This document is a Deliverable Items List and Schedule (DILS) for a Wide Field Infrared Survey Telescope (WFIRST) High Gain Antenna procurement. It lists 47 deliverables required from the contractor, including design documents, test plans, reports, and hardware. Key deliverables include a protoflight unit and potential flight spare unit due 16 months after contract award, as well as associated ground support equipment. The contractor must submit design packages and analyses at least 14 days before Design Conformance Review, and provide verification test procedures at least 28 days before testing begins. Test plans and reports are due prior to Pre-Ship Review for the antenna units. The solicitation is issued by the National Aeronautics and Space Administration Goddard Space Flight Center for the WFIRST Project, and specifies response requirements and formats for the various deliverables.

View the file

Other files for this federal contract opportunity

Other files attached to NASA/GSFC WFIRST HIGH GAIN ANTENNA, newest first.
File Type Posted
Amendment 1 - Ext to 3-18-20.pdf PDF
Questions and Answers #2.pdf PDF
Questions and Answers #1.pdf PDF
Attachment A WFIRST COMM-SOW-0026-.pdf PDF
Attachment D WFIRST-SMA-REQ-0032 B - Revised MAR.pdf PDF
Attachment F IT Security Applicable Documents List.pdf PDF
Attachment G IT Security Management plan.pdf PDF
Attachment H QA Plan.pdf PDF
Enclosure 1 QASP Fixed Price Contract Template-1.pdf PDF
Enclosure 2 IT Security Management Plan Template.pdf PDF
Cover Letter.pdf PDF
Attachment E Small Business Subcontracting Plan.pdf PDF
Final RFP.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Effective Date: February 11, 2020

National Aeronautics and

Space Administration

Goddard Space Flight Center

Greenbelt, Maryland

WFIRST-COMM-LIST-0061, Revision A

Wide Field Infrared Survey Telescope (WFIRST), Code 448

High Gain Antenna

Deliverable Items List and Schedule

(DILS)

GSFC WFIRST CMO

February 11, 2020

Released

High Gain Antenna DILS WFIRST-COMM-LIST-0061, Revision A ii

High Gain Antenna

Deliverable Items List and Schedule

(DILS)

Review/Signature/Approval Page

Prepared by:

Rene Gosselin

Approved by:

Jason Hylan

Electronic Approval available on CM Tool iii

Preface

This document is a Wide Field Infrared Survey Telescope (WFIRST) Configuration Management (CM)-controlled document. Changes to this document require prior approval of the applicable Configuration Control Board (CCB) Chairperson or designee.

Proposed changes shall be submitted to the WFIRST CM Office (CMO), along with supportive material justifying the proposed change.

In this document, a requirement is identified by “shall,” a good practice by “should,” permission by “may” or “can,” expectation by “will,” and descriptive material by “is.”

Questions or comments concerning this document should be addressed to:

WFIRST Configuration Management Office Mail Stop 448 Goddard Space Flight Center Greenbelt, Maryland 20771 iv

Change History Log

Revision Effective Date Description of Changes

(Reference the CCR & CCB/ERB Approval Date)

Revision - February 6, 2020 Initial release per WFIRST-CCR-0087

Revision A February 11, 2020 Per WFIRST-CCR-0177 updated Item 44 FROM: Flight TO: Protoflight v

Table of TBDs/TBRs/TBSs [optional]

Item No. Location Summary Individual/

Organization

Actionee

Due Date vi

Table of Contents

1 INTRODUCTION

1.1 Purpose

1.2 Scope

1.3 Related Documentation

1.3.1 Applicable Documents [and Forms]

1.3.2 Reference Documents

2 DELIVERABLES

APPENDIX A ABBREVIATIONS AND ACRONYMS

List of Tables

Table 1. Data Delivery Documentation and Schedule

1 INTRODUCTION

1.1 Purpose

The Wide Field InfraRed Survey Telescope (WFIRST) is a mission responding to the 2010

National Research Council New Worlds, New Horizons (NWNH) Astronomy and Astrophysics Decadal Survey top priority recommendation in the large space mission category. The science program includes two dedicated investigations to tackle outstanding questions in dark energy research and exoplanet exploration, and includes a substantial General Observer program to enable targeted investigations of astrophysical phenomena to advance other goals from the Decadal Survey. A coronagraph instrument is included in the payload for purposes of advancing the present state of the art of coronagraph technology. This document is the Wide Field Infrared Survey Telescope (WFIRST) High Gain Antenna (HGA) Deliverable Items List and Schedule (DILS).

1.2 Scope

This document lists all of the deliverables for HGA, the SOW paragraph number where the deliverable is described further, the type of response required from NASA GSFC, the format of the deliverable, and the schedule for delivery.

