AMENDMENT 0002 SF30.pdf

PDF 456 KB Posted

Attached to
Minor Construction Contract - V (MCC-V) Federal contract opportunity
Solicitation number
80MSFC23R0008
Issued by
National Aeronautics and Space Administration Marshall Space Flight Center

About this file

This document is an amendment to a solicitation for the Minor Construction Contract - V (MCC-V) opportunity with the National Aeronautics and Space Administration Marshall Space Flight Center. The amendment provides clarification to questions from potential offerors. It confirms that no pricing data is required for proposal submission and that the contract may be awarded to multiple companies. Each task order will specify the response date, period of performance, and identify any required materials or personnel. A site supervisor must be identified for each task order. Security and badging requirements apply, and materials submittals will use Procore. Performance evaluations should be completed by the Contracting Officer or Contracting Officer's Representative involved in monitoring contract compliance.

View the file

Other files for this federal contract opportunity

Other files attached to Minor Construction Contract - V (MCC-V), newest first.
File Type Posted
AMENDMENT 0001 _Attachment_L-1_Offeror_Information_Form.pdf PDF
AMENDMENT 0001 SF30.pdf PDF
AMENDMENT 0001_ SF1442.pdf PDF
ATTACHMENT_L-2__Past_Performance_Questionaire_Recipient_List.pdf PDF
SF1442.pdf PDF
ATTACHMENT_L-3__Past_Performance_Questionnaire.pdf PDF
Minor Construction Contract V (MCC-V) TERMS.pdf PDF
ATTACHMENT_L-1_Offeror_Information_Form MCC V.pdf PDF
Attachment J-4 WAGE DETERMINATION.pdf PDF
ATTACHMENT_L-4_Historical Projects_List.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1

1. CONTRACT ID CODE

I

PA

E OF PAGES

I 3

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER

5. PROJECT NUMBER (If applicable)

0002 11/16/2023

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE I

NASA NASA

Marshall Space Flight Center Marshall Space Flight Center Office of Procurement Office of Procurement/PS32 Marshall Space Flight Center AL 35812 Marshall Space Flight Center AL 35812

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) SA. AMENDMENT OF SOLICITATION NUMBER

ALL PROSPECTIVE OFFERORS

80MSFC23R0008

� SB. DATED (SEE ITEM 11)

11/16/2023

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE I FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

� The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers D is extended. � is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning _____ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor Dis not Dis required to sign this document and return ____ _ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this Amendment 0002 is as follows:

The purpose of this Amendment 0002 is to respond to questions and provide answers/clarifications. See Clarification to All Potential Offerers (Attachment A).

Except as provided herein, all terms and conditions of the document referenced in Item SA or 1 OA, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED

(Signature of person authorized to sign)

Previous edition unusable

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

(Signature of Contracting Officer)

STANDARD FORM 30 (REV.11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

27 November 2023

Joseph R. Tynes

Attachment A-1

ATTACHMENT A – CLARIFICATIONS TO ALL POTENTIAL OFFERORS

Questions Template

Minor Construction Contract V (MCC-V)

80MSFC23R0008

Number Question Answer

1) Is there any further document or drawing or information (like quantities) regarding the works that would be required out there?

See Section C clause MSFC 52.211-93 Description/Specifications/Statement of Work for a description of project disciplines and Historical and Project List Attachment L-4.

2) Would be allowed to include, for the past performance, CPARS in lieu of sending PPQs out?

No, responses shall be provided in accordance with the solicitation.

3) Was the Virtual Briefing mandatory to attend in order to bid?

No, the virtual briefing was voluntary.

4) I am submitting my bid as a prime contractor. My subcontractors meet the bond capability, insurance, workman’s comp, past performance and financial capability. Am I able to submit my subcontractors information or am I required to submit this documentation for my company?

The Government’s relationship is with the Prime therefore all solicitation requirements shall be proposed from the Prime.

5) We are working on this proposal and wondering if the slides that were presented will be shared through email or added on SAM.gov?

See SAM.gov 80MSFC23R0008 Amendment 0001 for Industry Briefing PowerPoint slides.

6) We need to access some of the links. Also, just to clarify, we will be possibly awarded based on skill set and ability to sub contract; so we don't need to provide detailed pricing for material or labor or do a site visit.. is that correct?

No pricing data is required for proposal submission.

7) Will this 5 year Multi award IDIQ contract be awarded to a single company or multiple companies to bid on the individual task orders?

There is no limit to the number of contracts that may be awarded to separate and distinct business entities which meet the criteria established in the solicitation.

8) Are there set rates for each individual task orders?

There are no set rates for each individual task order.

Attachment A-2

9) What is the time frame for when a task order is published to when notice to proceed is issued?

Each task order will have a response date for bids along with a period of performance stated in each bid package.

10) What are the required on-site key personnel and can those individuals hold multiple roles?

A site supervisor will be required and identified for each task order. Additional personnel may be required depending on complexity scope as identified in the task order bid package.

11) Is there an area on site for a permanent office or location for office trailer?

There are no provisions for permanent/on-site office trailers. The Government does provide an area for storage /Conex boxes.

12) What are the badging/access requirements for contractors to get on site at Marshall Space Flight Center?

See MSFC 52.204-91 Security and Badging Requirements (NOV 2016). Further information will be supplied after award at the MCC-V pre-construction meeting.

13) Is there a material submittal process for each task order or are all the materials used in the individual specifically identified when the task order is published?

Currently material submittals are processed using Procore. Materials required will be identified on the drawings/SOW for each task order.

14) If our company was a subcontractor working under a prime on a project, would we send the request to complete the contractor performance report to the prime contractor on the project, or directly to the MSFC CO/COR over the project? We were a sub on most of the projects we have completed at MSFC and just trying to confirm who we need to send this to.

The evaluation should be completed by the Contracting Officer (CO) or Contracting Officer’s Representative (COR), Task Monitor (TM), or other Customer designee identified to monitor the Contractor’s compliance with the requirements of the contract.

2023-11-27T14:09:58-0600
Joseph Tynes