80AFRC24R0008-DRD List.pdf
PDF 127 KB Posted
- Attached to
- GULFSTREAM-IV NEXT GENERATION AIRBORNE SYNTHETIC APERTURE RADAR (AirSAR-NG) MODIFICATION
- Solicitation number
- 80AFRC24R0008
About this file
This document contains four Data Requirements Descriptions (DRDs) for a federal contract solicitation to modify a Gulfstream-IV aircraft for synthetic aperture radar capabilities. The solicitation requires the contractor to provide a project milestone schedule, weekly project status reports, an aircraft modification design package upon completion of modifications, and a tool control plan. The contractor must complete fuselage and ventral modifications and deliver the aircraft by May 2024. The National Aeronautics and Space Administration Armstrong Flight Research Center will award a firm-fixed price contract and make government property available for performance. Offerors must submit proposals through NASA's Enterprise File Sharing and Sync Box by April 8, 2024 and encourage past performance references to submit directly to the contracting officer.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
List of Data Requirements Descriptions (DRD)
DRD No. Title of DRD No. Pages DRD-1 Project Milestone Schedule 1 DRD-2 Project Status Reports 1 DRD-3 Aircraft Modification Design Package 1 DRD-4 Tool Control Plan 1
DATA REQUIREMENTS DESCRIPTION
1. TITLE 2. NUMBER
Project Milestone Schedule DRD-1
3. USE 4. DATE
Nov 2, 2023 To provide an initial baseline schedule for the AirSAR- NG project
5. PREPARED BY:
Franzeska Becker, Project Manager
6. APPROVED BY:
Franzeska Becker, Project Manager
7. DUE DATE: 8. References:
15 days after contract award SOW Section 3.0, 4.0, 6.0
9. PREPARATION INFORMATION
Contractor Format – Microsoft Project or Equilevant
The CONTRACTOR shall provide a schedule to demonstrate their planning and ability to meet the following technical milestones/project events:
Project Event(s)
• Aircraft Modification Design Package Completion
• Fuselage Blister-Only Modification Completion
• Ventral Canoe-Only Modification Completion
• Aircraft Maintenance Inspection Completion
Submit Project Milestone Schedule to the following addresses:
(1) Contracting Officer, Angela Stinchfield, angela.t.stinchfield@nasa.gov
(2) Contract Specialist, Kimberly Beck, kimberly.a.beck-1@nasa.gov
(3) Contracting Officer’s Technical Representative, Franzeska Becker, franzeska.becker@nasa.gov
(4) Alternate Contracting Officer’s Technical Representative, Ting Tseng, ting.c.tseng@nasa.gov
1. TITLE 2. NUMBER
Project Status Reports DRD-2
3. USE 4. DATE
To track technical progress and identify issues associated with Nov 2, 2023 Gulfstream-IV Next Generation Airborne Synthetic Aperture Radar (AirSAR-NG) Modification
5. PREPARED BY:
6. APPROVED BY:
7. Due Date: 8. REFERENCES
Weekly after Contract Award
SOW Section 3.0, 4.0, 6.0
Regularly scheduled weekly status meetings (on-site or electronic) between Contractor and NASA project representatives
Contractor Format - Microsoft Word or Equivalent
• Schedule Updates: Provide weekly updates highlighting changes to project schedule
• Problem Reports: Identify, track and discuss project risks
Submit Project Milestone Schedule to the following addresses:
1. TITLE
Aircraft Modification Design Package (AMDP)
2. NUMBER
DRD-3
3. USE
Upon completion of the Aircraft Modification Design f
4. DATE
Nov 2, 2023 (CLIN 001), a Technical Data Package will be provided for government approval.
5.PREPARED BY:
Ting Tseng, AirSAR-NG Chief Engineer
6. APPROVED BY
Ting Tseng, AirSAR-NG Chief Engineer
7. DUE DATE
At time of delivery
8. REFERENCES
SOW Section 3.0, 6.0, Appendix 1, Appendix 2
Items required in the AMDP are as follows:
1. Mechanical Design Package
a. Comprehensive mechanical design model files (Specify modeling application)
b. All mechanical and electrical design drawing files (Specify CAD file, no PDFs)
c. Structural analysis
d. Aerodynamic analysis
e. Aircraft performance analysis
f. Thermal load management analysis (internal to enclosures)
2. Quality Assurance Artifacts
g. Material certifications
h. GSE loads test report
Submit AMDP to the following addresses:
2. TITLE
Tool Control Plan
2. NUMBER
DRD-4
3. USE
4. DATE
Nov 2, 2023 To ensure the Contractor manages tools and hardware properly.
5.PREPARED BY:
6. APPROVED BY
7. DUE DATE
15 days after contract award
8. REFERENCES
SOW Section 9.0
The Contractor shall develop and implement a NASA approved tool control plan that ensures the accuracy of tool inventories at specific intervals, contains a lost tool process, and prohibits aircraft from flying until all tools used on an aircraft have been accounted for. The tool control plan shall establish policy and responsibilities for implementing, maintaining, controlling, storing, replacing, and inventorying common hand tools. Plan shall include missing tool actions.
Submit Tool Control Plan to the following addresses: