756-21-100_VAEP_Water Booster Pump - Addendum_001_Drawings.pdf
PDF 20 MB Posted
- Solicitation number
- 36C25725B0010
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
APPROVING OFFICIAL:
ANGEL R. MORALES, COR
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
A/E:
OEI-LBL Joint Venture LLC
2340 E. Trinity Mills Rd. Ste 220
Carrollton, TX 75006
O'Brend Engineering Inc., Managing Partner
972-233-2288
1O'Brien Engineering, Inc.
Carrollton, TX 75006
972-233-2288
2340 E. Trinity Mills Rd. Ste 220 www.obrieneng.com
A/E:
www.obrieneng.com
GI001
COVER SHEET WATER BOOSTER PUMP
STATIONS
EL PASO, TX
756-21-100
11/03/2023 KL CH
ISSUE FOR
CONSTRUCTION
11/03/2023
WATER BOOSTER PUMP STATIONS : 756-21-100
EL PASO, TEXAS
EL PASO VA HEALTHCARE SYSTEM
SHEET INDEX
SHEET NUMBER SHEET NAME
00_GENERAL
GI001 COVER SHEET
GI002 ABBREVIATIONS, SYMBOLS AND NOTES
GI003 ARCHITECTURAL SITE PLAN
07_STRUCTURAL
SS001 GENERAL NOTES & SPECIAL INSPECTIONS
SS002 SPECIAL INSPECTIONS NOTES
SS201 FOUNDATION PLAN AND DETAILS
08_ARCHITECTURAL
AS101 FLOOR PLAN, REFLECTED CEILING PLAN & ROOF PLAN
AS201 EXTERIOR ELEVATIONS / BUILDING SECTIONS / DETAILS
11_PLUMBING
P001 COVER SHEET - GENERAL NOTES
P002 GENERAL NOTES
P003 SYMBOLS & LEGENDS
PD102 OVERALL PLUMBING DEMOLITION PLAN
PD301 PLUMBING DEMOLITION SECTIONS
PD401 ENLARGED PLUMBING DEMOLITION PLAN
PP102 PLUMBING PLAN - SECOND FLOOR
PP301 PLUMBING SECTIONS
PP401 PLUMBING ENLARGED PLANS
PP501 PLUMBING DETAILS
PP502 PLUMBING BOOSTER PUMP DETAILS
ISSUE FOR CONSTRUCTION
SHEET INDEX
SHEET NUMBER SHEET NAME
13_MECHANICAL
M001 COVER SHEET - SHEET INDEX & GENERAL NOTES
M002 GENERAL NOTES, SYMBOLS, LEGENDS & ABBREVIATIONS
MH101 OVERALL MECHANICAL HVAC PLAN
MH401 MECHANICAL HVAC ENLARGED PLANS
M501 MECHANICAL DETAILS
MI601 MECHANICAL INSTRUMENTATION SCHEDULES
14_ELECTRICAL
E001 COVER SHEET - GENERAL NOTES & SHEET INDEX
E002 GENERAL NOTES
E003 SYMBOLS & LEGENDS
ED101 ELECTRICAL DEMOLITION PLAN - FIRST FLOOR
ED102 ELECTRICAL DEMOLITION PLAN - SECOND FLOOR
ED401 ELECTRICAL DEMO ENLARGED PLANS
ED402 ELECTRICAL DEMO ENLARGED PLANS
ED403 ELECTRICAL DEMO ENLARGED PLANS
EP102 ELECTRICAL POWER PLAN - SECOND FLOOR
EP402 ELECTRICAL POWER ENLARGED PLAN - SECOND FLOOR
EP601 SCHEDULES & DIAGRAMS
EP602 SCHEDULES & DIAGRAMS
Revisions: Date:
Revision 1 - Addendum 001 11/03/2023
0 COLUMN GRID LINE
DOOR NUMBER
SYMBOL
DETAIL - SECTION
POSITION ON SHEET
SHEET NUMBER
DETAIL - PLAN/ RCP
POSITION ON SHEET
SHEET NUMBER
WALL SECTION
POSITION ON SHEET
SHEET NUMBER
EXTERIOR ELEVATION
POSITION ON SHEET
SHEET NUMBER
INTERIOR ELEVATION
POSITION ON SHEET
SHEET NUMBER
EXTERIOR WALL TYPE TAG
EXTERIOR WINDOW
SIGN TYPE, SEE SIGNAGE
SCHEDULE
DRAWING NUMBER
DRAWING SCALE
VIEW TITLE
NOTES BY NUMBER
DRAWING REVISION
LEVEL DATUM
LEVEL NAME
LEVEL ELEVATION
NORTH ARROW
INTERIOR WINDOW
GRAPHIC SCALE
0 4'-0" 8'-0" 16'-0"
-G D
XX
XX
XXXX
7'-0" R 3'-11"
100°
SIM
X
X-XXX
DIMENSION TO FACE OF FINISH,
FACE OF CONCRETE, COLUMN
CENTERLINE, OR AS NOTED.
CENTERLINE
X
X X
X
A1
A101
SIM
A101
SIM
ROOM TAG (FOR SPECIALTY PLANS)
ROOM NAME
ROOM NUMBER
FLOOR FINISH
ROOM NAME
XXXX
FLOR
BASE
WALL
CEIL BASE TYPE
WALL FINISH
CEILING TYPE
A
A101
SIM
Name Elevation
1/8" = 1'-0"
AC1
N
INTERIOR PARTITION TYPE TAGA3
ROOM NAME
150 SF
ROOM NAME
ROOM NUMBER
ROOM AREA
ROOM TAG (FOR STANDARD PLANS)
BUILDING SECTION
POSITION ON SHEET
SHEET NUMBER
A101
SIM
BATT. INSULATION
CAST IN PLACE CONCRETE
CAST STONE
CONCRETE MASONRY/CMU
EARTH IN SECTION
FACE BRICK
GYP./GYPSUM BOARD
MARBLE
PARTICLE BOARD/PLYWOOD
ROOF INSULATION
STUCCO
CONTINUOUS WOOD BLOCKING
DISCONTINUOUS WOOD BLOCKING
FINISHED WOOD
OWNER
ARCHITECT
O'BRIEN ENGINEERING, INC.
CONTRACT OFFICER REPRESENTATIVE
ANGEL R. MORALES, COR
EL PASO VA HEALTH CARE SYSTEM
STRUCTURAL ENGINEER
R.L.WOODS & ASSOCIATES (RLWA)
MECHANICAL, PLUMBING, AND
ELECTRICAL ENGINEER
O'BRIEN ENGINEERING, INC.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
APPROVING OFFICIAL:
ANGEL R. MORALES, COR
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
A/E:
OEI-LBL Joint Venture LLC
2340 E. Trinity Mills Rd. Ste 220
Carrollton, TX 75006
O'Brend Engineering Inc., Managing Partner
972-233-2288
1O'Brien Engineering, Inc.
