Amendment 02 - 80GSFC23R0037.pdf

PDF 1 MB Posted

Attached to
Space Weather Next L1 Series Magnetometer (MAG)
Solicitation number
80GSFC23R0037
Issued by

About this file

This document provides an amendment to a solicitation for the Space Weather Next L1 Series Magnetometer instrument. The amendment revises the scope of work and mission suitability proposal instructions. Specifically, it updates references to contract attachments in the scope of work clause and changes references to certain requirement identification documents. The electronic submission instructions are also revised to provide an updated Box link for proposal submissions. Offerors are encouraged to review all attachments and amendments to the solicitation, which is for the design, development, integration, testing, evaluation, launch support, ground support equipment, and mission operations for two tri-axial fluxgate magnetometers to measure the three components of the interplanetary magnetic field carried by the solar wind. The resulting contract will be awarded by the National Aeronautics and Space Administration Goddard Space Flight Center and National Oceanic and Atmospheric Administration.

View the file

Other files

File Type Posted
Amendment 03 - 80GSFC23R0037.pdf PDF
Attachment B - REQ SPEC - MAG L1 Series 02-12-2024 (AMD 02).pdf PDF
Amendment 01 - 80GSFC23R0037.pdf PDF
Attachment H - Financial Management Reporting Requirements.pdf PDF
Attachment A - SOW - L1 Series MAG 12-20-2023.pdf PDF
Attachment P - Data Requierments Description - OCI Plan.pdf PDF
Attachment J - ITSM Plan.pdf PDF
Attachment Q - Diversity Equity Inclusion and Accessibility Plan.pdf PDF
RFP - L1 Next Series Magnetometer (MAG) 1-12-2024.pdf PDF
Attachment C - CDRL - L1 Series MAG 01-11-2024.pdf PDF
Attachment R - Diversity Equality and Inclusion Plan.pdf PDF
Exhibit - CPFF Completion Services by GFY v2.1m.pdf PDF
SF33 - MAG.pdf PDF
Attachment N - Safety and Health Plan.pdf PDF
Attachment K - Quality Assurance Plan.pdf PDF
Attachment F - GFP List L1 Series MAG 12-1-2023.pdf PDF
Attachment D - MAR - L1 Series MAG 08-28-2023.pdf PDF
Attachment G - Small Business Subcontracting Plan.pdf PDF
Attachment I - OCI Avoidance Plan.pdf PDF
Enclosure 3 - Past Performance Questionnaire .pdf PDF
Attachment B - REQ SPEC - L1 Series MAG 01-11-2024.pdf PDF
Attachment S - Radiation Harndness Assurance Requirements Document - L1 Series 11-03-2023.pdf PDF
Attachment M - IT Security Applicable Documents List.pdf PDF
Attachment O - Contract Data Requirements List II.pdf PDF
Attachment T - Radiation Requirements Document - L1 Series 11-03-2023.pdf PDF
Enclosure 1 - QASP - L1 Series MAG 08-28 2023.pdf PDF
Cover Letter - 1-12-2024.pdf PDF
Enclosure 2 - IT Security Management Plan Template.pdf PDF
Attachment L - Contractor Proposed Enhancements.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Change GSFC clause 52.211-91 entitled “SCOPE OF WORK. (FEB 2016)” located on page C-1.

From:

GSFC 52.211-91 SCOPE OF WORK. (FEB 2016)

The Contractor shall provide the personnel, materials, and facilities, except as otherwise specified in this contract, necessary to perform the work and to furnish the items specified in the Supplies and/or Services To Be Provided clause of this contract in accordance with the Statement of Work, Attachment A; Requirements Specification, Attachment B; Contract Deliverable Requirements List, Attachment C; and Mission Assurance Requirements, Attachment D; Safety and Health Plan, Attachment N.

(End of clause)

To:

GSFC 52.211-91 SCOPE OF WORK. (FEB 2016)

The Contractor shall provide the personnel, materials, and facilities, except as otherwise specified in this contract, necessary to perform the work and to furnish the items specified in the Supplies and/or Services To Be Provided clause of this contract in accordance with the Statement of Work, Attachment A and the contract attachments listed in GSFC 52.211-101, located in Section J.

(End of clause)

2. Revise “Mission Suitability” information contained in GSFC Provision 52.215-210 entitled

“MISSION SUITABILITY PROPOSAL INSTRUCTIONS (COMPETITIVE). (MAY 2022)”

located on page L-14.

From:

1. MISSION SUITABILITY

1.5 SCHEDULE - Provide a detailed schedule consistent with the preparation requirements for DID RM-5, at the instrument and subsystem level, showing the critical path for the development of the Magnetometer from contract award through delivery of both flight models (FM). Define all slack/float for all major aspects of the schedule. Offerors are encouraged to propose a schedule that can be completed earlier than the contract requirements if that schedule can be adequately supported.

