MEASUREMENT AND PAYMENT FOR BID SCHEDULE LINE ITEMS
MOBILIZATION AND DEMOBILIZATION
Payment for transportation of equipment, material, and personnel to and from the job site location (regardless of trips required), required permits and fees, taxes, and all other necessary items to complete the work.
REPLACEMENT 2HP SUBMERSIBLE WELL PUMP (Goulds 10GS20 or equal)
Payment for the replacement submersible well pump shall be made at the contract lump sum price for the size of pump listed. Compensation shall include removal and replacement of the pump, motor, pump control box and all other necessary items for a complete and operational installation. Compensation shall include proper disposal of removed equipment.
REPLACEMENT 1-1/4 INCH SCH 120 PVC DROP PIPE AND SUBMERSIBLE CABLE
Payment for the replacement drop pipe and submersible cable shall be paid for at the contract unit price for the size and type of pipe listed based on the number of linear feet installed. Compensation shall include removal and replacement of the drop pipe, check valve, adapters, torque arrestor, submersible cable, safety line, and all other necessary items for a complete and operational installation. Compensation shall include proper disposal of removed equipment.
REPLACEMENT 6-INCH WELL CAP
Payment for the replacement well cap shall be made at the contract lump sum price. Compensation shall include removal and replacement of the well cap, seal, vent, conduit, and all other necessary items for a complete and operational installation. Compensation shall include proper disposal of removed equipment.
REPLACEMENT PRESSURE SYSTEM (Amtrol WX255 or equal 80 gallon tank)
Payment for the replacement pressure system as specified in Detail Drawing shall be made at the contract lump sum price. Compensation shall include removal of the existing pressure tank, piping, equipment, and controls;
and replacement pressure system as specified in the Detail Drawing. The replacement pressure system shall include the pressure tank, pump disconnect, pressure gauge, pressure switch, pressure relief valve, miscellaneous electrical and plumbing fittings, electrical inspection, and all other necessary items for a complete and operational installation. Compensation shall include proper disposal of removed equipment.
1-1/2 INCH HDPE SDR 7 WATER SERVICE LINE
Payment for water service line as specified in Detail Drawing shall be made at the contract unit price for the size of line listed based on the number of linear feet installed. Compensation shall include excavation, backfilling and compaction; resurfacing trenched areas to equal or better condition than existing; locating and connecting to existing service lines; leak testing; and all other necessary items for a complete and operational installation.
4-INCH SCH 80 PVC ENCASEMENT PIPE FOR WATER SERVICE LINE
Payment for encasement pipe installed for water service lines in open cut road crossings shall be made for the size of pipe listed based on the number of linear feet installed. Compensation shall include the encasement pipe and all other necessary items required for a complete installation.
GRAVEL RESURFACING
Payment for gravel resurfacing of roads, driveways, parking lots, etc., shall be made at the contract unit price based on the volume of gravel in cubic yards measured in place. Compensation shall include the required preparation, gravel, compaction, and other incidentals. Compensation shall be made only for that gravel placed with prior approval and at a minimum thickness of 3-inches to complete the work in accordance with the plans and specifications. No payment shall be made for that portion of gravel resurfacing which has not been authorized by the Contract Officer.
FREEZELESS YARD HYDRANT
Payment for the freezeless yard hydrant as specified in Detail Drawing shall be made at the contract unit price for the number of yard hydrants installed. Compensation shall include excavation and backfill, yard hydrant, 3/4-inch brass hose thread on outlet, fittings, connection to water service line, gravel subbase, and all other necessary items for a complete and operational installation.
1-INCH INDIVIDUAL PRV (Watts LF25AUB 10-35 psi or equal) WITH BOX
Payment for the lead free individual pressure reducing valve (PRV) as specified in Detail Drawing shall be made at the contract lump sum price for the size of PRV listed. Compensation shall include adapter fittings, brass pipe, elbows, ball vale, PRV, meter box, non-locking meter box lid, meter box gravel base, and all other necessary items for a complete and operational installation. PRV shall be Watts Lead Free LF25AUB 10-35 psi or equal.