ATTACHMENT O (CWBS).pdf

PDF 277 KB Posted

Attached to
GeoXO Ocean Color (OCX) Instrument Implementation Federal contract opportunity
Solicitation number
80GSFC23R0014
Issued by
National Aeronautics and Space Administration Goddard Space Center

View the file

Other files for this federal contract opportunity

Other files attached to GeoXO Ocean Color (OCX) Instrument Implementation, newest first.
File Type Posted
Amendment 1 FINAL ATTACHMENT N DEIA PLAN.pdf PDF
Amendment 1 FRFP ATTACHMENT E 418-XO-IMAR-0026 V2_2.pdf PDF
Amendment 1 FRFP 80GSFC23R0014 Amendment 1 - Continuation pages.pdf PDF
FINAL ENCLOSURE C QASP.pdf PDF
FINAL ENCLOSURE B OCX PEP.pdf PDF
OCX FRFP Cost Exhibits R1.pdf PDF
FINAL ATTACHMENT Q GOES RDDP.pdf PDF
FINAL ATTACHMENT P Radiances Upwelling Document.pdf PDF
FINAL ATTACHMENT K SMALL BUSINESS SUBCONTRACTING PLAN.pdf PDF
FINAL ATTACHMENT E IMAR.pdf PDF
FINAL OCX RFP 80GSFC23R0014 083123.pdf PDF
FINAL EXHIBIT 8 Past Performance Questionnaire.pdf PDF
FINAL ATTACHMENT W OCI PLAN.pdf PDF
FINAL ATTACHMENT R Radiation Environment for Electronic Devices.pdf PDF
FINAL ATTACHMENT O CWBS.pdf PDF
FINAL ATTACHMENT N (DEIA) PLAN.pdf PDF
FINAL ATTACHMENT J SAFETY AND HEALTH PLAN.docx.pdf PDF
FINAL ATTACHMENT I OCI DRD.pdf PDF
FINAL ATTACHMENT H Financial Mgmt Reporting Requirements.pdf PDF
FINAL ATTACHMENT C GIRD.pdf PDF
FINAL ATTACHMENT F CDRL.pdf PDF
FINAL ATTACHMENT B PORD.pdf PDF
FINAL ENCLOSURE A IT Security Management Plan.pdf PDF
FINAL ATTACHMENT V Requirements Statements.pdf PDF
OCX Instrument Draft RFP QA.pdf PDF
UPDATED ATTACHMENT F - OCXCDRL 08032023.pdf PDF
ENCLOSURE B OCX PEP Draft.pdf PDF
ATTACHMENT W OCI.pdf PDF
ATTACHMENT S Concept of Operations (CONOPS).pdf PDF
ATTACHMENT R Radiation Environment.pdf PDF
Attachment H - Financial Rptg.pdf PDF
ATTACHMENT F - CDRL.pdf PDF
ATTACHMENT D - UIID.pdf PDF
ATTACHMENT C - GIRD 1.pdf PDF
ATTACHMENT B - PORD 1.pdf PDF
OCX DRAFT RFP 7.10.23.pdf PDF
OCX DRFP SF33.pdf PDF
ENCLOSURE C Quality Assurance Surveillance Plan (QASP).pdf PDF
ATTACHMENT V REQUIREMENTS STATEMENT.pdf PDF
ATTACHMENT K SMALL BUSINESS SUBCONTRACTING PLAN.pdf PDF
ATTACHMENT E - IMAR.pdf PDF
OCX DRFP Cover Letter.pdf PDF
ATTACHMENT P OCX Radiances Upwelling Doc.pdf PDF
ENCLOSURE A IT Security Management Plan Fillable Form V9.pdf PDF
ATTACHMENT U FPGA.pdf PDF
ATTACHMENT T DIVERSITY EQUITY INCLUSION DEIA DRD.pdf PDF
ATTACHMENT N (DEIA).pdf PDF
ATTACHMENT L IT SECURITY MANAGEMENT PLAN.pdf PDF
ATTACHMENT J- Safety and Health Plan.pdf PDF
ATTACHMENT G.pdf PDF
Show all 50

