This is a solicitation for a construction contract to perform modifications to the Converter Compressor Facility at the John F. Kennedy Space Center in Florida. The work includes general renovation of the existing facility including replacement of the roofing system, ceilings, architectural elements, utilities, and structural modifications. It also involves modifications and upgrades to the liquid helium transfer area and valve yard. A new ground support pneumatics console will be installed along with associated control equipment. Existing equipment containing hazardous materials like asbestos will be abated. The work must be phased to keep the operational facility from significant downtime. The selected contractor will furnish all labor, equipment, materials and documentation to complete the tasks defined in the drawings and specifications by the completion date in the contract.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

CODE

4. CONTRACT NUMBER

7. ISSUED BY

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

February 12, 2020 . If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

1/13/2020

PAGE OF PAGES

80KSC020R0001

TBD

John F. Kennedy Space Center, NASA Procurement Office Code: OP-CS Kennedy Space Center, FL 32899

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

The contractor shall furnish all labor, equipment, materials, supervision and related activities necessary to perform Modifications to the Converter Compressor Facility (CCF) for SLS Block 1B, Phase 1 at Kennedy Space Center, Florida.

This is an unrestricted procurement. All responsible sources may submit an offer.

Offeror MUST enter their CAGE Code and DUNS number in block 14, page 2 of the SF 1442.

Offeror MUST be registered in SAM and VETS-4212.

8. ADDRESS OFFER TO

John F. Kennedy Space Center, NASA Procurement Office Code: OP-CS Bldg M7-0301 (HQ), Rm 5426B, Attn: Anthony Caruvana Kennedy Space Center, FL 32899 Email to KSC-IDIQbids@mail.nasa.gov

5. REQUISITION/PURCHASE REQUEST NUMBER

TBD

OP-CS

Anthony Caruvana 321-867-3464

6. PROJECT NUMBER

98833.1

1 89 local time

2:00:00 PM

* Contract F.1(c)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

OP-CS

John F. Kennedy Space Center, NASA Procurement Office Code: OP-CS Kennedy Space Center, FL 32899

NASA Shared Service Center (NSSC) Financial Management Division (FMD) - Accounts Payable Bldg. 1111, C. Road Stennis Space Center, MS 39529

NASA/KSC SOLICITATION 80KSC020R0001

TABLE OF CONTENTS

SECTION A SOLICITATION/CONTRACT FORM (SF1442)

SECTION B SUPPLIES OR SERVICES AND PRICE/COSTS

SECTION C DESCRIPTION/SPECIFICATIONS/STATEMENT OF

WORK

SECTION D PACKAGING AND MARKING

SECTION E INSPECTION AND ACCEPTANCE

SECTION F DELIVERIES OR PERFORMANCE

SECTION G CONTRACT ADMINISTRATION DATA

SECTION H SPECIAL CONTRACT REQUIREMENTS

SECTION I CONTRACT CLAUSES

SECTION J LIST OF ATTACHMENTS

SECTION K REPRESENTATIONS, CERTIFICATIONS, AND OTHER

STATEMENTS OF OFFERORS OR RESPONDENTS

SECTION L INSTRUCTIONS, CONDITIONS, AND NOTICES TO

OFFERORS OR RESPONDENTS

SECTION M EVALUATION FACTORS FOR AWARD

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 CONSTRUCTION SERVICES AND PRICES

Line Item Description Unit Total

0001 Modifications to Converter Compressor Facility JOB $_____________ for SLS Block 1B, Phase 1

(End of Clause)

B. 2 NFS 1852.216-78 FIRM FIXED PRICE (DEC 1988)

The total firm fixed price of this contract is TBD. (To be completed at award)

B.3 PROJECT DELIVERABLES (JAN 2018)

Contract deliverables (manuals, reports, plans, and other written documentation) to be provided under this contract are identified in Section J, Attachment J-A, Project Deliverables. The costs associated with providing the data in Attachment J-A are included in the firm-fixed price of the awarded contract. Nothing contained in Attachment J-A shall relieve the Contractor from furnishing data called for by, or under the authority of, other provisions of this contract, which are not identified and described in Attachment J-A.

SECTION C – DESCRIPTION/SPECIFICATION/WORK STATEMENT

C. 1 SCOPE OF WORK (JAN 2018)

The Contractor shall furnish all management, supervision, labor, transportation, facilities, materials, tools, equipment, disposal, and documentation (except any property, including utilities, specified in the Schedule to be Government-Furnished) to perform all work for the Task(s) named below, and defined in the contract drawings, maps, specifications, and/or statements of work.

Line Item Task Description

0001 Modifications to Converter Compressor Facility (CCF) for SLS Block 1B, Phase 1.

C. 2 CONTRACT DRAWINGS, MAPS, SPECIFICATIONS, AND/OR STATEMENTS OF

WORK (JAN 2018)

(a) Five sets of full scale contract drawings, maps, specifications, and/or statements of work (excluding applicable publications incorporated into the technical provisions by reference), plus one CD or DVD containing electronic, portable document format (PDF) versions, will be furnished at award to the Contractor without charge. The work shall conform to the following contract drawings, maps, specifications, and/or statements of work, attached to this contract.