Carrollton, TX 75006
972-233-2288
2340 E. Trinity Mills Rd. Ste 220 www.obrieneng.com
A/E:
www.obrieneng.com
GI002
ABBREVIATIONS, SYMBOLS AND
NOTES
WATER BOOSTER PUMP
STATIONS
EL PASO, TX
756-21-100
11/03/2023 KL CH
ISSUE FOR
CONSTRUCTION
11/03/2023
DRAWING LEGENDABBREVIATIONS
ACT. ACTUAL
ADJ. ADJUSTABLE
A.F.F. ABOVE FINISH FLOOR
A.F.S. ABOVE FINISH SLAB
AGG. AGGREGATE
AHJ AUTHORITY HAVING JURISDICTION
ALUM. ALUMINUM
BLDG. BUILDING
BK. BRICK
BM. BEAM
CAB. CABINET
CPT. CARPET
C.J. CONTROL JOINT
CENTERLINE
CG CORNER GUARD
CLG. CEILING
COL. COLUMN
CONC. CONCRETE
COND. CONDITION
CONT. CONTINUOUS
C.T. COUNTERTOP
DBL. DOUBLE
DEMO. DEMOLITION
DIA. DIAMETER
DIM. DIMENSION
DISP. DISPENSER
DN. DOWN
DWG. DRAWING
E.W.C. ELECTRIC WATER COOLER
EA. EACH
E.J. EXPANSION JOINT
EXP. EXPANSION
E.W. EACH WAY
EXT. EXTERIOR
EXIST. EXISTING
F.E.C. FIRE EXTINGUISHER CABINET
F.D. FINISH DIMENSION
F.D.V.B. FIRE DEPARTMENT VALVE BOX
F.F. FINISH FLOOR
FIN. FINISH(ED)
FRT. FIRE RETARDANT TREATED
G.I. GALVANIZED IRON
G.B./GYP.BD. GYPSUM BOARD
GA. GAUGE
GALV. GALVANIZED
GL. GLASS
H.M. HOLLOW METAL
H.S. HORIZONTAL IN SPLASH
I.C.U. INTENSIVE CARE UNIT
INT. INTERIOR
INSUL. INSULATION
I.T.C. INSTALLED THIS CONTRACT
K.S. KNEE SPACE
LAM. LAMINATED
LAV. LAVATORY
L.L.V. LONG LEG VERTICAL
L.L.H. LONG LEG HORIZONTAL
MANUF. MANUFACTURER
MAX. MAXIMUM
MECH. MECHANICAL
MIN. MINIMUM
M.O. MASONRY OPENING
MTL./MET. METAL
MNT. MOUNTED
N/A NOT APPLICABLE
NOM. NOMINAL
N.T.S. NOT TO SCALE
N.I.C. NOT IN CONTRACT
O.C. ON CENTER
O.D. OVERFLOW DRAIN
O.H/OPP.H. OPPOSITE HAND
P.D. PLAN DIMENSION
PLAS. LAM. PLASTIC LAMINATE
P.T. PORCELAIN TILE
P.T.D. PAPER TOWEL DISPENSER
RB RUBBER BASE
R./REV. REVISED/REVERSE
R./RAD. RADIUS
REINF. REINFORCE
REF. REFERENCE/REFER TO
REQ'D REQUIRED
R.D. ROOF DRAIN
RM. ROOM
R.O. ROUGH OPENING
SCHED. SCHEDULED
SAB. SOUND ATTENUATION BATTS
SHT. SHEET
SIM. SIMILAR
SL. SLOPE
STL. STEEL
S.S. STAINLESS STEEL
S.S.V. SOLID SURFACE VENEER
SUSP. SUSPENDED
S.V. SHEET VINYL
T.A.S. TEXAS ACCESSIBILITY STANDARDS
T.B. TACK BOARD
T.D.H. TEXAS DEPARTMENT OF HEALTH
TEMP. TEMPERED GLASS
THK. THICK
TOIL. TOILET
TYP. TYPICAL
U.C. UNDER COUNTER
UCR UNDER COUNTER REFRIGERATOR
U.L. UNDERWRITERS LABORATORIES
U.N.O. UNLESS NOTED OTHERWISE
UR. NEW URINAL
VCT VINYL COMPOSITION TILE
V.T. VINYL TILE
VERT. VERTICAL
W.C. NEW WATER CLOSET
WDW. WINDOW
WD. WOOD
WH WATER HEATER
W/ WITH
W/O WITHOUT
MATERIALS LEGEND GENERAL NOTES
1. ALL WORK RELATING TO THIS CONSTRUCTION SHALL COMPLY WITH U.S. DEPARTMENT OF
LABOR, THE OCCUPATIONAL SAFETY AND HEALTH STANDARDS AND ALL RELATED LOCAL AND
FEDERAL BUILDING CODES AND ORDINANCES.
2. DO NOT SCALE THE DOCUMENTS.
3. ALL DIMENSIONS ARE TO BE FIELD VERIFIED AND BACK CHECKED FOR CORRECTNESS. IF ANY
DEVIATIONS OR DISCREPANCIES OCCUR, CONTACT CONTRACTING OFFICER REPRESENTATIVE
(COR) FOR VERIFICATION PRIOR TO PROCEEDING WITH THE WORK.
4. THE GENERAL CONTRACTOR IS TO VERIFY ALL EXISTING CONDITIONS AND DIMENSIONS ON THE
SITE PRIOR TO THE BEGINNING OF THE WORK AND ADVISE THE COR OF ANY AND ALL
DISCREPANCIES.
5. ALL DIMESIONS ON PLANS ARE TO FACE OF FINISHED WALL, METAL PANEL OR CENTER LINE OF
STRUCTURAL COLUMNS.
6. THE GENERAL CONTRACTOR AND ALL SUBCONTRACTORS SHALL CAREFULLY REVIEW THE
DRAWINGS, SPECIFICATIONS DETAILS AND NOTES FOR INFORMATION REGARDING THE SCOPE
OF WORK INTENDED PRIOR TO PROCEEDING WITH THE WORK.
7. THE CONTRACTOR SHALL BE RESPONSIBLE TO COORDINATE ALL MECHANICAL, ELECTRICAL,
AND PLUMBING PENETRATIONS REQUIRED BY THE WORK WHETHER EXPRESSLY NOTED IN THE
DOCUMENTS OR NOT.
8. THE CONTRACTOR SHALL REVIEW THE SOILS REPORT, AND THESE DOCUMENTS (ALL IN THEIR
ENTIRETY) TO INSURE THAT ALL REQUIRED EARTHWORK, PAVING, AND STRUCTURAL SLAB
WORK IS FULLY COVERED IN THE SCOPE OF THE CONTRACTOR'S BID. THE CONTRACTOR SHALL
FULLY COORDINATE ALL OF THE ABOVE REFERENCED WORK WITH THE OWNER'S
REPRESENTATIVE TO INSURE THAT ALL WORK IS FULLLY COORDINATED AND COMPLETED.
9. ALL MATERIALS SHALL BE INSTALLED ACCORDING TO INDUSTRY STANDARDS, ALL AGENCIES OR
"STANDARD" RECOMMENDATIONS REFERENCED IN THE SPECIFICATIONS, OR MANUFACTURER'S
RECOMMENDED INSTALLATION PROCEDURES, WHICHEVER IS THE MOST STRINGENT.
10. THE CONTRACTOR REPRESENTS AND WARRANTS THAT IT HAS EXAMINED THE PLANS,
DRAWINGS, SPECIFICATIONS AND ALL CONSTRUCTION CRITERIA OF THE OWNER AND HAS
SATISFIED ITSELF THAT THE INFORMATION CONTAINED THEREIN IS SUFFICIENT TO FULLY AND
COMPLETELY CONSTRUCT THE PROJECT.
11. IN THE EVENT OF A CONFLICT WITH THE CONSTRUCTION DOCUMENTS, THE MORE EXPENSIVE, GREATER QUALITY, AND LARGER SCOPE SHALL GOVERN.
12. THE CONTRACTOR SHALL PROVIDE ALL NECESSARY BLOCKING IN WALLS / PARTITIONS FOR
THE MOUNTING OF EQUIPMENT, ACCESSORIES, ETC. THAT ARE PROVIDED BY THE
CONTRACTOR OR THE OWNER.
EXISTING METAL BUILDING
EXISTING BUILDING 1
SCOPE OF WORK
AS101
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
APPROVING OFFICIAL:
ANGEL R. MORALES, COR
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
A/E:
OEI-LBL Joint Venture LLC
2340 E. Trinity Mills Rd. Ste 220
Carrollton, TX 75006
O'Brend Engineering Inc., Managing Partner
972-233-2288
1O'Brien Engineering, Inc.
Carrollton, TX 75006
972-233-2288
2340 E. Trinity Mills Rd. Ste 220 www.obrieneng.com
A/E:
www.obrieneng.com
GI003
ARCHITECTURAL SITE PLAN WATER BOOSTER PUMP
STATIONS
EL PASO, TX
756-21-100
11/03/2023 KL CH
ISSUE FOR
CONSTRUCTION
11/03/2023
1/16" = 1'-0"
ARCHITECTURAL SITE PLAN
N
PLAN NORTHACTUAL NORTH
N
FLOOR
FLANGE
FIXED CONNECTION
KIPS
JOISTS
JOINT
INTERMEDIATE
INTERIOR
INSIDE FACE
INSIDE DIAMETER
INFORMATION
HORIZONTAL LOAD
HORIZONTAL
HIGH POINT
HEIGHT
HEADED STUD
GYPSUM BOARD
GRADE BEAM
GRADE
GENERAL
GALVANIZED
GAGE OR GAUGE
FOUNDATION
FOOTING
FINISHED FLOOR
FINISH(ED)
FAR SIDE
FACE TO FACE
EXTERIOR
EXISTING
EXPANSION JOINT
EXPANSION
EQUAL(EQUALLY)
ENGINEER
ELEVATOR
ELEVATION
ELECTRICAL
EACH WAY
EACH FACE
EACH
DRAWING
DOWN
DOWELS
DOUBLE
DIMENSION
DIAMETER
DIAGONAL BRACE
DIAGONAL
DEAD LOAD
DETAIL
COORDINATE
CONSTRUCTION JOINT
CONTINUOUS
CONNECTION(S)
CONDENSING UNIT
CONCRETE MASONRY UNIT
CONCRETE
COMPRESSION
- K.
- INTERM.
- JST(S)
- JT.
- INT.
- I.F.
- I.D.
- INFO.
- GR.
- GYP. BD.
- H.L.
- HORIZ.
- H.P.
- HT.
- H.S.
- G.B.
- GEN.
- GALV.
- GA.
- FDN.
- FTG.
- FL.
- FLG.
- F.C.
WELDED WIRE MESH (FABRIC)
X-BRACING
WORK POINT
WATERSTOP
WITH
WOOD
WIND LOAD
WEIGHT
- XB
- W.P.
- WD.
- W/
- W.L.
- W.W.F.
- WT.
- W.S.
UNLESS OTHERWISE NOTED
TOP OF STRUCTURAL CONCRETE
TOP OF STRUCTURAL STEEL
TRANSVERSE
TOTAL LOAD
TOP OF WALL
VERTICAL
TYPICAL
TOP OF PIER CAP
TOP OF PIER
TOP OF METAL DECK
TOP OF JOIST
TOP OF FOOTING
TOP OF BEAM
TOP & BOTTOM
TONGUE & GROOVE
- T.O.S.C.
- VERT.
- U.N.O.
- TYP.
- TRAN.
- T.L.
- T.O.W.
- T.O.S.S.
- T.O.P.C.
- T.O.P.
- T.M.D.
- T.O.J.
- T.O.F.
- T.O.B.
- T & B
- T & G
- DRWG.
- FIN. FL.
- FIN.
- F.S.
- F/F
- EXT.
- EXIST. ; (E)
- E.J.
- EXP.
- ELEC'L.
- EQ.
- ENGR.
- ELEV.
- EL.
- E.W.
- E.F.
- EA.
- DET.
- DIA. OR
- DN.
- DWL(S)
- DBL.
- DIM.
- D.B.
- DIAG.
- D.L.
- CONN.(S)
- COORD.
- C.J.
- CONT.
- CU
- CMU
- CONC.
- C.
- V.SHEAR
TEMPERATURE
TOP CHORD EXTENSION
SYMMETRICAL
STRUCTURAL
STRUCTURE
THICK
TENSION
SUPPORT
SPECIFICATIONS
SLIP CONNECTION
STIRRUPS
STIFFENER
STEEL
STANDARD
SPACE
SIMILAR
SHEET
- THK.
- TEMP.
- TCX
- SYMM.
- SUPT.
- STRUCT'L.
- STRUCT.
- T.
- STIR.
- STIFF.
- STL.
- STD.
- SPEC.
- SP.
- S.C.
- SIM.
- SHT.
REMAINDER
SAWN JOINT
ROOF DRAIN
ROOF TOP UNIT
RIGID FRAME
SECTION
SCHEDULE
REQUIRED
REINFORCING
PROJECTION
PRECAST CONCRETE
PIPE BRACE
REFER
RADIUS
POINT
PLATE
- REM.
- SECT.
- SCHED.
- S.J.
- R.D.
- RTU
- R.F.
- REQ'D.
- REINF.
- REF.
- RAD.
- PROJ.
- P/C
- PT.
- P.B.
L- P ; PL.
COLUMN
CLEAR
CHANNEL
CENTERED
CENTER LINE
CENTER TO CENTER
CEILING
BUILDING LINE
BUILDING
BRIDGING
BOTTOM CHORD EXTENSION
BOTTOM
BOTH WAYS
BLOCKING
BETWEEN
BEARING
BEAM
BASE PLATE
BACK TO BACK
AIR HANDLING UNIT
AIR CONDITIONER
AT
ARCHITECTURAL
APPROXIMATE
ANGLE
AND
ANCHOR BOLT
ALTERNATE
ADJACENT
ADDITIONAL
ABOVE FIN. FL.
ABBREVIATIONS USED ON STRUCTURAL DRAWINGS
L- BP
L- C
- COL.
- CL.
- C
- CNTRD.
- C/C
- CLG.
- B.L.
- B.W.
- BLDG.
- BRDG.
- BCX
- BOT.
- BLK'G.
- BTWN.
- BRG.
- BM.
- APPROX.
- B/B
- AHU
- A/C
- ARCH'L.
- L
- A.F.F.
- A.B.
- ALT.
- ADJ.
- ADDT'L.
- MIN.MINIMUM
PERPENDICULAR
PENETRATION
OUTSIDE FACE
OUTSIDE DIAMETER
OPPOSITE HAND
OPENING(S)
PERIMETER
OPPOSITE
ON CENTER
NOT TO SCALE
MOMENT CONNECTIONS
MISCELLANEOUS
NEAR SIDE
NUMBER
MOMENT
- PERP.
- PERIM.
- PEN.
- O.F.
- O.D.
- O.H.
- OPP.
- OPNG.(S)
- O.C.
- NO.
- N.T.S.
- N.S.
- M.C.
- MISC.
- M.
LESS THAN OR EQUAL TO
LARGER THAN OR EQUAL TO
LONG LEG VERTICAL
MECHANICAL
MANUFACTURER
MEZZANINE
METAL
MAXIMUM
MATERIAL
LOW POINT
LONG LEG HORIZONTAL
LONGITUDINAL
LIVE LOAD
- LLV
- MEZZ.
- MET.
- MECH'L.
- MAX.
- MAT'L.
- MFR.
- L.P.
- LLH
- LONG.
- L.L.
DEFORMED BAR ANCHOR - DBA.
LONG SIDE VERTICAL - LSV
NEW - (N)
FIELD VERIFY - F.V.
CAMBER - C
1151 W. PIONEER PKWY. (817) 277-6686
ARLINGTON, TX 76013
Texas Registered Engineering Firm F-8284 C 2023 Copyright R. L. Woods & Associates, LLC
Structural and Forensic Engineering
R. L. Woods & Associates, LLC
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
APPROVING OFFICIAL:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
O'Brien Engineering, Inc.
2340 E. Trinity Mills Rd. Ste 220
Carrollton, TX 75006
(972) 233-2288 www.obrieneng.com
Managing Partner
ANGEL R. MORALES, COR
11/03/2023
ISSUE FOR
CONSTRUCTION 1
11-03-2311 /2
/2
1:
:3
P
M
SS001
GENERAL NOTES & SPECIAL
INSPECTIONS
WATER BOOSTER PUMP
STATIONS
EL PASO, TX
756-21-100
RLW BWT
Bar size Class A splice Class B splice
3 16" 21"
4 22" 28"
5 28" 36"
6 32" 42"
7 47" 62"
8 54" 70"
9 61" 79"
10 68" 88"
1. Design loads are as follows:
A. Roof live loads 20 PSF
B. Roof dead loads 6 PSF
C. Floor live loads:
i. Mech'l 100 PSF or equipment loads
D. Equipment loads:
i. Water Booster Pumps 2166 pounds
E. Ground snow loads: 5 PSF
F. Wind pressure: unless noted otherwise, per ASCE 7-16 for:
i. Basic wind speed = 112 mph (Risk Category III).
ii. Exposure C.
iii. Component and cladding wind pressure:
a. Roof zone 1: (+16.0, -43.54) PSF
b. Roof zone 2: (+16.0, -57.38) PSF
c. Roof zone 3: (+16.0, -78.20) PSF
d. Wall zone 4: (+27.35, -29.62) PSF
e. Wall zone 5: (+27.35, -36.57) PSF
G. Seismic design (per ASCE 7):
a. Seismic Risk Category: III.
b. Seismic Importance Factor: 1.25
c. Mapped Spectral Response Acceleration Parameters:
Ss=0.359g
S =0.111g
d. Spectral Response Coefficients: S ds
= 0.362; S di
= 0.174
e. Site Class: D
f. Seismic Design Category: C
g. Seismic Force Resisting System: Concentric Steel Moment Frames
h. Design Base Shear: n/a
i. Seismic Response Coefficient (Cs) = 0.0188
j. Analysis procedure: Equivalent Frame Method
2. Structure was designed in accordance with the International Building Code (IBC), 2021 edition.
3. Consult structural engineer if locations or design weights of roof, floor, and floor supported Mech'l units differ from those indicated on structural plans.
4. All existing conditions shall be field verified.
5. Contractor shall verify all dimensions prior to start of construction.
6. General contractor shall be responsible for coordination of other trades (Mech'l, Elec'l, etc.) Prior to fabrication and installation of materials.
7. General contractor shall be responsible for coordination of architectural and structural drawings prior to fabrication, forming, or placement of materials. General contractor shall report discrepancies immediately to architect and shall proceed with construction only after discrepancy has been resolved.
8. The details designated as "Typical Details" apply generally to the drawings in all areas where conditions are similar to those shown in the details.
1. Building pad shall be as follows:
A. Site preparation shall be in accordance with project geotechnical report. Reference Intertek
Professional Service Industries, Inc. report no. 06252812, dated 04/12/2023, and any supplementary report and letters prepared by the geotechnical company. Specifically reference report section 4.2 for building site preparation.
B. Unless noted otherwise in geotechnical report, the building site and areas to be paved shall be stripped of all topsoil, vegetation, roots, old construction debris, or other organic material.
C. The subgrade shall be firm and able to support the construction equipment without displacement and be compacted as recommended in geotechnical report. Soft or yielding subgrade shall be corrected and made stable before construction proceeds. Any old fill found on the site shall be reworked to provide adequate support for foundations and pavements or shall be removed. The subgrade shall be proof rolled to detect any soft spots, which if exists, shall be reworked, compacted and tested.
D. Contractor shall place a minimum of 1.5 feet, or 8 inches below existing grade, whichever is greater, of select conditioned fill in accordance with section 4.3.1 of geotechnical report. The soils exposed at the base of all excavations should be scarified to a depth of at least 8 inches, moisture conditioned and then compacted prior to placing Engineered Fill above, in accordance with section 4.3.1 of geotechnical report.
E. Compaction testing of controlled fills shall be taken as follows: one field density test per lift, for each 2500 SF of building area, with a minimum of two tests per lift. Each lift shall be compacted, tested, and approved before another lift is added.
2. Design Bearing Pressure at bottom of footings is 3000 PSF.
1. Concrete shall be composed of type 1 Portland Cement (ASTM C150), fine and coarse aggregates
(ASTM C33), fiber mesh additive, and potable water. Fly ash (ASTM C618, class C or F) may replace up to 20 percent of cementitious material. Set altering or water reducing admixtures (ASTM C494) may be used as conditions warrant. Fiber mesh shall be Fibermesh 150 synthetic fiber or equivalent,
2. Maximum water/cement ratio is 0.4 for exposed-to-view building slabs and 0.5 for all other concrete.
3. All concrete shall have a minimum compressive strength of 3500 psi at 28 days.
4. Maximum nominal coarse aggregate size shall be 1” max., unless noted otherwise.
5. Concrete building slabs and grade beams that are exposed to weather shall be air entrained to between 4 and 6%.
6. Unless noted otherwise, concrete slump shall be as follows: 5” max., 3” min.
7. Reinforcing steel shall be ASTM A615 grade 60.
8. Unless noted otherwise, concrete protection for reinforcement shall be as follows:
Grade beams 3” bottom, 2” sides, 1 ½” top
Slabs on grade centered
9. Unless noted otherwise, lap all reinforcing splices as follows:
10.Provide corner bars to match and lap horizontal reinforcement at all grade beam and wall intersections. 30 bar dia. Lap minimum.
11.All reinforcement shall be detailed in accordance with the latest ACI Detailing Manual.
12.Contractor shall coordinate all penetrations, conduit, chamfers and embedded items prior to concrete placement.
1. Structural steel shall conform to AISC “Specification For The Design, Fabrication And Erection Of
Structural Steel For Buildings”, latest edition.
2. Galvanizing of steel members shall conform to ASTM A1236/A123M.
3. All structural steel wide flange shapes shall be ASTM A992 (grade 50). HSS shapes shall be A500
gr. B. Standard pipe shall be ASTM A53, grade B. All other structural steel shall be A36.
4. Welded construction shall conform to the American Welding Society “Structural Welding Code”, D1.1
5. All welding shall be performed by welders certified with the last 12 months.
6. Full and partial penetration welds performed in the field shall be ultrasonically tested.
7. When welds are not called-out on drawings, they are minimum size continuous fillet welds in accordance with AWS D1.1.
8. All welds shall be made using E70 series electrodes.
9. All bolted connections shall use ASTM F3125 bolts unless noted otherwise. Temporary erection bolts may be ASTM A307
10.All bolts exposed to the elements shall be hot dipped galvanized or group 1, alloy 304 stainless steel
1. Design and construction of premanufactured steel frame are the responsibility of the manufacturer.
2. Steel frame shall be designed and constructed in accordance with the noted codes.
3. The contractor shall coordinate the manufacturer's work with all trades and conform to performance and appearance criteria indicated in sections and details provided by the architect.
4. Submit shop drawings and connection details for review.
5. Provide structural calculations, sealed by an engineer licensed to practice in the state of Texas.
6. Design loads and structural performance criteria shall be as follows:
A. Wind: see general notes for wind speed and exposure. Design for uplift forces specified by the building code, limit lateral deflection to l/240.
B. Gravity: per General Notes
i. Roof live load: 20 psf, non-reducible.
ii. Roof dead load: structure weight + weight of applied materials and equipment loads.
iii. Cladding dead load: steel sheathing per manufacturer.
C. Deflections limits: LL= l/240; total load = l/180.
7. Rigid frame building manufacturer shall design frames, columns, base plates, anchor bolts, purlins, girts and other miscellaneous structure in accordance with the noted codes and loads.
8. Foundation was designed assuming rigid frames and columns with pinned bases. Any deviation of this assumption may cause the foundation to be revised, which shall be the pre-engineered building manufacturer's responsibility.
9. Contractor shall submit frame reactions to structural engineer for verification of foundation design criteria prior to beginning construction of any foundation element.
1. Except where indicated on the drawings, post-installed anchors shall consist of the following anchor types as provided by Hilti, Inc. Contact Hilti at (800) 879-8000 for product related questions.
A. Anchorage to concrete
1. Adhesive anchors for cracked and uncracked concrete use:
a. Adhesives for use:
(i) Hilti HIT-HY 200 safe set system with Hilti HIT-Z rod per ICC ESR-3187
(ii) Hilti HIT-HY 200 safe set system with Hilti hollow drill bit and vacuum with HAS threaded rod per ICC ESR-3187
(iii) Hilti HIT-RE 500V3 safe set system with Hilti hollow drill bit and vacuum with HAS threaded rod per ICC ESR-3814
(iv) Hilti HIT-RE 500V3 safe set system with Hilti roughening tool (HIT RT) with HAS threaded rod per ICC ESR-3814 for diamond cored holes
b. Steel elements for use with adhesive:
(i) Hilti HAS-V-36 grade 36 carbon steel rod
(ii) Hilti HAS-R-304 stainless steel rod
(iii) Hilti HAS-R-316 stainless steel rod
(iv) Hilti HIT-Z rod (with HY 200 only)
2. Basis of design includes the following design parameters:
a. Cracked concrete
b. Water-saturated concrete
c. Base material temperature of 23-104 degrees Fahrenheit
d. Allowable with hammer-drill, hollow drill bit system, and core drilling methods
3. Medium duty mechanical anchors for cracked and uncracked concrete use:
a. Hilti KWIK HUS EZ and KWIK HUS EZ-I screw anchor safe set system with hollow drill bit and vacuum per ICC ESR-3027
b. Hilti KWIK BOLT-TZ expansion anchor safe set system with hollow drill bit and vacuum and SI-AT-A22 tool with adaptive torque for applicable sizes per ICC ESR-1917
c. Hilti KWIK BOLT 3 expansion anchor safe set system with hollow drill bit and vacuum and
SI-AT-A22 tool with adaptive torque for applicable sizes (uncracked concrete only) per ICC
ESR-2302
4. Heavy duty mechanical anchors for cracked and uncracked concrete use:
a. Hilti HDA undercut anchors per ICC ESR 1546
b. Hilti HSL-3 expansion anchors per ICC ESR 1545
B. Rebar doweling into concrete
1. Adhesive anchors for cracked and uncracked concrete use:
a. Hilti HIT-HY 200 safe set system with Hilti hollow drill bit and vacuum with continuously deformed rebar per ICC ESR-3187
b. Hilti HIT-HY 500V3 safe set system with Hilti hollow drill bit and vacuum with continuously
DEFORMED REBAR PER ICC ESR-3814
c. HILTI HIT-re 500v3 safe set system with Hilti roughening tool (HIT RT) with continuously deformed rebar per ICC ESR-3814 in diamond cored holes
2. Basis of design includes the following design parameters:
a. Cracked concrete
b. Water-saturated concrete
c. Base material temperature of 23-104 degrees Fahrenheit
d. Allowable with hammer-drill, hollow drill bit system, and core drilling methods
e. Current ICC-ES report with approval for development of bar using ACI provisions for embedment depths greater than 20 bar diameters
2. Anchor capacity used in design shall be based on the technical data published by Hilti or other such method as approved by the structural engineer of record. Substitution requests for alternate products must be approved in writing by the structural engineer of record prior to use. Contractor shall provide calculations that have been sealed by another licensed engineer demonstrating that the substituted product is capable of meeting the performance of the specified product. Fasteners submitted for substitution must also have an ICC ESR showing compliance with the relevant building code for seismic uses, load resistance, installation category, and availability of comprehensive installation instructions for that particular fastener. Adhesive anchor evaluation will also consider creep, in-service temperature, installation temperature, moisture condition of concrete, and drilling methods.