GeoXO Ocean Color (OCX) Instrument Implementation has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Heather Matthews

Digitally signed by Heather Matthews Date: 2023.03.23 10:38:26 -04'00'

Candace Carlisle Digitally signed by Candace Carlisle Date: 2023.03.23 10:55:28 -04'00'

Geostationary eXtended Observations (GeoXO) Flight Project

Ocean Color (OCX) Contractor Work Breakdown Structure

(CWBS)

March, 2023

Prepared by:

Heather Matthews GeoXO Flight Deputy Project Manager/Resources

Approved by:

Candace Carlisle GeoXO Flight Project Manager

Attachment O: Contractor Work Breakdown Structure (CWBS) and CWBS Dictionary

1. DESCRIPTION / PURPOSE

The CWBS establishes a product-oriented framework for reporting program cost, schedule, and technical performance and provides a basis for uniform planning, reporting status, program visibility, and assignment of responsibilities. Additionally, the CWBS provides a product-oriented logical subdivision of hardware, software, services, facilities, etc., that contribute to and/or make up the total project scope of effort and work. The CWBS dictionary provides a narrative description of the work tasks and effort to be performed in each CWBS element.

2. PREPARATION INFORMATION

Contents:

The CWBS and CWBS dictionary are two distinct project documents used for defining the approved project scope of work. The contents of each document are detailed in the following paragraphs:

CWBS – A logical, hierarchical display of the subdivision of all project work to be completed.

The CWBS shall include the approved element title and element number.

CWBS dictionary – The CWBS dictionary shall briefly describe and document the work content of every CWBS element and relevant efforts associated with each element (e.g., design, development, and manufacturing).

The CWBS levels shall be governed by the Following. The actual letter and number designations can be adapted to meet the needs of the Contractor’s systems

Level 1 - Total contract effort

Level 2 Definitions: Major contract activity as described below

A. Engineering Unit / Non-Recurring Activities – All effort to plan and manage the design of the instrument including detailed design activities, design reviews, risk reduction (engineering models, etc), software development, ground support equipment (GSE) development, verification planning, etc.

B. Flight Model (FM) -1 – All effort related to fabrication, assembly, test, launch operations and on-orbit testing of the satellite

C. FM-2

D. FM-3

E. FM-4

F. Special Tasks – all un-issued special task funds remain in this level 2 WBS G. Mission Operations - Long term mission support including any management, business management support, systems engineering etc that is not unique to a particular mission

Level 3 Definitions (Note: X denotes the Level 2 Contract Activity) – the work content as described is not necessarily all inclusive.

X.01 Program Management – Including program leadership, resource management, program planning (schedule), data management, configuration management, support for major design reviews

X.02 Systems Engineering - Including system engineering leadership, interface management (instrument, launch vehicle, ground), system specification definition and flow-down, verification planning, system level analysis and modeling

X.03 Mission Assurance - Including mission assurance leadership, quality engineering, subcontract surveillance, safety, reliability, parts and materials management

X.04 Hardware / Software – All subsystem hardware and software effort including parts and materials which should be accounted for in a separate line. Effort included in each level 2 WBS

X.05 Integration & Test - Including instrument baseline testing and environmental testing and post environment test activities including instrument packing and shipping.

X.06 GSE – design, fabrication, procurement assembly, test and maintenance of electrical, mechanical GSE and mission simulation and GSE software

X.07 Post Delivery Support (PDS) – Any support required after the Pre-Ship Review/Pre- Storage Review including satellite integration and testing and if needed storage costs or testing during storage prior to shipping to spacecraft vendor

X.08 Launch and Post Launch Testing– support for pre-launch planning, launch site support, support for mission unique or special launch services, launch-vehicle integration (spacecraft portion), and the first 6 months of post-launch testing prior to the handoff to NOAA.

X.09 Special Tasks – Actual and projected cost of special tasks issued for a specific level 2

WBS.

X.10 Long Term Support – Long term mission support including any management, business management support, systems engineering etc. that is not unique to a particular mission

Level 4 – The Contractor shall define WBS level within each level 3 and provide a brief description of the work content. For example, A.04.01 C&DH