QA_20200618.docx
DOCX document 12 KB Posted
- Attached to
- Inconel 718 DMLS Material Testing/ QTY:1 Federal contract opportunity
- Solicitation number
- 80NSSC20732473QR2
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QA_20200618.docx | DOCX document | |
| RFQ 80NSSC20732473QR2.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q: Do you need certifications for the stress relief cycle?
A: No. if there is a standard that is followed, or a company standard that is followed please provide that. The AMS standard only applies to ageing and heat treatment.
Q: “For evaluation of bid, supplier shall provide description and applicable standards used for: Stress Relieving process, Heat-treat process, HIP process.” The RFQ was changed to specify a heat treat and HIP cycle. Can this line of the RFQ be changed to reflect that the description and applicable standards used for heat treat and HIP are provided by NASA?
A: although the standards were provide please provide the information asked for. This will be used for documentation and presentations.