8-2. BID-275-26 Notes.pdf
PDF 466 KB Posted
- Attached to
- 2026 Long Line Striping
- Solicitation number
- BID-275-26
- Issued by
- Boulder County, Colorado
About this file
This is a construction notes document issued by the Boulder County Public Works Department Engineering Division for BID-275-26, a 2026 Long Line Striping project. Boulder County Public Works is procuring roadway striping services, which include the removal of old striping and application of new striping to sections of roadway, as well as refreshing of existing roadway striping using specialized pavement marking trucks and marking removal equipment. The contract will terminate on December 31, 2026, with striping activities anticipated to commence after May 31, 2026. Contractors may be required to stripe additional roadways beyond those specified in the solicitation during the 2026 calendar year and must remain available for any additional striping needs through contract expiration. Valmont Road striping is planned for completion in September 2026 and involves the removal of all edge lines, center lines, and lane markings between 55th Street and 61st Street, with removal of edge lines between 61st and 75th Street, followed by installation of new markings with all lanes standardized to 11 feet in width, subject to county project manager approval.
New striping on chip seal roads shall not commence until the chip seal has been applied and striping has received approval from the county's project manager. No additional information regarding pricing terms, set asides, incumbents, funding sources, or other salient contract details is provided in this document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PUBLIC WORKS DEPARTMENT
ENGINEERING
2525 13th Street • Boulder, Colorado 80304 • 303-441-3200 Mailing Address: P.O. Box 471 • Boulder, Colorado 80306
Claire Levy Marta Loachamin Ashley Stolzmann
County Commissioner County Commissioner County Commissioner
Long Line Striping Construction Notes
1. The contract will end on December 31, 2026.
2. Contractor may be asked to stripe additional roadways not listed in this solicitation within the 2026 calendar year. It is expected that the contractor will be available for any additional striping needed until the contract expires.
3. Striping activities are not anticipated to start until after May 31st, 2026.
4. “Chip Seal Striping” roads shall not be striped until the chip seal has been applied to that road and striping has been approved by the county’s project manager.
5. Valmont Road Striping Notes:
a. Striping planned to be completed in September/2026.
b. All edge lines, center lines, and lane lanes on Valmont Rd between 55th St and 61st St shall be removed.
c. All edge lines between 61st and 75th St shall be removed.
d. New edge lines, center lines, and lane lanes shall be laid out by the contractor and approved by the county’s project manager.
e. All lanes on Valmont shall be 11 feet in width.