This is a 2018 Commercial Prevailing Wage Rate Schedule issued by the State of Michigan for Dowagiac Union School District in Cass County for a to-be-determined project. The document indicates the contract must be awarded by April 17, 2018, and provides detailed wage rates for various construction trades including asbestos/lead abatement, boilermakers, bricklayers, carpenters, cement masons, electricians, elevator constructors, glaziers, insulation workers, ironworkers, laborers, operating engineers, painters, plumbers/pipefitters, roofers, sheet metal workers, sprinkler fitters, and truck drivers.
The wage schedule specifies straight time hourly rates, time-and-a-half rates, and double time rates for each classification, along with apprentice rate schedules where applicable. It includes provisions for make-up days and alternate work schedules like four 10-hour days. The document serves as the official prevailing wage determination that must be posted on construction sites and followed by contractors and subcontractors working on this state-funded project in Cass County.
Text of this file
State of Michigan
| WHPWRequest@michigan.gov | ||||||||||||
| Official Request #: | 71 | |||||||||||
| Requestor: | Dowagiac Union School District | |||||||||||
| Project Description: | To be determined | |||||||||||
| Project Number: | To be determined | |||||||||||
| Cass County | ||||||||||||
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 1 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Asbestos & Lead Abatement Laborer | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| MLDC | 9/7/2017 | |||||||||||
| Asbestos & Lead Abatement Laborer | $41.30 | $55.23 | $69.16 | H | H | H | X | X | X | X | D | Y |
| Apprentice Rates: | ||||||||||||
| Trainee 600 hours + 1 calendar year | $30.22 | $33.28 | $41.73 | |||||||||
| comment | ||||||||||||
| 4 ten hour days @ straight time allowed Monday-Saturday, must be consecutive | ||||||||||||
| calendar days | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Asbestos, Lead and Mold Abatement, Hazardous Material Handler | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| AS207 | 3/27/2017 | |||||||||||
| Asbestos, Lead and Mold Abatement, Hazardous Material Handler | $40.75 | $54.25 | $67.75 | H | H | H | X | X | X | X | D | Y |
| comment | ||||||||||||
| Four ten hour days @ straight time allowed Monday-Saturday, must be consecutive | ||||||||||||
| calendar days | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Boilermaker | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| BO169 | 2/17/2015 | |||||||||||
| Boilermaker | $54.70 | $81.08 | $107.45 | H | H | H | H | H | H | H | D | Y |
| Apprentice Rates: | ||||||||||||
| 1st 6 months | $40.31 | $59.49 | $78.67 | |||||||||
| 2nd 6 months | $41.45 | $61.21 | $80.95 | |||||||||
| 3rd 6 months | $42.57 | $62.88 | $83.19 | |||||||||
| 4th 6 months | $43.69 | $64.57 | $85.43 | |||||||||
| 5th 6 months | $44.81 | $66.24 | $87.67 | |||||||||
| 6th 6 months | $48.63 | $72.50 | $96.36 | |||||||||
| 7th 6 months | $49.32 | $73.01 | $96.69 | |||||||||
| 8th 6 months | $51.58 | $76.40 | $101.21 |
| .................................................................................................................................................................................................................................. | ||
| ========================================================================================================= | ||
| Official Request #: | 71 | Official Rate Schedule |
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted |
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy |
| of all prevailing wage and fringe benefit rates | ||
| Project Number: | To be determined | prescribed in a contract. |
| County: | Cass | |
| Page 1 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 2 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Bricklayer | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| BR9-17-BL | 11/9/2016 | |||||||||||
| Bricklayer and Block | $44.75 | $57.48 | $70.20 | H | H | H | H | H | H | H | D | Y |
| Apprentice Rates: | ||||||||||||
| 0 - 749 hours | $33.67 | $41.13 | $48.58 | |||||||||
| 750 - 1,499 hours | $35.06 | $43.21 | $51.36 | |||||||||
| 1,500 - 2,249 hours | $36.44 | $45.28 | $54.12 | |||||||||
