This document is an amendment to a request for proposals for a Hope Index Perception Survey issued by the US Agency for International Development in El Salvador. The amendment clarifies that the contractor will provide survey deliverables including data collection five times over a five-year period from 2021 through 2025. It also answers questions from interested offerors, such as confirming the proposal should include costs for the full five-year period and clarifying the methodology does not need to be either longitudinal or cross-sectional.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFP 72051921R00004 Hope Index Perception Survey.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
Hope Index Perception Survey
RFP No. 72051921R00004
Amendment No. 01
The purpose of this amendment is to: A) amend F. 4 Deliverables, page 16; and B) provide answers to the questions submitted by interested parties in regards to this RFP.
A. Please take note of the following amendment under F. 4 Deliverables, page 16 of the
RFP. The changes are highlighted in yellow:
Original version:
The Offeror will provide deliverables 4, 5, 6, and 7 four times: a baseline in 2021, second data collection in 2022, third data collection in 2023, four data collection in 2024, and an end line in 2025. Depending on the availability of funds, the Mission can commission a sixth data collection in 2026. Unless anything changes, the Offeror will present deliverables 1, 2, and 3 only once before the baseline. Any change to the Work
Plan, the DMP, or the questionnaire must be approved by USAID/El Salvador.
Revised version:
The Offeror will provide deliverables 4, 5, 6, and 7 five times: a baseline in 2021, second data collection in 2022, third data collection in 2023, fourth data collection in
2024, and an end line in 2025. Depending on the availability of funds, the Mission can commission a sixth data collection in 2026. Unless anything changes, the Offeror will present deliverables 1, 2, and 3 only once before the baseline. Any change to the Work
Plan, the DMP, or the questionnaire must be approved by USAID/El Salvador.
B. The following Questions and Answers to the Hope Index Perception Survey RFP:
1. Is it possible to have the SOW in Spanish? Our organization is interested in applying.
USAID response: Thank you for your interest in participating in submitting a proposal for the Hope Index Perception Survey. Unfortunately, we are unable to provide the documents in Spanish since our official language for documentation is English.
2. On page 6, when you request a margin of error no larger than 2.5% and at least 90% confident, should it be an error of 2.5 and an interval of confidence of 97.5%?
USAID response: 90% is a reference to the confidence level, not to the confidence interval.
3. On the same page you mention about “hubs”, these include between 18 and 28 municipalities and the size must be representative to the hub, in which case, do you require that the sample be taken from all the municipalities or can we select the municipalities according to statistical criteria (randomly)?
USAID response: It is not a requirement that the sample must be taken from all the municipalities. In the technical proposal, the Offeror will describe and justify their approach and methodology to get the sample that satisfies the requirement of representativity at the hub level.
4. The “hope index” needs to be comparative or have the ability to be replicated in LAPOP?
, or only the general results? In page 6, it mentions that the index needs to be made with data collected and third-party sources. These third-party sources would be the data from
LAPOP?
USAID response: The offeror will use the data collected through the survey and any other data that the offeror considers necessary to build a robust hope index comparable on an annual basis and within the hubs. The additional data can be administrative data, third party sources, or own surveys. USAID is not proposing a specific data source, additional to this survey, to be included in the construction of the hope index.
The survey must mirror as much as possible, and when applicable, the questions of the instruments used for the bi-annual LAPOP (not all the questions in LAPOP questionnaires are applicable for the purposes of this study). USAID expects to make comparisons for the general results.
5. Is it necessary to subscribe to a bank of consultants?
USAID response: The RFP does not mention that it is necessary. The requirement is that the Contractor will propose the most adequate team size and composition. The team must be a combination of Specialists with relevant experience in similar studies.
6. Under F.4 Deliverables: “The Offeror will provide deliverables 4,5,6, and 7 four times; a baseline in 2021, second data collection in 2022, third data collection in 2023, four data collection in 2024, and an end line in 2025. Depending on the availability of funds, the
Mission can commission a sixth data collection in 2026. Unless anything changes, the
Offeror will present deliverables 1,2,3 only once before the baseline. Any change to the
Work Plan, the DMP, or the questionnaire must be approved by USAID/El Salvador”.
