Contractor Questions.pdf

PDF 34 KB Posted

Attached to
Integrated Graphics, Operations, and Analysis Lab (IGOAL) IV
Solicitation number
80JSC021Q0002
Issued by

View the file

Other files

File Type Posted
SF1449.pdf PDF
80JSC021Q0002 Solicitation SAF.doc.pdf PDF
SF1449.pdf PDF
SF1449.pdf PDF
DRDs Attachments.pdf PDF
80JSC021Q0002 Solicitation.pdf PDF
Statement of Work _ IGOAL IV.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACTOR (NON-TECHNICAL) QUESTIONS AND ANSWERS

80JSC021Q0002

IGOAL IV

1. Section 4.4 Contract Value Table:

a. Can you please clarify if the Contract Core Value is our proposed Base Year value only?

b. Can you please clarify if the Contract Core value is also exclusive of profit, since Table B-1 in Section 4.5 Labor Rates, is exclusive of profit?

Answer: Contract Core Value was removed and not required, see updated RFQ

2. DRD Attachment D-09, Technical Acceptability Outline (Page Limit of 10 pages) versus Past Performance (1 page each, up to 3 citations)

a. Can you please clarify if a separate volume is to be submitted for evaluation of Past Performance citations? Or, are the 1 page citations to be included in the 10 page limit of the Technical Acceptability volume?

Answer: A separate volume is to be submitted for evaluation of Past Performance citations

3. We are completing our proposal for the IGOAL RFP and are concerned that the file may be too large for email. Is there a limit on the acceptable file size you can accept by email?

Answer: You have the option of sending zip files or multiple emails before the due date

File details come from the government source that posted it. Updated .