8-Pay Application and Certificate for Payment.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
27B-019 Concrete Wall Installation at Marion County Judicial Center Parking
Solicitation number
27-019
Issued by
Marion County, Florida

About this file

This file is an Application and Certificate for Payment form used by Marion County, Florida for construction project payments. The form serves as the official documentation through which contractors submit payment requests and project managers certify work completion and payment authorization. The document is designed for the concrete wall installation project at Marion County Judicial Center Parking (Bid Number 27B-019), which involves the installation of a concrete barrier perimeter wall around the judges' parking lot and removal of the existing aluminum picket fence. The form tracks the original contract sum, net changes from change orders, total completed and stored work to date, retainage amounts, and current payment due amounts, with specific fields for contractor certification, notarization, and department project manager approval before payment authorization.

The payment application utilizes a 5.0% retainage rate applied to both completed work and stored materials. The form requires the contractor to certify that work has been completed in accordance with contract documents and that all prior payments have been received and obligations satisfied. The department project manager must verify that work has progressed as indicated, quality meets contract standards, and the contractor is entitled to payment of the certified amount. The certificate includes a change order summary section tracking additions and deductions approved in previous months and the current month. All figures on the application and continuation sheet must be initialed if changed to conform to the certified amount, and the certificate is non-negotiable, payable only to the named contractor without prejudice to any rights of either party under the contract.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pay App - Cover

APPLICATION AND CERTIFICATE FOR PAYMENT

TO OWNER:PROJECT:APPLICATION #:numberDistribution to:
Marion County BOCC -Project NameAPPLICATION DATE:dateOwner:
AddessPERIOD TO:time frameConstruction Division:X
AddressBID NUMBER:list full numberArchitect/Engineer:
FROM CONTRACTOR:MC CONSTRUCTION DIVISION:PO #:list full numberContractor:
NameAttn:CONTRACT DATE:BCC approved dateOther:
Address
Address
CONTRACTOR'S APPLICATION FOR PAYMENTThe undersigned Contractor certifies that to the best of the Contractor's knowledge, information and belief the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for Work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown therein is now due.
Application is made for payment, as shown below, in connection with the Contract.
Continuation Sheet is attached.

1. ORIGINAL CONTRACT SUM……………………………………………………………….. 0.00 CONTRACTOR:

2. Net change by Change Orders……………………………………………………………$0.00By:Date:
Name
3. CONTRACT SUM TO DATE (Line 1 +/- 2)………………………………………………$ - 0
State of:Florida
4. TOTAL COMPLETED & STORED TO DATE………………………………………………$ - 0County of:Marion
(Column M on Continuation Sheet)Subscribed and sworn to before
me thisday of
5. RETAINAGE
a.5.0%of Completed Work$ - 0Notary Public:
b.5.0%of Stored Material$ - 0My Commission expires:
Total Retainage Line (5a + 5b)…………………………………………………….$ - 0CERTIFICATE FOR PAYMENT
In accordance with Contract Documents, based on on-site observations and the data comprising this application, the Department Project Manager certifies to the Owner that to the best of his/her knowledge, information and belief the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the AMOUNT CERTIFIED.
6. TOTAL EARNED LESS RETAINAGE………………………………………………………..$ - 0
(Line 4 less Line 5 Total)
7. LESS PREVIOUS CERTIFICATES FOR PAYMENT……………………………………..$ - 0AMOUNT CERTIFIED………………………………………………………………………….$0.00
(Line 6 from prior Certificate)
(Attach explanation if amount certified differs from the amount applied for. Initial all figures on this application and on the Continuation Sheet that are changed to conform to the amount certified.)
8. CURRENT PAYMENT DUE…………………………………………………………………..$ - 0
9. BALANCE TO FINISH, INCLUDING RETAINAGEName of Department Project Manager
(Line 3 less Line 6)$ - 0
CHANGE ORDER SUMMARYADDITIONSDEDUCTIONSBy:Date:
Total changes approved in previous months by Owner$ - 0$ - 0
Total approved this Month$ - 0$ - 0This Certificate is not negotiable. The AMOUNT CERTIFIED is payable only to the Contractor named herein. Issuance, payment and acceptance of payment are without prejudice to any rights of the Owner of Contractor under this Contract.
TOTALS$ - 0$ - 0
NET CHANGES by Change Order$0.00

Page &P of &N