ERAE Synopsis Amendment 0001 (signed).pdf

PDF 243 KB Posted

Attached to
Eastern Regional Architecture and Engineering (“ERAE”) Synopsis Federal contract opportunity
Solicitation number
80GRC024R0006_Synopsis
Issued by
National Aeronautics and Space Administration Glenn Research Center

About this file

This document is an amendment to a federal solicitation for architect-engineering (A-E) services across the Eastern Regional Area of Operations for the National Aeronautics and Space Administration (NASA) Glenn Research Center. The key changes in the amendment include: extending the evaluation period from 6 years to 10 years, modifying the A-E professional qualifications requirement, providing additional submission instructions, and incorporating questions and responses. The solicitation is seeking A-E services for design, engineering, and construction support for facilities at various NASA centers, including Glenn Research Center, Armstrong Test Facility, Goddard Space Flight Center, Wallops Flight Facility, and Langley Research Center. Responses to the solicitation are due by 5:00 PM Eastern Time on August 22, 2024. This is a full and open competition with a NAICS code of 541330 and a $25.5 million small business size standard.

View the file

Other files for this federal contract opportunity

Other files attached to Eastern Regional Architecture and Engineering (“ERAE”) Synopsis, newest first.
File Type Posted
Attachment 1 - Government Responses.pdf PDF
ERAE Attachment 2 Synopsis Provisions.pdf PDF
80GRC024R0006 ERAE Synopsis 07182024.pdf PDF
ERAE Attachment 3 Scope of Services.pdf PDF
ERAE Attachment 4 Standard Form (SF) 330 Parts I and II.pdf PDF
ERAE Attachment 1 Past Performance Questionnaire.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Eastern Regional Architecture and Engineering (ERAE)

80GRC024R0006

SYNOPSIS AMENDMENT 0001

C. Architect-Engineer Services

Contracting Office Address: NASA Glenn Research Center / 21000 Brookpark Rd Cleveland, OH 44135 Amendment 0001 Release Date: August 2, 2024

I. The purpose of this amendment is to:

1. Incorporate Questions and Responses (see Attachment 1 – Government Responses)

2. Amend the Synopsis as provided in Section II below.

3. All other terms and conditions remain unchanged.

II. The following sections of Synopsis 80GRC024R0006 are hereby changed as follows:

a. From: IV. SELECTION CRITERIA/EVALUATION PROCESS

PHASE 1 SF 330 Qualifications:

Interested firms shall submit a completed SF 330, Architect-Engineer Qualifications, Parts I and II to include specific information addressing each of the five selection criteria described in this section of the synopsis. Firms will be evaluated to determine the most highly qualified in relation to the selection criteria detailed in this section of the synopsis. Failure to provide the requested data or to comply with the instructions in this notice may result in an evaluation that a firm is non-responsive.

The following factors will be used in the evaluation of the SF 330 submittals in response to this synopsis.

NASA will consider the immediate past six (6) years from the date of this synopsis as the period of time for evaluation.

1. Professional qualifications necessary for satisfactory performance of required services.

• One (1) Architect AIA with demonstrated design and ESDC experience of architectural systems.

2. Specialized experience and technical competence in the types of work required.

Provide no more than fifteen (15) projects in Section F of the SF 330. Firms must include the customer’s/owner’s point-of-contact (POC), project title and location (include a customer’s identification number, if applicable, such as delivery order number/s, contract number) in Section F of each SF 330 for each project. All projects must be ongoing or completed within six (6) years from the date of this synopsis. For submittal purposes, a single project may be considered to include multiple phases of a single effort, even under separate task orders, to include planning and feasibility studies, permitting, preliminary engineering reports, design, engineering services during construction, activation and commissioning. General engineering contracts, IDIQ contracts, basic agreements, and basic ordering agreements are not considered “projects.” One task order under an IDIQ/general engineering contract will be considered one “project.” Firms are encouraged to submit projects that demonstrate their experience in design of a variety of the systems listed above.

To: IV. SELECTION CRITERIA/EVALUATION PROCESS

PHASE 1 SF 330 Qualifications:

Interested firms shall submit a completed SF 330, Architect-Engineer Qualifications, Parts I and II to include specific information addressing each of the five selection criteria described in this section of the synopsis. Firms will be evaluated to determine the most highly qualified in relation to the selection criteria detailed in this section of the synopsis. Failure to provide the requested data or to comply with the instructions in this notice may result in an evaluation that a firm is non-responsive.

The following factors will be used in the evaluation of the SF 330 submittals in response to this synopsis.

NASA will consider the immediate past ten (10) years from the date of this synopsis as the period of time for evaluation.

1. Professional qualifications necessary for satisfactory performance of required services.

• One (1) licensed or registered Architect with demonstrated design and ESDC experience of architectural systems.

2. Specialized experience and technical competence in the types of work required.

Provide no more than fifteen (15) projects in Section F of the SF 330. Firms must include the customer’s/owner’s point-of-contact (POC), project title and location (include a customer’s identification number, if applicable, such as delivery order number/s, contract number) in Section F of each SF 330 for each project. All projects must be ongoing or completed within ten (10) years from the date of this synopsis. For submittal purposes, a single project may be considered to include multiple phases of a single effort, even under separate task orders, to include planning and feasibility studies, permitting, preliminary engineering reports, design, engineering services during construction, activation and commissioning. General engineering contracts, IDIQ contracts, basic agreements, and basic ordering agreements are not considered “projects.” One task order under an IDIQ/general engineering contract will be considered one “project.” Firms are encouraged to submit projects that demonstrate their experience in design of a variety of the systems listed above.

b. From: VII. SUBMISSION PAGE LIMITATIONS

A-E firms responding to this synopsis must submit a completed SF 330 package. Unique Entity Identifier

(UEI), Commercial and Government Entity (CAGE) and Taxpayer Identification Number (TIN) numbers must be included in Block 30 of the SF 330. The submission must include SF 330 Parts I and II, together which shall not exceed 40 pages. The firm may use its discretion on how best to present the information requested within the synopsis. Pages exceeding the maximum page limit will not be evaluated. The following are excluded from the 40-page limitation: submission transmittal cover pages, tab pages, tables of contents, signed amendments (if applicable), licensure/accreditation copies, copies of Section I from submitted PPQs, and completed CPARS evaluations.

A tab page is defined as a blank sheet used to separate the submission pages and may include a section heading. Any additional information provided on a tab page, other than section heading, will result in the tab page being counted against the 40-page limitation.

A page is defined as one side of an 8½" x 11" sheet of paper, with at least a one-inch margin on all sides, using Times New Roman font with a type-size of 12-point font. The one-inch margin and 12-point font limits are applicable to pages formatted by the A-E firm. The SF 330 form has its own instructions and is exempt from the above margin and character size limits.

To: VII. SUBMISSION PAGE LIMITATIONS

A-E firms responding to this synopsis must submit a completed SF 330 package. Unique Entity Identifier

(UEI), Commercial and Government Entity (CAGE) and Taxpayer Identification Number (TIN) numbers must be included in Block 30 of the SF 330. The submission must include SF 330 Parts I and II as well as any Extra Section pages downloaded from GSA.gov and information provided to supplement the SF330, all of which shall not exceed 40 pages. The firm may use its discretion on how best to present the information requested within the synopsis. Pages exceeding the maximum page limit will not be evaluated. The following are excluded from the 40-page limitation: submission transmittal cover pages, tab pages, tables of contents, acronym lists, Joint Venture (JV) agreements, signed amendments (if applicable), licensure/accreditation copies, copies of Section I from submitted PPQs, and completed

CPARS evaluations.

A tab page is defined as a blank sheet used to separate the submission pages and may include a section heading. Any additional information provided on a tab page, other than section heading, will result in the tab page being counted against the 40-page limitation.

A page is defined as one side of an 8½" x 11" sheet of paper, with at least a one-inch margin on all sides, using Calibri font with a type-size of 11-point font. The one-inch margin and 11-point font limits are applicable to pages formatted by the A-E firm. The SF 330 form and its Extra Section pages have their own instructions and are exempt from the above margin and character type and size limits.

c. From: VIII. SUBMISSION INSTRUCTIONS

SF 330 Due Date: All SF 330 package submissions shall be submitted to Enterprise File Sync and Sharing

(EFSS) Box by 5:00 PM Eastern Time (ET) on August 22nd, 2024. Late submissions will not be accepted.

FIRMS SHALL SUBMIT THEIR REPONSE IN THE FOLLOWING FORMAT:

VOLUME I: CONTRACT INFORMATION

i. Proof of registration as an A-E firm OR Proof of eligibility to practice as A-E firm as described in Section IV of this synopsis.

ii. Completed fill-ins from Attachment 2: Synopsis Provisions.

VOLUME II: SF 330 QUALIFICATIONS

i. Completed SF 330 Parts I and II.

ii. Copy of PPQ Section I for each customer contact for projects identified in

Section F of the SF330.

iii. CPARS evaluations, if available for projects identified in Section F of the SF330.

No email submissions will be accepted. Note: All submissions shall use the fillable version of the SF330 provided as Attachment 4 to this synopsis.

1) To ensure all firms are evaluated equally, any submissions that have altered the SF 330

Sections A-H in any way will be considered nonresponsive and will not be considered for selection. The prohibited alterations include, but are not limited to:

• Insertion of photos, tables, or graphics in Sections A-G.

• Modifying, deleting, or altering any block sizes.

• Altering the font or font size. Note: The form natively uses Times New Roman font with 12-point type with a set cell size.

• Altering paragraph line spacing.

• Modifying or deleting page layouts or using an in-house form.

• Altering the margins of the form.

2) Any additional information that cannot fit within the SF 330 Sections A-G can be included in

Section H.

• At least one page in Section H must include the standard form with blocks 31-

33 filled in.

• The firm may choose to use multiple pages of the section H form; however, the form shall not be altered in any way as described above.

• The firm may choose to use supplemental Section H pages, (edited in Microsoft

Word or similar) in which photos and/or tables may be included. The format of the pages shall include:

▪ Font no smaller than Times New Roman 12-point.

▪ Margins set at one inch on all sides.

▪ All Section H pages, including supplemental pages, count towards the 40 page limit.

NOTE: Any supplemental information provided in Section H regarding Specialized Experience that is not part of Projects 1-15 will not be evaluated under the Specialized Experience evaluation criterion.

Firms are cautioned to ensure that the cut/paste of data into the form must use the native settings.

To: VIII. SUBMISSION INSTRUCTIONS

SF 330 Due Date: All SF 330 package submissions shall be submitted to Enterprise File Sync and Sharing

(EFSS) Box by 5:00 PM Eastern Time (ET) on August 22nd, 2024. Late submissions will not be accepted.

FIRMS SHALL SUBMIT THEIR REPONSE IN THE FOLLOWING FORMAT:

VOLUME I: CONTRACT INFORMATION

iii. Proof of registration as an A-E firm OR Proof of eligibility to practice as A-E firm as described in Section IV of this synopsis.

iv. Completed fill-ins from Attachment 2: Synopsis Provisions.

VOLUME II: SF 330 QUALIFICATIONS

iv. Completed SF 330 Parts I and II as well as any Extra Sections.

v. Copy of PPQ Section I for each customer contact for projects identified in

Section F of the SF330.

vi. CPARS evaluations, if available for projects identified in Section F of the SF330.

No email submissions will be accepted. Note: All submissions shall use the fillable version of the SF330 provided as Attachment 4 to this synopsis.

1) To ensure all firms are evaluated equally, any submissions that have altered the SF 330

Sections A-H in any way will be considered nonresponsive and will not be considered for selection. The prohibited alterations include, but are not limited to:

• Insertion of photos, tables, or graphics in Sections A-G.

• Modifying, deleting, or altering any block sizes.

• Altering the font or font size.

• Altering paragraph line spacing.

• Modifying or deleting page layouts or using an in-house form.

• Altering the margins of the form.

2) Any additional information that cannot fit within the SF 330 Sections A-G can be included in

Section H.

• At least one page in Section H must include the standard form with blocks 31-

33 filled in.

• The firm may choose to use multiple pages of the section H form; however, the form shall not be altered in any way as described above.

• The firm may choose to use supplemental Section H pages, (edited in Microsoft

Word or similar) in which photos and/or tables may be included. The format of the pages shall include:

▪ Font no smaller than Calibri 11-point.

▪ Margins set at one inch on all sides.

▪ All Section H pages, including supplemental pages, count towards the 40 page limit.

NOTE: Any supplemental information provided in Section H regarding Specialized Experience that is not part of Projects 1-15 will not be evaluated under the Specialized Experience evaluation criterion.

Firms are cautioned to ensure that the cut/paste of data into the form must use the native settings.

THE CLOSING DATE FOR THIS SYNOPSIS REMAINS THURSDAY, AUGUST 22, 2024 AT 5:00 PM EASTERN

TIME (ET).

Stephanie D’Anniballe Contracting Officer

2024-08-02T09:24:17-0400
Stephanie D'Anniballe

File details come from the government source that posted it. Updated .