1.3 Related Documentation

The latest versions of all documents below should be used. WFIRST documents can be obtained in the CM Tool

1.3.1 Applicable Documents [and Forms]

The following documents are referenced within this document and are directly applicable or contain policies or other directive matters that are binding for the contents of this document. In the event of conflict between an Applicable Document and the content of this document, the WFIRST Project Configuration Change Board (CCB) has the final authority for conflict resolution.

Document Number Title WFIRST-COMM-SOW-0026 WFIRST High Gain Antenna Statement of Work (SOW)

1.3.2 Reference Documents

The following documents are referenced herein and amplify or clarify the information presented in this document. These documents are not binding on the content of this document.

Document Number Title WFIRST-COMM-SPEC-0090 WFIRST High Gain Antenna Specification file:///C:/Users/ddusterw/AppData/Local/Temp/1/CM

2 DELIVERABLES

Description: This provides the Title of the deliverable item.

Reference: This provides the reference back to the pertinent document calling out the deliverable.

Category:

A = Approval – Items in this category require approval from the National Aeronautics and

Space Administration (NASA)/Goddard Space Flight Center (GSFC) Contracting Officer (CO). In general, documents shall be provided in contractor format as long as required content, as specified in the Wide Field Infrared Survey Telescope (WFIRST) HGA Statement of Work (WFIRST-COMM-SOW-0026), is addressed. The NASA GSFC CO reserves the time-limited right of disapproval for each submission. The time-limited period is 30 working days from receipt of documents.

R = Review – Items in this category do not require formal NASA GSFC CO approval, but will be reviewed by the GSFC or its designated representatives in order to determine contractor effectiveness in meeting contract objectives. When Government review reveals inadequacies, the contractor may be requested to correct the inadequacies. GSFC will review and comment within 20 working days of receipt.

I = Information – Items in this category are informal and are for information only.

Format: This provides the format for the deliverable. For documents, the following format applies:

E = Electronic – Provide submittal in electronic format to the COR, and Contracting Officer. The vendor and COR shall jointly determine the type of electronic format (e.g., Word, Excel, PowerPoint, PDF, MATLAB) acceptable for each deliverable.

Table 1. Data Delivery Documentation and Schedule

Item

Description Reference Schedule Category/Format

1 SOW Compliance Matrix SOW 1.2 With Proposal Electronic – Provide submittal in electronic format to the COR and Contracting Officer.

Approval Required.

2 Monthly Status Report SOW 2.2 Fourteen (14) calendar days following the month being reported.

Electronic – Provide submittal in electronic format to the COR and Contracting Officer.

For Information Purposes.

3 Milestone List SOW 2.2 With Proposal

4 Notifications SOW 2.3 Seven (7) calendar days in advance of all mandatory hardware inspections, test activities, TIM’s, and deliveries.

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

5 Kick Off Meeting SOW 2.4.1 Fourteen (14) calendar days after contract award

In person at Contractor Facility.

Review Required.

6 Kick Off Meeting Package SOW 2.4.1 Three (3) working days before the meeting

Electronic – Provide submittal in electronic format to the COR and Contracting Officer.

Review Required

7 Design Conformance Review

(DCR)

SOW 2.4.2 Three (3) months after Award of Contract

In person at Contractor Facility.

Review Required.

8 Design Conformance Review Presentation Package

SOW 2.4.2 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

9 Design Conformance Review Report

SOW 2.4.2 Fourteen (14) calendar days after completion of DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

10 Pre-Environmental Review

(PER)

SOW 2.4.3 Seven (7) calendar days before start of environmental testing on first Flight Unit

In person at Contractor

Facility.

Review Required.

Item

Description Reference Schedule Category/Format

11 Pre-Environmental Review Presentation

SOW 2.4.3 At PER Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

12 Flight Unit(s) Pre-Ship Review (PSR)

SOW 2.4.4 Seven (7) calendar days prior to delivery of each

Flight Unit

In person at Contractor Facility.

Approval Required.

13 Flight Unit(s) Pre-Ship Review Presentation Package

SOW 2.4.4 At PSR Electronic – Provide submittal in electronic format to the COR and Contracting Officer.

Review Required.

14 Flight Unit(s) End Item Data Package(s) (EIDP)

SOW

2.4.4, 6.5.3, 6.7.3, 6.7.6, 6.8.2

With each delivered Flight Unit and available at PSR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

15 TIM SOW 2.4.5 As Negotiated In person at Contractor

Facility.

Review Required.

16 Interface Control Document(s) SOW 3.1 Preliminary at Kick-off Meeting

Final at fourteen (14) calendar days before

DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

17 Drawing Package SOW 3.2 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

18 Computer Models SOW 3.3 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

For Information Purposes.

19 Structural Analysis Report SOW 3.4 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

20 Structural Finite Element Model

SOW 3.5 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Description Reference Schedule Category/Format

Contracting Officer.

Review Required.

21 Thermal Analysis Report SOW 3.6 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and Contracting Officer.

Review Required.

22 Thermal Model & Documentation

SOW 3.7 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and Contracting Officer.

Review Required.

23 Reserved SOW 3.8 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and Contracting Officer.

Review Required.

24 Error Analysis Report SOW 3.9 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and Contracting Officer.

Review Required.

25 Y Reserved Reserved Reserved Reserved

26 User/Instruction Manual SOW 3.11 Fourteen (14) calendar days before PSR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required

27 Reserved

28 Verification Plan (Including Verification Matrix)

SOW 5.1,

6.5.1

Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

29 Individual Verification Test Plan(s) (if needed)

SOW 5.1 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

30 Verification Test Procedure(s) SOW 5.2 Twenty-eight (28) calendar days before start of testing and as changes occur.

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

Description Reference Schedule Category/Format

31 Verification Test Report(s) SOW 5.3 At PSR Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

32 Mission Assurance Implementation Plan / Quality Assurance Plan

SOW 6.1 Twenty-eight (28) calendar days after contract award

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

33 Class I Configuration Management (CM) Changes

SOW 6.2 Seven (7) calendar days after Contractor CM review

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

34 Class II CM Changes SOW 6.2 Seven (7) calendar days after Contractor CM review

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

35 Radiation Test Plans (if applicable)

SOW 6.6.2 Twenty-eight (28) calendar days prior to test.

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

36 Radiation Test Reports SOW 6.6.2 Fourteen (14) calendar days after test

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

37 Recertification Plans for EEE Parts > 5 years old (if applicable)

SOW 6.6.3 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

See

As-Built Materials List SOW 6.7.3 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

38 Materials Usage Agreement SOW 6.7.4 Fourteen (14) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Description Reference Schedule Category/Format

See

Materials Certificate of Compliance

SOW 6.7.6 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

39 Additive Manufacturing & Qualification Plan SOW

6.7.5.2.2

Thirty (30) calendar days before hardware fabrication

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

40 Fastener Integrity Control Plan SOW

6.7.5.4.1

Thirty (30) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

41 List of Critical Fasteners

SOW

6.7.5.4.1

Thirty (30) calendar days before DCR

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

See

Cleanliness Certification Report

SOW 6.8.2 As part of EIDP (DILS #14) Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

42 Thermal Vacuum Bakeout Plan

SOW 6.8.3 Twenty-eight (28) calendar days prior to beginning of Thermal Vacuum Bakeout

Tests

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Approval Required.

43 Thermal Vacuum Bakeout Test Results (if not part of Thermal Vacuum Report)

SOW 6.8.3 Fourteen (14) calendar days after completion of Thermal

Vacuum Bakeout Tests

Electronic – Provide submittal in electronic format to the COR and

Contracting Officer.

Review Required.

44 HGA Protoflight Unit

Qty: 1

SOW 4.2 16 months after contract award (ACA)

As specified in Clause

GSFC 52.247-94

Approval Required.

45 S-Band Connector Saver(s)

(provided as GFE)

SOW 4.3 With Item #44 As specified in Clause

GSFC 52.247-94

Approval Required.

46 Reserved Reserved Reserved Reserved

47 HGA GSE SOW 4.5 With Item #44, and #48 if option is exercised

As specified in Clause

GSFC 52.247-94

Description Reference Schedule Category/Format

48 HGA Flight Spare Unit

Qty: 1 [Option]

SOW 4.2 16 months after contract award (ACA)

As specified in Clause

GSFC 52.247-94

Appendix A Abbreviations and Acronyms

Abbreviation/

Acronym

DEFINITION

ACA After contract award

CIR Configuration Initial Release

CCB Configuration Control Board

CCR Configuration Change Request CM Configuration Management

CMO Configuration Management Office

CO Contracting Officer

COR Contracting Officer's Representative

DCR Design Conformance Review

DILS Deliverable Items List and Schedule

EEE Electrical, Electronic, and Electromechanical

EIDP End Item Data Package(s) FMEA Failure Modes and Effects Analysis

FMECA Failure Modes and Effects Criticality Analysis

GIDEP Government Industry Data Exchange Program

GSE Ground Support Equipment

GSFC Goddard Space Flight Center

HGA High Gain Antenna

I Information

INST Instrument NASA National Aeronautics and Space Administration

NDE Nondestructive Evaluation

PDL Product Design Lead

PEM Plastic Encapsulated Microcircuit

PER Pre-Environmental Review

PSR Pre-Ship Review

PWB Printed Wiring Board

R Review SOW Statement of Work

TBD To Be Determined

TBR To Be Resolved

TIM Technical Interchange Meeting

WFIRST Wide Field Infrared Survey Telescope

Yrs years

File details come from the government source that posted it. Updated .