| 2,250 - 2,999 hours | $37.83 | $47.37 | $56.90 | |||||||||
| 3,000 - 3,749 hours | $39.21 | $49.43 | $59.66 | |||||||||
| 3,750 - 4,499 hours | $40.60 | $51.52 | $62.44 | |||||||||
| 4,500 - 5,249 hours | $41.98 | $53.59 | $65.20 | |||||||||
| 5,250 - 6,000 hours | $43.37 | $55.67 | $67.98 | |||||||||
| comment | make up day allowed | |||||||||||
| Saturday, Four 10s allowed M-F | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| BR9-17-S | 11/9/2016 | |||||||||||
| Stone, Artificial and Marble Masonry, and Pointer, Cleaner, Caulker | $44.75 | $57.48 | $70.20 | H | H | H | H | H | H | H | D | Y |
| Apprentice Rates: | ||||||||||||
| 0-749 hours | $35.06 | $43.21 | $51.36 | |||||||||
| 750-1499 hours | $36.44 | $45.28 | $54.12 | |||||||||
| 1500-2249 hours | $37.83 | $47.37 | $56.90 | |||||||||
| 2250-2999 hours | $39.21 | $49.43 | $59.66 | |||||||||
| 3000-3749 hours | $40.60 | $51.52 | $62.44 | |||||||||
| 3750-4499 hours | $41.98 | $53.59 | $65.20 | |||||||||
| comment | ||||||||||||
| Four 10s allowed M-F | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Carpenter | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| CA-100FL | 7/5/2017 | |||||||||||
| Floor Layer | $42.09 | $53.76 | $65.42 | X | X | H | H | H | H | H | D | N |
| Apprentice Rates: | ||||||||||||
| 1st year | $32.76 | $39.76 | $46.76 | |||||||||
| 2nd year | $35.09 | $43.26 | $51.42 | |||||||||
| 3rd year | $37.42 | $46.75 | $56.08 | |||||||||
| 4th year | $38.59 | $48.50 | $58.42 | |||||||||
| comment | make up day allowed | |||||||||||
| Saturday | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ========================================================================================================= | ||||||||||||
| Official Request #: | 71 | Official Rate Schedule | ||||||||||
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted | ||||||||||
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy | ||||||||||
| of all prevailing wage and fringe benefit rates | ||||||||||||
| Project Number: | To be determined | prescribed in a contract. | ||||||||||
| County: | Cass | |||||||||||
| Page 2 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 3 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| CA-525 | 7/5/2017 | |||||||||||
| Carpenter | $41.35 | $52.43 | $63.50 | X | X | H | H | H | H | H | D | N |
| Apprentice Rates: | ||||||||||||
| 1st year | $34.70 | $42.45 | $50.20 | |||||||||
| 2nd year | $35.81 | $44.12 | $52.42 | |||||||||
| 3rd year | $38.03 | $47.44 | $56.86 | |||||||||
| 4th year | $40.24 | $50.76 | $61.28 | |||||||||
| comment | make up day allowed | |||||||||||
| Saturday | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| CA-525-FL | 7/5/2017 | |||||||||||
| Resilient Floorlayer | $42.09 | $53.76 | $65.42 | X | X | X | H | H | H | H | D | N |
| Apprentice Rates: | ||||||||||||
| 1st year | $32.76 | $39.76 | $46.76 | |||||||||
| 2nd year | $35.09 | $43.26 | $51.42 | |||||||||
| 3rd year | $37.42 | $46.75 | $56.08 | |||||||||
| 4th year | $38.59 | $48.50 | $58.42 |
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Cement Mason | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| BR9-17-CM | 11/9/2016 | |||||||||||
| Cement Mason | $42.48 | $53.97 | $65.46 | X | X | H | X | X | X | H | D | Y |
| Apprentice Rates: | ||||||||||||
| 0 - 749 hours | $33.68 | $41.03 | $48.37 | |||||||||
| 750 - 1,499 hours | $34.94 | $42.91 | $50.89 | |||||||||
| 1,500 - 2,249 hours | $36.20 | $44.81 | $53.41 | |||||||||
| 2,250 - 2,999 hours | $37.45 | $46.68 | $55.91 | |||||||||
| 3,000 - 3,749 hours | $38.71 | $48.57 | $58.43 | |||||||||
| 3,750 - 4,499 hours | $39.97 | $50.46 | $60.95 | |||||||||
| comment | ||||||||||||
| Four 10s allowed M-F | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| PL16-14 | 8/18/2016 | |||||||||||
| Cement Mason | $40.88 | $54.37 | $67.86 | H | H | H | H | H | H | H | D | Y |
| Apprentice Rates: | ||||||||||||
| 1st year | $31.44 | $40.21 | $48.98 | |||||||||
| 2nd year | $34.14 | $44.26 | $54.38 | |||||||||
| 3rd year | $36.83 | $48.30 | $59.76 | |||||||||
| ========================================================================================================= | ||||||||||||
| Official Request #: | 71 | Official Rate Schedule | ||||||||||
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted | ||||||||||