3. Use of diamond core bit with roughening tool for anchor holes requires approval from engineer of record prior to drilling. Unless otherwise shown in the drawings, all holes shall be drilled perpendicular to the concrete surface.
4. Install anchors per the manufacturer's printed installation instructions, as included in the anchor packaging.
5. The contractor shall arrange an anchor manufacturer's representative to provide onsite installation training for all anchor products specified.
6. Anchor capacity is dependent upon spacing between adjacent anchors and proximity of anchors to edge of concrete. Install anchors in accordance with spacing and edge clearances indicated on the drawings.
7. Existing reinforcing bars in the concrete structure may conflict with specific anchor locations. Unless noted otherwise on the drawings, existing bars may not be cut. The contractor shall review the existing structural drawings and shall undertake to locate the position of the reinforcing bars at the locations of the concrete anchors by gpr, x-ray, chipping or other approved means.
1. Shop drawings and/or product data for the following items are to be submitted to the COR for review:
A. Reinforcing steel data and shop drawings
B. Concrete mix designs
C. Pre-engineered metal buildings shop drawings, reactions, and calculations.
2. General contractor shall pre-check all shop drawings before submission to the engineer for review.
All submittals materials must bear the review stamp of the general contractor.
3. Allow 20 working days after date of delivery to the COR for review of shop drawings.
4. The use of reproductions of these contract drawings, including the use of electronic files, by any contractor, subcontractor, erector, fabricator, or material supplier in lieu of the independent preparation of shop drawings signified their acceptance of all information shown hereon as correct and obligates themselves to any job expense, real or implied, arising due to any errors that may occur thereon. Such use of reproductions of these contract documents will not be allowed without prior consent from the engineer.
1. An independent testing lab shall be engaged to perform quality control testing and inspections.
2. Contractor shall cooperate and coordinate activities with designated testing lab.
3. Testing lab shall perform the following services:
A. Observe reinforcing steel and items embedded in concrete.
B. Observe concrete pours.
C. Provide concrete testing as follows:
i. Prepare one set of six cylinders, from each day's pour for each type of concrete used, for compressive strength testing. Break two cylinders at 7 days, two at 28 days, and hold two for future testing, if required.
ii. Perform one slump test for ea. Set of cylinders prepared. Perform additional slump tests as required when changes in concrete consistency are discernable.
D. Provide inspection of structural steel connections with testing of a minimum of 20 percent of bolts and welds, per specifications.
E. Provide inspection of roof and floor deck attachments.
4. Refer to special inspections notes for special inspections required by code. Special inspections are in addition to the general quality control inspections indicated above.
GENERAL CONDITIONS
GENERAL NOTES
SITE
CONCRETE
STRUCTURAL STEEL
PREENGINEERED METAL BUILDING
POST-INSTALLED ANCHORS
SHOP DRAWING REVIEW AND SUBMITTAL NOTES
TESTING LAB SERVICES
at an application rate of 1.0 lbs per cubic yard.
Revisions: Date:
Revision 1 - Addendum 001 11/03/2023
1151 W. PIONEER PKWY. (817) 277-6686
ARLINGTON, TX 76013
Texas Registered Engineering Firm F-8284 C 2023 Copyright R. L. Woods & Associates, LLC
Structural and Forensic Engineering
R. L. Woods & Associates, LLC
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
APPROVING OFFICIAL:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
O'Brien Engineering, Inc.
2340 E. Trinity Mills Rd. Ste 220
Carrollton, TX 75006
(972) 233-2288 www.obrieneng.com
Managing Partner
ANGEL R. MORALES, COR
11/03/2023
ISSUE FOR
CONSTRUCTION 1
11-03-2311 /2
/2
1:
:1
P
M
SS002
SPECIAL INSPECTIONS NOTES WATER BOOSTER PUMP
STATIONS
EL PASO, TX
756-21-100
RLW BWT
SI-1 The registered design professional in responsible charge (RDPiRC) for this project is the architect & COR. Submit all inspection reports to COR for review.
SI-2 The RDPiRC contracts with or is employed by the owner.
SI-4 Inspection of Fabricators - Fabricator shall submit to the RDPiRC, with a copy to the owner and the GC, a certificate of compliance stating the he fabricated his work under the inspections services of a special inspector or under the inspection services of a nationally recognized trade organization that requires quality control inspections.
<<The following special inspections in table form are required only if marked by a 'X', 'C', or 'P'.
X - Denotes that the inspection is required, one time occurrence.
C - Denotes that the inspection is required and shall be continuous.
P - Denotes that the inspection is required and shall be periodic.
NA - Denotes not applicable to this project.
SI-5 Open Web Steel Joists & Joist Girders (Per 2021 IBC Table 1705.2.3) - NOT APPLICABLE
SPECIAL INSPECTIONS
SI-7 Concrete Construction (Per 2021 IBC Table 1705.3)
1. Inspect reinforcement, including prestressing tendons, and verify placement.P
SI-8A Masonry Construction (Per TMS 602-16 Table 4) - NOT APPLICABLE
SI-11 Soils (Per 2021 IBC Table 1705.6)
1. Verify materials below shallow foundations are adequate to achieve the design bearing capacity.P
SI-12 Pile Foundations (Per IBC 2021 Table 1705.7) - NOT APPLICABLE
Mark Description Referenced Standard
Mark Description
2. Verify excavations are extended to proper depth and have reached proper material.P
3. Perform classification and testing of compacted fill materials.P
C
5. Prior to placement o compacted fill, inspect subgrade and verify that site has been prepared properly.P
SI-13 Pier Foundations - NOT APPLICABLE
IBC Reference
2. Reinforcing bar welding:
3. Inspect anchors cast in concrete.P
a. Verify weldability of reinforcing bars other than ASTM A706;NA
4. Inspect anchors post-installed in hardened concrete membersa
ACI 318 Ch. 20, 25.2, 25.3, 26.6.1-26.6.3
AWS D1.4
ACI 318: 17.8.2
C
a. Adhesive anchors installed in horizontally or upwardly inclined orientations to resist sustained tension loads.
ACI 318: 17.8.2.4
b. Mechanical anchors and adhesive anchors not defined in 4.a.P
P 5. Verify use of required design mix.
C
6. Prior to concrete placement, fabricate specimens for strength tests, perform slump and air content tests, and determine the temperature of the concrete.
C 7. Inspect concrete and shotcrete placement for proper application techniques.
P 8. Verify maintenance of specified curing temperature and techniques.
9. Inspect prestressed concrete for:
NA a. Application of prestressing forces; and
NA b. Grouting of bonded prestressing tendons.
NA 10. Inspect erection of precast concrete members.
NA
13. Verify in-situ concrete strength, prior to stressing of tendons in post-tensioned concrete and prior to removal of shores and forms from beams and structural slabs.
P 14. Inspect formwork for shape, location and dimensions of the concrete member being formed. ACI 318: 26.11.1.2(b)
ACI 318: 26.11.2
ACI 318: Ch. 26.8
ACI 318: 26.10
ACI 318: 26.5.3-26.5.5
ACI 318: 26.5
ASTM C172
ASTM C31
ACI 318: 26.4, 26.12
ACI 318: Ch. 19, 26.4.3, 1904.1, 1904.2 26.4.4
ACI 318: 17.8.2
P
SI-6 Structural Steel Construction
P
Mark Description RemarkREFERNCED
STANDARD
IBC
REFERENCED
P
P
NA
NA
NA
P
NA
SI-9 Wood Construction - NOT APPLICABLE
SI-10 Cold-Formed Steel Light-Frame Construction - NOT APPLICABLE
"- - -" - Observe, or perform in accordance with applicable standards.
R - Denotes that inspection/testing is required and shall be performed with applicable standards.
SI-8B Masonry Construction (Per TMS 602-16 Table 3) - NOT APPLICABLE
b. Inspect single-pass fillet welds, maximum 5/16"; andP ACI 318: 26.6.4
c. Inspect all other welds.C
11. For precast concrete diaphragm connections or reinforcement at joints classified as moderate ACI 318: 26.13.1.3(MDE or HDE) in structures assigned to Seismic Design Category C, D, E, or F, inspect such connections and reinforcement in the field for:
NA a. Installation of the embedded parts
NA b. Completion of the continuity of reinforcement across joints. ACI 550.5
NA c. Completion of connections in the field.
NA
12. Inspect installation tolerances of precast concrete diaphragm connections for compliance with ACI 550.5. ACI 318: 26.13.1.3
NA
NA
P
NA
P
NA
NA
NA
NA
NA
NA
Note:
a. Specific requirements for special inspection shall be included in the research report for the anchor issued by an approved source in accordance with
17.8.2 in ACI 318, or other qualification procedures. Where specific requirements are not provided, special inspection requirements shall be specified by the registered design professional and shall be approved by the building official prior to the commencement of the work.
1. Material verification of structural steel.
Structural Steel:
ASTM 6
ASTM Standards
AISC 360 A3.1
2. Verify structural steel indentification markings.
Applicable ASTM
Standards
Review Structural steel mill certificates and test reports
3. Structural steel welding:
AWS D1.1
AISC 360M2.4
a. Inspection tasks Prior to Welding.
QA tasks listed in AISC 360, Table N5.4-1
b. Inspection tasks During Welding.
QA tasks listed in AISC 360, Table N5.4-2
c. Inspection tasks After Welding.
QA tasks listed in AISC 360, Table N5.4-3
d. Nondestructive testing (NDT) of welded joints:
EXCEPTION: NDT of welds completed in an approved fabricator's shop. See AISC 360, N6
1) Complete penetration groove welds 5/16" or greater in risk category III or IV
AISC 360
N5b UT on 100%, may reduce to 25% per AISC 360, N5e
2) Complete penetration groove welds 5/16" or greater in risk category II
AISC 360,
N5b UT on 10%, may increase to
100% per AISC 360, N5f
3) Welded joints subject to fatigue when required by
Aisc 360, Appendix 3, Table A-3.1
4) Fabricator's NDT reports when fabricator performs NDT AISC 360, N6
4. Structural steel bolting: RCSC Specification
a. Inspection tasks Prior to Bolting QA tasks listed in AISC 360, Table N5.6-1
b. Inspection tasks During Bolting QA tasks listed in AISC 360, Table N5.6-2
QA tasks listed in AISC 360, Table N5.6-3
c. Inspection tasks After Bolting
Other Inspection Tasks:
AISC 360 Ch.N 1705.2
AISC 360 N5.8
1. Inspect steel frames to verify compliance with the details shown on the construction documents, such as braces, stiffeners, member locations and proper application of joint details at each connection.
2. Inspect the placement of anchor rods and other embedments supporting structural steel for compliance with the construction documents. The diameter, grade, type and length of the anchor rod or embedded item, and the extent or depth of embedment into the concrete, shall be verified prior to the placement of concrete.
Inspection of steel elements of composite construction prior to concrete placement:
AWS D1.1, D1.5,
D1.6
1. Placement and Installation of steel headed stud anchors
Verification of Steel Construction Other Than Structural Steel:
1) Verification of weldability of reinforcing steel other than
ASTMA A706
AWS D1.4
ACI 318:
Ch. 26.6.1.1(g), 26.6.4.1
2) Reinforcing steel resisting flexural and axial forces in intermediate and special moment frames, and boundary elements of special structural walls of concrete and shear reinforcement.
AWS D1.4
ACI 318:
Ch. 26.6.1.1(g), 26.6.4.1
3) Shear reinforcement
AWS D1.4
ACI 318:
Ch. 26.6.1.1(g), 26.6.4.1
AWS D1.4
ACI 318:
Ch. 26.6.1.1(g), 26.6.4.1
4) Other reinforcement
5. Visual inspection of exposed cut surfaces of galvanized structural steel main members and exposed corners of the rectangular
HSS for cracks subsequent to galvanizing.
Cold-Formed Steel Deck: SDI QA/QC
1. Manufacturer documents listed ins SDI QA/QC, Section 2.1 & 2.2 SDI QA/QC Sec. 2
2. Cold-formed steel deck placement:
a. Inspection tasks prior to deck placement SDI QA/QC, Appendix 1 Table 1.1
b. Inspection tasks after deck placement SDI QA/QC, Appendix 1 Table 1.2
3. Cold-formed steel deck welding: AWS D1.3
a. Inspection tasks prior to welding SDI QA/QC, Appendix 1 Table 1.3
b. Inspections tasks during welding SDI QA/QC, Appendix 1 Table 1.4
c. Inspection tasks after welding SDI QA/QC, Appendix 1 Table 1.5
4. Cold-formed steel deck mechanical fastening:
a. Inspection tasks prior to mechanical fastening SDI QA/QC, Appendix 1 Table 1.6
SDI QA/QC, Appendix 1 Table 1.7
SDI QA/QC, Appendix 1 Table 1.8
b. Inspections tasks during mechanical fastening
c. Inspection tasks after mechanical fastening
1. Inspection of welding:
a. Reinforcing steel:
AISC 360, N5c
SI-3 These inspections are in addition to the inspections specified in Section 110 of the 2021 International Building Code (IBC). Refer to the building code, and any amendments to the building code for this jurisdiction, to determine all the required inspections in addition to the special inspections listed below.
4. During fill placement, verify use of proper materials and procedure in accordance with the provisions of the approved geotechnical report. Verify densities and lift thicknesses during placement and compaction of compacted fill.
Revisions: Date:
6' - 6"
SS201
SS201
SS201
SS201
6' - 2"
2" 2"
1' - 0" WIDE STRIP
OF EXIST. PAD TO
BE SAW-CUT &
REMOVED
SS201
SS201
O.F. PEMB FRAME
SS201
EXIST. 6" THICK PAD TO
BE PARTIALLY DEMO'D.
NEW 6" THICK SLAB, REINF.
w/ #4 @ 16" O.C.B.W.
CENTERED IN SLAB
(F
IE
LD
V
E R
IF
Y
TRENCH DRAIN,
REF. PLUMBING
M
IN
1'
MIN.
6"
PEMB STRUCTURE
BY OTHERS
6"
#4 @ 16" O.C. B.W.
(2) #6 CONT.
F
IE
LD
V
E R
IF
Y
2"
1/
2"
GRADE BEAMS TO BEAR ON
FIRM PROPERLY COMPACTED
SUBGRADE WITH MIN. 3000 PSF
BEARING CAPACITY
1' - 2"
OR EQUIP. PAD (WHICHEVER IS LESS)
5'-0" OR TO FACE OF EXIST. BUILDING
D
E P
T H
O F
E N
G
IN
E E
R E
D
F
IL
L S
H A
L L
B E
T H
E G
R E
A T
E R
O F
'-8
B
E L
O W
E X
IS
T
G
R A
D E
O R
B E
L O
W B
O T
T O
M O
F G
R A
D E
B E
A M
S
SUBGRADE
F
IL
L
E N
G
IN
E E
R E
D
1' - 2"
M
IN
1'
MIN.
6"
PEMB STRUCTURE
BY OTHERS
6"
(2) #6 CONT.
F
IE
LD
V
E R
IF
Y
2"
1/
2"
GRADE BEAMS TO BEAR ON
FIRM PROPERLY COMPACTED
SUBGRADE WITH MIN. 3000 PSF
BEARING CAPACITY
#4 x 1'-6" DWLS @ 16" O.C.
DRILL 6" INTO EXIST. SLAB
& SET w/ ADHESIVE
(2) #6 CONT.
EXIST. SLAB
D E
P T
H O
F E
N G
IN
E
E R
E D
F
IL
L S
H A
L L
B E
T H
E G
R E
A T
E R
O F
'-8
B
E L
O W
E X
IS
T
G
R A
D E
O R
B E
L O
W B
O T
T O
M O
F G
R A
D E
B E
A M
S
SUBGRADE
OR EQUIP. PAD (WHICHEVER IS LESS)
5'-0" OR TO FACE OF EXIST. BUILDING
ENGINEERED FILL
NEW 6" SLAB REINF. w/ #4 @ 16" O.C. B.W.
#4 x DWLS @ 16" O.C.
DRILL 6" INTO EXIST. SLAB & SET
w/ ADHESIVE
EXIST. SLAB
10"
6"
(2) #4 CONT.
