Amendment 003

View the file

Other files for this federal contract opportunity

Other files attached to Replace Air Handling Units, Space Station Processing Facility (SSPF), Bid Package #5 (AHUs 21 & 23), newest first.
File Type Posted
80KSC018R0001_-_Source_Select_State.pdf PDF
80KSC018R0001_Amend_002.pdf PDF
Site_Visit_Log.pdf PDF
Attach_J-A,_Project_Deliverables.pdf PDF
Sect_L_App_3_-_Pre-Proposal_Inquiry_Form.xlsx XLSX spreadsheet
Attach_J-B,_KSC_Project_Specific_Reqs.pdf PDF
Sect_L_App_4_-_Past_Perf_Quest.docx DOCX document
Attach_J-D,_Cert_of_Prog_Pay.doc DOC document
Attach_J-C,_DBW_13Oct17.pdf PDF
80KSC018R0001_(Rpl_AHU_SSPF)_Solicitation.pdf PDF
Sect_L_App_2_-_Acceptable_Identity_Guide.pdf PDF
Sect_L_App_1_-_KSC_Form_28-889_Visitor_Badge_Request.pdf PDF
Attach_J-G,_PIV_KDP-KSC-P-3722.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Modification to existing BAS Control

Panels

Modifications to the existing BAS Control

Panels will be required for new control points being added. Can you please submit an RFI requesting the as‐built drawings for

BAS system associated with AHU‐18, AHU‐21, and AHU‐22.

The latest vesion of Drawing 82K05179 Kennedy

Space Center Space Station Processing Facility, HVAC Controls System will be uploaded securely in FedBizOpps for download.

Precision Mechanical would like to request an additional site visit for the

Replace AHU’s at SSPF

No additional site visit will be provided at this time. If there are some specific questions that can be answered without a site visit the Government will try an address them if time allows.

Was any information ever issued or possible to issue the model number and quantity required for Additive #1: existing

HEPA filters required in case changed out before job completion

See the attached Flanders Air Filters reference information.

Is there any chance that the Replace AHU’s at the SSPF technical proposal that’s due on Monday, 11/20 can be postponed until after Thanksgiving?

The Government is extending the proposal due date to November 27, 2017 2PM EST.

1. Reference: Specification 79K39209, page 199, Para. 3.1 Forth Paragraph:

Submit Installation Drawings for pipes, valves and specialties. Drawings shall include the manufacturer's design and construction calculations, forces required to obtain rated axial, lateral, or angular movements, installation criteria, anchor and guide requirements for equipment, and equipment room layout and design.

Drawings shall specifically advise on procedures to be followed and provisions required to protect expansion joints during specified hydrostatic testing operations.

Will the submittal of Shop drawings and manufacture cut sheets on pipe, valves and specialties satisfy the above requirement as a build to print? Or, is the contractor to hire a registered engineer to fabricate sealed and stamped drawing to satisfy the above requirement?

The submission of a shop drawing is sufficent, reference example document uploaded securely in

FedBizOpps for download.

2. Reference: Specification 79K39209, page 200, Para. 3.1 6th & 7th

Paragraphs. Field welded joints shall conform to the requirements of the AWS

WHB-2.9, ASME B31.3, and ASME

BPVC SEC IX.

Preheat and post heat treatment of welds shall be done in accordance with ASME

BPVC SEC IX and ASME B31.3.

Does the chilled water piping fall under

Category D of ASME B31.3? If so, is visual inspection for the welds the only requirement?

The chilled water system under this contract does fall under Category D of ASME B31.3, therefore, only visual inspection are requires of the welds

Amend

No.

Solicitation No. 80KSC018R0001 Project Title: Replace AHU SSPF, Bid Pkg #5

No.

Reference

(Section Paragraph/Page, Drawing

Sheet/Page)

QUESTION GOVERNMENT RESPONSE