This document is Addendum No. 1 to Request for Proposal (RFP) 7-B164-P-00002-00 issued by Argonne National Laboratory, a U.S. Department of Energy facility managed by UChicago Argonne, LLC, dated November 3, 2026. The addendum modifies the Rapid Response Department Site Wide General Construction Blanket Purchase Agreement (BPA) solicitation. The BPA seeks qualified construction contractors for general construction services at Argonne National Laboratory's Building 201 facility located at 9700 South Cass Avenue, Lemont, Illinois 60439. The estimated contract value is $500,000 to $4 million annually per award, with approximately 50 task orders anticipated per year. Argonne anticipates making two BPA awards. The BPA base year ceiling is established at $4 million, with option years available through 2030. Contractors must provide fully burdened hourly labor rates (including bond costs), equipment rental rates, and a markup percentage for subcontractor costs and third-party equipment rentals. Labor rates are fixed across all contract periods with no adjustments permitted for prevailing wage increases. Equipment rates follow a base and option year schedule.

Contractors must provide $4 million performance bonds and $4 million payment bonds covering the full BPA amount at time of award, to remain in force for the contract duration. Key personnel requirements include a Project Manager, Superintendent, Corporate Safety Manager, and On-Site Environmental, Safety & Health (ES&H) Representative, all with substantial laboratory or equivalent-facility experience; these are minimum qualifications for technical acceptability. Personnel may be engaged through consulting or subcontracting arrangements subject to Argonne approval. Contractors must maintain continuous emergency response capability for construction work and provide dedicated ES&H coverage during all on-site construction activities. Formal prequalification is not required to submit a proposal but may be completed during pre-award evaluation. The addendum clarifies pricing submission requirements, confirms labor rate schedule applicability, addresses Davis-Bacon wage determination compliance, and provides responses to 19 contractor questions regarding bonding, contract value, prequalification, pricing formats, insurance, material cost recovery, retainage administration, staffing requirements, and Illinois sales tax exemption procedures. Argonne-specific safety forms will be furnished after award.

View the file

Other files

File Type Posted
RFP 7-B164-P-00002-00 (RR GC BPA).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U. S. Department of Energy laboratory managed by UChicago Argonne, LLC

November 3, 2026

TO ALL PROSPECTIVE OFFERORS:

Subject: Rapid Response Department Site Wide General Construction Blanket Purchase

Agreement (BPA)

Request for Proposal (RFP) No. 7-B164-P-00002-00

Addendum No. 1

Attached herewith for your information and use in preparing your proposal for subject project is one (1) copy of Addendum No. 1.

Kindly acknowledge receipt of this Addendum by signing and returning one (1) copy of this letter.

Please e-mail acknowledgement to Procurement at nhitzler@anl.gov.

Sincerely, Nicholas Hitzler

Procurement Specialist 2

Procurement Department

Receipt Acknowledged:

Company:

By:

cc: File

CF

Nicholas Hitzler Procurement Specialist 2

Financial Management and

Procurement Services Procurement Department

Argonne National Laboratory

9700 South Cass Avenue, Bldg. 201 Lemont, IL 60439

(630)252-6804 nhitzler@anl.gov mailto:nhitzler@anl.gov

ADDENDUM NO. 1

TO

REQUEST FOR Proposal (RFP) 7-B164-P-00002-00

FOR

Argonne National Laboratory

BLDG. 201 OCF

9700 S. Cass Ave.

Lemont, IL 60439

11/03/2026

This addendum is being issued to modify the subject Proposal (RFP) as follows:

I. Clarifications:

1. Please do not modify the proposal spreadsheet (Enclosure No. 7) in any way. The offeror need only populate values in columns C, D, E, and F of the Labor Rates tab, columns C, D, and E of the Equipment Rates tab, and cell S14 of the Equipment

Rates tab for proposed markup.

2. Equipment rates shall not include an operator.

II. RFI and Responses:

1. Contractor Question:

Bonding Requirements: Please confirm whether the $4 million performance bond and $4 million payment bond are required against the full BPA at award, regardless of individual task order size, and whether any alternative bonding arrangements are permissible.

ANL Response:

Per Appendix A, Argonne Terms and Conditions for Fixed-Price Construction Contracts, the amount of the payment bond and performance bond shall be $4,000,000.00. The bonds shall be in force for the duration of the contract.

2. Contractor Question:

Contract Value: Does the estimated $500,000–$4 million potential represent annual BPA volume or the entire agreement term? Additionally, is the estimated 50 annual task orders across both BPA holders or per contractor?

Value estimates are per year and per award.

3. Contractor Question:

Prequalification: We recently submitted Argonne's Construction Contractor

Prequalification Questionnaire. Is formal prequalification approval required before proposal submission, or may the process be finalized before contract award?

Formal pre-qualification is not required in order to submit a proposal.

4. Contractor Question:

Pricing: Please confirm whether Appendix E pricing schedules and Enclosure 7 Proposal

Form establish the required pricing format and evaluation basis.

Values entered on Enclosure No. 7 will ultimately be used to populate Appendix E-1 and

E-2 and will be incorporated into any resulting award.

5. Contractor Question:

Please provide a document outlining the insurance requirements for the contractors.

Please see RFP section 6. INSURANCE for details.

6. Contractor Question:

The labor pricing schedule contains four date ranges, while equipment pricing uses three annual periods. The labor worksheet also identifies estimated hours per year, including periods shorter than twelve months.

Are the estimated labor quantities intended to apply in full to each date range for evaluation purposes, or should they be prorated for the partial-year periods?

The hourly rate schedule date ranges correlate with generally accepted union wage adjustments. Equipment rates follow a base and option year schedule as no mid-year adjustments are required. Hours identified on the proposal form are estimates only and provide a weighted metric for proposal comparison purposes.

7. Contractor Question:

Appendix E-2 establishes a proposed markup for subcontractor costs and third-party equipment rentals. However, we were unable to identify a separate pricing field or clearly stated markup method for purchased construction materials.

How should contractors calculate and recover material purchasing, handling, delivery, and associated costs when preparing individual task-order estimates?

Please see updated language on revised Appendix E-1, E-2, and Enclosure No. 7.

8. Contractor Question:

Appendix F provides the applicable 2026 Davis-Bacon wage determination, while the proposed agreement may extend through 2030.

If applicable prevailing wages or fringe-benefit requirements increase beyond the rates anticipated when the proposal is submitted, will corresponding adjustments to established labor billing rates be permitted during the base and option years?

Proposed labor rates for all periods are fixed.

9. Contractor Question:

The solicitation requires a $4 million performance bond and a $4 million payment bond for the duration of the BPA.

Please confirm whether each bond must cover the full BPA amount at award or whether

Argonne would consider an alternative bonding arrangement based on individual task orders or cumulative outstanding work.

The bonds must cover the full amount at the time of award.

10. Contractor Question:

Appendix E-1 states that hourly rates include bond costs, while Appendix A, Clause

16(e), provides for reimbursement of documented performance and payment bond premiums.

Could you clarify how contractors should account for these costs in their proposed hourly rates to avoid duplication while ensuring compliance with the contract?

As stated in Appendix E-1, hourly rates are to be fully burdened, including bonds.

11. Contractor Question:

The solicitation references approximately 50 task orders annually and estimated aggregate potential of $500,000 to $4 million per BPA.

Does the estimated dollar range represent annual anticipated volume or the aggregate potential over the full agreement term? Also, are the approximately 50 annual task orders expected across both BPA holders or per contractor?

Additionally, when will the estimated maximum ceiling for the base year, currently shown as TBD in the sample agreement, be established?

Estimates are per year and per award. The estimated maximum ceiling for the base year is $4 million and will be populated as such in the final executed award.

12. Contractor Question:

Appendix A allows retainage of up to 10% on progress payments.

For this BPA, will retainage be administered and released separately upon completion and acceptance of each individual task order, rather than being held through the full BPA period?

Any retainage withholding will be on a task order basis.

13. Contractor Question:

Enclosure No. 4 identifies substantial laboratory or equivalent-facility experience for the

Project Manager, Superintendent, Corporate Safety Manager, and On-Site ES&H

Representative.

Are the listed project experience thresholds minimum qualifications for technical acceptability, or desired attributes used in the technical evaluation?

Additionally, may contractors identify qualified personnel engaged through dedicated consulting or subcontracting arrangements to fulfill the key personnel positions, subject to Argonne's approval?

These are required minimum qualifications for technical acceptability. Yes, subject to

Argonne approval.

14. Contractor Question:

The Statement of Work requires dedicated qualified safety coverage whenever on-site construction activities are being performed.

For multiple simultaneous task orders, must each separate worksite have its own dedicated ES&H Representative?

Also, may an appropriately qualified Superintendent serve concurrently as the On-Site

ES&H Representative when approved by Argonne?

Since a separate ES&H Representative billing category is not clearly identified in

Appendix E-1, should those costs be included in the fully burdened labor rates or separately identified within individual task-order estimates?

Typically, an ES&H representative can oversee multiple smaller/less complex task orders, however for more complete or high risk tasks a dedicated ES&H representative might be required. This is typically specified during the bid/pricing of each task order.

Yes, a qualified Superintendent can serve concurrently, and is usually preferred.

An ES&H representative is an individual identified onsite that is responsible for health & safety of the entire project/task being completed. That person has to be an employee of the General Contractor and is required to be at ANL site when work is being performed, even by a subcontractor. GC Superintendent, Laborer, Carpenter, etc. can be named as the ESH representative. This person can be identified within each individual task-order estimate.

15. Contractor Question:

The Statement of Work requires contractors to respond and staff emergency work within two hours.

Does this requirement apply continuously, including nights, weekends, and holidays, or during defined Laboratory operating periods?

For after-hours emergencies, will previously approved contractor personnel have an established expedited site-access procedure?

Yes, this is a continuous requirement, for emergency work only such as storm repair, or watermain break, etc.

Yes, contractor Superintendent or ESH will have an approved off hours badge for emergency response.

16. Contractor Question:

Article III of the sample BPA states that cumulative change orders shall not exceed 20% of the individual task-order amount.

If unforeseen conditions or owner-directed scope changes require modifications exceeding that threshold, what contractual procedure would Argonne use to authorize the additional work?

Should this circumstance arise, Procurement will confer with the project Technical

Representative to determine the appropriate course of action.

17. Contractor Question:

Is formal approval through Argonne's Construction Contractor Prequalification

Application required before proposal submission, or may the process be completed during the pre-award evaluation?

Also, does the Quality Assurance classification identified in the Contractor Safety

Information Questionnaire establish a minimum acceptable QA level for award?

Pre-qualification is not required to submit a proposal. The Quality Assurance level selected will be evaluated on an individual basis and addressed as needed by ESH with the contractor.

18. Contractor Question:

The Statement of Work and technical specifications reference several Argonne-specific safety documents, including LMS-FORM-P-123-1 and Construction Job Safety Analysis

Form ANL-209C.

We did not identify these templates as separate documents within the downloaded solicitation package.

Could you confirm whether these forms, along with the referenced Construction Project

Health and Safety Plan template, will be furnished after award or are available for prospective bidders to review?

These forms will be furnished after award to the successful offeror(s).

19. Contractor Question:

The solicitation identifies the agreement as exempt from Illinois Occupation and Use

Taxes.

Will Argonne provide exemption documentation for qualifying project material purchases, and should contractor task-order estimates exclude applicable material taxes where the exemption is available?

An Argonne specific Illinois Sales Tax Exemption Certificate can be provided to the successful offeror(s) upon award.

III. Enclosures:

1. Enclosure 1F - Appendix E-1, Hourly Rate Schedule is deleted in its entirety and replaced with Enclosure 1F - Appendix E-1 Hourly Rate Schedule Revision 1.

2. Enclosure 1F - Appendix E-2, Equipment Rate Schedule is deleted in its entirety and replaced with Enclosure 1F - Appendix E-2 Equipment Rate Schedule Revision 1.

3. Enclosure No. 7: Proposal Form dated 10/14/2026 is deleted in its entirety and replaced with Enclosure No. 7 - Proposal Form Revision 1 dated 11/02/2026.

ALL OTHER TERMS AND CONDITIONS OF THE ABOVE REFERENCED RFP

REMAIN THE SAME.