This is a solicitation for the installation of water booster pumps at the El Paso VA Main Clinic, issued by the Department of Veterans Affairs (VA) Temple CTX Contracting Office. The project includes installing a new government-furnished AquaForce VS by Goulds Water Technology pump and replacing the existing Canariis pump model TE-375-46 system including suspension tank in mechanical room C106.
The solicitation is set aside 100% for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under NAICS code 237110, with an estimated project value between $500,000 and $1,000,000. Bids are due by February 19, 2025, at 10:00 AM MST. The period of performance is 360 days (180 days for preconstruction phase and 180 days for construction phase) from notice to proceed. A pre-bid site visit is scheduled for January 27, 2025, at 9:30 AM MST. Questions are due by January 31, 2025. The contractor must obtain an excavation permit from Ft. Bliss DPW prior to construction mobilization, which can take up to six months for approval. A bid guarantee of 20% of the bid price (not to exceed $3,000,000) is required.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES
4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER
7. ISSUED BY CODE 8. ADDRESS OFFER TO
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATIONSOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES NO
a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b. An offer guarantee is, is not required.
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
1 65
36C25725B0010 X
756-25-200
Department of Veterans Affairs (NCO 17) Temple CTX Contracting (90C) 1901 Veterans Memorial Dr. Building #171 Temple TX 76504
Department of Veterans Affairs Temple CTX Contracting (90C) 1901 Veterans Memorial Dr. Building 171 Temple TX 76504
Andres Garcia andres.garcia1@va.gov
Install Water Booster Pumps, Project No. 756-25-100 located at the El Paso VA Main Clinic on 5001 North Piedras St., El Paso, TX 79930.
Contractor shall provide all necessary labor, materials, equipment, and supervision to complete all required project work in accordance with the provided SOW, Drawings, and Specifications.
This is a "Competitive" requirement Set Aside 100% Service Disabled Veteran Owned Small Business (SDVOSB).
Estimated magnitude of the construction project: Between Between $500,000 and $1,000,000.
The applicable North American Industry Classification System (NAICS) code for this project is 237110.
A Pre-Bid Site Visit is scheduled for January 27, 2025 at 9:30 AM Mountain Standard Time (MST).
Site visit RFI(s)/Questions shall be submitted via email no later than January 31,2025, by 1:00 p.m. MST to andres.garcia1@va.gov. Answers to RFIs will be posted in sam.gov as an amendment, o/a February 10, 2025.
All Bidders shall submit a Bid Guarantee as part of their Bid Package. Additionally, the Awardee must be able to obtain the necessary level of Performance and Payment Bonds.
SUBMISSION OF BIDS: See Preparation of Bids section for additional information.
10 360
X X 52.211-10
X 10
0 10:00 am MST
02-19-2025
X
14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )
26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY
PHONE: FAX:
28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code)
(Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(4 copies unless otherwise specified)
(Type or print) (Type or print)
(Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror)
(To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
Department of Veterans Affairs Central Texas Veterans HCS 1901 Veterans Memorial Dr. Building 171 Temple TX 76504
This is accomplished through the Tungsten Network located at:
http://www.fsc.va.gov/einvoice.asp This is mandatory and the sole method for submitting invoices.
(877) 353-9791 (512) 460-5540
36C25725B0010
Table of Contents
PART I - THE SCHEDULE
SECTION A - SOLICITATION/CONTRACT FORM
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,
ALTERATION, OR REPAIR)– BACK
A.3 PRICE/COST SCHEDULE
A.4 SOW
A.5 Drawings and Specifications A.6 Special Standard of Responsibility
A.7 INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK
IAW “Limitations on Subcontracting” (VAAR 852.219-73)
A.8 PREPARATION OF BIDS
A.9 PCRA/ICRA
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE
OF THE WORK (MAY 2014)
2.3 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE
EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
2.4 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION
MATERIALS (MAY 2014)
2.5 52.228-1 BID GUARANTEE (SEP 1996)
2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)
2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)
2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB
1998)
2.9 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND
VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)
2.10 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE
RESOLUTION (OCT 2018)
2.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)
REPRESENTATIONS AND CERTIFICATIONS
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAY 2024)...30
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS
AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)
3.3 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
3.4 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—
CERTIFICATION (NOV 2021)
GENERAL CONDITIONS
4.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK
(APR 1984)
4.2 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION
(FEB 2024)
4.3 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)
4.4 SUPPLEMENTAL INSURANCE REQUIREMENTS
4.5 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
4.6 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED
SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023)
(DEVIATION)
4.7 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)
4.8 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION
CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)
4.9 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV
2018)
4.10 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION
(APR 2019)
4.11 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)
4.12 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)
4.13 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT
ADMINISTRATION (OCT 2020)
4.14 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) ..62
4.15 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT
(SEP 2019)
WAGE DETERMINATION
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 Install and Replace Water Booster Pumps
1.00 JB ___________ __________
The contractor shall provide all labor, equipment, tools, materials, supplies and supervision install the new government furnished AquaForce VS by Goulds Water Technology pump and replace the current Canariis pump model TE-375-46 system including the suspension tank in mechanical room C106, in accordance with the SOW, Drawings, and Specifications.
0002 Payment Bond 1.00 EA ___________ ___________
GRAND TOTAL ___________
A.4 SOW
STATEMENT OF WORK
for
El Paso VA Main Clinic 756-25-100 Install Water Booster Pumps
1. General Information
1.1. General Scope.
1.1.1. Description of Services. The Contractor must provide all the necessary labor, transportation, materials, tools, equipment, etc. to install the new government furnished AquaForce VS by Goulds Water Technology pump located south of the existing water softener room and replace the current Canariis pump model TE-375- 46 system including the suspension tank in mechanical room C106. Replacement Basis of Design: Canariis model TM-400-60-3SV Triplex Booster skid with suspension tank.
1.2. Facility Information. The El Paso VA Health Care System (EPVAHCS) serves Veterans in far Southwest Texas and Doña Ana County, New Mexico.
1.3. Period of Performance. This project is divided into two phases: Preconstruction phase of 180 days to process Ft. Bliss DPW Excavation permit, submittals, long lead time items etc., and 180 days for the construction phase to include the installation, commissioning, etc., for a total of 360 days from issuance of Notice to Proceed (NTP).
1.4. Hours of Operations. Due to the nature of EPVAHCS operations, contractor to submit construction schedule to determine the scope of work that can be perform during regular hours and afterhours of operation. It is estimated that 80 percent of the work will be perform during regular hours, and 20 percent of the work will be performed during afterhours. Regular hours of operation are Monday thru Friday from 7:00 AM to 4:30
pm. Afterhours of operation are from 4:30 pm to 11:30 pm Monday through Friday except for Federal Holidays. Contractor is allowed to work Saturday from 7:30 am to 4:00 pm. If Contractor desires to work on Sundays, holidays, or outside the project’s site working hours, the Contractor must submit a written request for approval to the VA- COR at least five (5) working days prior to the proposed start of such work.
1.5. Place of Performance. The work to be performed under this contract will be performed at the El Paso VA Main Clinic located on 5001 North Piedras Street, El Paso, TX 79930.
1.6. Quality Control. Quality control is the responsibility of the Contractor. The Contractor is responsible for the delivery of quality services to the Government in accordance with (IAW) the terms and conditions contained in Federal Acquisition Regulation (FAR) Subpart 52.246-1 entitled, “Contractor Inspection Requirements” and applicable sub-clauses pertaining to quality control. The Contractor shall develop, implement and maintain an effective Quality Control System which includes a written Quality Control Plan (QCP). The QCP shall implement standardized procedure/methodology for monitoring and documenting contract performance to ensure all contract requirements are met.
1.7. Safety.
1.7.1. Safety Plan. The Contractor shall establish and maintain a safety plan. The plan shall include an Accident Prevention Plan for the specific work and hazards of the contract. The plan will be signed by a representative of the Contractor’s project management team. The plan will be job-specific and include work to be performed by control hazards associated with material, services, or equipment. The safety plan shall also include the subcontractors and suppliers.
1.7.2. Contractors shall have and provide all necessary tools, equipment, and Personal Protective Equipment (PPE) for arc flash level to perform the work safely, effectively, and timely. Tools, equipment, and PPE shall comply with the requirements of OSHA Standard 29 CFR 1910, Subpart I, and NFPA 70E. Prior to initiating work, Contractor shall provide documentation that all instruments, test equipment, tools and PPE have current calibration. Dated calibration labels shall be visible on all instruments, test equipment, tools, and PPE as appropriate.
Contractors will be required to attend a Safety Class to be informed about EPVA Clinic Safety Rules prior to commence of work by EPVA-FSS Safety Specialist who will also inspect the tools and equipment used for work.