Drawing Number 79K40378 Rev A, Titled Upgrades and Modifications to Converter

Compressor Facility (CCF) LHe Systems and Revitilization, Dated 10/30/19, Sheets 1 through 171.

Specification Number 79K40379 Rev A, Titled Upgrades and Modifications to Converter

Compressor Facility, Dated 10/30/19, Pages 1 through 1259.

Report KSC-NE-14767, Titled Helium Control System GUI and PLC Software

Programming Requirements – WP1, Dated 5/15/18, Pages 1 through 21.

SK-001 – Protection of GSPN Console, Dated 11/25/19, Sheet 1.

SK-002 – Exterior Canopy Area Reduction, Dated 11/25/19, Sheet 1.

(b) Addenda to Drawings, Maps, Specifications, and/or Statements of Work:

1. Drawing 79K40378 Sheets AD-101, A-101, and MD-101: The existing GSPN Console Area in Room 1020 must remain operational and be protected for the duration of construction until the new GSPN Console is functionally tested and has had an operational burn-in period. “SK-001 – Protection of GSPN Console” shows the level of protection required for the existing GSPN Console. This area will require a self-supporting temporary wall allowing access to the GSPN Console, Room 1022, and Room 1027. This will also require a temporary ceiling that is self-supporting over the console area. This enclosed space must be conditioned to 70 +/- 4 degrees Fahrenheit and kept between 40% and 60% relative humidity. The temporary space must be at a positive pressure to the adjacent spaces. The temporary HVAC for this enclosed space must be continually provided 24 hours per day, 7 days per week without any significant downtime. The space will require temporary lighting on a circuit that can remain in place until the time at which the temporary wall and ceiling can be removed. Temporary lighting must be equivalent to current lighting for operations. The contractor shall submit a shop drawing (add submittal item Temporary Enclosure of GSPN Console; G under Specification 79K40379 Section 01 50 00) for approval detailing the temporary enclosure, HVAC, and lighting. The temporary enclosure, HVAC, and lighting must be installed, inspected, and approved prior to demolition starting in Room 1020.

2. Drawing 79K40378 Sheet AD-101, AD-121, and A-101: There are existing communications and power cables in conduit, cable tray, and routed exposed above ceiling in Room 1020 and some adjacent spaces that must remain independently supported and in service while the demolition occurs. Not all cables are clearly labeled above ceiling. Many of these cables are critical to the functionality of the GSPN Console that allow monitoring and control of the GHe and GN2 distribution and usage from the CCF. Submit a shop drawing (add submittal item Temporary Support of Cables; G under Specification 79K40379 Section 01 50 00) identifying how cables will be temporary supported, associated existing conditions, and any impacts to demolition or new work.

3. Drawing 79K40378 Sheets C-121, A-102, A-201, and S-002: The area of the canopy required to be provided per these drawing sheets is reduced as shown in “SK-002 – Canopy Area Reduction” to account for the existing LHe pump and vaporizer that must remain operational and in place during the construction performance period.

4. Drawing 79K40378 Sheet C-101: Flag Note E is considered to include disposal of the light pole and concrete base in addition to what is stated.

5. Drawing 79K40378 Sheet C-101: Flag Note G is considered to include disposal of the panel and concrete foundation in addition to what is stated.

6. Drawing 79K40378 Sheet C-121: CGTs and Hydropacs shown will not be in place during construction activities. LHe Tankers will require access to the existing valve yard during construction similar to the location shown on this sheet. As shown on the MP Sheets, existing connections for LHe Tankers are to remain.

7. Drawing 79K40378 Sheet AD-141: For the existing vent stack, handling of lead materials shall comply with Specification 79K40379 Section 02 82 33.13 20.

8. Drawing 79K40378 Sheet FP-102: Add Flag Note J. Flag Note J points to the west exterior wall in Zone E8 of the drawing sheet. Flag Note J states, “INSTALL A DRY SIDEWALL

SPRINKLER RATED FOR EXTERIOR USE THROUGH THE WEST EXTERIOR WALL

OF EQUIPMENT ROOM 1000 ABOVE THE NORTH DOOR TO PROTECT THE NEW

COVERED WALKWAY AT THE BUILDING ENVELOPE.”

9. Drawing 79K40378 Sheet FA-102 and FA-601: Add a Low Temperature Sensor on the west wall of West Equipment Room 1000. Add a Low Temperature Sensor on the east of wall of East Equipment Room 1040. Low Temperature Sensors shall be UL listed for compatibility with the fire alarm control panel, have a configurable temperature setting, and include all components (modules, conduit, wiring, etc.) required for monitoring by the fire alarm control panel. Include Low Temperature Sensors in shop drawings and product data submittals required by Specification 79K40379 Section 28 31 00.00 98. The Low Temperature Sensors shall report a supervisory signal at the fire alarm control panel and have their own zone on the radio transmitter for reporting to the Central Radio Monitoring System.

