new bearings.

viii. Assemble, test run, paint.

11/16/2026

c. Contractor shall provide a detailed report on state of the motor within 5 business days and report if any additional work (such as rewinding, resurfacing) is needed beyond the stated refurbishment criteria above.

d. Contractor shall provide a report for each motor, including before / after pictures of internal parts, list of parts replaced, and tests performed prior to installation.

e. Contractor shall transport the refurbished motors back to Owner’s facility for reinstallation.

f. All transportation shall comply with applicable DOT regulations, and motors shall be secured and protected to prevent damage.

5. Installation of Refurbished Motors:

a. Contractor shall reinstall the two refurbished 200HP GE induction motors.

i. Installation shall include rigging, precise alignment, and reconnection of electrical systems.

b. Alignment shall be performed (e.g., using laser alignment tools or vibration analysis devices) to ensure vanes do not interfere with shrouds during operation or deviate from eccentricity/unbalance.

i. Alignment data shall be provided to the Owner in final report.

c. Existing motor mounting bolts shall be replaced with new bolts of adequate strength, meeting or exceeding OEM specifications (e.g., Grade 8 or equivalent, sized appropriately for the application). Torque specification to equal industry ASME standards.

d. Contractor shall perform post-installation vibration analysis to verify proper operation and alignment. Results shall be provided to the Owner in final report.

6. Testing and Commissioning:

a. Contractor shall conduct functional testing of each refurbished motor to verify performance meets manufacturer specifications and provide documentation such as torque values for fasteners.

b. Testing shall confirm no interference between vanes and shrouds under operational conditions.

c. Any deviations or issues identified during testing shall be corrected at no additional cost to Owner.

d. The Amentum Technology Project Manager will be present to sign off that all work / testing has been completed to satisfactory standards.

7. Responsibilities:

a. Contractor:

i. Provide all labor, materials, tools, rigging equipment, new mounting bolts, and transportation necessary to complete the scope of work.

ii. Ensure all work complies with applicable OSHA, NEC, ASME, ANSI and Ames Research

Center safety regulations.

iii. Coordinate scheduling with Owner to minimize disruption to the facility operations.

b. Owner:

i. Provide access to the work area, including removal of the switchgear room door and any obstructions. This will include removal of the blower shrouds.

ii. Approve Lift Plan and any chemicals needed to complete the work onsite.

iii. Complete LOTO of system after pre-removal and vibration analysis. Review LOTO plan and associated schematic drawings with contractor.

. 6/2026 11/16/2026

iv. Provide necessary facility-specific safety training or permits, if required.

8. Schedule: Work is to be performed within the dates shown in the schedule below. Contractor shall submit a proposed schedule within 15 business days of contract award. Work shall be completed within 40 days from the agreed start date, barring unforeseen delays. Work shall be completed during normal working hours Monday – Friday, 6 a.m. – 6 p.m.

9. Deliverables:

a. Lift plan for extraction and installation of motors. Due: 03/01/2027

b. Safety Data Sheet’s (SDS) for any hazardous materials shall be provided to the owner by contractor prior to start of work for approval.

c. Contractor shall provide proof of insurance and certifications for rigging and electrical work prior to starting.

d. Vibration analysis reports for existing motors (pre-removal) within 5 days of testing and refurbished motors (post-installation).

e. Documentation of electrical disconnection and reconnection procedures.

f. Per Section 4(c): Contractor shall provide a detailed report on state of the removed motor within 5 business days and report if any additional work (such as rewinding, resurfacing) is needed beyond the stated refurbishment criteria in Section 4(b).

g. Per Section 4(d): Contractor shall provide a report for each motor, including before / after pictures of internal parts, list of parts replaced, and tests performed prior to installation.

h. Confirmation of successful motor installation and testing, including verification and written specifications of vane / shroud clearances per Section 5(b(i).

i. The PM will sign off that all work / testing has been completed to specifications.

10. Warranty:

a. Contractor shall provide a 1-year warranty on the refurbished motors and installation work, effective from the date of successful commissioning.

b. Warranty shall cover defects in materials, workmanship, and performance, with Contractor responsible for repairs or replacements at no additional cost to Owner.

11. Additional Considerations:

a. Contractors shall dispose of any replaced components (e.g., old bolts, worn parts) per local regulations, unless Owner requests retention.

b. Any hazardous materials (e.g., lubricants, insulation) encountered during removal or refurbishment within Ames Research Center shall be handled and disposed of by the owner (NASA UPWT) via Form A process. Form ARC749, Form A by a trained Hazardous Waste Generator via Satern Training who will then contact the Centers Hazardous Waste Disposal, Code JQ.

Description Date 1 Bids due TBD 2 Contract Award 12/11/2026 3 Lift Plan submitted to Owner 03/01/2027 4 Work Start 04/12/2027 5 Work Complete 05/21/2027

11/16/2026

c. No special environmental conditions (e.g., extreme temperature, dust, noise) are present in the work area requiring additional preparation.

d. Contractors shall promptly notify NASA UPWT of any foreseeable issues that may cause the work to exceed the 40-day schedule as soon as such issues are identified.

12. Approval:

a. This SOW is subject to review and approval by both parties. Any modifications or additional requirements shall be documented in writing and agreed upon prior to commencement of work.

File details come from the government source that posted it. Updated .