1.8. Environment and OSHA. The Contractor shall comply with all local, State, and Federal environmental and occupational safety laws, rules, and regulations. The Contractor shall be liable for all fines, penalties, and costs which result from violations of, or failure to comply with, all such local State, or Federal laws, rules, and regulations. All unsafe acts or conditions fostered by the Contractor or Contractor personnel may be grounds for the Contracting Officer or authorized representative to halt any and all Contractor performance. The Contractor shall take due caution not to endanger personnel during performance of this contract.
1.9. Emergency Services. The Contractor shall have competent personnel trained and capable of dealing with minor personnel injuries. The Contractor of their employees shall immediately notify their supervisor of any accident requiring emergency medical treatment. The Contractor will, in turn, notify the COR or Government representative of the incident. Emergency medical treatment and services for Contractor personnel is the responsibility of the Contractor.
1.10. Personnel Safety. The Contractor shall immediately correct all safety deficiencies upon notification of the deficiencies by the COR or Government representative and shall notify the Government of the corrective action to be taken.
1.11. Personnel. For purposes of this paragraph, the term “personnel” or “employee(s)” refers to any person performing work related to this contract, including but not limited to, the Contractor’s employees, agents, representatives, or subcontractor. The Contractor shall staff this effort with trained, competent and capable employee(s) for the discipline they are assigned to. Contractor personnel shall present a clean, neat and professional appearance. The Contractor shall ensure that employees meet all applicable federal, state, local, and installation certification, licensing, medical requirements, and qualifications to perform all assigned tasks and functions as defined in this contract prior to commencement of work. The Contractor shall not permit any personnel to work under this contract if such person is identified by a Government authorized representative to the Contractor as a potential threat to the health, safety, security, general well-being, or operational mission of Department of Veterans Affairs (VA) and the EPVAHCS.
1.12. Conduct of Employees. Contractor personnel’s conduct shall not reflect discredit upon the Government. The Contractor shall ensure that personnel present a professional appearance. The Contractor’s employees shall observe and comply with all local policies and procedures concerning fire, safety, environmental protection, sanitation, security, and possession of firearms or other lethal or illegal weapons or substance.
The Contractor is responsible for ensuring that any Contractor employees providing services under this contract conduct themselves and perform services in a professional, safe, and responsible manner. The Contractor shall remove from the job site any employee for reasons of misconduct or security. The Contractor shall ensure no contractor employees conduct political related activities or events on VA Facilities.
1.13. Supervision of Contractor Employees. The Government will not exercise any supervision or control over Contractor or Subcontractor employees while performing work under the contract. Such employees shall be accountable solely to the Contractor, not the Government. The Contractor, in turn, shall be accountable to the Government for Contractor or Subcontractor employees.
2. Government Furnished property, Equipment, and Services
2.1. Facilities. The Government will not provide facilities. A staging area for the Contractor’s use to support this contract can be provided upon request.
2.2. Equipment and Materials. The Government will only provide the new AquaForce VS by Goulds Water Technology duplex water booster pump for this project.
3. General Tasks
3.1. General. The contractor shall provide all skilled personnel, equipment, supplies, tools, material, supervision, and other items necessary to perform this prescribed project as defined in this SOW to meet the performance requirements, except for those items specified as Government furnished property and services.
3.1.1. Contractor shall ensure that construction will be planned, coordinated, and inspected following EPVA standards and regulations.
3.1.2. Site Conditions. The contractor shall verify all dimensions and investigate existing site conditions. All technical questions shall be addressed to the COR or Government representative for resolution.
3.1.3. Contractor shall be experienced General Contractor, with properly trained and licensed, as applicable, permanent staff required to perform the proposed work.
The contractor shall provide continuous competent supervision and adequate number of skilled workmen, materials, and equipment to meet the construction schedule.
3.2. Specific Tasks:
3.2.1.1. Pre-Construction Task: Contractor to obtain excavation permit from Ft.
Bliss Directorate of Public Work (Ft. Bliss DPW). This permit can take up to six months for approval. This permit must be approved prior to construction mobilization. VA to assist ONLY.
3.2.1.2. Contractor to provide field density soil test report at minimum of 95% compaction.
3.2.1.3. Contractor to provide concrete test reports for slump and compressive strength for a 7 and 28 minimum of 4,000 psi.
3.2.1.4. Contractor to redline existing EPVA site drawings to indicate any deviations made from the requirements indicated in those drawings during the production of the work.
3.2.1.5. Contractor must perform hand dig excavation as necessary.
3.2.1.6. All plumbing piping must be copper with proper insulation except for flanges and other connections. Propress connections are not allowed.
