Q&A_No._02.pdf
PDF 30 KB Posted
- Attached to
- Tanzania Vector Control ActIvity (TVCA)
- Solicitation number
- 72062119R00001
About this file
This document provides clarification to questions regarding the Tanzania Vector Control Activity solicitation number 72062119R00001 issued by the US Agency for International Development Tanzania.
The clarifications address key personnel costs under objectives 3 and 5 of the cost-plus-fixed-fee portion of the contract. Initially, offerors were required to budget key personnel costs only under objectives 3 and 5. However, the clarification confirms that key personnel compensation and allowances should be allocated to all three components of the CPFF services, which include objectives 3 and 5 as well as optional services. Additionally, the cover letter range for the total estimated CPFF portion of the contract between $500,000 and $2,500,000 was amended to between $1,500,000 and $7,500,000 to incorporate the $1,000,000 to $5,000,000 range for optional services.
2nd round of questions received from potential offerors on TVCA RFP; and USAID responses.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tanzania Vector Control Activity (TVCA) RFP No. 72062119R00001
Questions and Answers No. 02
Questions Answers
Page 13 of the Q&A states that for the purpose of budgeting, offerors are required to budget the key personnel costs under objectives 3 and
5. This contradicts Q&A page 3 where “USAID confirms that key personnel compensation and allowances should be allocated to the CPFF services.” Since the CPFF services include not only objectives 3 and 5, but also optional services, please confirm that the key personnel costs should be allocated to all three components of the CPFF services (i.e., objectives 3 and 5 and optional services) or to only objectives 3 and 5.
Offerors are required to budget the key personnel costs under the objective 3 and 5 CPFF budget only.
The cover letter in the revised RFP states that the estimated cost of the CPFF portion of the contract is between $500,000 and $2,500,000. However, the RFP section B.3.1.(a) states that the total estimated cost plus fixed fee for the performance of services related to objectives 3 and 5 is between $500,000 and $2,500,000 and the estimated CPFF budget for the optional service is between $1M and $5M.
If the CPFF portion includes not only objectives 3 and 5, but also optional services (between $1 million and $5 million), the revised cover letter is incorrect. Please clarify.
The cover letter has been amended to clarify that the total estimated cost plus fixed fee portion of the contract is between $1,500,000 and $7,500,000 – range of between $500,000 and $2,500,000 for objectives 3 and 5 tasks and between $1,000,000 and $5,000,000 for the optional service.