245080 Sunnyview Road NE and Hollywood Drive NE Pedestrian Crossing Improvements
Solicitation number
S-KS0043-00012168
Issued by
Marion County, Oregon

About this file

This is a bid tabulation document for the Sunnyview Road NE and Hollywood Drive NE Pedestrian Crossing Improvements project in Salem, Oregon, managed by Josh Adelman, PE as Project Manager. The project includes traffic control across three stages, earthwork, erosion control measures, concrete and asphalt work, curbing, landscaping, fencing, signing and striping, and installation of a Rectangular Rapid Flashing Beacon System. Key quantities include 35 cubic yards of common excavation, 110 linear feet of sawed joints, 28 square yards of HMAC paving, 65 linear feet of PCC curb and gutter, and 620 square feet of permanent seeding. The bid closing date is listed as January 28, 2025.

Civil West Construction, LLC of Salem was the low bidder at $107,265.91, followed by Knife River Corporation-Northwest at $125,956.00 and A.B Utility Contractors, Inc. at $128,291.00. The Engineer's Estimate for the project was $188,950.00. Four bidders were marked as non-responsive, and the remaining bids ranged from $128,383.00 to $226,680.00. The project includes 17 major bid items, with the Rectangular Rapid Flashing Beacon System being the largest single item at $60,000.00 in the Engineer's Estimate, but bid at $30,188.77 by the low bidder.

View the file

Other files

File Type Posted
721504-Intent to Award Letter.pdf PDF
245087 Supplemental Letter 3.pdf PDF
Supplemental Letter 1.pdf PDF
721504 Final Plans - Signed.pdf PDF
721504-Project Manual.pdf PDF
721504-Addendum 1.pdf PDF
721504-Bid Opening Register with Rank ~1.pdf PDF
245080 Bid Opening Zoom Link.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TABULATION OF BIDS FOR:

Average of 3

(*) figures changed to reflect accurate extension or addition 2 nd

Low Bidder 3 rd

Low Bidder Lowest Bidders

SCHED NO. QUANTITY

UNIT OF

MEASURE UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE UNIT PRICE UNIT PRICE

1 Mobilization All Req'd Lump Sum 23,000.00 23,000.00 11,200.00 11,200.00 13,575.00 12,772.00 12,515.67

Base 2 Temporary Traffic Control

Base a Traffic Safety and Control: Stage 1 All Req'd Lump Sum 4,000.00 4,000.00 5,195.17 5,195.17 1,465.00 2,459.00 3,039.72

Base b Traffic Safety and Control: Stage 2 All Req'd Lump Sum 4,000.00 4,000.00 1,614.49 1,614.49 1,465.00 2,459.00 1,846.16

Base c Traffic Safety and Control: Stage 3 All Req'd Lump Sum 2,000.00 2,000.00 729.12 729.12 1,465.00 2,459.00 1,551.04

Base 3 Earthwork

Base a Common Excavation 35 Cu. Yd. 160.00 5,600.00 271.76 9,511.60 148.41 140.00 186.72

Base b Clearing and Grubbing All Req'd Lump Sum 1,000.00 1,000.00 3,696.49 3,696.49 1,865.00 395.00 1,985.50

Base 4 Restoration and Cleanup All Req'd Lump Sum 3,000.00 3,000.00 355.04 355.04 1,715.00 4,061.00 2,043.68

Base 5

Erosion Prevention and Sediment

Control

Base a Erosion Control All Req'd Lump Sum 1,200.00 1,200.00 3,734.29 3,734.29 2,250.00 984.00 2,322.76

Base b Fiber Rolls (Wattles) 80 Lin. Ft. 12.00 960.00 2.60 208.00 4.50 6.00 4.37

Sunnyview Road NE and Hollywood Drive NE Pedestrian Crossing Improvements

Cilvil West Construction, LLC

P.O Box 6082

Low Bidder

Salem, OR 97304

Project Number:

Bid/Contract Number:

