About this file
This document is an Addendum to the 720001 Crestview Waterline Project Manual for the state of Oregon. The project is estimated to be valued between $1.5M - $1.7M. The addendum provides clarification and changes to the original scope of work, including revised drawings and specifications. Key details include:
The project involves the construction of a new waterline system in the Crestview area. The work includes the installation of approximately 5,000 linear feet of 12-inch PVC water main, fire hydrants, valves, service connections, and related appurtenances. Bids are due on October 3, 2022, and the project is anticipated to be awarded on October 17, 2022. The contract term is 180 calendar days from the Notice to Proceed.
Pricing for the project is to be submitted on a unit cost basis. There are no set-asides or incumbent contractors identified. Funding for the project is provided through state and local sources, with no specific details provided on the amounts or sources. The addendum also includes information on a pre-bid conference held on September 19, 2022.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .