Attach_J-B,_KSC_Project_Specific_Reqs.pdf
PDF 68 KB Posted
- Attached to
- Replace Air Handling Units, Space Station Processing Facility (SSPF), Bid Package #5 (AHUs 21 & 23) Federal contract opportunity
- Solicitation number
- 80KSC018R0001
About this file
Attach J-B, KSC Project Specific Reqs
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 80KSC018R0001_-_Source_Select_State.pdf | ||
| 80KSC018R0001_Amend_003.pdf | ||
| 80KSC018R0001_Amend_002.pdf | ||
| Site_Visit_Log.pdf | ||
| Attach_J-G,_PIV_KDP-KSC-P-3722.pdf | ||
| Attach_J-A,_Project_Deliverables.pdf | ||
| Sect_L_App_3_-_Pre-Proposal_Inquiry_Form.xlsx | XLSX spreadsheet | |
| Sect_L_App_4_-_Past_Perf_Quest.docx | DOCX document | |
| Attach_J-D,_Cert_of_Prog_Pay.doc | DOC document | |
| Attach_J-C,_DBW_13Oct17.pdf | ||
| 80KSC018R0001_(Rpl_AHU_SSPF)_Solicitation.pdf | ||
| Sect_L_App_2_-_Acceptable_Identity_Guide.pdf | ||
| Sect_L_App_1_-_KSC_Form_28-889_Visitor_Badge_Request.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NASA/KSC SOLICITATION 80KSC018R0001
ATTACHMENT J-B – KSC PROJECT SPECIFIC REQUIREMENTS
KENNEDY SPACE CENTER PROJECT SPECIFIC REQUIREMENTS APPLICABLE TO ALL
WORK PERFORMED UNDER THIS CONTRACT
The Kennedy Space Center project specific requirements supporting Contract Section I are identified in this Attachment J-B. Nothing contained in this Attachment J-B shall relieve the Contractor from complying with other requirements of this contract, which are not identified and described in this Attachment J-B. All costs associated with the requirements of this Attachment J-B are included in the firm-fixed price of this contract.
J-B-1 UTILITY OUTAGE, ENERGIZED ELECTRICAL WORK, ELECTRICAL
HAZARD ANALYSIS, AND EXCAVATION PERMITS (JAN 2017)
(a) Utility Outage Requests and Electrical Work Permits
(1) Utility Outage Requests: All outages required during the prosecution of work which affects utility systems, such as electrical, water, fire detection and protection systems and air handling systems will require permits. Work shall be scheduled to hold outages to a minimum. Request for utility outage permits shall be made in writing to the Contracting Officer at least fourteen (14) working days in advance of the time required. The request shall state the system involved, area involved, approximate time of outage, and the nature of the work involved. The fact that the Contractor requests an outage for a specific time period does not necessarily mean that the outage will take place. Due to the nature of the operations at Kennedy Space Center, the Contractor probably will not know until the day before the requested date if the outage will take place as scheduled. All outages will take place outside regular working hours. The Contractor will not be entitled to additional payment for working irregular hours due to outages.
(2) Electrical Work Permits: Prior to beginning work on an electrical system under an approved outage, the Contractor shall obtain an executed Work Permit (form number KSC- 26-400NS) from the Institutional Services Contractor, and then execute complex lockout/tag-out procedures for all Work Permit related work as follows:
(i) The Contractor’s employee in charge of the required lockout/tag-out shall be present at the time the Government switches high-, medium-, or low-voltage circuits under Government access control which are to be locked and tagged out by the Contractor.
The Contractor shall coordinate with the Contracting Officer’s Representative (COR) for the required switching period time and date. Due to KSC operational considerations the switching period time and date may be at any time, and outside of normal working hours or work days.
(ii) Once Government switching is complete the Contractor’s employee in charge of the lockout/tag-out shall sign the Work Permit and immediately install the required OSHA compliant lockout / tag-out on the required switching device(s). Once installed the Contractor’s employee in charge of the lockout/tag-out shall individually note the locations of the locks and tags on the Work Permit form.
(iii) A lockout/tag-out lock box shall be used for all such lockout / tag-outs. The key(s) from the lock(s) installed by the Contractor’s employee in charge of the lockout/tag-out shall be placed in the box and the employee in charge shall place an additional personal lock on the lock box to secure the keys inside. Lock box shall be kept at the work site and all other Contractor employees shall attach their personal lockout/tag-out on this box at any time they are working on the applicable equipment.
(iv) At the start of the first standard work period following the lockout/tag-out of a Government switched circuit for which a Work Permit is issued, the Contractor’s employee in charge of the lockout/tag-out shall complete the required lockout/tag-out (lock box) procedures. Immediately upon completing the lockout/tag-out the Contractor shall verify no voltage is present on all circuit conductors using suitable testing equipment, safe work practices, and all required personal protective equipment. All other circuit safeguards such as grounding shall occur immediately after the voltage test and each safeguard shall be individually recorded on the Work Permit.
(b) Energized Electrical Work and Hazard Analysis
(1) Live parts to which an employee might be exposed shall be put into an electrically safe work condition before an employee works on or near them, unless the employer can demonstrate that de-energizing introduces additional or increased hazards or is infeasible due to equipment design or operational limitations. If live parts are not placed in an electrically safe work condition (i.e., due to increased or additional hazards or infeasibility), work to be performed shall be considered energized electrical work. Safety plans, job hazard analysis, and work practices for work on or in proximity to energized parts shall be in accordance with KNPR 8715.7, KSC Construction Contractor Safety and Health Practices Procedural Requirements.
(2) Electrical Hazard Analysis:
Arc-flash and shock prevention personal protective equipment (PPE) is required for all energized electrical, work and where energized or exposed live parts may not be present, but a potential hazard exists including: manhole or cable vault/tray insulated cable inspections, circuit breaker or switch operation, and de-energized voltage checks to electrically safe equipment.
The Contractor shall provide a qualified electrical safety professional to perform an arc-flash and shock hazard analysis in accordance with NFPA 70E for all such electrical work.
The analysis shall be submitted with the Contractor’s Site Specific Safety Plan (SSSP) and referenced in any applicable Job Hazard Analysis (JHA). The safety professional shall perform and review a power system analysis using computer software specifically designed for the purpose to determine short circuit levels and arc flash hazard incident energy at all locations to be worked on by the Contractor. Table 130.7(C) (9) in NFPA 70E may be used in lieu of calculations when all applicable general notes for the table apply.
The Government will provide source short circuit levels and clearing times for Government operated electrical source equipment as well as any applicable design information. The analysis shall include a table summarizing the results of the analysis with the following information for each location or piece of equipment:
(i) Protective Device Name
(ii) Protective Device Clearing Time
(iii) Maximum Voltage
(iv) Calculated Bolted Three Phase Fault Level
(v) Calculated Bolted Ground Fault Level
(vi) Calculated Minimum Arcing Fault Level
(vii)Arc-Distance if applicable for the calculation
(viii) Employee Working Distance
(ix) Calculated Arc-Flash Boundary
(x) Calculated Maximum Arc-Flash Incident Energy
(xi) Arc-Flash PPE Category
(xii) Shock Prevention PPE Insulating Class
(xiii) Limited Approach Boundary
(xiv) Restricted Approach Boundary
(xv) Prohibited Approach Boundary
(3) Electrical Manhole / Vault Confined Space Requirements: Reference KNPR 8715.7, KSC Construction Contractor Safety and Health Practices Procedural Requirements. During the site specific safety plan submittal phase, the Contractor shall complete a hazard evaluation of confined space(s) ensuring all hazards associated with the space or that may be introduced to the space have been identified and mitigated. The Contractor's designated safety professional shall coordinate with the Contracting Officer’s Representative (COR) to complete a confined space hazard assessment (KSC Form 28-750NS) in accordance with KNPR 1840.19 for each confined space, and to schedule a job-site inspection meeting with KSC Environmental Health and Safety personnel. Within 35 calendar days after this meeting the COR will provide a confined space hazard assessment to the Contractor. This assessment must be complete prior to any manhole entry and will be used in generating the confined space entry permit(s) required for the project.
The contractor shall provide supplementary lighting for all manhole work.
(c) Excavation Permits:
The Contractor shall request and obtain excavation permit(s) prior to performing any excavation.
KSC Form 26-312V3 NS, Utility Locate/Excavation Permit Request, shall be prepared by the Contractor and submitted to the Government for approval at least 15 working days prior to the planned excavation date. The Contractor shall comply with the requirements of the Institutional Base Support Contractor’s "Utility Locate / Excavation Permit Procedure” ENG-I-MP07 (latest revision), in the preparation, submission and use of the permit(s).
(End of Project Specific Requirement)
J-B-2 FIRE PROTECTION AND REQUIRED PERMITS (MAR 2014)
The KSC Fire Department will provide fire suppression, inspection and rescue services to the Contractor as necessary. The Contractor shall:
(a) Provide approved fire extinguishers of appropriate type for hazards involved.
(b) Report all fires to the Fire Service at 867-7911 or 867-1911.
(c) Comply with all requirements of KHB 1710.2C Section 504 (Heat Producing Devices) and NSS 1740.11 “NASA Safety Standard for Fire Protection” Section 702 and Chapter 8 for work performed at the Kennedy Space Center.
(d) Provide a fire watch in accordance with Federal OSHA Safety and Health Standards 29 CFR 1926.352/1910.252 when required by the welding and burning permitting official.
(e) Prevent false fire alarms by providing 24-hour advance notice to the Contracting Officer's Representative (COR) when construction activities in areas protected by fire alarm and/or detection systems may produce airborne particulates (smoke or dust) caused by construction activities such as painting, stripping, cutting drywall or concrete, sandblasting, and/or removing raised floor panels.
(f) Request permits for all welding and burning operations. Requests for these permits shall be made in writing to the Government at least seven (7) working days in advance of the time required.
(g) Report in the Contractor’s Safety and Health Plan how it intends to comply with the above requirements.
(End of Project Specific Requirement)
J-B-3 PERMANENTLY INSTALLED SAFETY SYSTEMS (MAR 2014)
(a) The Contractor shall protect and in no way interrupt the service of any installed safety systems or personnel safety devices.
(b) In the event that the Contractor requires entrance into systems serving safety devices, the Contractor shall obtain prior approval from the Contracting Officer. In the event the Contractor determines that it is necessary to temporarily remove or render inoperable any personnel safety devices in order to accomplish contract requirements, the Contractor shall provide alternate means of protection prior to removing or rendering inoperable any permanently installed safety devices or equipment and shall obtain prior approval of the Contracting Officer.