3.2.1.7. Scope includes all necessary labor, materials, tools, equipment, etc. for the installation of the new government furnished AquaForce VS by Goulds Water Technology water booster pump located south of the existing water softener. Work to be performed per new stamped drawings.
3.2.1.8. Scope includes all necessary labor, materials, tools, equipment, etc. to replace the existing Canariis TE-375-46 pump located inside mechanical room C106, the new pump must be a direct Canariis replacement and piping must be replaced to meet NFPA 99, UPC, IPC and all other applicable building codes. This includes, but not limited to, the existing plumbing connections, headers, and suspension tank.
4. Applicable Codes and Regulations
4.1. The contractor (to include Subcontractors) must abide by all applicable regulations, publications, manuals, and local policies and procedures. Although some publication dates are given, the design shall be by current references and standards.
4.1.1. Current Federal, State and Local codes, regulations and specifications involving architectural, civil, structural, electrical, environmental, mechanical and any other disciplines associated with the design and construction of this project.
4.1.2. Americans with Disabilities Act (ADA) through adoption of the ADA ABA Accessibility Guidelines, July 2004 with corrections, Aug 2005.
4.1.3. 29 CFR 1910, Occupational Health and Safety
4.1.4. ICC International Building Code
4.1.5. NFPA 70, National Electrical Code.
4.2. Review and adhere to all pertinent VA design and standard details. Responsible for incorporating all such standards in the project. May obtain design criteria and copies of the complete VA Design Guides, Design Manuals & other resources from VA Facilities Management Technical Information.
Library at web site/page: https://www.cfm.va.gov/TIL/index.asp
All Wayfinding and Signage shall follow VA’s Guidelines found at:
https://www.cfm.va.gov/til/spclRqmts.asp#SIGN
4.3. Records Management
4.3.1. Contractor shall comply with all applicable records management laws and regulations, as well as National Archives and Records Administration (NARA) records policies, including but not limited to the Federal Records Act (44 U.S.C.
chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, and those policies associated with the safeguarding of records covered by the Privacy Act of 1974 (5 U.S.C. 552a). These policies include the preservation of all records, regardless of form or characteristics, mode of transmission, or state of completion.
4.3.2. In accordance with 36 CFR 1222.32, all data created for Government use and delivered to, or falling under the legal control of, the Government are Federal records subject to the provisions of 44 U.S.C. chapters 21, 29, 31, and 33, the Freedom of Information Act (FOIA) (5 U.S.C. 552), as amended, and the Privacy Act of 1974 (5 U.S.C. 552a), as amended and must be managed and scheduled for disposition only as permitted by statute or regulation.
4.3.3. In accordance with 36 CFR 1222.32, Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law. Electronic records and associated metadata must be accompanied by sufficient technical documentation to permit understanding and use of the records and data.
4.3.4. El Paso Veteran Affairs Health Care System (EPVAHCS) and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Records may not be removed from the legal custody of EPVAHCS or destroyed except for in accordance with the provisions of the agency records schedules and with the written concurrence of the Head of the Contracting Activity. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. In the event of any unlawful or accidental removal, defacing, alteration, or destruction of records, Contractor must report to EPVAHCS. The agency must report promptly to NARA in accordance with 36 CFR 1230.
4.3.5. The Contractor shall immediately notify the appropriate Contracting Officer upon discovery of any inadvertent or unauthorized disclosures of information, data, documentary materials, records or equipment. Disclosure of non-public information is limited to authorized personnel with a need-to-know as described in the [contract vehicle]. The Contractor shall ensure that the appropriate personnel, administrative, technical, and physical safeguards are established to ensure the security and confidentiality of this information, data, documentary material, records and/or equipment is properly protected. The Contractor shall not remove material from Government facilities or systems, or facilities or systems operated or maintained on the Government’s behalf, without the express written permission of the Head of the Contracting Activity. When information, data, documentary material, records and/or equipment is no longer required, it shall be returned to EPVAHCS control or the Contractor must hold it until otherwise directed. Items returned to the Government shall be hand carried, mailed, emailed, or securely electronically transmitted to the Contracting Officer or address prescribed in the [contract vehicle]. Destruction of records is EXPRESSLY PROHIBITED unless in accordance with Paragraph (4).
4.3.6. The Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, contracts. The Contractor (and any sub-contractor) is required to abide by Government and EPVAHCS guidance for protecting sensitive, proprietary information, classified, and controlled unclassified information.