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy | ||||||||||
| of all prevailing wage and fringe benefit rates | ||||||||||||
| Project Number: | To be determined | prescribed in a contract. | ||||||||||
| County: | Cass | |||||||||||
| Page 3 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 4 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| comment | make up day allowed | |||||||||||
| Four 10s allowed Monday-Thursday with Friday or Saturday inclement weather make up | ||||||||||||
| days. Saturday hours for inclement weather make up shall be paid straight rate unless | ||||||||||||
| over 40 hours worked. | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Electrician | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| EC-153-IW | 5/26/2017 | |||||||||||
| Journeyman Electrician - Inside Wireman | $55.48 | $72.79 | $90.09 | H | H | H | H | H | H | H | D | Y |
| Apprentice Rates: | ||||||||||||
| 1st period | $23.87 | $30.79 | $37.72 | |||||||||
| 2nd period | $26.65 | $34.44 | $42.23 | |||||||||
| 3rd period | $30.11 | $39.63 | $49.15 | |||||||||
| 4th period | $36.03 | $47.27 | $58.52 | |||||||||
| 5th period | $41.94 | $54.91 | $67.89 | |||||||||
| 6th period | $47.84 | $62.55 | $77.25 | |||||||||
| comment | make up day allowed | |||||||||||
| Four tens may be worked if consecutive days Monday-Thursday, Friday make up day for | ||||||||||||
| 4 10s. | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| EC-153-SC | 5/26/2017 | |||||||||||
| Sound and Communication Installer/Technician | $42.20 | $55.59 | $68.98 | H | H | H | H | H | H | H | D | Y |
| Apprentice Rates: | ||||||||||||
| Period 1 | $23.87 | $30.79 | $37.72 | |||||||||
| Period 2 | $26.65 | $34.44 | $42.23 | |||||||||
| Period 3 | $30.11 | $39.63 | $49.15 | |||||||||
| Period 4 | $35.51 | $45.55 | $55.59 | |||||||||
| Period 5 | $36.84 | $47.56 | $58.27 | |||||||||
| Period 6 | $38.18 | $49.56 | $60.95 | |||||||||
| comment | make up day allowed | |||||||||||
| 4 10s allowed M-Th or if a holiday falls on a M, T-F | ||||||||||||
| Friday make up day | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Elevator Constructor | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| EL-44 | 2/4/2015 | |||||||||||
| Elevator Constructor Mechanic | $77.53 | $122.30 | D | D | D | D | D | D | D | D | Y | |
| Apprentice Rates: | ||||||||||||
| 1st year | $55.41 | $80.03 | ||||||||||
| 2nd year | $60.33 | $89.43 | ||||||||||
| 3rd year | $62.79 | $94.13 | ||||||||||
| 4th year | $67.71 | $103.53 | ||||||||||
| ========================================================================================================= | ||||||||||||
| Official Request #: | 71 | Official Rate Schedule | ||||||||||
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted | ||||||||||
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy | ||||||||||
| of all prevailing wage and fringe benefit rates | ||||||||||||
| Project Number: | To be determined | prescribed in a contract. | ||||||||||
| County: | Cass | |||||||||||
| Page 4 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 5 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| comment | ||||||||||||
| 4 10s allowed M-Th | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Glazier | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| GL-1165 | 6/15/2016 | |||||||||||
| Glazier | $40.34 | $53.17 | $66.00 | H | H | H | H | H | H | D | D | Y |
| Apprentice Rates: | ||||||||||||
| 1st 6 months | $27.51 | $33.92 | $40.34 | |||||||||
| 2nd 6 months | $28.79 | $35.84 | $42.90 | |||||||||
| 3rd 6 months | $30.08 | $37.78 | $45.48 | |||||||||
| 4th 6 months | $31.36 | $39.70 | $48.04 | |||||||||
| 5th 6 months | $32.64 | $41.62 | $50.60 | |||||||||
| 6th 6 months | $33.92 | $43.54 | $53.16 | |||||||||
| 7th 6 months | $35.21 | $45.48 | $55.74 | |||||||||
| 8th 6 months | $37.77 | $49.32 | $60.86 | |||||||||
| comment | make up day allowed | |||||||||||
| 4 10s allowed M-F on consecutive days, for work missed due to holidays or inclement | ||||||||||||
| weather M-F | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Heat and Frost Insulator | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| AS25S | 3/31/2017 | |||||||||||
| Spray Insulation - Qualified Senior Sprayer, application of all products | $29.04 | $42.35 | X | X | X | H | H | H | H | H | N |
