Attachment 2_Amendment 2 to RFQ 75H70427Q00003 (07OCT2026).pdf
PDF 97 KB Posted
- Attached to
- Health Economics Analysis Services
- Solicitation number
- 75H70427Q00003
About this file
This is Amendment 2 to Request for Quotes (RFQ) 75H70427Q00003, issued October 7, 2026, which extends the quote submission deadline from October 9, 2026 to October 14, 2026 at 10:00 AM Eastern Time. The amendment corrects all references to the previous RFQ number 75H70426Q00034 to the current RFQ number and removes all PhD-level requirements. The deliverable timeline for the Final Economic Decision Support Package and Transfer of Code/Workbooks has been accelerated from 52 weeks to 47 weeks after contract date. A duplicate clause 52.207-13 has been deleted from the solicitation.
The contract will be awarded as a firm-fixed-price (FFP) agreement with pricing allocated across priced contract line item numbers (CLINs) for each performance period, with payment earned upon Government written acceptance of each deliverable. Offerors are prohibited from pricing on a level-of-effort or hourly basis. The Government will inspect each deliverable and issue written acceptance or notice of deficiencies within fifteen business days of receipt. The contractor must deliver a transition-out package no later than thirty-five days before contract completion containing all models, workbooks, code, documentation, and assumptions register in a form permitting Government staff to independently rerun and update analyses. Within fifteen days after contract completion, the contractor must sanitize or return all Government data and furnish a written certificate of destruction or return. Technical Exhibit 1 has been revised to reflect the 47-week delivery date, and Option Year deliverables are identified with an asterisk.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 2 to RFQ 75H70427Q00003 October 07, 2026
Amendment 2 to RFQ 7570427Q00003 revises the following:
RFQ:
1. The due date for quotes is changed from October 09, 2026 10:00AM Eastern Time to October 14, 2026 10:00AM Eastern Time.
2. Any reference to 75H70426Q00034 is changed to 75H70427Q00003.
3. Deliverables table:
a. The delivery due date for the Final Economic Decision Support Package and Transfer of code/workbooks is changed from 52 weeks to 47 weeks.
b. Option Year deliverables are identified at asterisk.
4. A duplicate of clause 52.207-13 deleted.
5. Any reference to PhD-level is removed.
PWS:
1. Section 1.6.4 is revised to the following:
The Government will award a firm-fixed-price (FFP) contract. The fixed price shall be allocated across a priced contract line item number (CLIN) for each period, with each deliverable payable against the CLIN upon Government written acceptance of the associated deliverable in Technical Exhibit 1. Offerors shall not price this requirement on a level-of-effort or hourly basis.
2. The last paragraph of Section 1.6.17 is revised to the following:
Deliverable dates in Technical Exhibit 1 shall allow the Government to inspect, and the Contractor to correct, within the period of performance. The final economic decision support package, which constitutes the transition-out package under PWS 1.6.23, is due at 47 weeks after date of contract.
3. Section 1.6.18 Inspection and Acceptance is revised to the following:
The Government shall inspect each deliverable and issue written acceptance or written notice of specific deficiencies within fifteen (15) business days of receipt. Payment of the deliverable is earned upon written acceptance.
4. Section 1.6.23 is revised to the following:
No later than thirty-five (35) days before the end of the period of performance, the Contractor shall deliver a transition-out package containing all models, workbooks, code, documentation, and the assumptions register in a form sufficient for Government staff to rerun and update the analysis without Contractor assistance. Within fifteen (15) days after contract completion, the Contractor shall sanitize or return all Government data in its possession and furnish the Contracting Officer a written certificate of destruction or return.
Amendment 2 to 75H70427Q00003
5. Technical Exhibit 1 is revised to the following:
a. The due date for the Final Economic Decision Support Package and Transfer of
Code/workbooks is changed to 47 weeks after date of contract.
b. Option Year deliverables are identified at asterisk.
File details come from the government source that posted it. Updated .