About this file
This Addendum No. 1 is issued by the State of Michigan's Department of Technology, Management and Budget (DTMB) and Department of Natural Resources (DNR) for the Yankee Springs Shooting Range project. The addendum, dated April 11, 2025, provides clarifications and responses to bidder questions for a construction project scheduled to start in May 2025 and be completed by mid-September 2025. Key project details include underground electrical work to be trenched along the entire length except under a gravel road, on-site disposal of site spoils and removed trees, and coordination requirements with Consumers Energy for transformer installation.
The addendum introduces Alternate No. 01, which requests bidders to state the amount required to provide a new utility pole mounted transformer with primary cabling installation. It also updates various specification and drawing documents, including adding a topographic mapping sheet, modifying site plan details, and updating general conditions related to prevailing wages. The project will involve constructing a shooting range facility, with state inspectors overseeing construction, and requires the contractor to coordinate site access and specific installation details with the DNR, including vault preparation, gate specifications, and salvaging existing backstops and benches.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB/DNR YANKEE SPRINGS SHOOTING RANGE| April 11, 2025 Page 1 | 3
ADDENDUM NO.1
State of Michigan Department of Technology, Management and Budget Yankee Springs Shooting Range File No:751/24162.DPL April 11, 2025
TO ALL BIDDERS:
This ADDENDUM is hereby included in and made part of the Contract Documents whether or not attached thereto. All requirements of the original Specifications and Drawings shall remain in force except as noted by this ADDENDUM No. 1.
THE PURPOSE OF THIS ADDENDUM IS TO CHANGE THE FOLLOWING ITEMS IN THE
CONSTRUCTION DOCUMENTS:
GENERAL CLARIFICATIONS / RESPONSE TO BIDDER’S QUESTIONS
1. Question: What is the project schedule?
• Answer: Project is expected to start on May 2025 and be completed by mid-September 2025.
2. Question: David Lenz noted that there is an update for the Prevailing wage rates.
• Answer: New directions will be provided for Prevailing Wage electronic submission requirements per specifications update to the DCSPEC document.
3. Question: Will the DNR be coordinating the electrical transformer work with Consumers?
• Answer: No, contractor will be coordinating the work directly with Consumers.
4. Question: Is Consumers aware of this project? Is there contact information available?
• Answer: Yes, Consumers is aware of the project and the contact information of the person involved is Derrick Rosenberger. Further information will be provided to the selected bidders for the project.
5. Question: Confirm if the work complete by Consumers is to be issued as an alternate since there is no guarantee that the work will be completed on time or by mid-September 2025?
• Answer: Yes, the work by Consumers will be referenced as an alternate in the bid documents. Bid
Documents to be update prior to bidding.
6. Question: Will the underground conduits be installed by directional drilling or trenching along its entire length?
• Answer: The underground electric will be trenched the entire length except under the gravel road.
Plans have been updated to clarify and will be included in the addendum.
DTMB/DNR YANKEE SPRINGS SHOOTING RANGE| April 11, 2025 Page 2 | 3
7. Question: There is soils report available?
• Answer: Yes, the soil report was included in the construction documents. Appendix VI in the specification.
8. Question: Can site spoils be disposed of on-site?
• Answer: Yes, site spoils can be disposed of or distributed on site. Selected contractor to coordinate on-site disposal with the DNR.
9. Question: Can removed trees be disposed of on-site?
• Answer: Yes, remove trees and brush may be disposed of on-site. All trees, tree trunks, and branches less than 12” in diameter are to be chipped down or shredded into mulch. Selected contractor to coordinate on-site disposal with the DNR.
10. Question: Will CAD files be provided for site staking?
• Answer: Yes, CAD files including benchmarks can be provided.
11. Question: What is the scope of the proposed vault?
• Answer: The vault location is indicated on the plans. The contractor will be responsible for digging the pit and having it ready for the Vault installation by others as coordinated by the DNR.
12. Question: Are the proposed gate specs available?
• Answer: DNR will provide specs for their preferred gate. We will include in our documents if received from the DNR prior to Bid opening.
13. Question: Who will be the contact person if access to the site is needed?
• Answer: Joseph Jandernoa will be the person to contact to provide access to the site.
Email: jandernoaj@michigan.gov . Phone: 269.795.9081.
14. Question: Confirm construction inspection process?
• Answer: Inspections will be provided through State of Michigan Inspectors.
15. Question: Will existing backstops and benches located on the east side of the site where the range building will be located be salvaged?
• Answer: Yes, the backstop and benches are to be salvaged and turned over the DNR.
16. Question: ON drawings sheet A522, wall sections note 5/8” tongue and groove? Should this be 5/4” tongue and groove to match the other wall sections details?
• Answer: Yes, tongue and groove should all be 5/4”.
mailto:jandernoaj@michigan.gov
DTMB/DNR YANKEE SPRINGS SHOOTING RANGE| April 11, 2025 Page 3 | 3
TO THE SPECIFICATIONS
1. Cover Page:
a. Added Addendum No. 1: April 11, 2025.
2. Bid Summary – Schedule of Alternates:
a. Added Alternate No. 01 - State the Amount required to provide a new utility pole mounted transformer including the installation of primary cabling from the pole mounted transformer to the meter located on the new structure.
3. Table of Contents:
a. Drawings/Architectural – added G000.
b. Drawings/Civil – Added X100.
4. Division 00 – Bidding Requirements and Contract Conditions:
a. Section 00700 General Conditions
i. Removed Article 2.5 and Replaced with new 2.5 Prevailing Wages, Access to
Payroll Records and Asbestos Abatement Project requirements:.
TO THE DRAWINGS
1. Drawing Sheet G000 – Cover Sheet (Reissued)
a. Updated Date and Description to 04/08/2025 – Addendum 1.
b. Added sheet X100 Topographic Mapping.
2. Drawing Sheet X100 – Topographic Mapping (New)
a. Added topographic mapping to the plans.
3. Drawing Sheet C200 – Site Plan (Reissued)
a. Added keynote G1 clarifying directional drilling the electrical conduit under the gravel road.
b. Added keynote J to indicate the proposed permanent chain link fence along the north side of the proposed building.
c. Updated gravel section on keynote A.
d. Updated keynote I to clarify the adjustment of the gravel drive to avoid removing large trees.
Attachments:
Specification Section - DCSPEC Bidding and Construction Document Minor Projects
Drawing Sheet G000.pdf
Drawing Sheet X100.pdf
Drawing Sheet C200.pdf
Yankee Springs Shooting Range Pre-Bid Attendance List – 04/07/2025
END OF ADDENDUM NO. 01