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Heat and Frost Insulator and Asbestos Worker | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| AW75 | 3/31/2017 | |||||||||||
| Heat and Frost Insulators and Asbestos Workers | $52.29 | $74.00 | $95.70 | H | H | D | H | D | D | D | D | N |
| Apprentice Rates: | ||||||||||||
| Pre-Apprentice | $38.11 | $52.73 | $67.34 | |||||||||
| 1st Year | $39.69 | $55.10 | $70.50 | |||||||||
| 2nd Year | $42.84 | $59.83 | $76.80 | |||||||||
| 3rd Year | $45.99 | $64.55 | $83.10 | |||||||||
| 4th Year | $49.14 | $69.27 | $89.40 |
| .................................................................................................................................................................................................................................. | ||
| ========================================================================================================= | ||
| Official Request #: | 71 | Official Rate Schedule |
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted |
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy |
| of all prevailing wage and fringe benefit rates | ||
| Project Number: | To be determined | prescribed in a contract. |
| County: | Cass | |
| Page 5 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 6 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Ironworker | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| IR-25-F2 | 3/31/2017 | |||||||||||
| Fence, Sound Barrier & Guardrail erection/installation and Exterior | $31.95 | $42.05 | $52.15 | X | X | H | X | X | X | H | D | Y |
| Signage work | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 60% Level | $22.99 | $29.05 | $35.11 | |||||||||
| 65% Level | $24.11 | $30.68 | $37.24 | |||||||||
| 70% Level | $25.24 | $32.31 | $39.38 | |||||||||
| 75% Level | $26.35 | $33.92 | $41.50 | |||||||||
| 80% Level | $27.47 | $35.55 | $43.63 | |||||||||
| 85% Level | $28.59 | $37.18 | $45.76 | |||||||||
| comment | ||||||||||||
| Four ten hour work days may be worked during Monday-Saturday. | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| IR-25-PE-Z2 | 3/31/2017 | |||||||||||
| Pre-engineered Metal Work | $45.87 | $56.03 | $66.19 | X | X | H | X | X | X | X | D | Y |
| Apprentice Rates: | ||||||||||||
| Probation 1st Year | $26.83 | $32.03 | $37.23 | |||||||||
| 1st Level | $28.96 | $34.92 | $40.88 | |||||||||
| 2nd Level | $28.96 | $34.92 | $40.88 | |||||||||
| 3rd Level | $31.08 | $37.79 | $44.50 | |||||||||
| 4th Level | $33.21 | $40.68 | $48.15 | |||||||||
| 5th Level | $35.33 | $43.55 | $51.77 | |||||||||
| 6th Level | $37.46 | $46.43 | $55.41 | |||||||||
| comment | make up day allowed | |||||||||||
| 4 tens allowed M-Th with Saturday make up day | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| IR-292 | 9/5/2007 | |||||||||||
| Ironworker | $38.66 | $50.16 | $61.66 | H | H | H | H | H | H | H | D | N |
| Apprentice Rates: | ||||||||||||
| 1st year | $29.46 | $36.36 | $43.26 | |||||||||
| 2nd year | $31.76 | $39.81 | $47.86 | |||||||||
| 3rd year | $34.06 | $43.26 | $52.46 | |||||||||
| 4th year | $36.36 | $46.71 | $57.06 | |||||||||
| make up day allowed | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| IR-292-CW | 9/5/2007 | |||||||||||
| Certified - Welder / CAD Welder | $39.16 | $50.91 | $62.66 | H | H | H | H | H | H | H | D | N |
| ========================================================================================================= | ||||||||||||
| Official Request #: | 71 | Official Rate Schedule | ||||||||||
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted | ||||||||||
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy | ||||||||||
| of all prevailing wage and fringe benefit rates | ||||||||||||
| Project Number: | To be determined | prescribed in a contract. | ||||||||||
| County: | Cass | |||||||||||
| Page 6 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 7 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| make up day allowed | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Laborer | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| L355-1-A | 5/31/2017 | |||||||||||
| Class A Laborer - All Construction Laborers on buildings, pumps, well | $33.19 | $43.30 | $53.41 | X | X | H | H | H | H | H | D | Y |
| wheels, air, electric or gasoline tools, motor driven buggies, Laborers on | ||||||||||||