4.3.7. The Contractor shall only use Government IT equipment for purposes specifically tied to or authorized by the contract and in accordance with EPVAHCS policy.
4.3.8. The Contractor shall not create or maintain any records containing any non-public EPVAHCS information that are not specifically tied to or authorized by the contract.
4.3.9. The Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected from public disclosure by an exemption to the Freedom of Information Act.
4.3.10. The EPVAHCS owns the rights to all data and records produced as part of this contract. All deliverables under the contract are the property of the U.S.
Government for which EPVAHCS shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.
Any Contractor rights in the data or deliverables must be identified as required by FAR 52.227-11 through FAR 52.227-20.
4.3.11. Training. All Contractor employees assigned to this contract who create, work with, or otherwise handle records are required to take VHA-provided records management training, Talent Management System (TMS) Item #10176, Privacy and Information Security, Rules of Behavior. The Contractor is responsible for confirming training has been completed according to agency policies, including initial training and any annual or refresher training.
- End of Statement of Work -
A.5 Drawings and Specifications See attached document: 756-25-100_CANARIIS Booster Specifications - For Reference
ONLY.
See attached document: 756-21-100_ Goulds Duplex Booster Pump Specs.
See attached document: 756-21-100_VAEP_Water Booster Pump - Addendum_001_Drawings.
A.6 Special Standard of Responsibility
Special Standard of Responsibility
Solicitation Submittal Requirements:
The Offeror shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)
1. OSHA or EPA Violation(s):
Offerors shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Offeror has no more than three serious, or one repeat, or one willful OSHA or EPA violation(s) in the past 3 years.
2. Experience Modification Rate (EMR):
Offerors shall provide documentation to show that the offeror has an Experience Modification Rate (EMR) of equal to or less than 1.0.
3. Limitation on Subcontracting:
IAW VAAR 852.219-75 each offeror will review the clause and complete the certificate included in the clause. This certificate will be complete prior to solicitation closing and submitted with the proposal documents. Failure to comply with this requirement will result in removal of proposal for consideration for award.
A.7 INSTRUCTIONS FOR CALCULATION OF SELF-PERFORMED WORK
IAW “Limitations on Subcontracting” (VAAR 852.219-73)
OFFEROR’S SELF PERFORMED ESTIMATED CALCULATIONS
At the time of proposal Offeror’s are required to complete.
a) Offeror’s total proposed price: $ __________
b) Amount projected to be paid to non *VetCert listed SDVOSBs: $ __________
c) Offeror’s percentage of estimated Non *VetCert work (b/a X 100 = %) __________%
d) Offeror’s percentage of estimated self-performed work (100 – c = %) __________%
A/E-Services. In the case of a contract for services (except construction), it will not pay more than 50% of the amount paid by the government to it to firms that are not SBA Certified VOSBs.
General construction. In the case of a contract for general construction, it will not pay more than 85% of the amount paid by the government to it to firms that are not SBA Certified SDVOSBs.
Special trade contractors. In the case of a contract for special trade contractors, it will not pay more than 75% of the amount paid by the government to it to firms that are not SBA Certified SDVOSBs.
*SBA certification database on the SBA Veterans Small Business Certification Program (VetCert) portal at https://veterans.certify.sba.gov/]
A.8 PREPARATION OF BIDS
PREPARATION OF BIDS
To assure responsiveness of submitted bids, bidders shall follow the instructions contained herein. These instructions prescribe the format of the bid and describe the approach for development and presentation of the bid package. These instructions are designed to ensure the submission of necessary information.
Bidders are required to meet all solicitation requirements, including terms and conditions, representations and certifications. The contracting officer has determined there is a high probability of adequate price competition in this acquisition. Interested bidders shall be solely responsible for all costs associated with this solicitation including but not limited to the preparation of bids.
1. Bids shall be (1) submitted on the forms furnished by the Government or on copies of those forms; and (2) manually signed. The person signing a bid shall initial each erasure or change appearing on any proposal form.
2. Bidders shall submit proposed prices for ALL bid items as listed in the bid schedule.
Failure to submit proposed prices for ALL bid items will result in the bid being rejected as nonresponsive without further consideration.
