This is an Abstract of Offers (Optional Form 1419) documenting five bids received for solicitation 70Z08825B0000069, a maintenance dredging project at U.S. Coast Guard Moorings Tongue Point in Astoria, Oregon. The bids were opened on February 20, 2025 at 1:00 PM PST.

The project scope includes mobilization/demobilization, dredging to -10.00 ft MLLW with 2 ft overdepth allowance for 25,000 cubic yards, and pre/post-dredge hydrographic surveys and reports. Total bids ranged from $874,500 (HME) to $2,499,685.52 (Reagent World), with other bidders including Bergerson ($1,596,660), Camenzind ($2,228,500), and Duwamish ($2,315,000). The government estimate was $1,294,429. Unit pricing varied significantly among bidders, particularly for mobilization/demobilization (ranging from $350,000 to $1,330,000) and dredging costs per cubic yard (ranging from $20.00 to $73.99).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

7A.

ITEM

NO.

7B. DESCRIPTION OF OFFERED ITEM 7C. EST.

QUANTITY

D.

UNIT

E. UNIT PRICE F. ESTIMATED

AMOUNT

D. UNIT PRICE D. UNIT PRICE

MOBILIZATION AND DEMOBILIZATION FOR

MAINTENANCE DREDGING AT THE U.S. COAST

GUARD (USCG), STATION CAPE

DISAPPOINTMENT

1 JB $739,429.00 $732,429.00 $350,000.00 $762,500.00

DREDGING AND DISPOSAL: Required Dredging depth is -10.00 ft mean lower low water (MLLW). Two foot of Over-depth is authorized to -12.00 ft

25000 CY $20.00 $500,000.00 $20.00 $32.00

3 HYDROGRAPHIC SURVEYS (Pre & Post) 2 EA $24,000.00 $48,000.00 $7,500.00 $14,230.00

4 PRE AND POST DREDGE REPORTS 2 EA $7,000.00 $14,000.00 $4,750.00 $2,850.00

5 $0.00

6 $0.00

7 $0.00

8 $0.00

9 $0.00

10 $0.00

11 $0.00

12 $0.00

TOTAL $1,294,429.00

NOTE: APPARENT LOW RANKING SHOWN PRIOR TO

CONTRACTING OFFICER MAKING A DETERMINATION

OF RESPONSIBILITY.

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is usable

NOTE: If more than two offers are received, continue on OF 1419A. OPTIONAL FORM 1419 (11-88) updated 10/27/16

$0.00

$874,500.00 $1,596,660.00

$0.00 $0.00

$0.00 $0.00

$0.00 $0.00

$0.00

$0.00 $0.00

$0.00 $0.00

$9,500.00 $5,700.00

$0.00 $0.00

$0.00 $0.00

$350,000.00 $762,500.00

$500,000.00 $800,000.00

$15,000.00 $28,460.00

NO. 1

C. AMENDMENTS ACKNOWLEDGED: C. AMENDMENTS ACKNOWLEDGED:

E. ESTIMATED

AMOUNT

E. ESTIMATED

AMOUNT

6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT

(Including Profit)

MAINTENANCE DREDGING AT THE U.S. COAST GUARD

MOORINGS TONGUE POINT-ASTORIA, OR.-PSN 6049804

B. REASONABLE CONTRACT

(Without Profit)

B. BID SECURITY : Included B. BID SECURITY : Included

A. OFFEROR

HME

A. OFFEROR

BERGERSON

8. GOVERNMENT ESTIMATE

(Check A, B or C and complete D, E, and F)

9. OFFERS

NO. 2

A. HIRED LABOR

5. PROJECT TITLE

I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

NAME AND TITLE OF CERTIFYING OFFICIAL (Type)

SIGNATURE DATE SIGNED

4. ISSUING OFFICE

Civil Engineering Unit Oakland (CN) 1301 Clay Street 7th Floor, Suite

700N Oakland, CA 94612-5203

Travis Cohen

ABSTRACT OF OFFERS - CONSTRUCTION PAGE1. SOLICITATION NUMBER

70Z08825B0000069

2. DATE ISSUED

1/17/2025

3. DATE OPENED

2/20/25 @ 1:00 PM PST

A. ITEM

NO.

B. ESTIMATED

QUANTITY

C.

UNIT

D. UNIT PRICE D. UNIT PRICE E. ESTIMATED

AMOUNT

D. UNIT PRICE E. ESTIMATED

AMOUNT

1 1 JB 1,330,000.00 1,200,000.00 $ 1,200,000.00 499,950.40 $ 499,950.40

2 25000 CY $ 35.00 $ 40.00 $ 1,000,000.00 $ 73.99 $ 1,849,750.00

3 2 EA $ 10,250.00 $ 47,500.00 $ 95,000.00 $ 37,496.28 $ 74,992.56

4 2 EA $ 1,500.00 $ 10,000.00 $ 20,000.00 $ 37,496.28 $ 74,992.56

5 0 0 $ - $ -

6 0 0 $ - $ -

7 0 0 $ - $ -

8 0 0 $ - $ -

9 0 0 $ - $ -

10 0 0 $ - $ -

11 0 0 $ - $ -

12 0 0 $ - $ -

TOTAL $ 2,315,000.00 $ 2,499,685.52

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition is usable

OPTIONAL FORM 1419A (11-88)

PAGE

INSTRUCTIONS Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on a construction project. Each Continuation Sheet will accommodate 13 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 13 and attach additional continuation Sheets (OF

1419A) as needed.

4. OFFERS (Continued)

NO.: 3 NO.:4 NO.:5 NO.:6

1. SOLICITATION NUMBER

70Z08825B0000069

2. PROJECT TITLE

Replace Heater and Control at MAINTENANCE DREDGING

AT THE U.S. COAST GUARD

MOORINGS TONGUE POINT-

ASTORIA, OR.-PSN 6049804

ABSTRACT OF OFFERS - CONSTRUCTION

CONTINUATION SHEET

A. OFFEROR A. OFFEROR

$ - $ 1,330,000.00

$ 875,000.00

E. ESTIMATED

AMOUNT

D. UNIT PRICE E. ESTIMATED

AMOUNT

$ 2,228,500.00

$ 20,500.00

$ 3,000.00

3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED: C. AMENDMENTS ACKNOWLEDGED: C. AMENDMENTS ACKNOWLEDGED:

A. OFFEROR A. OFFEROR

B. BID SECURITY : Waived B. BID SECURITY: Waived B. BID SECURITY: Waived B. BID SECURITY: Waived

CAMENZIND DUWAMISH REAGENT WORLD

C. AMENDMENTS ACKNOWLEDGED:

2025-02-20T18:42:34-0800
COHEN.TRAVIS.CLARK.1282778943

File details come from the government source that posted it. Updated .