(End of Project Specific Requirement)
J-B-4 BREATHING AIR COMPATIBILITY (JAN 2017)
(a) The contractor shall take precautions to assure that connectors used in contractor-supplied breathing air systems are incompatible with connectors present on either KSC gas systems or on contractor supplied systems that are used to supply non-respirable gases. KSC-STD- Z0008, ‘Standard for Design of Ground Life Support Systems and Equipment’, establishes requirements for connectors to be used in KSC facility breathing air and non-respirable gas systems. Facility breathing air systems located at KSC/CCAFS are to use a Hansen 3/8 inch quick disconnect as a breathing air distribution interface. KSC facility non-respirable gas systems are to use ¼ inch quick disconnects for gas distribution interfaces. Although most facility systems were designed in accordance with this standard, there are nonconforming locations at KSC/CCAFS.
(b) The Contractor may use KSC facility breathing air systems, if available at the work location.
The contractor shall perform a pre-work site inspection to identify coupling types in use at the work location before mobilizing or using any breathing air equipment. The contractor shall also submit a written certification to show the contractor’s breathing air system has been recently inspected and meets Grade D breathing air standards. Alternately, the contractor may arrange for on-site testing of contractor-supplied breathing air by the Government at least five days prior to start of work. In addition, the contractor shall also provide a work site evaluation for the NASA Safety Office to review before using any breathing air system. The breathing air test and the safety inspection can be coordinated through the Contracting Officer, and will be at no cost to the contractor.
(c) The contractor shall tag or label connector ends of all lines and flexible hoses of contractor-provided breathing air or non-respirable gas distribution systems. The tags or labels will clearly identify the contents of the lines or hoses.
(d) The contractor shall provide a description of the steps taken to comply with the requirements of this clause in their safety plan submittal.
(End of Project Specific Requirement)
J-B-5 TRAFFIC RESTRICTIONS (MAR 2014)
(a) The Contractor will not move oversized loads and/or slow moving vehicles on established roads within the Kennedy Space Center from 6:30 A.M. to 8:30 A.M. and 3:30 P.M. to 5:30 P.M. on week days. Other than the above restricted hours, the Contractor may move oversize and/or slow moving vehicles to the work site provided all requirements of the Florida State Highway Department have been met.
(b) Movement of any Contractor vehicle in excess of maximum width, height and length specified by Florida Statues Chapter 316 shall be accompanied by the Contractor's designated Convoy Commander. The Contractor's Convoy Commander shall be totally responsible for the oversized vehicular movement to include making a physical inspection for possible obstructions along the intended route and obtaining all required special permits.
(End of Project Specific Requirement)
J-B-6 STORAGE AND PROTECTION OF MATERIAL TO BE RE-USED (MAR 2014)
All items of material to be removed and re-installed by the Contractor shall be protected during removal and stored in a manner such that the material will not be damaged during removal or storage. Any material designated for re-use, which is not suitable due to the Contractor's damage, will be replaced by the Contractor at no additional cost to the Government.
(End of Project Specific Requirement)
J-B-7 MAINTENANCE OF GOVERNMENT EQUIPMENT (MAR 2014)
(a) Government systems and equipment in the Contractor's work area may require servicing, maintenance, or modification by Government support contractors during the contract performance period. This maintenance activity may include work on systems, including underground utilities, that connect with Contractor installed systems and equipment. The Contractor shall allow the Government support contractors into his work area to perform the maintenance work.
(b) Existing systems and equipment require periodic maintenance that cannot be readily defined in terms of frequency and duration. This maintenance will be coordinated with the Contractor through the Contracting Officer, and will be performed on a non-interference basis as much as possible. The Contractor shall notify the Contracting Officer regarding any uncoordinated maintenance activity.
(c) The Contractor shall arrange and conduct a joint pre-operations briefing with Government support contractor personnel on each occasion that the support contractor requires access to the contractor’s work area. The Contractor shall take the following steps as required to prevent collateral damage to, or interference with, Contractor installed systems and equipment.
(1) Verify the scope and limits of the support contractor’s planned maintenance activity.
(2) Advise the support contractor regarding the scope of the Contractor’s work that may be affected by the maintenance activity, including specific locations and dimensions of planned or installed facilities, systems and equipment. Notify the Contracting Officer immediately regarding any resulting conflicts or interferences.
(3) Ensure that temporary barriers or protective measures are provided as needed to protect Contractor installed work and preserve job-site safety.
The Contractor shall notify the Contracting Officer immediately regarding any issues that cannot be resolved with the support contractor.
(End of Project Specific Requirement)
J-B-8 AVIATION OBSTRUCTION LIGHTS (MAR 2014)
The Contractor will provide at least two Aviation Red Obstruction Lights or two High Intensity White Obstruction Lights on all structures over 100 feet above ground level. All construction cranes/booms shall be lighted regardless of height. Lights must be constructed and installed in accordance with U.S. Department of Transportation, Federal Aviation Administration publication AC 70/7460-1F (as revised), Chapter 4, paragraph 15, subparagraph e. Lights will be operated during all periods of reduced visibility, between sunset and sunrise, and as directed by the Contracting Officer.
(End of Project Specific Requirement)
J-B-9 INTERFERENCES AND COORDINATION OF WORK (MAR 2014)
(a) The Contractor shall coordinate construction layout, systems configuration and work scheduling to avoid interference’s between the various construction trades and their installations. Interferences and obstructions resulting from lack of Contractor coordination shall be corrected by the Contractor as approved by the Contracting Officer. All components, fittings and reworking necessary for such corrections shall be provided by the Contractor at no additional cost to the government. Dimensions shown for existing work, and all dimensions required for work that is to connect to existing work, shall be verified by the Contractor by actual field measurement of the existing work. Any work at variance with that specified or shown in the drawings shall not be performed by the Contractor until approved in writing by the Contracting Officer.