10. Specification 79K40379 Section 28 31 00.00 98 Subpart 2.2.1: Add Duct Smoke Detector for Zone 5. Add Low Temperature Sensors for Zone 6.

(c) "Or Equal" Items”

Throughout the technical specifications and drawings of this contract, where certain manufacturers’ trade names and model numbers are specified and followed by the term "or equal," the manufacturer's name and data as specified shall represent the minimum standard type, quality, and capacity acceptable for incorporation into the work covered by this contract.

The products of other manufacturers will be considered as being acceptable, provided that such products fully meet or exceed all minimum structural or use and operational features of the particular manufacturers’ items as specified, and provided that the other manufacturers’ items are easily interchangeable and can be adequately incorporated within the allocated space in the building or structure. In all cases, the acceptability of "or equal" items shall be at the Contracting Officer's discretion, based upon data submitted by the Contractor in accordance with the requirements under the Shop Drawings Clause.

(d) Omissions from the drawings or specifications, or the omission or misdescription of details of work which are manifestly necessary to carry out the intent of the drawings and specifications, or which are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work but they shall be performed as if fully and correctly set forth and described in the drawings and specifications.

(e) The Contractor shall check all drawings furnished him immediately upon their receipt and shall promptly notify the Contracting Officer of any discrepancies. Figures marked on drawings shall in general be followed in preference to scale measurements. Large scale drawings shall in general govern small scale drawings. The Contractor shall compare all drawings and verify the figures before laying out the work and will be responsible for any errors which might have been avoided thereby.

C. 3 REQUEST FOR INFORMATION/CLARIFICATION (RFIC) (JAN 2018)

The Contractor shall promptly report to the Contracting Officer all problems or conflicting technical information encountered during the contract performance so that the Government may provide solutions or appropriate direction. Such problems shall be reported on KSC Form No. 8- 268, "Request for Information/Clarification," to be provided by the Government. A copy of each RFIC will be provided to the Contracting Officer’s Representative (COR) concurrently with the transmittal to the Contracting Officer. The Contractor shall log and control each Request for Information/Clarification (RFI/C), including those generated by subcontractors.

C. 4 DEVIATIONS AND WAIVERS (JAN 2018)

(a) When the Contractor proposes to perform work which does not conform to the requirements of the applicable contract drawings and specifications, the Contractor shall submit to the Contracting Officer for approval, a written request for deviation or request for waiver on the nonconforming work.

(b) All requests by the Contractor shall be submitted on KSC Form 50-314 (Contractor Request

For Deviation/Waiver) including an offer of consideration to the Government. The request must be technically supported by justification, rationale, design considerations, calculations and other data which permits ready and conclusive evaluation by the Government as to acceptability or nonacceptability.

(c) Where a requested deviation or waiver on a particular aspect of the work has a relation to, or affects, other aspects of the work, those other aspects of the work shall be clearly identified and referenced. And, if the requested deviation or waiver necessitates a deviation or waiver on other aspects, requests for all such deviations and waivers must be submitted concurrently.

(d) Any request not submitted in strict accordance with this provision will not be considered.

SECTION D – PACKAGING AND MARKING

NOT APPLICABLE TO THIS SOLICITATION/CONTRACT

SECTION E - INSPECTION AND ACCEPTANCE

E.1 FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

INCORPORATED BY REFERENCE

FAR 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)

E. 2 BASIC INSPECTION SYSTEM (JAN 2018)

Pursuant to FAR Clause 52.246-12, Inspection of Construction, or FAR Clause 246-13, Inspection

– Dismantling, Demolition, or Removal of Improvements:

The Contractor shall maintain and implement a basic inspection system as identified below:

(a) Definitions:

"Inspection" means examining and testing supplies or services (including, when appropriate, raw materials, components, and intermediate assemblies) to determine whether they conform to contract requirements.

"Testing" means that element of inspection that determines the properties or elements, including functional operation of supplies or their components, by the application of established scientific principles and procedures.

"Independent Testing Laboratory" means an independent organization, accepted by the Contracting Officer, engaged to perform specific inspections or tests of the work, either at the site or elsewhere, and report the results of these inspections or tests.

(b) The inspection system shall be documented to ensure and provide objective evidence of quality control in the form of records of inspections and test results. The system shall also ensure that nonconforming articles or materials are discovered, documented, and controlled through effective remedial and preventive actions.

The Contractor may use, at his option, in whole or in part, his existing higher level inspection system or quality assurance program provided such system is revised and identified to the requirements below.

(c) The Contractor shall provide a narrative description of an inspection system which provides for compliance with the quality requirements and technical criteria of the contract.

(1) The description shall be submitted for review by the Contracting Officer not later than 7 days after contract award.

