SATPC0043055 Tab 06 BNJ REV.pdf

PDF 492 KB Posted

Attached to
UPS for Microfabrication Laboratory
Solicitation number
80NSSC27947369Q
Issued by

About this file

This is a NASA Shared Services Center Recommendation and Determination to Solicit from One Source or Brand Name form justifying a brand name procurement. NASA Glenn Research Center is procuring Vertiv Uninterruptible Power Supply (UPS) systems as direct replacements for existing UPS systems in the Microfabrication Laboratory. The existing systems are approximately 20 years old, require extensive replacement parts, and will no longer receive manufacturer support after December 2026. The requirement includes a 10 kVA/kW UPS operating at 208V and a 40 kVA/kW UPS operating at 480V with specific electrical configurations and dimensional limitations to support critical laboratory exhaust ventilation equipment essential to semiconductor fabrication and research operations.

The total estimated cost is $89,850.00 with an estimated period of performance or lead-time for delivery of 6 months. The justification emphasizes that Vertiv systems closely match the existing electrical infrastructure, installation space, power capacity, and cooling requirements, minimizing facility modifications. The document demonstrates that utilizing UPS systems from alternative manufacturers could require significant modifications to electrical infrastructure, including rerouting high-voltage cabling, modifying power connections, and potentially relocating equipment, resulting in additional engineering, installation, labor, and material costs plus delays in timely equipment replacement. The document was signed by Contracting Officer Karen L. Artis on the final approval page, with the RDSS (Recommendation and Determination to Solicit from One Source) box selected indicating this exceeds $25,000 and will be posted on SAM.gov.

View the file

Other files

File Type Posted
SATPC0043055 Tab 10 RFQ Open Market.pdf PDF
SATPC0043055 Tab 04 4 SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 V2.0 3-15-2017

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION

NASA SHARED SERVICES CENTER

RECOMMENDATION AND DETERMINATION TO SOLICIT FROM ONE SOURCE

OR BRAND NAME

PICK ONE Sole Source:

☐I recommend that NASA, NASA Shared Services Center negotiate with Vendor Name only for Enter

Supply or Service to be procured. The total estimated cost of this effort is Enter Dollar amount and the estimated period of performance or lead-time for delivery is Date.

OR Brand Name

Justification:

☒I recommend that NASA, NASA Shared Services Center negotiate with only with vendors who can provide the subject brand name from Vertiv for UPS. The total estimated cost of this effort is $89,850.00 and the estimated period of performance or lead-time for delivery is 6 months.

This recommendation is for the acquisition of supplies or services determined to be reasonably available from only one source/only one manufacture. Competition is impractical for the following reasons (please answer the questions below):

1. What are the reasons for soliciting only the suggested source/suggested brand name? Please provide the unique characteristics of the items or services along with the supporting rationale and the market research performed to substantiate your reason for the suggested source/brand name. The Vertiv Uninterruptible Power Supply (UPS) systems are being requested as direct replacements for the existing UPS systems currently installed in NASA Glenn Research Center's Microfabrication Laboratory. The existing systems are approximately 20 years old, require extensive replacement parts to restore reliable operation, and will no longer receive manufacturer support after December 2026. The proposed Vertiv systems closely match the existing electrical infrastructure, available installation space, power capacity, and cooling requirements, minimizing the need for extensive facility modifications. The replacement systems must support the laboratory's critical exhaust ventilation equipment, which is essential to ongoing semiconductor fabrication and research operations. The required systems include a 10 kVA/kW UPS operating at 208V and a 40 kVA/kW UPS operating at 480V, with specific electrical configurations, dimensional limitations, modular architecture, and maintenance capabilities. The proposed Vertiv systems are intended to meet these requirements while allowing integration into the existing facility infrastructure. Based on the compatibility of the proposed replacement systems with the existing installation and the anticipated costs and operational disruptions associated with significant infrastructure modifications, Vertiv is the recommended brand for this acquisition.

2. What is the impact to the government if another vendor/brand is used? Include any dollar, schedule, or compatibility impacts if possible.