(b) To the extent possible, the as-built dimensions of all new work shall be verified by actual field measurement prior to ordering or fabricating mechanical, electrical, or specialty equipment and materials to be installed. If such field measurement is not possible, then the contract drawings and applicable shop drawings shall be checked by the contractor for dimensional accuracy prior to ordering or fabricating equipment and materials to ensure proper fit for field installation.
(c) The Contractor shall be responsible for correction of all field fitup problems and interferences which could have been avoided by field measurement or drawing checks prior to equipment fabrication.
(End of Project Specific Requirement)
J-B-10 RESTORATION OF GRASSED AREAS DISTURBED BY CONSTRUCTION (MAR
2014)
The Contractor shall, prior to completion of the contract, grass all areas disturbed by construction activities by seeding and mulching or, when erosion may occur, by sodding, except where specifically directed otherwise in the drawings and specifications.
(End of Project Specific Requirement)
J-B-11 TEMPORARY CONSTRUCTION TRAILERS (MAR 2014)
(a) The Government will provide a location for temporary office and/or storage facilities if needed for performance of on-site work under this contract. Specific location(s) at or reasonably close to the work site will be identified at the pre-work conference. The contractor is responsible for providing his own telephone service and for making his own connections to KSC utility services, if provided.
(b) All temporary facilities must be structurally sound, in roadworthy condition, and shall be installed and anchored in accordance with KSC-PLN-1904, Trailer/Equipment Tie Down Plan for the John F. Kennedy Space Center; or Rules of Department of Highway Safety and Motor Vehicles, Division of Motor Vehicles Chapter 15C-1, whichever is more stringent. Copies of the standards will be made available to the contractor at the pre-work conference. The contractor shall provide written certification of compliance for all temporary facilities to the Contracting Officer within three days of installation. Any facilities that fail to meet these requirements shall be immediately removed from Government property.
(c) All temporary facilities shall be removed from government property within two weeks following final acceptance of work performed under this contract.
(End of Project Specific Requirement)
J-B-12 CONFINED SPACE WORK REQUIREMENTS (JAN 2017)
(a) Special requirements, coordination, and precautions will apply to any contract work taking place in confined spaces. Each contractor contracted to perform work in confined spaces is required to provide a written program for such work as part of its health and safety plan which is consistent with the requirements of 29 CFR 1910.146. For work in telecommunications manholes, provisions of 29 CFR 1910.268(o) are also applicable. The contractor shall coordinate any such work in confined spaces with the KSC Environmental Health Support Contractor, KSC Fire Services Support Contractor, and any other resident government or contractor organization whose employees may have access to the work location. The provision of Environmental Health services by the government does not prohibit the contractor from providing their own atmospheric testing. Government provided services include environmental health monitoring and consultation support for testing of atmospheres in confined spaces as well as fire rescue and emergency medical services.
(b) Entry into and work in confined spaces shall be in accordance with the requirements of KNPR 8715.7, KSC Construction Contractor Safety and Health Practices Procedural Requirements, and all other applicable clauses of this contract.
(c) Confined spaces, which contain water, shall be pumped out by the contractor prior to scheduling a confined space entry check.
(d) In addition to the requirements set forth above, the Contractor shall notify and obtain approval from the Power Coordinator, telephone 321-867-7300, and/or from Communications Control, telephone 321-867-4141, respectively, prior to performing work in electrical and/or communications manholes.
(End of Project Specific Requirement)
J-B-13 TESTING OF CONSTRUCTION MATERIALS (MAR 2014)
Tests of construction materials indicated to be performed by the Contractor shall be accomplished by the Contractor utilizing the services of an acceptable independent testing laboratory.
(End of Project Specific Requirement)
J-B-14 AFFIRMATIVE PROCUREMENT (JUN 2017)
(a) Affirmative Procurement (AP) is the purchase of environmentally friendly products and services (i.e. products made from recycled or recovered materials). Federal agencies, their Contractors and subcontractors are required to maximize the purchase materials on the list of “EPA Designated Guideline Items” with the minimum recycled or recovered materials content whenever practicable according to RCRA 6002 and EO 13101. The requirements of RCRA 6002 include the following language:
“The decision not to procure such items shall be based on a determination that such procurement items:
(A) are not reasonably available within a reasonable period of time
(B) fail to meet the performance standards set forth in the applicable specifications or fail to meet the reasonable performance standards of the procuring agencies and/or
(C) are only available at an unreasonable price
Any determination under subparagraph (B) shall be made on the basis of the guidelines of the National Institute of Standards and Technology in any case in which such material is covered by such guidelines.”
(b) The Contractor shall provide AP approved items as specified within the contract documents.
Submittals for AP items shall be provided for approval in accordance with Shop Drawing provisions. If the Contractor proposes to substitute an item that does not conform with AP requirements, the applicable Shop Drawing shall be accompanied by KSC Form 50-314, Contractor Request For Deviation/Waiver, identifying the reason for the proposed substitution.
(c) Non-conforming items without approved D/W’s will be rejected and the contractor shall be responsible for any costs and schedule impacts associated with replacing such non-conforming items at no additional cost to the Government.
(d) At the conclusion of the project, the Contractor shall provide the Contracting Officer (CO) with a report itemizing all AP items used.
