80KSC022Q0002

Attachment 1

STATEMENT OF WORK (SOW)

ARTEMIS CREW TRANSPORTATION VEHICLE(S)

1.0 INTRODUCTION

1.1 The mission of the National Aeronautics and Space Administration (NASA) Kennedy Space Center (KSC)

Exploration Ground Systems (LX) Program is to Build. Launch. Recover. NASA KSC LX is seeking to augment its mission with a transportation solution to serve as the Artemis Crew Transport Vehicle(s) (CTV(s)) for transporting the NASA Artemis Astronauts from the suiting up facility in the Neil Armstrong Operations and Checkout Building

(O&C) to the Launch Pad on launch day at NASA KSC, as well as during test operations prior to launch at the

Vehicle Assembly Building (VAB) and Launch Control Center (LCC).

2.0 BACKGROUND

2.1 Every Government-led, NASA manned spaceflight program is equipped with a unique capability to transport

NASA astronauts from the living quarters on-site at NASA KSC to Launch Complex 39B (LC39B), the VAB, or the

LCC for testing and launch operations. NASA requires zero-emission transportation vehicle(s) to serve as the new

Artemis CTV(s); to be designed, built, and tested to transport NASA flight crew members and support personnel for all future Artemis missions. The CTV(s) will also be used to transport the NASA flight crews for launch operations as well as training and launch rehearsals.

2.2 On launch day, the Artemis CTV(s) will be stationed outside the O&C on standby for the suited flight crew members and support personnel to board. Once personnel and equipment are loaded, the CTV(s) will transport

Artemis personnel to LC-39B for launch operations. After personnel are safely offloaded at LC39B, the CTV(s) will move to a standby location outside the Launch Danger Area (LDA) until the end of launch countdown operations. If launch occurs, the CTV(s) return to a storage location aboard NASA KSC until the next mission. If the launch does not occur, or scrubs, the CTV(s) return to LC39B to pick up the NASA flight crew members for return to the living quarters at the O&C for the next launch attempt.

2.3 For training and launch rehearsals, the CTV(s) will be utilized in the same manner described in paragraph 2.2 above. For some flight crew training events, the CTV(s) will transport the astronauts from the O&C to the transfer aisle of the VAB or LCC instead of LC39B.

3.0 SCOPE

3.1 The contractor shall provide transportation vehicle(s) to serve as the Artemis CTV(s). The contractor shall design, fabricate, and test one or multiple vehicles to be used as the Artemis CTV(s). The CTV(s) shall meet the technical requirements and standards as specified in the SOW.

3.2 The contractor shall provide project management of schedule, technical issues, and risk to ensure the proposed transportation vehicle(s) are delivered to the Government. The contractor shall be responsible for delivering the completed Artemis CTV(s) to NASA KSC no later than June 2023.

3.3 The Contractor shall furnish all required labor, tools, equipment, materials, transportation, facilities, management, and supervision necessary for the performance of all operations incidental to the contractor’s proposed transportation solution.

4.0 ARTEMIS CTV(S) TECHNICAL REQUIREMENTS

4.1 In accordance with Executive Order 14037 Strengthening American Leadership in Clean Cars and Trucks, the contractor shall provide the required pre-production zero emission transportation vehicle(s) to transport NASA flight crew, support personnel, and associated equipment from the O&C to LC-39B and from the O&C to the VAB for

Artemis testing, training, and launch operations. Zero emission shall be: battery electric, plug-in hybrid electric, or fuel cell electric.

4.2 The Contractor shall design, manufacture, and deliver the Artemis CTV(s). The Artemis CTV’s shall be certified in accordance with current National Highway Transportation Safety Administration (NHTSA) standards.

4.3 The CTV(s) shall visually embody Artemis to the NASA agency and the public; as well as safely and securely transport the Artemis Astronauts and support personnel.

4.4 Artemis CTV(s) Preliminary Design. As part of the response to this solicitation, the Contractor shall be responsible for creating a preliminary design of the proposed Artemis CTV(s). The Artemis CTV(s) preliminary design shall be submitted as part of their proposed transportation vehicle(s). After award, the Government will approve the preliminary design for production. The Contractor shall be responsible for executing the design concept, such as: fabrication; manufacturing; acquisition and installation of all vehicle equipment and material components;

vehicle wrap and graphics; NHTSA safety certifications; and freight for final delivery of the Artemis CTV(s) to

NASA KSC.

4.4.1 Changes to Design. Authorized changes that deviate from the Government approved Artemis CTV(s) design, shall be reviewed, and approved by the Government. Approved changes in design shall not entitle the Contractor to an equitable adjustment of the contract price, reimbursement for resulting increased costs, or an adjustment of the delivery schedule.

4.5 Personal Capacity. The contractor shall provide one or multiple CTVs capable of carrying and seating the following NASA personnel:

Personnel Description Required Capacity (Qty.)

Driver 1 (per CTV)

Fully Suited NASA Flight Crew Members 4

Suit Technician 1

Flight Operations Director (FOD) 1

Protective Services Agent 1

4.6 Storage Capacity. The contractor shall provide equipment storage capacity within the CTV(s) interior, adjacent to Flight Crew member seating, and readily available and accessible during transportation. The equipment description, quantity, and approximate dimensions are as follows:

Description Quantity Dimensions (approx.)

Equipment Bags 4 20 in x 20 in x 20 in;

8000 cubic inches per bag

Ice Cooling Units 4 28 in x 16 in x 22 in;

9856 cubic inches per unit

Equipment Bag 1 31 in x 12 in x 16 in;

5952 total cubic inches

Pad Transfer Bag with Miscellaneous

Equipment

31 in x 12 in x 16 in;

5952 total cubic inches

Miscellaneous Storage Space, adjacent to

Flight Crew member 4 (2) cubic feet per passenger

4.7 Primary Access. The Artemis CTV(s) shall be equipped with a primary access point of no less than 24-inch to

36-inch width to serve as the primary personnel ingress and egress.

4.8 Secondary Access. The Artemis CTV(s) shall be equipped with a secondary access point of no less than 24-inch to 36-inch width to serve as the secondary personnel ingress and egress. Secondary access point can be used in the event the primary access point fails or during an emergency situation that prevents the use of the primary access point.

4.9 Air Conditioning. The Artemis CTV(s) shall provide environmental conditioning (cool and heat) inside the main cabin to maintain passenger comfort for year-round, central Florida average temperatures.

4.10 Artemis CTV(s) Cabin Power. The Artemis CTV(s) shall provide power within the CTV(s) as follows: (a)

Each Flight Crew member seating position shall have a 12VDC female power connector per ANSI/SAE J563 size.

This shall equate to four (4) total connectors; and (b) Each connector and associated wiring shall be rated to a minimum of ten (10) amps.

4.11 Vehicle(s) Materials and Components. All materials and components used in the design, fabrication, and manufacture of the Artemis CTV(s) shall be new and free of defects.

4.12 Agency Markings. As part of the contractor’s preliminary design, the Contractor shall propose the vehicle wrap, graphics, markings and/or artwork on the exterior of the Artemis CTV(s) that inspire the NASA agency and the public for future Artemis missions. After contract award, the Government shall approve all graphics and artwork prior to Contractor fabrication and installation on the Artemis CTV(s). The Government shall provide NASA marking and artwork specifications to the contractor.

4.13 Commercial Markings. Manufacturer’s markings on OEM equipment, such as the vehicle manufacturer’s logo, is considered a standard commercial marking, and is permitted and not needed to be removed from such equipment.

No other markings such as the Contractor’s company name or advertising is permitted on the Artemis CTV(s). All non-standard commercial markings/artwork shall be reviewed by the NASA Government Technical Representative for approval and installation.

4.14 Artemis CTV(s) Operator Manuals. The contractor shall develop and provide, at a minimum, a user’s manual for the Artemis CTV(s) that documents vehicle features, operations, maintenance, and servicing instructions, and other information as directed by the Government Technical Representative. The format and quantity shall be two (2) hardcopy and one (1) digital copy of the required CTV(s) manual.

4.15 The Artemis CTV(s) shall be designed and manufactured to be driven with a Florida Department of Highway

Safety and Motor Vehicles (FLHSMV) Class E Driver’s License.

4.16 The Artemis CTV(s) shall be designed and manufactured to sustain an eight (8) hour duty day and cover no less than a minimum range of 50 miles aboard NASA KSC without requiring re-charging of the vehicle(s).

4.17 Operation during the eight (8) hour duty day shall require air conditioning or heat depending on the exterior central Florida temperature.

4.18 The Artemis CTV(s) shall be capable of driving on paved highways only. The Artemis CTVs will not be required to be driven in off-road conditions.

5.0 INSPECTION AND ACCEPTANCE

5.1 Inspection and acceptance will be conducted in accordance with FAR Clause 52.212-4

6.0 DELIVERY

6.1 Delivery of the Artemis CTV(s) shall be no later than June 2023

6.2 The contractor shall be responsible for delivering the Artemis CTV(s) to NASA KSC after fabrication, build, and testing is complete. For delivery, the contractor shall coordinate with the CO, Government Technical

Representative, and the KSC Logistics and Transportation office.

6.3 Contractor Notice Regarding Late Delivery: In the event the Contractor anticipates or encounters difficulty in complying with the contract delivery schedule or in meeting any of the other requirements of the contract, the

Contractor shall immediately notify the Government and follow up, in writing, indicating the reason(s). The information shall not be construed as a waiver by the Government: (i) of any delivery schedule or date; (ii) of compliance with any other contract requirement by the Contractor; or (iii) of any other rights or remedies provided to the Government by law under this contract.

6.4 Early Deliveries: The Contractor is authorized and encouraged to deliver earlier and/or exceed the Completion

Schedule. Accelerated delivery shall not obligate the Government to any additional costs.

7.0 GOVERNMENT QUALITY ASSURANCE

7.1 The Government will monitor the Artemis CTV(s) progress using a combination of virtual and physical onsite meetings with the Contractor. A Government Technical Representative will be designated to represent the

Contracting Officer for the purpose of coordinating with the contractor in administering the technical aspects of contract performance. The Contracting Officer may issue written instructions to fill in details in the scope of work set forth in this contract via the Government Technical Representative. The Government Technical Representative is not authorized to make any changes which affect the contract amount, terms, or conditions. The Contracting Officer is the only party authorized to obligate the Government.

7.2 This contract is subject to Government monitoring during any phase of the vehicle(s) development, manufacturing, and final delivery. Only issues identified not in compliance with the SOW; Government approved

Artemis CTV(s) design; GSDO-RQMT-1315, Exploration Ground Systems Program System Requirements

Document for the Crew Transportation Vehicle (CTV); and NHTSA standards will be considered and counted as a defect.

7.3 Performance Evaluation Meetings: The Contractor’s representative shall meet with the Government Technical

Representative and Contracting Officer weekly during the first month after contract award. Meetings shall be conducted in one of the following formats: in-person or collaboration app, such as Microsoft Teams (video-conferencing, teleconferencing, or chat). Thereafter, meetings will be as often as necessary, however, no less than monthly, at the discretion of the Government. A mutual effort will be made during these meetings to resolve all issues identified. The written minutes of these meetings, prepared by the Government Technical Representative, shall be reviewed, and signed by the Contractor. If the Contractor does not concur with the minutes, the Contractor shall state any areas of disagreement to the Government Technical Representative in writing, within three (3) days.

The Government Technical Representative is not authorized to make any changes in cost or price, estimates or changes in delivery dates. The Government Technical Representative is not authorized to change any of the terms and conditions of the resulting order.

7.3.1 The following schedule provides a preliminary meeting plan that is subject to change at the Government’s discretion. All changes shall be coordinated between the Contractor and the Government. Only the Contracting

Officer shall approve changes to the schedule:

Meeting Description Occurrence Schedule

Detailed Artemis CTV(s) rendering and specifications presented. Virtual Concept Design

Presentation via Microsoft Teams.

Once Approximately 30 days after award

Final design approved for fabrication and manufacture Once

Approximately 30 days after contractor presentation

Virtual meetings to discuss progress, technical issues and concerns that require Government input, and any contractual issues and concerns.

Approximately every two (2) weeks TBD by Government

Physical Meeting at Contractor Facility. The contractor shall provide workspace with wireless access for no less than eight (8) NASA personnel to utilize while at the Contractor site during the quarterly visits

Quarterly TBD – 30 days in advance by

Government.

7.4 The Government Technical Representative is: TBD. The Government Technical Representative monitors all technical aspects of the contract and assists in contract administration. The Government Technical Representative is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, specifications; monitor Contractor’s performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. The Government Technical Representative is not authorized to make any changes in cost or price, estimates or changes in delivery dates. The Government Technical

Representative is not authorized to change any of the terms and conditions of the resulting order.

8.0. OTHER REQUIREMENTS

8.1 The contractor shall provide a Project Manager who shall be responsible for the development of the Artemis

CTV(s). The name of this person and an alternate who shall act for the Contractor when the Project Manager is absent shall be designated in writing to the Contracting Officer. The Project Manager or alternate shall have full authority to act for the Contractor on all contract matters relating to this contract. The Project Manager or alternate shall be available between 8:00 a.m. to 4:30 p.m. EST., Monday thru Friday except Federal holidays or when the government facility is closed for administrative reasons.

8.2 Media Usage. NASA Public Affairs may work with the contractor to document and share with the public the

Contractor’s effort to develop, fabricate, manufacture, and deliver the Artemis CTV(s) to NASA KSC. The media usage process shall be enacted post contract award by the Contractor. For additional details, please see NASA Media

Usage Guidelines at https://www.nasa.gov/multimedia/guidelines/index.html https://www.nasa.gov/multimedia/guidelines/index.html