The text document should say “fourth collection” or indeed “four data collections in
2024” should be made? Confirm if they are four times or are five times, including the final line.
USAID response: This is a typo. The offeror will provide deliverables 4, 5, 6, and 7 five times, including for the end line. The reference for 2024 is the “fourth” data collection.
Please see Part A for the amended version.
Availability of funds of the contractor or contracting party?
USAID response: Depending on the availability of funds of USAID.
7. H.7 Language requirements: “Contractor personnel and/or consultants must have English and Spanish language proficiency as needed to perform technical services. USAID reserves the right to test proposed individuals to ensure that they have the required language capability as required by the Contract”.
Regarding the command of the English language, is it possible to include a person who performs the simultaneous translation work?
USAID response: If you would like to include a simultaneous translation, you can, but please note that this is not a requirement in the RFP. Be aware that all official verbal and written communication will be in English. The communication should not be delayed if the translator is not available. The clause in FAR Part 52.225-14 states that, “in the event of inconsistency between any terms of the contract and any translation into another language, the English language meaning shall control”.
8. Should the proposal (technical and budget) include the five surveys or just the first year?
USAID response: The proposal is for the five-year period.
9. Are you considering the yearly surveys to be cross-sectional or longitudinal (panel)?
USAID response: Neither longitudinal nor cross-sectional studies are required.
However, the offeror is free to propose in the technical proposal the approach and methodologies that they consider necessary to get the results of the SOW.
10. Is the cost proposal and narrative included in the 15-page limit?
USAID response: No, the cost proposal and narrative do not have a page limit. The
Technical Proposal does have a 15-page limit.
11. Is there a specific format (template) for the budget? Or can we just follow L.9 instructions?
USAID response: There is no specific format. You can follow L. 9 as a model and make sure to provide a narrative discussing the different elements to adequately justify the total price. Please include the budget for a period of performance of five years.
| topmostSubform[0]: |
| Page1[0]: |
| AmendmentNo[0]: 01 |
| Code[0]: |
| Code[1]: |
| AccountingData[0]: |
| A13[0]: |
| C13[0]: |
| D13[0]: |
| NameandTitleSigner[0]: |
| NameandTitleOfficer[0]: Craig Riegler, Contracting Officer |
| Description[0]: |
Amendment No. 01 to RFP 72051921R00004 is hereby issued to:
A) Amend F.4 Deliverables, page 16 B) Provide answers to the questions submitted by interested parties in regards to this RFP
| FacilityCode[0]: |
| Code[2]: |
| IssuedBy[0]: Regional Office of Acquisition and Assistance (ROAA) |
USAlD/EI Salvador 3450 San Salvador Place Washington. DC 20521-3450
| NameandAddress[0]: |
| AdministeredBy[0]: |
| ContractIDCode[0]: |
| ReqNumber[0]: |
| AmendmentNo[1]: 72051921R00004 |
| ModificationNo[0]: |
| ProjectNo[0]: |
| Page[0]: 1 |
| Pages[0]: 5 |
| EffectiveDate[0]: See block 16C |
| Dated9B[0]: 06/24/2021 |
| Dated10B[0]: |
| CheckBox9[0]: 1 |
| CheckBox10[0]: Off |
| CheckBox11[0]: 1 |
| CheckBox13A[0]: Off |
| CheckBox13B[0]: Off |
| CheckBox13C[0]: Off |
| CheckBox13D[0]: Off |
| IsNot[0]: 1 |
| Is[0]: Off |
| Extended[0]: Off |
| NotExtended[0]: 1 |
| DateSigned[0]: |
| DateSigned[1]: |
| Copies[0]: |
| CopiesReturned[0]: |
| 2021-06-24T13:48:27-0600 | |
| Craig Riegler |
File details come from the government source that posted it. Updated .