Amendment 1 - Attachment 4 Milestone Payment Schedule.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Amendment 1 to Solicitation 80GRC026R0011 Special Test Equipment (STE) Vacuum Chamber 3 (Chamber Shell, Thermal Shroud, and Thermal Conditioning Unit (TCU)
Solicitation number
80GRC026R0011
Issued by

About this file

This is a Milestone Payment Schedule template for the VC3 Vacuum Chamber project under solicitation 80GRC026R0011 issued by NASA Glenn Research Center. The schedule outlines 18 distinct milestones spanning the full lifecycle of a custom thermal vacuum chamber system, including chamber shell, thermal shroud, and thermal conditioning unit (TCU). The milestones progress sequentially from project initiation through design phases (50%, 90%, and final design completion), material acquisition, fabrication of major components, procurement activities, shop acceptance testing, onsite installation, acceptance testing of individual components, punchlist completion, and delivery of as-built documentation and operation manuals. A critical constraint requires that onsite installation and acceptance testing activities must collectively represent a minimum of 35% of the total contract value across milestones 11 through 17. The template includes fields for milestone amounts, period completion percentages and dollar values, cumulative completion metrics, and comments, though all values currently display as zero dollars pending contract award and negotiation. The schedule also incorporates a contingency milestone (VC3 18) for standby or storage costs that may be required during project execution.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VC3

Vacuum ChamberMilestonesMilestone DescriptionMilestone Amount ($)Milestone Complete this Period (%)Complete this Period ($)Total Milestone Completion (%)Total Complete to Date ($)Comments
VC31Kick-off Meeting and Requirements Review$ - 0$ - 0$ - 0
VC3250% Design Completion$ - 0$ - 0$ - 0
VC3390% Design Completion$ - 0$ - 0$ - 0
VC34For Construction Design Completion$ - 0$ - 0$ - 0
VC35Material Acquisition$ - 0$ - 0$ - 0
VC36Fabrication of Vacuum Shell$ - 0$ - 0$ - 0
VC37Fabrication of Thermal Shroud$ - 0$ - 0$ - 0
VC38Procurement of TCU$ - 0$ - 0$ - 0
VC39Shop Acceptance Testing of Thermal Shroud$ - 0$ - 0$ - 0
VC310Shop Acceptance Testing of TCU$ - 0$ - 0$ - 0
VC311Onsite Installation of Shell, Shroud, and TCU$ - 0$ - 0$ - 0Onsite installation and acceptance testing must amount to a minimum of 35% of total contract value
VC312Acceptance Testing of Vacuum Shell$ - 0$ - 0$ - 0Onsite installation and acceptance testing must amount to a minimum of 35% of total contract value
VC313Acceptance Testing of Thermal Shroud$ - 0$ - 0$ - 0Onsite installation and acceptance testing must amount to a minimum of 35% of total contract value
VC314Acceptance Testing of TCU$ - 0$ - 0$ - 0Onsite installation and acceptance testing must amount to a minimum of 35% of total contract value
VC315Punchlist Item Completion$ - 0$ - 0$ - 0Onsite installation and acceptance testing must amount to a minimum of 35% of total contract value
VC316As-Built Deliverables$ - 0$ - 0$ - 0Onsite installation and acceptance testing must amount to a minimum of 35% of total contract value
VC317Operation and Maintenance Manuals$ - 0$ - 0$ - 0Onsite installation and acceptance testing must amount to a minimum of 35% of total contract value
TOTAL$ - 0$ - 0$ - 0
VC318Standby/Storage Costs$ - 0$ - 0$ - 0

File details come from the government source that posted it. Updated .