This is a Recommendation and Determination to Solicit from One Source (RDSS) form from NASA Shared Services Center requesting approval to negotiate with Mayer Electric Supply Company Inc. for a Switchboard with a 12-week delivery timeline after receipt of order (ARO). The document indicates this is a sole source procurement rather than a brand name justification.

The justification cites that lead time estimates from Square D for the same unit were over 50 weeks, while Mayer Electric can deliver in 12 weeks. The switchboard must be installed and operational by June 1, 2025, and using another manufacturer with longer lead times would result in test delays and additional costs for test contractors. The document is currently on hold pending completion of market research as of January 21, 2025. The form includes various procurement authority options but none are selected, awaiting contracting officer review and signature.

View the file

Other files

File Type Posted
SATPC0037271 Tab 07 Capability Statement SAM.gov.pdf PDF
SATPC0037271 Tab 04 4 SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page 1 V2.0 3-15-2017

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION

NASA SHARED SERVICES CENTER

RECOMMENDATION AND DETERMINATION TO SOLICIT FROM ONE SOURCE

OR BRAND NAME

PICK ONE

Sole Source:

☒I recommend that NASA, NASA Shared Services Center negotiate with MAYER ELECTRIC SUPPLY COMPANY INC only for the Switchboard . The total estimated cost of this effort is and the estimated period of performance or lead-time for delivery is 12 weeks ARO.

OR

Brand Name Justification:

☐I recommend that NASA, NASA Shared Services Center negotiate only with vendors who can provide the subject brand name from Manufacturer Name for supply or service to be procured. The total estimated cost of this effort is Dollar Amount and the estimated period of performance or lead-time for delivery is Date.

This recommendation is for the acquisition of supplies or services determined to be reasonably available from only one source/only one manufacture. Competition is impractical for the following reasons (please answer the questions below):

1. What are the reasons for soliciting only the suggested source/suggested brand name? Please provide the unique characteristics of the items or services along with the supporting rationale and the market research performed to substantiate your reason for the suggested source/brand name.

Lead time estimates from Square D were 50+ Weeks for this same unit

2. What is the impact to the government if another vendor/brand is used? Include any dollar, schedule, or compatibility impacts if possible.

This equipment in necessary to provide test support. This Switchboard must be installed and operational by June 1, 2025. Failure to meet this deadline could result in test delays and additional costs for test contractors due to the longer leadtime required by the other manufacturer

ADDITIONAL COMMENTS:

ON HOLD UNTIL MARKET RESEARCH IS COMPLETED. sct--1-21-2025 strigg Highlight

Page 2 V3.0 01/18/2023

****FOR NSSC SAT USE ONLY****

The above justification in pursuant to one of the following (only select one):

☐ - Recommendation and Determination to Solicit from One Source (RDSS): For open market purchases, pursuant to FAR 5.101(a)(1), the proposed contract action will be placed on SAM.gov under the authority of FAR 13.106 - 1(b)(1)(i).

☐ - Recommendation and Determination to Solicit from One Source (RDSS): For open market purchases, pursuant to FAR 5.101(a)(2), the proposed contraction action was not placed on SAM.gov as oral solicitation will be used to solicit quotation under the authority of FAR 13.106-1(c).

☐ - Recommendation and Determination to Solicit from One Source (RDSS): For open market purchases, pursuant to FAR 5.202(a)(2), the proposed contract action is exempt from publication on SAM.gov because the government would be seriously injured if the Agency complies with the time periods specified in FAR 5.203.

☐ - Brand Name Justification (BNJ): For open market purchases, pursuant to FAR 13.106-1(b)(1)(i), the acquisition of the referenced brand name item is hereby justified. (Under $25,000)

☐ - Brand Name Justification (BNJ): For open market purchases, pursuant to FAR 13.106-1(b)(1)(i), the acquisition of the referenced brand name item is hereby justified. Pursuant to FAR 5.201, any contract action over $25,000 shall be synopsized in the Government wide Point of Entry (GPE) and the brand name justification must be attached.

☐ - SEWP/IDIQ Brand Name Justification (BNJ): For schedule/IDIQ purchases, pursuant to FAR 16.505(4)(i) (ii), the acquisition of the referenced brand name item(s) is hereby justified. (under $30,000)

☐ - SEWP/IDIQ Brand Name Justification (BNJ): For schedule/IDIQ purchases, pursuant to FAR 16.505(a)(4)(i)(ii)(iii)(A), the acquisition of the referenced brand name item(s) is hereby justified. Any action over $30,000 the brand name shall be posted on the agency website used to solicit offers for orders.

☐ - Limited Source Justification (LSJ) Sole Source: For GSA orders, pursuant to FAR 8.405-6(a)(1)(i)(B), only one source is capable of providing the supplies or services required at the level of quality required because the supplies or services are unique or highly specialized. Action will be performed against GSA Contract ___________________.

☐ - Limited Source Justification (LSJ) Brand Name: For GSA orders, pursuant to FAR 8.405-6(b), the item is peculiar to one manufacturer. A brand name item, whether available on one or more schedule contracts, is an item peculiar to one manufacturer.

☐ - Exception to Fair Opportunity (EFO): For SEWP orders or orders placed against other IDIQ contracts, under the authority of the Federal Acquisition Streamlining Act (FASA) and Pursuant to FAR 16.505(b), exemption under FAR 16.505(b)(2) used is based on the following:

☐ (A) The agency need for the supplies or services is so urgent that providing a fair opportunity would result in unacceptable delays ☐ (B) Only one awardee is capable of providing the supplies or services required at the level of quality required because the supplies or services ordered are unique or highly specialized.

☐ (C) The order must be issued on a sole-source basis in the interest of economy and efficiency because it is a logical follow-on to an order already issued under the contract, provided that all awardees were given a fair opportunity to be considered for the original order.

I hereby accept the above stated recommendation and determine that the circumstances of the contract action deem only one source reasonably available.

X Contracting Officer