Closing Date:

721504

245080 Josh Adelman, PE

Project Manager

#2 Knife River

Corporation-

#3 A.B Utility

Contractors, 1/28/2025

Engineer's

Estimate

\\pubwks\pwfiles\Group\Engineering\Projects\CIP\721504 Sunnyview-Hollywood Ped Crossing\11 Ad Bid Award\Contract Book\721504-aba-master.xlsm\Bid Tabulation

Tabulation of Bids jadelman Snapshot

(*) figures changed to reflect accurate extension or addition 2 nd

Low Bidder 3 rd

Low Bidder Lowest Bidders

SCHED NO. QUANTITY

UNIT OF

MEASURE UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE UNIT PRICE UNIT PRICE

Sunnyview Road NE and Hollywood Drive NE Pedestrian Crossing Improvements

Cilvil West Construction, LLC

P.O Box 6082

Low Bidder

Salem, OR 97304

Project Number:

Bid/Contract Number:

Closing Date:

721504

245080 Josh Adelman, PE

Project Manager

#2 Knife River

Corporation-

#3 A.B Utility

Contractors, 1/28/2025

Engineer's

Estimate

Base c Prefabricated Fileter Inserts (Silt Sacks) 4 Each 225.00 900.00 44.80 179.20 148.00 126.00 106.27

Base d Concrete Management Facilities All Req'd Lump Sum 2,000.00 2,000.00 632.80 632.80 1,160.00 492.00 761.60

Base 6

Sawed Joints, Portland Cement Concrete or Asphalt (All Depths) 110 Lin. Ft. 10.00 1,100.00 10.00 1,100.00 14.50 6.00 10.17

Base 7

6 inches of Level 3, 1/2-inch Dense

Graded HMAC Over 12 inches of 1"-0

Aggregate Base 28 Sq. Yd. 400.00 11,200.00 138.51 3,878.28 223.17 256.00 205.89

Base 8

Temporary Asphalt Pavement

Replacement (2 inches Thick) 28 Sq. Yd. 150.00 4,200.00 74.12 2,075.36 45.66 43.00 54.26

Base 9 Curbs

Base a

Type A, PCC Curb and Gutter over

Variable Thickness of 1"-0 Aggregate

Base 65 Lin. Ft. 95.00 6,175.00 22.01 1,430.65 70.83 108.00 66.95

Base b

Landscape Curb Over 2-inches of 1"-0

Aggregate Base 19 Lin. Ft. 90.00 1,710.00 6.61 125.59 35.06 85.00 42.22

Base 10

Miscellaneous Portland Cement

Concrete (PCC)/Aggregate Base

Base a

Sidewalk, 6 inches of PCC Over 2 inches of 1"-0 Aggregate Base 52 Sq. Yd. 370.00 19,240.00 207.52 10,791.04 395.87 167.00 256.80

Base 11 Detectable Warning Surface 24 Sq. Ft. 85.00 2,040.00 25.48 611.52 58.42 47.00 43.63

Base 12 Landscaping

Base a Permanent Seed Mix No. 1 620 Sq. Ft. 3.00 1,860.00 0.17 105.40 1.93 2.00 1.37

\\pubwks\pwfiles\Group\Engineering\Projects\CIP\721504 Sunnyview-Hollywood Ped Crossing\11 Ad Bid Award\Contract Book\721504-aba-master.xlsm\Bid Tabulation

Tabulation of Bids

(*) figures changed to reflect accurate extension or addition 2 nd

Low Bidder 3 rd

Low Bidder Lowest Bidders

SCHED NO. QUANTITY

UNIT OF

MEASURE UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE UNIT PRICE UNIT PRICE

Sunnyview Road NE and Hollywood Drive NE Pedestrian Crossing Improvements

Cilvil West Construction, LLC

P.O Box 6082

Low Bidder

Salem, OR 97304

Project Number:

Bid/Contract Number:

Closing Date:

721504

245080 Josh Adelman, PE

Project Manager

#2 Knife River

Corporation-

#3 A.B Utility

Contractors, 1/28/2025

Engineer's

Estimate

Base b Planting Soil Mixture, 3-inch Depth 620 Sq. Ft. 3.00 1,860.00 1.48 917.60 2.92 2.00 2.13

Base c Bark Mulch, 3-inch Depth 170 Sq. Ft. 8.00 1,360.00 4.11 698.70 3.02 4.00 3.71

Base 13 Fencing

Base a Chain Link Fence 75 Lin. Ft. 100.00 7,500.00 13.02 976.50 45.31 84.00 47.44

Base 14 Signing and Striping

Base a Pavement Line Removal 150 Lin. Ft. 15.00 2,250.00 3.74 561.00 3.62 20.00 9.12

Base b Pavement Bar, Type B-HS 270 Sq. Ft. 20.00 5,400.00 14.56 3,931.20 15.71 17.00 15.76

Base c Steel Pipe Sign Supports 2 Each 600.00 1,200.00 319.42 638.84 245.00 1,953.00 839.14

Base d New Permanent Sign In-Place (All Types) 22 Sq. Ft. 85.00 1,870.00 26.60 585.20 60.41 22.00 36.34

Base e Relocate Sign 1 Each 500.00 500.00 182.78 182.78 1,210.00 1,860.00 1,084.26

Base 15 Electrical Conduit

Base a 2-inch Electrical Conduit, Complete 35 Lin. Ft. 85.00 2,975.00 34.81 1,218.35 5.00 101.00 46.94

Base b

HDD Installed 2-inch Roadway Electrical

Conduit, Complete 65 Lin. Ft. 90.00 5,850.00 124.88 8,117.20 134.72 128.00 129.20

Base 16 Underground Enclosures

\\pubwks\pwfiles\Group\Engineering\Projects\CIP\721504 Sunnyview-Hollywood Ped Crossing\11 Ad Bid Award\Contract Book\721504-aba-master.xlsm\Bid Tabulation

(*) figures changed to reflect accurate extension or addition 2 nd

Low Bidder 3 rd

Low Bidder Lowest Bidders

SCHED NO. QUANTITY

UNIT OF

MEASURE UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE UNIT PRICE UNIT PRICE

Sunnyview Road NE and Hollywood Drive NE Pedestrian Crossing Improvements

Cilvil West Construction, LLC

P.O Box 6082

Low Bidder

Salem, OR 97304

Project Number:

Bid/Contract Number:

Closing Date:

721504

245080 Josh Adelman, PE

Project Manager

#2 Knife River

Corporation-

#3 A.B Utility

Contractors, 1/28/2025

Engineer's

Estimate

Base a

Type 2 Junction Box (13-inch x 24-inch x

18-inch) with Lid Marked "TRAFFIC

SIGNAL" 3 Each 1,000.00 3,000.00 691.91 2,075.73 746.41 651.00 696.44

Base 17

Rectangular Rapid Flashing Beacon

System, Complete All Req'd Lump Sum 60,000.00 60,000.00 30,188.77 30,188.77 32,566.60 31,739.00 31,498.12

Total 188,950.00 107,265.91

2nd Low Bidder 125,956.00

3rd Low Bidder 128,291.00

128,383.00

141,188.00

141,369.00

141,403.99 non-responsive non-responsive non-responsive non-responsive

188,000.00

191,001.00

226,680.00

#7 SLE Inc.

#8 Dalke Construction Co, Inc.

#2 Knife River Corporation- Northwest

#3 A.B Utility Contractors, Inc.

#14 HP Civil Inc.

#9 Turney Excavation, Inc

#10 Brown Contracting, Inc

#11 Roy Houck Construction LLC

#12 Pacific Excavation LLC

#13 Aaken Corporation

#4 Gelco Construction Co

#5 North Santiam Paving Co.

#6 R&R General Contractors, Inc

Remaining Bidders