(e) Detailed information on the EPA AP specified/approved products and manufacturers providing these products is available at www.epa.gov/cpg/products.htm.
(End of Project Specific Requirement)
J-B-15 SPILLS (OCT 2015)
(a) The Contractor shall make all reasonable and safe efforts to contain and control any spills or releases that may occur. The Contractor shall immediately report (by phone) any occurrence of a pollution incident or spill, first to the Emergency 911 (321-867-7911 from a non 867/861 exchange), then to the Contracting Officer (CO). The Contractor shall document the incident or spill on KSC Form 21-555, "Pollution Incident Report," and submit it to the CO and NASA Environmental Assurance Branch (EAB), SI-E2, within 24 hours of the incident.
(b) The Contractor shall provide spill response materials to contain and control spills including, but not limited to, containers, absorbent material, shovels, and personal protective equipment.
Spill response materials shall be available at all times in which materials/wastes are being handled or transported. Spill response materials shall be compatible with the type of material being handled.
(c) The KSC Spill Cleanup Team will be responsible for the final cleanup and validation of a spill or release.
(d) The Contractor’s prompt action to minimize the impacted area and to timely report any occurrence will increase the Spill Cleanup Team’s ability to complete the spill cleanup and therefore reduce the Contractor’s liability for a larger cleanup.
(End of Project Specific Requirement)
J-B-16 REGULARLY SCHEDULED STATUS MEETINGS (JAN 2017)
The Contractor shall attend routine progress/status meetings to be scheduled by the Contracting Officer for the purpose of determining progress status, delay factors, material delivery schedules, and status of shop drawing submittals. In addition, a representative of each first tier subcontractor may be required to be present for the meeting.
(End of Project Specific Requirement)
J-B-17 SUPERINTENDENT ASSIGNMENT – WORKING SUPERINTENDENT
(DEC 2016)
Pursuant to FAR clause 52.236-6, entitled "Superintendence by the Contractor," the Contractor shall assign a superintendent, on the Contractor’s payroll, whose primary responsibility will be to superintend the work and who has the authority to act for the Contractor. One or more alternate superintendents, each with full authority to supervise the work, shall be designated in writing and approved by the Contracting Officer. The superintendent or an alternate shall be physically present at each work site at all times during performance of the contract and until the work is completed and accepted.
The individual(s) appointed as superintendent(s) shall complete the OSHA 10 hour Construction Course prior to starting any field work on the project. The class shall be taught by an authorized provider of the course (e.g., United Safety Council, Florida Safety Council) and be attended in person. The appointed superintendent(s) shall provide the course completion certificate to the government stating the required training and testing was satisfactorily completed and the date of completion. The course completion date shall not be greater than 5 years from the start of the contract.
(End of Project Specific Requirement)
J-B-18 MATERIAL SAFETY DATA SHEETS (MSDS) SUBMITTAL/CHEMICAL
INVENTORY REPORTING AND MANAGEMENT (MAR 2014)
The Contractor shall provide a complete and accurate list, accompanied by the applicable Material Safety Data Sheets (MSDS), of all materials and chemicals listed on the Consolidated List of Chemicals Subject to the Emergency Planning and Community Right-To-Know Act (EPCRA) and Section 112(r) of the Clean Air Act that will be stored onsite and/or used in the execution of this contract, regardless of the quantity. This information shall be provided to the Contracting Officer (CO) prior to the time of delivery of the materials and chemicals to the site. This inventory is to be updated and resubmitted to the CO on a monthly basis. All inventory reporting is to be completed on the Chemical Inventory for Construction Projects at Kennedy Space Center Form (8-313NS).
Appropriate labels and MSDS shall be provided for all chemical shipments.
(End of Project Specific Requirement)
J-B-19 WASTE CHARACTERIZATION (MAR 2014)
KSC Form 26-551 "Process Waste Questionnaire" (PWQ) shall be prepared and processed for all waste streams generated during the execution of this project in accordance with article entitled “Hazardous Wastes”.
(End of Project Specific Requirement)
J-B-20 CONCRETE WASTEWATER (MAR 2014)
The following checked paragraphs are applicable to this acquisition:
CONCRETE WASHOUT
The Contractor shall not allow wastewater from standard concrete construction activities (such as on-site material processing, concrete curing, foundation and concrete clean-up, water used in concrete trucks, forms, directional drilling, etc.) to enter waterways or to be discharged before being treated to remove pollutants.
The Contractor shall dispose of the construction-related concrete wastewater and concrete excess by collecting and placing it in a contractor constructed settling pond where suspended material can be settled out and/or the water can evaporate to separate solids from the water. The location of the settling pond shall be coordinated with and approved by the Contracting Officer (CO). The Contractor shall remove and dispose of the residue left in the pond and restore site to original condition. Disposal of solidified concrete shall be performed in accordance with the solid waste article.
LIGHTWEIGHT CONCRETE
Reference contract article entitled “Hazardous Wastes”. The use of light-weight concrete materials has been confirmed to have the potential to be hazardous due to pH but may also exhibit other hazardous characteristics depending upon processes and products used. The contractor shall not allow wastewater from light-weight concrete construction activities (such as on-site material processing; concrete curing;
concrete clean-up; and water used in concrete trucks, forms, etc.) to enter waterways or to be discharged on the ground before being analyzed for hazardous waste characteristics. A representative sample shall be collected from the first "flush" of light-weight concrete wash water waste at the time of generation, and will be analyzed by the government for hazardous waste characteristics. Pending completion of this analysis, all such waste water shall be containerized, labeled, and handled in accordance with the “Unknown Wastes” in “Hazardous Waste” article.
If the waste wash water from light-weight concrete usage is determined to be hazardous, it shall be handled, stored, labeled, and managed as hazardous waste in accordance with RCRA regulatory requirements and applicable contract provisions.
If the analysis shows the wash water is not hazardous, this wash water waste and any additional wash water waste generated at the same job using the same product and process may be handled as described under “Concrete Washout” paragraph above.
(End of Project Specific Requirement)
J-B-21 HAZARDOUS WASTES (OCT 2015)
(a) Hazardous and controlled waste shall be managed in accordance with all applicable statutes, rules, orders, and regulations which may include but are not limited to 40 CFR Parts 260 - 268, 273, 279, 761 and KNPR 8500.1 KSC Environmental Requirements. All hazardous waste generated during the execution of this contract shall be disposed of by the Government. Unless directed by the Contracting officer, in no case shall the Contractor or the Contractor’s representative transport hazardous waste from KSC.
(b) The Contractor shall be responsible for identifying processes and operations and the location and nature of all potentially hazardous and controlled waste and their containers, as defined in 40 CFR Parts 261, 273, 279, or 761. KSC has established policies and procedures in place to assist the contractor for characterization, handling and storage of wastes generated on KSC.
Any request for assistance shall be in writing and submitted to the Contracting officer.
(c) Contractor personnel generating and managing the waste shall have hazardous waste training per 40 CFR 265.16. The Contracting Officer may at any time during the course of the contract performance period require the Contractor to provide individual training records for any employee involved in the performance of this contract, and the contents of the course or courses completed to satisfy the training requirements. Attendance at KSC Training Course QG-211
"Hazardous Waste Management" will satisfy the above training requirements.
(d) The Contractor shall prepare copies of Material Safety Data Sheets (MSDS) for each material utilized on the project and provide copies to the Contracting Officer (CO) thirty (30) days before the start of the waste generation process. No substances shall be delivered to KSC without the appropriate Material Safety Data Sheets.
GOVERNMENT ASSISTANCE
KSC has established procedures for the handling, storage and disposal of hazardous waste.
To aide with proper compliance of site-specific requirements, the Government will assign a NASA Environmental Point of Contact (EPOC) for each project. The EPOC shall, upon request, assist with waste hazard determination, packaging, labeling, and disposal requirements for waste generated on KSC. The establishment of the NASA EPOC in no way relieves the contractor for compliance with requirements defined in 40 CFR Parts 261, 273, 279, or 761.
WASTE CONTAINERS
The Government will provide DOT compliant storage containers and labels upon request. The Contractor shall request the storage containers, by providing quantity and type needed, in writing to the Contracting Officer a minimum of one week before the required need date. The containers will be available for pickup by the Contractor at a location designated by the Contracting Officer. For projects that will be generating large quantities of waste (>500 gallon or 75 cu feet), a two week notice must be provided to the CO to ensure availability of waste containers. The Contractor shall be responsible for transporting the containers from storage location to the project site.
SATELLITE WASTE ACCUMULATION AREA (SAA)
The Contractor shall establish an on-site Satellite Waste Accumulation Area within 50 feet
(ft) of and within sight of any point where hazardous or controlled wastes may be generated. If a Satellite Waste Accumulation Area must be more than 50 ft from the point of generation, or out of sight of the generator, the Contractor shall provide a written request to the CO fourteen (14) days before the start of the waste generating process. The CO will send a notification to the NASA Environmental Assurance Branch (EAB), SI-E2, for their review and concurrence. The EAB will then request approval for a non-routine Satellite Waste Accumulation Area from Florida Department of Environmental Protection. The Contractor shall not place the Satellite Waste Accumulation Area in service before receiving written approval of the variance from the CO. The Contractor shall store potential or identified hazardous and/or controlled wastes in the appropriate properly labeled containers inside the Satellite Waste Accumulation Area in accordance with KNPR 8500.1 (as revised).
UNKNOWN WASTES
If during the course of the project unidentified waste is discovered by the contractor or subcontractors, the contractor shall immediately contact the Contracting Officer and handle the waste as hazardous. The contractor shall not attempt to move, open or test any unknown commodities.
If a hazardous/nonhazardous waste determination cannot be made by process knowledge and no MSDS is available for the waste stream, the container of waste shall be marked with a Hazardous Waste Determination In Progress (HWDIP) label until chemical analysis is completed. At the request of the Contractor, the CO and EPOC will provide any analytical support required by the TRP. The EPOC will arrange for all sampling and testing of potentially hazardous or controlled waste.
If the material is hazardous, the analysis completion date serves as the accumulation start date (ASD). Waste streams labeled with HWDIP labels are a potentially hazardous waste stream; therefore they must be managed as a hazardous waste. In order to fulfill this requirement, the generator shall manage those containers in a Satellite Waste Accumulation Area or 90-day storage area. HWDIP waste generated in amounts less than 55 gallons may be managed as a satellite container. If HWDIP waste is generated in amounts greater than 55 gallons, the additional volume must be moved within 72 hours to a 90-day storage site.
UNIVERSAL WASTES (UW)
For items meeting the definition of UW, the Contractor shall handle, collect and manage in accordance with 40 CFR 273 and Chapters 62-730 and 62-737 FAC. The EPA established Universal Waste regulations to ease the requirements for managing hazardous wastes that can be recycled. Waste streams currently adopted by the State for management as UW are rechargeable batteries, mercury-containing lamps and devices, capacitors, and certain pesticides.
The Contractor’s representative or “Handler” of UW shall be trained for the proper waste handling and emergency response procedures. Attendance at the KSC training course QG- 299 “Universal Waste Rule” will satisfy the above. The Contractor shall provide to the CO training records of any “handler” of UW upon request of the CO.
(End of Project Specific Requirement)
J-B-22 RECYCLING AND SALVAGING MATERIALS (MAR 2014)
The Contractor shall divert all of the following Construction and Demolition (C&D) waste items from the list below from disposal at landfills and incinerators to facilitate their recycling or reuse.
The Contractor shall require all subcontractors, vendors, and suppliers to participate in this effort.
CONTRACTOR PROPERTY
All materials and real property items checked below shall become property of the contractor at the NTP. The Contractor may, at his discretion, assume ownership of and recycle all other Construction and Demolition Debris that has not been identified for salvage in the Contract Documents, or has otherwise been designated as Government property. All recyclable material obtained by the Contractor for recycling shall be removed from the Kennedy Space Center and recycled; it shall not be stockpiled at the Kennedy Space Center.
The Contractor shall assume ownership of these recyclable materials once they are transported off of the Kennedy Space Center.
ELECTRICAL, OFFICE, AND OTHER EQUIPMENT
These items require inspection by RRMF/Environmental Management Branch recycling personnel to provide proper disposition of material. Electrical equipment (transformers / switchgear / panels / disconnects…..) disposition will be made on a case by case basis based on level of contamination and value.
METALS: ALUMINUM, BRASS, COPPER, REBAR, STAINLESS
STEEL, STEEL, OTHER FERROUS, OTHER NON-FERROUS, SCRAP
METAL
All metals coated with non-liquid PCB paints with levels below 50 parts per million shall be recycled by the contractor. Any metals coated with non-liquid PCB paints with levels above 50 ppm shall utilize the Schwartz Road Landfill after Government approval.
REPORTING REQUIREMENT
The Contractor shall record C&D waste materials on the “Construction & Demolition Projects Report“, KSC Form 7-648 NS (02/07) and submit the form on a monthly basis and keep log on site per direction of the Contracting Officer (CO).
(End of Project Specific Requirement)
J-B-23 SOLID WASTE (MAR 2014)
(a) The Contractor shall be responsible for the proper management of all solid waste generated at the Kennedy Space Center from the execution of this contract. The Contractor shall segregate and transport all solid waste to disposal locations designated in the Contract Documents. The Contractor shall police work areas daily for loose trash and debris. The Contractor shall collect and properly dispose of wind-blown debris daily to prevent migration of debris/trash offsite.
(b) Trash items not requiring special handling, or which cannot be resold or recycled, shall be disposed of in receptacles slated for disposal in either the KSC Landfill or the Brevard County Landfill. The Kennedy Space Center has numerous policies and processes in place to properly categorize, handle, store and dispose of waste streams generated during the project. It is the contractor’s responsibility to make every effort to reduce the impact of the project on the environment. This includes utilizing all practical means to reduce the amount of waste that is landfilled or incinerated.
(End of Project Specific Requirement)
J-B-24 DIVERTED SOLID WASTE (MAR 2014)
The Contractor shall dispose of the following solid wastes at onsite KSC disposal facilities:
Soils, Trees / tree remains, Vegetative material, Non-pressure treated wood, Dimensional non-pressure treated lumber, Pallets (Unserviceable Wood), Blast Media (non-hazardous), and clean non-coated concrete. The contractor shall segregate clean, unpainted concrete from other Construction and Demolition Debris and deliver it to the Kennedy Space Center’s Diverted Aggregate Recycling and Collection Yard (DARCY). The DARCY is located west of the Schwartz Road Landfill entrance. The Government shall retain ownership of all material delivered to the DARCY. EPOC shall provide DARCY operating plan upon request.
(End of Project Specific Requirement)
J-B-25 SCHWARTZ ROAD LANDFILL OPERATIONS (JAN 2017)
(a) The KSC Landfill is an unlined Class III landfill. Any waste permitted by DEP regulations for disposal in a Class III landfill as defined in Rule 62-701.200(14), FAC can be accepted at the landfill (excluding friable asbestos). For the purpose of meeting recycling, waste diversion and reuse goals, KSC has restricted certain solid waste from landfill disposal (See Project Specific Requirement titled Recycling and Salvaging Materials). Landfilling of waste shall be the Contractor’s last option for disposal.
(b) The physical dimensions of the waste shall be within the handling capabilities of the landfill disposal equipment. The physical dimensions for the landfill handling capabilities are 8 feet in length x 8 feet in width. Only the following items listed will be accepted at the landfill:
(1) Asphalt: Asphalt removed from parking lots, driveways, and roadways.
(2) Blast Media: The blast media must be as free from debris as possible and determined nonhazardous for acceptance into the KSC Landfill. The Spent Sandblast Media Disposal Form must accompany the blast media to the landfill and will be reviewed by the landfill operator. Blasting media determined to be a hazardous waste must be managed as hazardous waste.