1.8 ALGORITHM AND CALIBRATION COEFFICIENT DEVELOPMENT – Explain the proposed strategy/approach to the sensor processing algorithm and calibration factors development and verification as described in the preparation requirements for DIDs I&T-5, I&T- 6, OPS-5, and OPS-6, Calibration Program Plan, Calibration Data Books, Ground Processing Algorithms Test and Validation Plan, and Ground Processing Algorithm Document.

1.9 CLASS C WITH 5-YEAR OPERATIONAL LIFE – Explain the proposed strategy/approach to developing and meeting NASA Payload Risk Classification C for a 5- year mission operational life at the Lagrange-1 orbit to include the approach to system reliability assumptions and assessments as described in the preparation requirements for DIDs MA-1, MA-4, and MA-5, Reliability Program Plan, Reliability Predictions, and Limited Life Items List, and the design approach to parts/components selection, redundancy, and cross[1]strapping methods.

To:

1. MISSION SUITABILITY

1.5 SCHEDULE - Provide a detailed schedule consistent with the preparation requirements for DID RM-3, at the instrument and subsystem level, showing the critical path for the development of the Magnetometer from contract award through delivery of both flight models (FM). Define all slack/float for all major aspects of the schedule. Offerors are encouraged to propose a schedule that can be completed earlier than the contract requirements if that schedule can be adequately supported.

1.8 ALGORITHM AND CALIBRATION COEFFICIENT DEVELOPMENT – Explain the proposed strategy/approach to the sensor processing algorithm and calibration factors development and verification as described in the preparation requirements for DIDs I&T-5, I&T- 6, OPS-4, and OPS-5, Calibration Program Plan, Calibration Data Books, Ground Processing Algorithms Test and Validation Plan, and Ground Processing Algorithm Document.

1.9 CLASS C WITH 5-YEAR OPERATIONAL LIFE – Explain the proposed strategy/approach to developing and meeting NASA Payload Risk Classification C for a 5- year mission operational life at the Lagrange-1 orbit to include the approach to system reliability assumptions and assessments as described in the preparation requirements for DIDs MA 4-4 and MA 4-5, Reliability Predictions and Limited Life Items List, and the design approach to parts/components selection, redundancy, and cross[1]strapping methods.

C Contract Deliverable Requirements List (CDRL) January 2024 116 D Instrument Mission Assurance Requirements (MAR) August 2023 34

E Reserved

F Government Furnished Property List December 2023 4

G Small Business Subcontracting Plan **TBS

H Financial Management Reporting Requirements June 2014 4

I Organizational Conflicts of Interest (OCI) Avoidance Plan

**TBS

J Information Technology (IT) Security Management Plan

*TBS

K Quality Assurance Plan **TBP

L Contractor Proposed Enhancements **TBP

M Information Technology (IT) Security Applicable Documents List (ADL)

August 2023 15

N Safety & Health Plan ***TBS

O Contract Data Requirements List II October 2021 7

P Organizational Conflicts of Interest (OCI) Plan March 2022 3

Q Diversity, Equity, Inclusion, and Accessibility (DEIA) Plan

March 2022 2

R Diversity, Equity, Inclusion, and Accessibility (DEIA) Plan

***TBS

S Radiation Hardness Assurance Document November 2023 25

T Radiation Requirements Document November 2023 36

TBS = To Be Submitted

TBP = To Be Proposed

*TBS within 30 days of the contract effective date

**TBS with proposal

***TBS within 30 days of contract award

(End of clause)

4. Change the information contained in the provision entitled “ELECTRONIC SUBMISSION

OF PROPOSALS – PROPOSAL MARKING AND DELIVERY THROUGH NASA’S EFSS

BOX (OCT 2023)” located on page L-33.

From:

(c) The offeror shall submit all proposal files to:

https://nasagov.box.com/s/gq8i3a2pfxp20z46exh7a93yvqjn0t73

The Offeror shall follow instructions regarding proposal submission found at:

https://www.hq.nasa.gov/office/procurement/other/EFSS-Box-Offeror-Proposal-Submission- Instructions.pdf.

To:

(c) The offeror shall submit all proposal files to:

https://nasagov.app.box.com/f/97d65e427ee6459db83d188ae9d4e1b8

The Offeror shall follow instructions regarding proposal submission found at:

https://www.hq.nasa.gov/office/procurement/other/EFSS-Box-Offeror-Proposal-Submission- Instructions.pdf.

End of Amendment 02