(2) The description shall address each of the Basic Inspection System Requirements identified in paragraph (d) below. This submittal shall address both the general inspection system that will be used during the performance of all work under the contract, including but not limited to those items identified under paragraphs d(1), d(2)(iv), d(2)(v), and d(2)(vi) below.

(d) Basic Inspection System Requirements: The Contractor shall describe how each of the following requirements is to be satisfied and what records will be maintained, both on-site and offsite.

(1) The Contractor shall identify the individual responsible for on-site contact and communication relative to implementation and operation of the inspection system. The name of this individual shall be provided, in writing, to the Contracting Officer’s Representative (COR).

(2) Standard requirements:

(i) A purchasing control system which ensures that all purchasing documents, including those of subcontractors and suppliers, are traceable to the drawings, specifications, and approved submittal requirements.

(ii) A receiving inspection system with documented evidence of Contractor inspection traceable to the procurement documents.

(iii) A system of controls and records for handling, recording, identification and disposition of nonconforming articles and materials.

(iv) A system of identification of inspections required by each specific section of the specifications and drawings and what records will be maintained.

(v) Identification of tests to be performed, including test procedures, test records, and the independent testing organization(s) be utilized.

(vi) Additional requirements (if included in the drawings, specifications, or contract provisions):

(A) Certification or recertification of personnel and qualification of procedures.

(B) Management and accountability of Government furnished equipment, components, or materials.

(C) Calibration of inspection test gages, tools, measuring instruments, and independent laboratories to be utilized.

E. 3 SYSTEMS ACCEPTANCE AND TESTING (JAN 2018)

Pursuant to FAR 52.246-12, Inspection of Construction:

Systems tests shall be performed as described below:

(a) SYSTEMS

Systems tests shall be performed on fire protection, fire suppression, HVAC, compressed air and all other assemblies of components which must be tested as an inter-related whole to verify proper functioning.

(b) SYSTEM TEST PROCEDURES

A test procedure and a recording form which documents every step of the system test shall be submitted for approval under the terms of the "Shop Drawings" clause of this contract.

Test procedures must be approved prior to requesting a date for testing. Each step in the test procedure shall be witnessed by the Contracting Officer's Representative who shall then date and sign the approved recording form for each step witnessed.

The procedure shall consist of step by step instructions for testing all specified system parameters, system components, and proper overall functioning of the system.

(c) SYSTEM TESTING AND ACCEPTANCE

The following tests shall be performed by the Contractor in strict accordance to the approved test procedure described above.

(1) Functional Test -- This shall be an "in house" test to verify proper installation and functioning of the system and its components. This functional test shall be performed in the presence of Government inspectors and shall be repeated until the Contractor can perform one full test without device or system malfunction.

(2) System Acceptance Test -- After successful completion of the functional testing the system shall be tested formally with full documentation using the previously approved recording form. The Contractor shall notify the Contracting Officer, in writing, forty eight (48) hours prior to system acceptance testing. The appointed Contracting Officer Representative will witness, date and stamp each test in the procedure. Acceptance of the system will be based upon the written approval of the Contracting Officer’s Representative.

Note: For work involving fire detection and suppression systems, additional testing & acceptance requirements are described in project technical specifications

The contractor shall use the following form for transfer of fire alarm / fire suppression systems from the government to the contractor:

KSC - TRANSFER OF RESPONSIBILITY

FROM:

BOSS FIRE PROTECTIVE SYSTEMS – KSC, K6-1446A / KSC-326 Ph. 321-861-4681 / 4683

TO: __________________COMPANY: ____________________ EFFECTIVE DATE: ________________

ADDRESS ___________________________________________ PHONE # __________________________

EMERGENCY CONTACT: ____________________________ PHONE # __________________________

SYSTEM: __________________________________________________________________________________

WON #: ____________________________________________________________________________________

SYSTEM STATUS: OPERATIONAL * PARTIALLY FUNCTIONAL * OUT OF SERVICE

(* Indicate Below)

TRANSFER OF: ENTIRE SYSTEM *PARTIAL (Explain Below)

REASON FOR TRANSFER:

CONDITIONS OF TRANSFER: The assignee agrees to the responsibility of the following:

Coordination of work on the transferred system described above with the COR. Assignee is responsible for documenting existing system condition prior to transfer. Assignee also agrees to implement safety plans and alternate workaround procedures that facilitate reporting of emergency/fire/security situations, when applicable. The assignee will assure that any and all modifications, installations and changes to the system are in compliance with the contract documents. The assignee assumes responsibility for returning the system/equipment in an operationally ready state and agrees to demonstrate through functional test, that the system has been installed in accordance with contract specifications and drawings.

Name: _______________________ Signature: _______________________ Dated: _______________________ [Assignee]

Name: _______________________ Signature: _______________________ Dated: _______________________ [BOSS Fire Protective Systems Representative]

Name: _______________________ Signature: _______________________ Dated: _______________________

[COR]

NOTE: A COPY OF THIS TRANSFER SHALL BE POSTED IN OR ATTACHED TO THE

SYSTEM/EQUIPMENT BEING TRANSFERRED.

