Amendment 5 Zuni RFI Responses 1-26.pdf
PDF 134 KB Posted
- Solicitation number
- 75H70125R00008
About this file
This is a questions and answers (Q&A) document containing 26 technical questions and responses related to the Zuni-Ramah Emergency Power Supply System (EPSS) Replacement project at the Zuni Comprehensive Community Health Center. The questions primarily focus on electrical specifications, including panel schedules, power risers, generator requirements, and equipment installation details.
Key technical specifications revealed in the responses include: the generator must be capable of 96 hours continuous operation, the existing fuel tank capacity is 5,000 gallons, power outages are limited to 1 hour maximum for main power, and work is preferred after hours or on weekends. The contractor is responsible for equipment disposal, RMCE will provide arc flash labels for contractor installation, and lightning protection systems must be recertified. Questions were due by 1/7/2025, with project proposals due by 1/17/2025 at 2:00 PM Pacific Time. The document includes references to amendments 2 & 3 for as-built drawings and existing electrical plans that can be obtained from the COR.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A B C Number Question Response
1 Electrical equipment suppliers are requesting panel schedules for the new panels in the oneline drawing. Will you provide those schedules?
See existing drawings. Existing building plans can be requested from the COR, Thomas
2 Panel LL , 15kv xfmr “TL” Panel PL are showing SPD device added. Is conduit/conductor designation #310 and #44 to be added to the installation? Same for Panel LF, xfmr TJ, panel PJ via 36,41?New feed to LJ #41?
All of that is new. SPD is to be provided in all panelboards and MCCs.
3 Please clarify the amendments to the power riser. Is this information or new installation? Question is unclear. Clarification requested from contractor on 1/17/2025.
4 On "One Line Diagram" some panels named "LL, PL, PJ & LJ" are shown in bold which are figured to be new but their schedule is not given. Can these be provided?
See existing drawings. Existing building plans can be requested from the COR, Thomas
5 Panel LA, LC, LK, LF, EMC1 & EMC2 are not shown on plans but their feeders shown on riser.
� �Also it is not clear if these are exis ng panels or not. As of now we figured these as exis ng �panels. Please Specify whether exis ng or to be installed.
Equipment is new. See construction sequencing on sheet A0.1.
6 There are 4 panel boards on the one line that do not have schedules See existing drawings.
7 The emergency power scheme is pretty complete, including a generator and multiple ATS's. To quote this, we need the panel schedules and the specifications. Please provide the MCC specs too.
See existing drawings. See book specifications provided.
8 I also noticed that the scale of ¼’’ =1’ does not look correct. I used 3/32’=1’ can you verify the scale?
Which drawing appears to be scaled incorrectly? Response requested from contractor on 1/17/2025.
9 I anticipate most conduit will be installed underground. Some conduits can be installed overhead to and from the existing equipment. Are there any pictures of this room available?
Ceiling?
Please see the attached photographs of our site visit from 9/23/2022
10 Is there an as built electrical sheet showing all the electrical panels? See amendments 2 & 3 11 Is there a Lead / Asbestos Survey available? Yes, both will be sent to Thupten Tsering for dissemination on 01/17 12 How long can any portion of the electrical system be offline? No more than1 hour, for main power; prefer work to be done after hours or weekend.
13 Who will be responsible for fueling the temporary generator when contractor is not on site? The Service Unit's Maintenance personnell will do provide this service when contractor is not on site.
14 Has the existing fuel tank been tested and certified recently for this use? Yes.
15 What is the total fuel capacity of the existing tank? 5,000 gallons.
16 How many total running hours will the generator be required to continuously run? 96 hours, per SECTION 263213.13 ‐ DIESEL‐ENGINE‐DRIVEN GENERATOR SETS; Part 2.3 (page
323 of the PDF) specifies a Class 96 EPSS according to NFPA 110.
17 Is there currently a leak detection of the existing tank and underground piping? Yes,.
18 When was the last time the generator was tested? Wednesday, January 8, 2025 19 If it was tested how long was did the generator run? 1 hour.
20 If gen‐set was tested was it under load? 30% load.
21 Will the existing lightning protection system need to be recertified after cable has been removed?
Yes.
22 If so, will a Master Table or UL labeling be required? Yes.
23 Will the electrical contractor be responsible for providing and installing arc flash labels? RMCE is to provide labels. Contractor is to install them.
24 Who will be responsible for the recycling/ disposal of the existing generator when removed? The contractor is responsible for disposal as per section 017419 of the spec book.
25 Is it possible to get a copy of the electrical as‐builts? See amendments 2 & 3 26 L.3. INQUIRIES states that questions are due “no later than 10 days prior to proposal due date.” Are these calendar days or working days?
RFI's due 1/7/2025