Utilizing a UPS system from another manufacturer could require significant modifications to the existing electrical infrastructure, including rerouting high-voltage cabling, modifying power connections, and potentially relocating equipment to accommodate different system dimensions, ventilation, or service-access requirements. The proposed Vertiv systems closely match the existing installation footprint, electrical configurations, and cooling infrastructure, reducing the need for costly facility modifications. Selecting an alternative brand that does not meet these requirements could result in additional engineering, installation, labor, and material costs, as well as delays associated with facility modifications and system integration. Such delays could affect the timely replacement of the existing UPS systems, which are approaching the end of manufacturer support in December 2026. Continued reliance on aging equipment could increase the risk of interrupted backup power to critical laboratory exhaust ventilation systems, potentially affecting ongoing research and fabrication operations. Therefore, the proposed Vertiv systems are expected to minimize installation costs, reduce operational disruptions, and support continuity of laboratory operations.

11/17/2026

Date Srihari Rajgopal Technical User Name

Engineer

Title/Office

****FOR NSSC SAT USE ONLY****

The above justification in pursuant to one of the following (only select one):

☐ - Recommendation and Determination to Solicit from One Source (RDSS): For open market purchases, pursuant to FAR 5.101(a) the proposed contract action in excess of $25,000 will be placed on SAM.gov.

☐ - Recommendation and Determination to Solicit from One Source (RDSS): For open market purchases, pursuant to FAR 5.101(a) the proposed contraction action is exempt from the posting requirement and will not be placed on SAM.gov, i.e., below $25,000.

☐ - Recommendation and Determination to Solicit from One Source (RDSS): For open market purchases, pursuant to FAR 5.202(a)(2), the proposed contract action is exempt from publication on SAM.gov because the government would be seriously injured if the Agency complies with the time periods specified in FAR 5.203.

☐ - Brand Name Justification (BNJ): For open market purchases, pursuant to FAR 12.102(a), the acquisition of the referenced brand name item is hereby justified.

☐ - SEWP/IDIQ Brand Name Justification (BNJ): For schedule/IDIQ purchases, pursuant to FAR 16.507-7(a), the acquisition of the referenced brand name item(s) is hereby justified (under $40,000)

☐ - SEWP/IDIQ Brand Name Justification (BNJ): For schedule/IDIQ purchases, pursuant to FAR 16.507- 7(c)(1), the acquisition of the referenced brand name item(s) is hereby justified. Any action over $40,000 the brand name shall be posted on the agency website used to solicit offers for orders.

☐ - Limited Source Justification (LSJ) Sole Source: For GSA orders, pursuant to FAR 8.401(b)(and by way of GSAR 538.7104-3(a)), only one source is capable of providing the supplies or services required at the level of quality required because the supplies or services are unique or highly specialized. Action will be performed against GSA Contract Number: ________________.

☐ Source Justification (LSJ) Brand Name: For GSA orders, pursuant to FAR 8.401(b) (and by way of GSAR 538.7104-4(a)), the item is peculiar to one manufacturer. A brand name item, whether available on one or more schedule contracts, is an item peculiar to one manufacturer.

☐ - Exception to Fair Opportunity (EFO): For SEWP orders or orders placed against other IDIQ contracts, under the authority of the exemption under FAR 16.507-6(b) used is based on the following:

☐ (A) The agency need for the supplies or services is so urgent that providing a fair opportunity would result in unacceptable delays ☐ (B) Only one awardee is capable of providing the supplies or services required at the level of quality required because the supplies or services ordered are unique or highly specialized.

☐ (C) The order must be issued on a sole-source basis in the interest of economy and efficiency because it is a logical follow-on to an order already issued under the contract, provided that all awardees were given a fair opportunity to be considered for the original order.

I hereby accept the above-mentioned recommendation and determine the circumstances of the contract action are deemed appropriate for this requirement.

Contracting Officer

Page 2 V5.0 SEP 2026

X

Justification - CO Page.pdf
****FOR NSSC SAT USE ONLY****
The above justification in pursuant to one of the following (only select one):

File details come from the government source that posted it. Updated .