The contractor shall use the following form to communicate readiness for Preliminary Fire Alarm Testing:

CONTRACTOR READINESS AFFIRMATION – For “Preliminary” Fire Alarm Testing NASA Contract Number: _______________________________

Instructions: The Prime Contractor is responsible to ensure the fire alarm system is “ready” for formal preliminary testing. Circle the proper response and write the date completed. Any ‘No’ response would typically prevent submission of the form.

CONTRACT #: ______________ LOCATION/FACILITY:__________________FACILITY #____________

(circle) Date

Yes No N/A ______ Conduit & wiring is complete. Includes continuity/insulation resistance tests & wiring labeling.

Yes No N/A ______ All fire alarm devices are installed.

Yes No N/A ______ Auxiliary functions are connected and known to be operational. Example: AHU shutdown

Yes No N/A ______ Fire alarm panel program, specific to this job, is loaded and operational.

Yes No N/A ______ All troubles, ground faults, etc. have been removed; system is effectively

NORMAL.

Yes No N/A ______ Fire alarm vendor/subcontractor conducted a “contractor checkout” of the fire alarm system, with completion on this date: ___________________ which included testing of a sample of inputs and outputs. Example: rang bells to verify operation in temporal-three pattern, tested 5% of all devices, verified AHU shutdown, verified FACP switched to battery upon loss of 120VAC, etc.

Yes No N/A ______ NFPA 72 Record of Completion form is started for the installation.

Yes No N/A ______ System drawings are available for addition of “red-lines”

Yes No N/A ______ Support needed for successful completion of the Preliminary Test has been identified in writing to the Contracting Officer. Examples: support to test existing fire suppressions systems, elevator crew support, HVAC crew support, security system crew support to verify mag-locks are de-energized, etc.

The undersigned attests that the subject fire alarm system is ready for PRELIMINARY TEST;

Name: __________________________________ Signature:__________________________________________ [Prime Contractor Representative]

Form Completion Date: __________________ Proposed Preliminary Test Date(s):_____________________

Transmit this form per submittal schedule in the contract.

Nothing in this clause shall relieve the contractor from the requirements of FAR 52.246-12, "Inspection of Construction."

E. 4 QUALITY REQUIREMENTS (NOV 2019)

(a) Construction Quality Control - General

The Contractor shall maintain an effective Quality Program that encompasses all actions involving selection of construction materials and sources, suppliers, subcontractor, on-site and off-site fabrication of Contractor-furnished items to be included in the work; on-site and off-site assembly, erection, work-placement procedures, workmanship, inspection, and testing.

The Contractor' program shall provide for a functional system of records to provide objective evidence that the quality provisions of the contract schedule, specifications, and drawings have been satisfactorily performed and recorded.

(b) Management and Organization

The Contractor shall ensure that effectiveness of the quality functions and the ability of assigned personnel to provide the necessary supervision, inspection, and test of all items of work, including that of his suppliers and subcontractors.

The program shall encompass all management and supervisory actions that affect quality of the finished construction work.

(1) The Contractor shall designate a qualified individual within his on-site organization whose sole responsibility shall be the day-to-day on-site management and direction of the Quality Program. Qualification credentials of the designated individual shall be provided to the Contracting Officer for review and concurrence. The individual may be assigned to more than one contract provided that the assigned contracts are all located at the Kennedy Space Center. The individual designated to direct the program shall report to the Contractor's management and shall have the necessary authority to discharge his responsibilities.

(2) The Contractor shall submit a monthly performance report that summarizes all quality operations. This summary report shall identify inspections made, tests performed, nonconformances, corrective action taken, status of plans/procedures being developed, and status of open items/problems in work.

(c) Quality and Assurance Plan

(1) Within 30 calendar days after Notice to Proceed, the Contractor shall submit five copies of his Quality Program Plan for the contract to the Contracting Officer for review and approval. Such approval will not relieve the Contractor of his responsibility for compliance with the contract requirements.

(2) The plan shall describe how the Contractor intends to ensure compliance with the quality requirements of the specifications and shall address each of the following as a minimum:

(i) Authority and responsibilities of quality control personnel along with a copy of the letter of delegation to the Contractor's representative and his staff for quality control that defines their delegated duties and responsibilities.

(ii) That part of the Contractor's organization that is concerned with the construction contract activities.

(iii) The Contractor's on-site organization, including his quality organization.

(iv) The Contractor's operational plan for accomplishing and reviewing work supervision, inspection, tests, construction material work controls, fabrication controls, certifications, and documentation of quality control operations, inspections, and tests records, including those for subcontractors. These provisions shall include the methods to be effected during the procurement cycle (order to deliver) for those items of materials or equipment which require source inspection, shop fabrication, and like operations away from the work site.

(v) The registered land surveyor or key individuals designated to accomplish the layout of the work.

(vi) Define the on-site/off-site coordinating procedures and authorities for the quality functions accomplished by personnel not located at the site or not directly under the control of the project manager.

(vii) Training

(viii) Certification(s) of personnel as required by the specifications.

(ix) Recertification of personnel.

(x) Certification of processes or equipment as required by the Specification.

(xi) Qualification of procedures.

(xii) Non-destructive testing requirements identified in the specification.

(xiii) Identification of independent certifying and testing laboratories to be used.

(xiv) The plan shall contain an appendix with a reproduction of each form, report format, or other similar records to be used in the program.

The Contractor may use, at his option, in whole or in part, his existing Quality Assurance Plan and procedures provided they are revised/updated and identified to these requirements, and submitted to the Contracting Officer for review as to acceptability.

The Contractor shall develop and maintain detailed quality control procedures to be scheduled as required to implement the Quality Program Plan and the requirements of the specifications and drawings.

(d) Identification and Data Retrieval

The Contractor shall develop and maintain an identification and data retrieval system to provide traceability of materials, equipment, inspections and tests to the requirements of the specifications, drawings, and contract provisions. All records, drawings, submittals, and equipment (as required) shall be identified and related as appropriate, to reference the following minimum controls:

(1) Contract Number

(2) Contract Specification Number

(3) Contract Drawing Number

(4) Submittal Document (SD) Numbers

(5) Contract Change Number

(6) Contractor's Drawing Number System

(e) Control of Procurements

The Contractor shall be responsible for adequate and effective control over his procurement sources and those of his subcontractors, to ensure that materials, supplies, and services purchased, including all subcontracts, meet all quality requirements.

(1) The Contractor shall ensure that his purchase documents include:

(i) The basic quality requirements, standards, drawings, and specifications called out in the contract specifications.

(ii) Inspection and test characteristics.

(iii) Inspection and test records.

(iv) O&M manuals, instructions, certification of compliance, and such other data as may be required by the specification.

(v) Preservation, packaging, shipping direction.

(2) When Government source inspection is required on a Contractor's purchase document, the document shall include the following statement:

"All work on this order is subject to inspection and test by the Government at any time and place. The Government Representative who has been delegated NASA Quality Assurance functions on this procurement shall be notified immediately upon receipt of this order. The Government Representative shall also be notified forty eight (48) hours in advance of the time articles or processes are ready for inspection or test."

(3) Procurements which do not require Government source inspections shall include the following statement:

"The Government reserves the right to inspect any or all of the materials included on this order at the Contractor's plant."

(4) The need for Government source inspection will be determined by the Contracting

Officer. Source inspection determined by the Contracting Officer. Source inspection performed by the Government on procured articles or materials shall not replace Contractor inspection or relieve the Contractor of his responsibility for ensuring the quality of procured articles and materials and the records necessary to verify all required quality control activities.

(f) Receiving Inspection Systems

The Contractor shall maintain a Receiving Inspection System which ensures that all procured materials and equipment are inspected and tested as prescribed by the applicable specifications and drawings, and the approved submittal documents (SD's).

A Receiving Inspection Record will accompany each materials/equipment delivery to the construction site. Records of all receiving inspections/tests and nonconformance records shall be maintained at the construction site by the Contractor.

These records shall include documentation of any defects, discrepancies, disposition and/or waivers, including evidence of Government source inspection when required.

(g) Nonconforming Articles And Material Control

The Contractor shall ensure control and recording of nonconformances discovered by the Contractor, subcontractors, suppliers or designated Government quality representatives to prevent their use and to correct deficient operations and procedures.

(1) The Contractor shall prepare a "nonconformance" report for each nonconformance comprising as a minimum:

(i) A unique and traceable number.

(ii) The nomenclature and identification of the nonconforming article or material.

(iii) A description of the nonconformance and the required characteristics(s) or specifications requirement.

(iv) Cause or reason for the nonconformance.

(v) Remedial actions taken or recommended.

(vi) Disposition of the nonconforming article or material.

(2) The Contractor shall identify and tag the nonconforming article and segregate/remove it from the work area.

(3) The Contractor shall establish a system for monitoring and correcting deficient procedures and operations.

(h) Responsibility for Inspection

The Contractor is responsible for the performance, on a one hundred percent (100%) basis of all inspections and tests and record requirements specified in the contract. Unless otherwise specified in the contract, the Contractor may utilize independent inspection and testing laboratories or services that are acceptable to the Government.

(i) Fabrication, Process, and Work Control

(1) The Contractor's procedures and operations controls shall be derived from the Quality requirements and work execution standards required by each section of the contract specification and drawings.

(2) The Contractor shall establish those in-process inspection points and controls over the work as necessary to ensure compliance with quality requirements and work standards which are not readily detectable, sealed, or measurable by inspection and test of a finished article or work element. When approval or certification of special processes, operating personnel, special equipment or procedures, is required by the specifications, the Contractor shall obtain necessary approvals or certification prior to starting the work/process.

(3) These special processes may include but are not limited to plating, anodizing, nondestructive testing, welding, soldering, etc. Records of in-process inspections and control away from the job site may be used as evidence of quality of materials/work and may reduce, but not eliminate further inspection or testing when delivery is made to the job site or during final testing and acceptance.

(j) Quality Control Records

(1) All quality control records shall be maintained in a central on-site location by the

Contractor. These records shall include all quality control data; factory tests or manufacturer's certification, quality control coordinating actions; records of quality control training/certifications as well as routine hydrostatic, electrical continuity, grounding, welding, and line cleaning, and similar tests. The quality records shall be available for examination by the Contracting Officer and the Contractor shall provide copies of tests and data to the Contracting Officer's on-site representative(s).

(2) The requirements to maintain quality control records, as described above, shall not be construed to relieve the Contractor of submitting samples, test data, shop drawings, material certificates, or other information required by the submittal documents (SD's) called out in the specification.

(3) The Contractor shall assure that each record of inspection, test, nonconformance and corrective action is identified and traceable to the specific requirement of the specifications and drawings.

(k) Inspection and Test Records

The Contractor shall maintain current records on site of each inspection and test performed, on appropriate form(s) throughout the life of the contract. These records shall include but not be limited to, factual evidence that the required inspections or tests have been performed, including type and number of inspections or tests involved, identification of operators and inspectors, result of inspections or tests, nature of defects, causes for rejection, proposed remedial action, and corrective actions taken.

All inspection records, test procedures, test results, and associated forms shall contain a place/space to indicate verification or witness by Government Inspectors or Representatives.

Legible copies of these records shall be furnished to the Contracting Officer and his on-site representative. The records shall cover all work placements, traceable to the contract schedule, specifications, and drawings, and shall be verified by the Prime Contractor's designated Quality Program on-site representative.

(l) Drawing and Change Control

A drawing-control system shall be maintained to provide for timely drawing and change distribution to all work locations and subcontractors and prompt removal of obsolete drawings from work areas. The system shall provide for timely initiation of drawings change requests.

Changes which involve interface with other work areas or that affect articles or materials controlled by others shall be numbered, logged, and controlled by the Prime Contractor. This system shall be effectively integrated with other document control requirements of the contract. Drawing-change affectivity shall be clearly specified. Accomplished changes shall be appropriately and clearly marked or identified, and associated drawings shall be revised accordingly. Only shop drawings that have been approved or approved as noted by the Contracting Officer shall be used for fabrication and inspection.

(m) Inspection, Measuring and Test Equipment - Calibration

(1) The Contractor shall provide and maintain currently calibrated gages and other measuring and testing devices necessary to assure that the work conforms to contract requirements.

These devices shall be calibrated against certified measurement standards which are traceable to national standards, as required by individual sections of the specification.

(2) Calibration records shall be maintained for each item of test/measuring equipment. Any equipment exceeding its required due date or tolerance shall be isolated, tagged, or otherwise marked to prevent its use.

(3) The Contractor may utilize his own certified test facilities or those of an independent testing laboratory acceptable to the Contracting Officer.

(n) Government Property Control

The Contractor shall establish property controls, inspections, and records as required by the provisions of the Contract Schedule.

(o) Handling, Storage, Preservation, and Shipping

(1) The Contractor shall establish a control system and appropriate procedures consistent with the requirements of each section of the Specifications.

(2) The Contractor shall include a complete documentation package with his shipment. The data package shall consist of any documentation required by the Contract Schedule and the Specifications required to identify, store, preserve, operate and maintain the equipment or assemblies shipped.

(p) Quality Program Audits

(1) The Contractor's program is subject to continuous evaluation, review and verification by the Contracting Officer or by his designated representatives. The Contractor will be notified in writing of any acceptance areas and will be given an appropriate period of time to correct identified deficiencies.

(2) The Contractor shall establish his own system of scheduled or random audits of his program to assure the objectives are met.

E. 5 CONCRETE PLACEMENT INSPECTION AND PLAN (JAN 2018)

(a) All forms, reinforcement and embedded items shall be placed and ready for inspection 24 hours to 48 hours prior to any concrete placement. After Government inspection of forms and embedded items and at least 24 hours before concrete placement the Contractor shall meet with the Contracting Officer's Representative and provide a written plan for concrete placement including the following information:

(1) Volume of concrete to be placed and calculations used in determining volume.

(2) Verification from concrete supplier of volume of concrete to be delivered and delivery date.

(3) Labor breakdown for crew to be used on concrete placement and finishing.

(4) Equipment to be used during placement and finishing.

(b) The Contractor's plan for concrete placement must be approved by the Contracting Officer's Representative prior to placement of concrete. The Government reserves the right to waive the above requirement for placement of less than 3 cubic yards. The Contractor shall place no concrete without an approved concrete placement plan or a written waiver from the Contracting Officer.