1'
1' - 4"
TRENCH DRAIN,
REF. PLUMBING
#4 x @ 16" O.C.
7"
10"
6" 1'-0"
1151 W. PIONEER PKWY. (817) 277-6686
ARLINGTON, TX 76013
Texas Registered Engineering Firm F-8284 C 2023 Copyright R. L. Woods & Associates, LLC
Structural and Forensic Engineering
R. L. Woods & Associates, LLC
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
APPROVING OFFICIAL:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
O'Brien Engineering, Inc.
2340 E. Trinity Mills Rd. Ste 220
Carrollton, TX 75006
(972) 233-2288 www.obrieneng.com
Managing Partner
ANGEL R. MORALES, COR
11/03/2023
ISSUE FOR
CONSTRUCTION 1
11-03-2311 /2
/2
1:
:4
P
M
SS201
FOUNDATION PLAN AND DETAILS WATER BOOSTER PUMP
STATIONS
EL PASO, TX
756-21-100
RLW BWT
N
PLAN NORTH
SCALE: 3/4" = 1'-0"
FOUNDATION PLAN
SCALE: 3/4" = 1'-0"
DETAIL
2 SCALE: 3/4" = 1'-0"
DETAIL
SCALE: 3/4" = 1'-0"
DETAIL
Revisions: Date:
'-1
7/
8"
VE
R
IF
Y
'-1
/8
EXISTING METAL BUILDING
NOT IN SCOPE
VERIFY
13'-10" 6'-2"
AS201
AS201
AS201
AS201
AS201
AS201
/8
/8
5'-11 1/2"
A B
129 SF
BOOSTER PUMP
ROOM
EXISTING BUILDING 1
NOT IN SCOPE
4' -1
/8
4'
-1
/8
4' -1
/8
4'
-1
/8
4' -1
/8
METAL FRAMING BY PRE-
ENGINEERED METAL BUILDING
MANUFACTURER - TYP.
6'-0"W X 7'-0"H HM DOUBLE DOOR
AND HM DOOR FRAME
EXIST. PAD TO
REMAIN.
REF. STRUCT.
TRENCH DRAIN
REF. PLUMBING
6'-2"
5' -6
'-0
EQ EQ
CL
EXISTING METAL BUILDING
NOT IN SCOPE
EXISTING BUILDING 1
NOT IN SCOPE
SUSPEND-MOUNTED
LIGHTING FIXTURES
METAL FRAMING BY PRE-
ENGINEERED METAL BUILDING
MANUFACTURER - TYP.
METAL ROOF
2 1/2:12
SLOPE DOWN
METAL FASCIA
METAL FASCIA
EXISTING METAL BUILDING
NOT IN SCOPE
EXISTING BUILDING 1
NOT IN SCOPE
GENERAL SHEET NOTES:
A. THE PRE-ENGINEERED METAL BUILDING IS TO BE DESIGNED AND INSTALLED BY THE
MANUFACTURER’S SPECIFICATIONS AND ALL RELEVANT BUILDING CODES AND
REGULATIONS.
B. ALL STRUCTURAL STEEL MEMBERS, FASTENERS, AND CONNECTIONS MUST BE
SUPPLIED BY THE MANUFACTURER AND INSTALLED BY THEIR INSTRUCTIONS.
C. THE BUILDING FOUNDATION AND ANCHORAGE MUST BE DESIGNED AND INSTALLED
BY THE MANUFACTURER’S SPECIFICATIONS AND THE REQUIREMENTS OF BUILDING
CODES.
D. THE ROOF AND WALL SYSTEMS, INCLUDING INSULATION AND VAPOR BARRIERS,
MUST BE INSTALLED BY THE MANUFACTURER’S SPECIFICATIONS AND THE
REQUIREMENTS OF BUILDING CODES.
E. ALL OPENINGS FOR DOORS, LOUVERS AND OTHER PENETRATION SHALL BE
PROPERLY FRAMED AND REINFORCED AS REQUIRED.
F. ALL ROOF AND WALL PENETRATION SHALL BE PROPERLY FLASHED AND SEALED TO
PREVENT LEAKS.
REFLECTED CEILING PLAN LEGEND
CEILINGS
NO CEILING - UNDERSIDE OF METAL ROOF
ROOF PLAN SYMBOL LEGEND
DIRECTION OF DOWN SLOPE. 2 1/2" PER FOOT
LIGHTING FIXTURE
SUSPEND-MOUNTED LIGHTING FIXTURE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
APPROVING OFFICIAL:
ANGEL R. MORALES, COR
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
A/E:
OEI-LBL Joint Venture LLC
2340 E. Trinity Mills Rd. Ste 220
Carrollton, TX 75006
O'Brend Engineering Inc., Managing Partner
972-233-2288
1O'Brien Engineering, Inc.
Carrollton, TX 75006
972-233-2288
2340 E. Trinity Mills Rd. Ste 220 www.obrieneng.com
A/E:
www.obrieneng.com
AS101
FLOOR PLAN, REFLECTED
CEILING PLAN & ROOF PLAN
WATER BOOSTER PUMP
STATIONS
EL PASO, TX
756-21-100
11/03/2023 KL CH
ISSUE FOR
CONSTRUCTION
11/03/2023
1/4" = 1'-0"
FLOOR PLAN
1/4" = 1'-0"
REFLECTED CEILING PLAN
1/4" = 1'-0"
ROOF PLAN
N
PLAN NORTHACTUAL NORTH
N
T.O.SLAB
15' - 3"
'-4
'-2
METAL ROOF
METAL FASCIA
METAL PANEL
CONC. SLAB
REF. STRUCT.
T.O.SLAB
15' - 3"
4' -6
7'
-0
METAL ROOF
METAL FASCIA
METAL PANEL
CONC. SLAB
REF. STRUCT.
METAL DOOR
6'-0"W X 7'-0"H HM DOUBLE DOOR
AND HM DOOR FRAME
T.O.SLAB
15' - 3"
'-2
" 11 '-6
METAL ROOF
METAL FASCIA
METAL PANEL
CONC. SLAB
REF. STRUCT.
T.O.SLAB
15' - 3"
1' -4
'-2
METAL ROOF
METAL FASCIA
METAL PANEL
CONC. SLAB
REF. STRUCT.
T.O.SLAB
15' - 3"
AS201 METAL ROOF
METAL FRAMING BY
PRE-ENGINEERED
METAL BUILDING
MANUFACTURER - TYP.
METAL PANEL
CONC. SLAB
REF. STRUCT.
BOOSTER PUMP
ROOM
SUSPEND MOUNTED
LIGHTING FIXTURE
AS201
AS201
AS201
6'-0"W X 7'-0"H HM DOUBLE DOOR
AND HM DOOR FRAME
T.O.SLAB
15' - 3"
AS201 METAL ROOF
METAL FASCIA
METAL PANEL
CONC. SLAB
REF. STRUCT.
SUSPEND MOUNTED
LIGHTING FIXTURE
METAL FRAMING BY
PRE-ENGINEERED
METAL BUILDING
MANUFACTURER - TYP.
AS201
DRIP FLASHING TURN UP 2"
HM DOOR FRAME
3/ 4"1/
4"
DOOR AS SCHEDULED
1 1/4"
WEATHER STRIPPING
METAL PANEL SYSTEM BY
PRE-ENGINEERED METAL
BUILDING MANUFACTURER
METAL PANEL SYSTEM BY
PRE-ENGINEERED METAL
BUILDING MANUFACTURER
JAMB TRIM
HM DOOR JAMB
FIELD FLATTEN TRIM LEG WHEN
REQ'D.
DOOR AS SCHEDULED
WEATHER STRIPPING
THRESHOLD SET IN
FULL MASTIC BED
SECURE THRESHOLD TO SLAB W/
EXPANSION FASTNERS
DOOR BOTTOM
WEATHERSTRIPPING
WEATHERSTRIPPING
AT JAMB BEYOND
DOOR AS SCHEDULED
GENERAL SHEET NOTES:
A. THE PRE-ENGINEERED METAL BUILDING IS TO BE DESIGNED AND INSTALLED BY THE
MANUFACTURER’S SPECIFICATIONS AND ALL RELEVANT BUILDING CODES AND
REGULATIONS.
B. ALL STRUCTURAL STEEL MEMBERS, FASTENERS, AND CONNECTIONS MUST BE
SUPPLIED BY THE MANUFACTURER AND INSTALLED BY THEIR INSTRUCTIONS.
C. THE BUILDING FOUNDATION AND ANCHORAGE MUST BE DESIGNED AND INSTALLED
BY THE MANUFACTURER’S SPECIFICATIONS AND THE REQUIREMENTS OF BUILDING
CODES.