3. Alternate bids Will NOT be considered unless this solicitation authorizes their submission.
4. BID SUBMISSION:
The following documents shall be submitted to the Contracting Officer on the due date and time listed on the SF 1442. Electronic bids transmitted through email are the only authorized form of submission under this solicitation. One (1) emailed electronic PDF document of the bid shall be submitted at the time of the bid opening. The emailed electronic PDF document of the bid shall be organized as follows:
a) Standard Form 1442: Page 2 of the SF1442 shall be completed and signed by the signatory authority. All blocks under section “OFFER” on page 2 of SF1442 (Item 14 thru 20C) shall be completed.
b) Price Schedule: Schedule of Prices/Description shall be completed by the bidder
c) Standard Form 30: Amendment of Solicitation: Bidders shall be solely responsible for monitoring Government’s website https://sam.gov for amendments to this solicitation if any and acknowledge them in accordance with the requirements stipulated in this solicitation and amendments. Page 1 (Item 15A-15C) shall be completed.
d) Bid Bond: Duly executed Bid Bond/Guarantee: IAW FAR 52.228-1 Bid guarantee is required if the bid is expected to exceed $150,000. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000.
e) Representations and Certifications Clause: 52.204-8 Annual Representations and Certifications: since 52.204-7 is incorporated by reference in this solicitation, paragraph (d) under clause 52.204-8 applies to this contract. Bidder shall check the box in front of paragraph (2)(i) under clause 52.204-8 and indicate any changes under paragraph (d) of clause 52.204-8. If no change has been made to the bidder’s annual representations and certifications accessed through https://sam.gov, please indicate “NONE”. Print out this clause in its entirety and submit it with the bid or you can submit your SAM.gov Reps and Certs on-line printout.
f) SBA VetCert Registration (evidence of SDVOSB Status): Evidence of certification from the U.S. Small Business Administration (SBA) Veteran Small Business Certification (VetCert) Program showing your firm as an eligible, visible, and certified Service-Disabled Veteran Owned Small Business (SDVOSB). To be eligible for award, Bidders are required to register their businesses at My SBA Certifications: https://certifications.sba.gov.
g) SAM.gov Registration: Please be advised that to be eligible for award, Bidders are required to register their businesses at https://sam.gov and complete the Reps and Certs Section. The bidder shall have an active registration in SAM at the time of bid submission otherwise the Contracting Officer shall deem the bidder’s bid non-responsive to the solicitation requirements (See FAR 52.204-7).
h) VAAR Clause 852.219-75 VA Notice of Limitations on Subcontracting: Print out this clause in its entirety and submit the completed certification portion with the bid.
i) Calculations on Self-Performed Work: Complete the Self-Performed Work Calculations and return with the bid.
j) 52.219-28 Post-Award Small Business Program Representation: (Required if Applicable) If the Contractor does not have representations and certifications in SAM.gov or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete Section (h) of this clause. Print out this clause in its entirety and complete Section (h), the authorized signer must sign and date.
k) 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment: Print out this clause in its entirety and complete (d)(1) and (d)(2).
l) Vets-4212 Forms: The bidder shall affirm that they have filed the Vets 4212 Report forms for prior fiscal year if the bid is expected to exceed $150,000.
Contractors are required to submit a required annual Form VETS-4212, Federal Contractor Veterans' Employment Report in all cases where the contractor or subcontractor has received an award of $150,000 or more in any fiscal year.
Contracting Officers are prohibited from awarding a contract to a contractor that has not submitted a required VETS-4212 Report with respect to the preceding fiscal year if the contractor was subject to the reporting requirement of 38 U.S.C.
4212(d). Submit this report as soon as possible, if not already submitted, to avoid delays in the contract award process. For more information on this requirement and/or for completing the web-based reporting form, visit the following website https://www.dol.gov/agencies/vets/programs/vets4212. See FAR provision 52.222-38, Compliance with Veterans' Employment Reporting Requirements under Representations and Certifications and FAR clause 52.222- 37, Employment Reports on Veterans.
m) SAFETY:
The Bidder shall submit the following information: (For a partnership or joint venture, the following submittal requirements are required for each Contractor who is part of the partnership or joint venture and for the entity itself. EMR shall not be submitted for subcontractors.)
(1) Occupational Safety and Health Administration (OSHA) and Environmental Protection Agency (EPA) Violation(s):
Bidders shall provide Summary of Work-Related Injuries and Illnesses, affirming that the Bidder has no more than three serious, or one repeat, or one willful Occupational Safety and Health Administration (OSHA) and Environmental Protection Agency (EPA) violation(s) in the past 3 years.
(2) Experience Modification Rate (EMR):
Bidders shall provide documentation (letter from insurance carrier) to show that the bidder has an Experience Modification Rate (EMR) of equal to or less than 1.0. If a Bidder’s EMR is above 1.0, Bidder must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.
Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and Puerto Rico shall obtain their EMR rating from their state-run worker’s compensation insurance rating bureau.
If the NCCI cannot issue an EMR because the Bidder lacks insurance history, Bidder shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead and include a letter from the NCCI indicating that it has assigned Bidder a Unity Rating of 1.0.
The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.
This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
Note: Failure to submit all aforementioned documents (a-m) shall result in a nonresponsive bid and the bid shall not be considered.
5. Bids shall be submitted electronically to the email address below by or on the due date set forth in this solicitation, Page 1, Form SF1442, Block 13:
a) Contracting Officer: Andres Garcia | Email: andres.garcia1@va.gov.
The Email Subject Line Shall include the Solicitation Number and Project Title
It is solely the responsibility of the bidders to ensure the Government receives the bids before or on the exact due date and time set forth in this solicitation. Emails are limited to five (5) MB.
REQUESTS FOR INFORMATION (RFIs)
1. To obtain clarifications and/or additional information concerning the solicitation requirements, specifications and/or drawings, or any other issue pertaining to the advertisement for bids, submit an RFI via email to the attention of the Contracting Officer at andres.garcia1@va.gov. The email subject line shall include the Solicitation number and project title.
a. RFIs related to the project technical documents must be specific identifying section, paragraph and page no. of the specifications or cite the drawing number and must be in question format.
b. RFIs related to the solicitation or other related documents shall refer to the specific provision, clause, etc. All requests for information must be submitted via email to the Contracting Officer for action no later than the date shown in Block 10 of the Standard Form 1442, Solicitation, Offer and Award. No phone or faxed inquiry will be accepted.
No questions will be answered after this date unless determined to be in the best interest of the Government as deemed by the Contracting Officer.
2. Government’s responses to inquiries will be issued in the form of an amendment to the original solicitation and posted to the same website where this solicitation is posted:
https://sam.gov. All interested bidders including those submitting inquiries are required to monitor the above website for any posted amendments and acknowledge them in accordance with the instructions provided in the amendments as well as in this solicitation.
BID OPENING
1. A public Bid Opening shall be a virtual public bid opening conducted the day bids are due. The time for this virtual public bid opening will start at 1:45 p.m. Mountain Standard Time (MST) with bid opening beginning promptly at 02:00 p.m. MST.
2. Attendance at the bid opening is not mandatory. If you are interested in attending, you are to email the Contracting Officer a separate email requesting attendance via email to:
andres.garcia1@va.gov. You must have access to Microsoft Teams or the ability to dial-in. No other opportunities for a bid opening will be provided. Questions will not be answered at the bid opening. Bids shall be opened by the bid opening officer and recorded on an official Bid Abstract.
Bid Abstracts will be available upon request via email to: andres.garcia1@va.gov.
Bid Opening Tentative Schedule:
Date: Day that bids are due 1:45 PM MST: Meeting Begins 1:55 PM MST: Instructions for Bid Opening 1:59 PM MST: One Minute Announcement of Opening of Bids 2:00 PM MST: Bid Opening Begins
BID EVALUATION
1. All bids submitted on time and in accordance with provision 52.214-5 shall be evaluated for the conformance to all requirements of this solicitation. Any bid that fails to conform to the requirements of this solicitation shall be determined non-responsive and therefore rejected.
2. Bid prices shall be evaluated as follows:
a) For the purpose of determining the low bid conforming to the solicitation, the Government shall evaluate the proposed total schedule bid items and make an award on the proposed total schedule bid items to the lowest responsive bidder.
BASIS FOR CONTRACT AWARD
1. Award shall be made to the lowest responsive bidder whose bid conforms to this solicitation and is deemed the most advantageous to the Government, considering only price and price-related factors specified in this solicitation.
2. Award shall be made in accordance with provision 52.214-19 Contract Award—Sealed Bidding—Construction incorporated by reference in this solicitation.
3. Determination of Responsibility:
a) Pursuant to FAR 9.103 prescribing that purchases shall be made from, and contracts shall be awarded to, responsible prospective contractors only, the Government will perform the determination of responsibility on the apparently lowest bidder whose bid is deemed conforming to the solicitation as stated under paragraph a). The Government’s determination of responsibility will be performed in accordance with FAR 9.1 and shall include but not limited to the review of all federal excluded or debarred lists from different U.S. departments, and from the SAM.gov Responsibility/Qualification (R/Q) records, FedDataCheck Contractor Responsibility Assessment (CRA) Report; Dun and Bradstreet (D&B) Report;
Contractor Performance Assessment Reporting System (CPARS), and Electronic Subcontract Reporting System (eSRS).
b) Since this solicitation is set aside 100% for Service-Disabled Veteran-Owned Small Business (SDVOSB), the Government shall refer the matter to the Small Business Administration which will decide whether to issue a Certificate of Competency if the Government deems a potential SDVOSB awardee non-responsible.