(3) Carpeting
(4) Construction and Demolition Debris: Materials considered not water soluble and non-hazardous in nature, including but not limited to steel, brick, glass, concrete, asphalt, pipe, gypsum wallboard and non-pressure treated or unpainted lumber. This also includes rocks, soils, tree remains and other vegetative matter, which normally result from land clearing or development. Scrap metal from demolition projects should be managed according to guidance provided under article entitled “Recycling and Salvaging Materials”. The landfill may not accept any painted materials that test above the lower Toxicity Characteristic Leaching Procedure (TCLP) detection limits for barium, cadmium, chromium, lead, and mercury. If TCLP results are above the lower TCLP detection limits, the Contractor shall submit a PWQ for evaluation per article entitled “Hazardous Wastes.”
(5) Fiberglass
(6) Glass (except light bulbs or lamps).
(7) Non-Friable Asbestos: Non-friable asbestos, also referred to as Non-Regulated Asbestos Containing Materials (NRACM) is handled on a case-by-case basis. KSC policy allows for the disposal of NRACM only. In order to dispose of non-friable asbestos, the Contractor shall complete and submit the KSC/Schwartz Road Landfill Non-Friable Asbestos form (KSC 28-1084 NS), which can be obtained from the Contracting Officer (CO) or the CO’s designee. The form shall be sent to NASA EAB, SI-E2. The following scheduling procedures shall be followed before NRACM wastes are accepted at the landfill:
(i) The waste generator/hauler shall make arrangements with the landfill operator a minimum of 24 hours before disposal of NRACM waste and shall inform the operator of the quantity of the waste and the scheduled date the shipment will arrive at the landfill.
(ii) NRACM will be accepted at the landfill with prior arrangement with the scale house attendant (minimum of 24 hours notification) Tuesday and Thursday, excluding holidays, from 0700 hours to 1100 hours and from 1200 hours to 1500 hours.
(8) Pallets (Unserviceable Wood and Plastics): Pallets that are not reusable or recyclable are accepted.
(9) PCB Bulk Product Waste: Refer to Clause “PCB Management.”
(10) Wood: Miscellaneous non-pressure treated wood items are accepted.
(11) Yard Waste (Vegetation): Vegetation from maintenance and land clearing activities is accepted.
(End of Project Specific Requirement)
J-B-26 NOISE AND DUST CONTAINMENT (MAR 2014)
Special measures (water suppression) shall be taken by the Contractor to limit the noise and dust migration during demolition and construction activities.
(End of Project Specific Requirement)
J-B-27 INDOOR AIR QUALITY (MAR 2014)
The Contractor is responsible for constructing, inspecting, and maintaining containment of the construction work area(s) that will prevent migration of dusts, smokes, fumes, gases, and vapors that are generated during demolition and construction activities into occupied space outside the construction zone. The Government will investigate Indoor Air Quality (IAQ) complaints received from employees in adjacent work areas throughout this project. If the Government identifies IAQ problems that are the result of inadequate containment of the demolition and construction work area(s), the Contractor shall be required to take appropriate control measures, at Contractor’s expense, to mitigate.
(End of Project Specific Requirement)
J-B-28 CONTRACTOR ACCESS (MAR 2014)
Access to existing facilities for coordination of work shall be provided on an as needed basis only with prior approval from the contracting officer. The Contractor shall notify the contracting officer a minimum of 7 days prior to requiring such access.
(End of Project Specific Requirement)
J-B-29 SPECIFIC ISSUES FOR MAINTAINING EGRESS (MAR 2014)
During the course of this contract, egress around the work site must be clearly marked in order to keep employees safely out of the work areas. The Contractor shall manage this by the use of fences, cones and barricades.
(End of Project Specific Requirement)
J-B-30 GRASS MOWING (JAN 2017)
Grass mowing for access to work areas and construction activities is the responsibility of the contractor. Contractor must also provide grass mowing for utility locates and must maintain grass mowing for utility locate purposes. The Government will not provide special grass mowing services due to construction activities.
(End of Project Specific Requirement)
J-B-31 USE OF SHAREPOINT (JUL 2017)
This project will use a government provided SharePoint website for the electronic submittal and repository of most project documentation required by the contract, including, but not limited to, shop drawings, safety plans, environmental plans, demolition plans, certifications, proposals, deviation waivers, pay requests, requests for proposals, and requests for information. In order to accomplish this, the contractor shall designate two administrators, with up to date IT security training, and maintain IT resources that will preserve the integrity of the KSC security firewall.
When certification of fulfilling these requirements is received by the government, the government will provide the contractor Cisco VPN software to install on its computers for logging into the SharePoint system and the two administrators will be provided RSA SecurID tokens. The vast majority of documents to be submitted in SharePoint will require the Contractor to use the latest edition of Adobe Acrobat software. Microsoft Explorer will also be required for SharePoint web access.
(End of Project Specific Requirement)
J-B-32 AS-BUILTS DURING CONSTRUCTION (JUL 2017)
The Contractor is responsible for providinge a full set of construction as-builts at the completion of the project. The Contractor is required to include as-built drawing status and completion percentage in the construction schedule and all schedule submittals. As-built status and submittal is a requirement and on all pay request submittals. As-built drawings or redline drawings shall be readily available at all times on the jobsite, in the prime contractor’s possession, for review by the Government, inspectors, or other authorized personnel.
(End of Project Specific Requirement)
J-B-33 AHU LIFTING, RIGGING AND TEMPORARY CONFIGURATIONS
Contractor shall submit for approval the required procedures for lifting, rigging and temporary configurations for the air handling units from delivery to final assembly. Any temporary configurations not specified by the manufacturer shall be defined and calculations provided by Professional Engineer as required.
(End of Project Specific Requirement)
File details come from the government source that posted it. Updated .