B05 A2-1 Pre-Proposal Inquiries 1-5.pdf
PDF 193 KB Posted
- Attached to
- Crow Creek Community Sewer Renovation
- Solicitation number
- 75H70125R00010
About this file
This is a Pre-Proposal Inquiries document (Amendment A00002) for the Crow Creek Community Sewer Renovation project (Solicitation 75H701-25-R-00010) issued by the Indian Health Service, Division of Engineering Service. The document contains five contractor questions and IHS approved responses regarding technical aspects of the sewer renovation project.
The inquiries and responses address key project details including: requests for as-built drawings and CCTV footage (which are available in Attachments J09-J11), clarification that concrete encasement is not required where sewer mains run below water mains, typical bypass pumping flow rates of 300 gpd/home, and confirmation that IHS personnel can provide staking and benchmarks with 14 days advance notice. The document also indicates that control point information can be provided to the awardee prior to the notice to proceed. The project is located on the Crow Creek Reservation and assigned project number GP-22-K29.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment of Solicitation Amendment A00002 under Solicitation 75H701-25-R-00010 Crow Creek Community Sewer Renovation
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-25-R-00010
PROJECT:
Crow Creek Community Sewer Renovation
LOCATION: Crow Creek Reservation
PROJECT NO: GP-22-K29
DOCUMENT
OWNER: Shaukat Syed PHONE: 214-767-3934 DOCUMENTS:
DATE: DEPARTMENT: IHS/DES
Item No.
Reference Drawing, Spec, Page COMMENTS POC IHS Approved Response
Amendment A00002 dated 12/02/2024
1. RFP
I would like to put in an official request for the existing as-built drawings and CCTV camera footage referenced on Sheet 2 of 16 of the plan set.
COR
Please see Attachment J09 – 2020 Crow Creek Report, Attachment J10 – 2024 Crow Creek Report and Attachment J11 – CC Community Sewer As-Builts.
2. RFP Water Main intersecting Sewer main near MH-5, MH-7 & MH-8 does not show a concrete encasement. Will this be required? COR
The sewer main runs below the water main, therefore, encasement is not anticipated to be required. Please see Attachment J01 Specification Section 02315 - Excavation, Trenching, and Backfill for information regarding when encasement is required.
3. RFP
Water Services intersecting Sewer Main at several locations. Will these need to be concrete encased?
COR
The sewer main runs below the water main, therefore, encasement is not anticipated to be required. Please see Attachment J01 Specification Section 02315 - Excavation, Trenching, and Backfill for information regarding when encasement is required.
4. RFP For the By-Pass Pumping, is there any approximate flow rates? COR Estimation of 300 gpd/home is typical.
5. RFP Will any alignment data/control data be provided? There is none listed in the plans. COR
Per Attachment J01 Specification Section 01720 - Staking and Construction Surveying, IHS personnel can set stakes and benchmarks that correspond with the plan set. The project engineer needs to be notified at least 14 calendar days in advance of any requested staking. Please see Attachment J01 Specification Section 01720 for more information.
At the request of the awardee, control point information can be provided prior to the notice to proceed.