E. 6 FINAL INSPECTION AND ACCEPTANCE (JAN 2018)

Final inspection and acceptance of all work under this contract will be conducted by the Contracting Officer’s Representative (COR). Upon satisfactory completion of the contract, the Contractor shall be paid the fixed-price value of the contract, less the amount of any progress payments made under FAR Clause 52.232.5, Payments Under Fixed-Price Construction Contracts, or FAR Clause 52.237-4, Payment by Government to Contractor.

NOTE: The contractor shall include a line item in the schedule of values and progress schedule for completion of punch-list items, site clean-up, demobilization and final construction (as-built) drawings. The amount of this line item shall be equal to 5% of the contract value. The Government will not pay final invoices for this amount until all punch-list, site clean-up, and demobilization activities are complete; final construction drawings are delivered; and final acceptance is made on DD Form 250, Material Inspection and Receiving Report.

SECTION F – DELIVERIES OR PERFORMANCE

F. 1 FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF

WORK (APR 1984)

Fill-Ins:

(a) The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the Contractor receives the notice to proceed.

(c) … (c) complete the entire work ready for use not later than 532 calendar days after the date the contractor receives the notice to proceed.

FAR 52.242-14 SUSPENSION OF WORK (APR 1984)

F. 2 WORK PERIOD (DEC 2019)

Contractor's work day will be limited to first shift, 7:00 A.M. to 3:30 P.M., on Monday through Friday except for high noise activities in Open Office Room 1020 (see Attachment J-B, paragraph J-B-70). Any other work period will require special written approval from the Contracting Officer seven (7) days in advance of proposed change in work periods.

F. 3 PLACE OF PERFORMANCE (JAN 2018)

This is a firm-fixed price construction contract for Modifications to Converter Compressor

Facility for SLS Block 1B, Phase 1 at the Converter Compressor Facility (CCF), Building K7- 0468 on Kennedy Space Center, FL 32899.

F. 4 DOWNTIME AND EXCAVATION HOLDS (JAN 2018)

For the purposes of this contract, the Contractor shall assume a maximum of 75 days during which all construction activities will be prohibited. In addition the Contractor shall assume a maximum of 40 days during which all excavation and other subsurface activities will be prohibited but other construction activities will be allowed.

SECTION G – CONTRACT ADMINISTRATION DATA

G. 1 NASA FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 18) CLAUSES

NFS 1852.223-71 AUTHORIZATION FOR RADIO FREQUENCY USE

(APR 2015)

G.2 NFS 1852.232-80 SUBMISSION OF VOUCHERS/INVOICES FOR PAYMENT

(APR 2018)

(a) The designated payment office is the NASA Shared Services Center (NSSC) located at FMD Accounts Payable, Bldg. 1111, Jerry Hlass Road, Stennis Space Center, MS 39529.

(b) Except for classified vouchers, the Contractor shall submit all vouchers and invoices using the steps described at NSSC’s Vendor Payment information web site at:

https://www.nssc.nasa.gov/vendorpayment. Please contact the NSSC Customer Contact Center at 1-877-NSSC123 (1-877-677-2123) with any additional questions or comments.

(c) Payment requests.

(1) The payment periods are stipulated in the payment clause(s) contained in this contract.

(2) Vouchers submitted under cost-type contracts and invoices submitted under fixed-price contracts shall include the items delineated in FAR 32.905(b) supported by relevant back-up documentation. Back-up documentation shall include at a minimum, the following information:

(i) Vouchers.

(A) Breakdown of billed labor costs and associated contractor generated supporting documentation for billed direct labor costs to include rates used and number of hours incurred.

(B) Breakdown of billed other direct costs (ODCs) and associated contractor generated supporting documentation for billed ODCs.

(C) Indirect rate(s) used to calculate the amount of billed indirect expenses.

(D) Progress reports, as required.

(ii) Invoices.

(A) Description of goods and services delivered as part of the contract’s terms and conditions, including the dates of delivery/performance.

(B) Progress reports, as required.

(C) Date goods and services were performed.

(iii) Fee vouchers.

(A) Listing of all provisionally-billed fee by period or date earned since contract award.

(B) A reconciliation of all billed and earned fee.

(C) A clear explanation of the fee calculations.

(d) Non-electronic payment requests. The Contractor may submit a non-electronic voucher/invoice using the steps for non-electronic payment requests described at https://www.nssc.nasa.gov/vendorpayment, when any of the following conditions are met:

(1) The Contracting Officer administering the contract for payment has determined, in writing, that electronic submission would be unduly burdensome to the Contractor.

(2) The contract includes provisions allowing the contractor to submit vouchers or invoices using the steps for non-electronic payment requests. In such instances the Contractor agrees to submit non-electronic payment requests using the method or methods specified in Section G of the contract.

(e) Improper vouchers/invoices. The NSSC Payment Office will notify the contractor of any apparent error, defect, or impropriety in a voucher/invoices within seven calendar days of receipt by the NSSC Payment Office.