D. THE ROOF AND WALL SYSTEMS, INCLUDING INSULATION AND VAPOR BARRIERS,
MUST BE INSTALLED BY THE MANUFACTURER’S SPECIFICATIONS AND THE
REQUIREMENTS OF BUILDING CODES.
E. ALL OPENINGS FOR DOORS, LOUVERS AND OTHER PENETRATION SHALL BE
PROPERLY FRAMED AND REINFORCED AS REQUIRED.
F. ALL ROOF AND WALL PENETRATION SHALL BE PROPERLY FLASHED AND SEALED TO
PREVENT LEAKS.
1"2"
1/2" SINGLE-BEAD BUTYL
TAPE SEALANT
7/8" DOUBLE BEAD BUTYL
TAPE SEALANT
1/4 - 14 X 7/8 LONG-LIFE
TEK1 SDS SEALER @
EVERY HIGH MESA, (10)
PER PANEL
FIELD INSTALLED INSULATION
EAVE TRIM
1/4 - 14 X 7/8 LONG-LIFE TEK1
SDS SEALER @ 8" O.C.
7/8" DOUBLE BEAD BUTYL
TAPE SEALANT
EAVE STRUT
NON-SKINNING BUTYL SEALANT
1/4 - 14 X 2-1/4 SDS SHOULDER
TEK3 (MIN. 2 PER CLIP)
RIDGELINE PANEL
INSULATED METAL PANEL
RIDGELINE PANEL CLIP
NON-SKINNING CAULK
INSULATED METAL PANEL
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
APPROVING OFFICIAL:
ANGEL R. MORALES, COR
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
A/E:
OEI-LBL Joint Venture LLC
2340 E. Trinity Mills Rd. Ste 220
Carrollton, TX 75006
O'Brend Engineering Inc., Managing Partner
972-233-2288
1O'Brien Engineering, Inc.
Carrollton, TX 75006
972-233-2288
2340 E. Trinity Mills Rd. Ste 220 www.obrieneng.com
A/E:
www.obrieneng.com
AS201
EXTERIOR ELEVATIONS /
BUILDING SECTIONS / DETAILS
WATER BOOSTER PUMP
STATIONS
EL PASO, TX
756-21-100
11/03/2023 KL CH
ISSUE FOR
CONSTRUCTION
11/03/2023
3/8" = 1'-0"
NORTH ELEVATION
3/8" = 1'-0"
EAST ELEVATION
3/8" = 1'-0"
SOUTH ELEVATION
3/8" = 1'-0"
WEST ELEVATION
3/8" = 1'-0"
BUILDING SECTION A-A'
3/8" = 1'-0"
BUILDING SECTION B-B'
3" = 1'-0"
DETAIL - DOOR HEAD
3" = 1'-0"
DETAIL - DOOR JAMB
3" = 1'-0"
DETAIL - DOOR THRESHOLD
3" = 1'-0"
DETAIL - INSULATED METAL PANEL - TYP.
GENERAL NOTES
1. GENERAL REQUIREMENTS
A. GENERAL
1. SUBMITTALS
a. CONTRACTOR SHALL MAKE ALL NECESSARY FIELD MEASUREMENTS AND INVESTIGATIONS TO ASSURE THAT THE EQUIPMENT
AND ASSEMBLIES WILL MEET CONTRACT REQUIREMENTS, AND ALL EQUIPMENT THAT REQUIRES REGULAR MAINTENANCE, CALIBRATION, ETC ARE ACCESSABLE FROM THE FLOOR OR PERMANENT WORK PLATFORM. IT IS THE CONTRACTOR’S RESPONSIBILITY TO ENSURE ALL SUBMITTALS MEET SPECIFICATIONS AND REQUIREMENTS AND IT IS ASSUMED BY THAT ALL SUBMITTALS DO MEET SPECIFICATIONS UNLESS THE CONTRACTOR HAS REQUESTED A VARIANCE IN WRITING AND APPROVED PRIOR TO THE SUBMITTAL. IF AT ANY TIME DURING THE PROJECT IT IS FOUND THAT ANY ITEM DOES NOT MEET SPECIFICATIONS AND THERE WAS NO VARIANCE APPROVAL THE CONTRACTOR SHALL CORRECT AT NO ADDITIONAL COST OR TIME EVEN IF A
SUBMITTAL WAS APPROVED.
b. SUBMITTALS AND SHOP DRAWINGS FOR INTERDEPENDENT ITEMS, CONTAINING APPLICABLE DESCRIPTIVE INFORMATION, SHALL BE FURNISHED TOGETHER AND COMPLETE IN A GROUP. COORDINATE AND PROPERLY INTEGRATE MATERIALS AND EQUIPMENT IN EACH GROUP TO PROVIDE A COMPLETELY COMPATIBLE AND EFFICIENT INSTALLATION. FINAL REVIEW AND APPROVALS WILL
BE MADE ONLY BY GROUPS.
2. COORDINATION/SHOP DRAWINGS:
a. SUBMIT COMPLETE CONSOLIDATED AND COORDINATED SHOP DRAWINGS FOR ALL NEW SYSTEMS, AND FOR EXISTING SYSTEMS
THAT ARE IN THE SAME AREAS.
b. THE COORDINATION/SHOP DRAWINGS SHALL INCLUDE PLAN VIEWS, ELEVATIONS AND SECTIONS OF ALL SYSTEMS AND SHALL
CLEARLY IDENTIFY AND DIMENSION THE PROPOSED LOCATIONS OF THE PRINCIPAL ITEMS OF EQUIPMENT. THE DRAWINGS SHALL CLEARLY SHOW LOCATIONS AND ADEQUATE CLEARANCE FOR ALL EQUIPMENT, PIPING, VALVES, CONTROL PANELS AND OTHER ITEMS. SHOW THE ACCESS MEANS FOR ALL ITEMS REQUIRING ACCESS FOR OPERATIONS AND MAINTENANCE. PROVIDE DETAILED COORDINATION/SHOP DRAWINGS OF ALL PIPING AND DUCT SYSTEMS. THE DRAWINGS SHOULD INCLUDE ALL LOCKOUT/TAGOUT POINTS FOR ALL ENERGY/HAZARD SOURCES FOR EACH PIECE OF EQUIPMENT. COORDINATE
LOCKOUT/TAGOUT PROCEDURES AND PRACTICES WITH LOCAL AHJ REQUIREMENTS.
c. DO NOT INSTALL EQUIPMENT FOUNDATIONS, EQUIPMENT OR PIPING UNTIL COORDINATION/SHOP DRAWINGS HAVE BEEN
APPROVED.
3. QUALITY ASSURANCE:
a. ALL ITEMS SHALL BE APPLIED AND INSTALLED IN ACCORDANCE WITH MANUFACTURER'S WRITTEN INSTRUCTIONS. CONFLICTS
BETWEEN THE MANUFACTURER'S INSTRUCTIONS AND THE CONTRACT DOCUMENTS SHALL BE REFERRED TO THE CLIENT PROJECT REPRESENTATIVE FOR RESOLUTION. PRINTED COPIES OR ELECTRONIC FILES OF MANUFACTURER’S INSTALLATION INSTRUCTIONS SHALL BE PROVIDED AT LEAST 10 WORKING DAYS PRIOR TO COMMENCING INSTALLATION OF ANY ITEM.
b. ALL ITEMS THAT REQUIRE ACCESS, SUCH AS FOR OPERATING, CLEANING, SERVICING, MAINTENANCE, AND CALIBRATION, SHALL BE EASILY AND SAFELY ACCESSIBLE BY PERSONS STANDING AT FLOOR LEVEL, OR STANDING ON PERMANENT PLATFORMS, WITHOUT THE USE OF PORTABLE LADDERS. EXAMPLES OF THESE ITEMS INCLUDE BUT ARE NOT LIMITED TO: ALL TYPES OF VALVES, FILTERS AND STRAINERS, TRANSMITTERS, AND CONTROL DEVICES. PRIOR TO COMMENCING INSTALLATION WORK, REFER CONFLICTS BETWEEN THIS REQUIREMENT AND CONTRACT DOCUMENTS FOR RESOLUTION. FAILURE OF THE CONTRACTOR TO RESOLVE OR CALL ATTENTION TO ANY DISCREPANCIES OR DEFICIENCIES WILL RESULT IN THE CONTRACTOR
CORRECTING AT NO ADDITIONAL COST OR TIME.
c. COMPLETE LAYOUT DRAWINGS SHALL…