OTHER IMPORTANT BIDDER INFORMATION:
WAGE DETERMINATION: The wage determination is included as an attachment to the solicitation and is applicable to any resultant contract. If necessary, subsequent revisions shall be posted to the solicitation via amendment prior to bid opening. Revision may also be applicable prior to any contract award. Wage determinations are available at https://sam.gov/.
EXCLUSIONS: Exclusion record identifies parties excluded from receiving Federal contracts, certain subcontracts, and certain types of Federal financial and non-financial assistance and benefits. Exclusions are also referred to as “suspensions” and “debarments.” The contractor is required to check exclusions located at https://sam.gov/ for each person or business providing services under this contract. During the performance of this contract the Contractor is prohibited from using any individual or business with active exclusions.
VHA-Pre-Construction Risk Assessment (VHA-PCRA): A VHA-PCRA is a formal assessment protocol required to identify potential safety risks in the health care facility environment (that evaluates the impacts of construction, renovation, and maintenance) and create mitigation strategies to prevent, reduce or eliminate them prior to the initiation of any construction-related activities. The assessment includes an assessment of potential risks to occupants for air quality, infection prevention and control, utility requirements, noise, vibration and any other hazards applicable to the work. The VHA-PCRA may also include a detailed VHA-Infection Control Risk Assessment (VHA-ICRA) to assess infection-related risks to patients and residents. VHA-PCRA for bidder awareness of VA assessed risks and required mitigation(s) that may impact contractor work activities are attached.
VHA-Infection Control Risk Assessment (VHA-ICRA). For those construction activities where the initial infection control review within the VHA-PCRA identifies potential risks of infectious disease transmission affecting the care, treatment or services of patients or residents, a detailed analysis must be conducted using the VHA-ICRA form to document an in-depth infection risk assessment(s) and identification of mitigation actions/activities. A VHA-ICRA is a systematic process, conducted as part of the VHA-PCRA, that determines the level of potential infection risks to patients or residents due to the physical environment throughout the construction and commissioning process and defines controls to reduce these infection related risks. VHA-ICRA for bidder awareness of VA assessed risks and required mitigation(s) that may impact contractor work activities are attached.
CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (CPARS)
1. As prescribed in Federal Acquisition Regulation (FAR) Part 42.15, the Department of Veterans Affairs (VA) evaluates contractor past performance on all construction contracts that exceed $750,000 and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS.
2. Each contractor whose construction contract award is estimated to exceed $750,000 is required to register with the CPARS database at the following web address: https://www.cpars.gov/ Help in registering can be obtained by contacting Customer Support Desk at 207-438-1690. Registration should occur no later than thirty days after contract award and must be kept current should there be any change to the contractor's registered representative.
3. For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor's performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor's designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.
4. Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government's evaluation being placed on file in the database with a statement that the “contractor failed to respond.”
A.9 PCRA/ICRA
See attached document: 756-25-100 Install Water Booster Pumps PCRA.
See attached document: 756-25-100 Install Water Booster Pumps ICRA.
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE
AND BONDS
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO
BIDDERS/OFFERORS
FAR
Number
Title Date
52.204-7 SYSTEM FOR AWARD MANAGEMENT NOV 2024
52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE
REPORTING
AUG 2020
52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017
52.211-6 BRAND NAME OR EQUAL AUG 1999
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS DEC 2016
52.214-4 FALSE STATEMENTS IN BIDS APR 1984
52.214-5 SUBMISSION OF BIDS DEC 2016
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS APR 1984
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND
WITHDRAWALS OF BIDS
NOV 1999
52.214-18 PREPARATION OF BIDS—CONSTRUCTION APR 1984
52.214-19 CONTRACT AWARD—SEALED BIDDING—
CONSTRUCTION
AUG 1996
52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE APR 1991
52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY APR 1991
52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID
GUARANTEE)
FEB 2021
852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY
ACCESSIBILITY NOTICE
FEB 2023
2.1 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—
SECONDARY SITE OF THE WORK (MAY 2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall…