Questions and Responses #2

View the file

Other files

File Type Posted
Questions_and_Responses4.pdf PDF
Questions_and_Responses3.pdf PDF
Questions_and_Responses.pdf PDF
Solicitation_Notice__AE_Bldg_28.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Responses for 75D301-18-R-67933

Question 12: Will responses to our questions and other questions be posted on public procurement website for everyone to review?

Response 12: Questions and responses to date were posted on the website about 30 minutes ago. (NOTE: This response was emailed on 9/26/2018. In addition, questions and responses were posted on Wednesday, September 26, 2018).

Question 13: Architectural firms professional liability insurance will not allow us to carry a rock blasting consultant. This would be typical for all responders. Is the intent for CDC to contract directly with this consultant? And/or ask the Construction Manager as Constructor (CMc) to carry it as part of their pre-construction services?

Response 13 is a three part response:

13a. Architectural firms professional liability insurance will not allow us to carry a rock blasting consultant. This would be typical for all responders. 13a. (CDC Response) A rock blasting consultant serving as part of the AE team will be a contractual requirement.

13b. Is the intent for CDC to contract directly with this consultant? 13b. (CDC Response) No 13c. And/or ask the Construction Manager as Constructor (CMc) to carry it as part of their pre-construction services? 13c. (CDC Response) CMc scope of work will be addressed separately from AE scope of work.