| fire watch duty, working on swing scaffolds, heavy construction work, | ||||||||||||
| confined space and FME, carpenter tender, cement finisher tender, | ||||||||||||
| heater tender, flagperson, except foremen and others falling within | ||||||||||||
| specified classifications. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $28.13 | $35.71 | $43.29 | |||||||||
| 1,001-2,000 work hours | $29.15 | $37.24 | $45.33 | |||||||||
| 2,001-3,000 work hours | $30.16 | $38.75 | $47.35 | |||||||||
| 3,001-4,000 work hours | $32.18 | $41.79 | $51.39 | |||||||||
| comment | make up day allowed | |||||||||||
| Monday - Saturday | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| L355-1-B | 5/31/2017 | |||||||||||
| Class B Laborer - jackhammer operator, crocklayer and caisson worker | $33.44 | $43.68 | $53.91 | X | X | H | H | H | H | H | D | Y |
| in buildings | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $28.32 | $35.99 | $43.67 | |||||||||
| 1,001-2,000 work hours | $29.35 | $37.54 | $45.73 | |||||||||
| 2,001-3,000 work hours | $30.37 | $39.07 | $47.77 | |||||||||
| 3,001-4,000 work hours | $32.42 | $42.15 | $51.87 | |||||||||
| comment | make up day allowed | |||||||||||
| Monday - Saturday | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| L355-1-C | 5/31/2017 | |||||||||||
| Class C Laborer - Top men on chimneys or towers over thirty feet (30’) | $33.94 | $44.43 | $54.91 | X | X | H | H | H | H | H | D | Y |
| in height, material mixers, operators of portable mixers, plasterer | ||||||||||||
| tenders, mason tenders that have received certification from the MLTAI | ||||||||||||
| for mason tending, and MLTAI-certified demolition burner. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $28.70 | $36.57 | $44.43 | |||||||||
| 1,001-2,000 work hours | $29.75 | $38.14 | $46.53 | |||||||||
| 2,001-3,000 work hours | $30.79 | $39.70 | $48.61 | |||||||||
| 3,001-4,000 work hours | $32.89 | $42.85 | $52.81 | |||||||||
| comment | make up day allowed | |||||||||||
| Monday - Saturday | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ========================================================================================================= | ||||||||||||
| Official Request #: | 71 | Official Rate Schedule | ||||||||||
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted | ||||||||||
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy | ||||||||||
| of all prevailing wage and fringe benefit rates | ||||||||||||
| Project Number: | To be determined | prescribed in a contract. | ||||||||||
| County: | Cass | |||||||||||
| Page 7 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 8 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| L355-1-D | 5/31/2017 | |||||||||||
| Class D Laborer - Concrete Specialist When there are no Cement | $38.39 | $51.05 | $63.71 | X | X | H | H | H | H | H | D | Y |
| Finishers available, the classification of Concrete Specialist may be | ||||||||||||
| utilized and shall include troweling, finishing, screeding, patching, cutting | ||||||||||||
| and curing of cast in place or precast concrete by any and all methods. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $32.06 | $41.55 | $51.05 | |||||||||
| 1,001-2,000 work hours | $33.33 | $43.46 | $53.59 | |||||||||
| 2,001-3,000 work hours | $34.59 | $45.35 | $56.11 | |||||||||
| 3,001-4,000 work hours | $37.12 | $49.15 | $61.17 | |||||||||
| comment | make up day allowed | |||||||||||
| Monday - Saturday | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Laborer - Hazardous | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| LHAZ-Z9-A | 11/13/2017 | |||||||||||
| Class A Laborer - performing work in conjunction with site preparation | $32.92 | $46.40 | $59.87 | H | H | H | H | H | H | H | D | Y |
| and other preliminary work prior to actual removal, handling, or | ||||||||||||
| containment of hazardous waste substances not requiring use of | ||||||||||||
| personal protective equipment required by state or federal regulations; | ||||||||||||
| or a laborer performing work in conjunction with the removal , handling, | ||||||||||||
| or containment of hazardous waste substances when use of personal | ||||||||||||
| protective equipment level " D" is required. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $27.93 | $38.91 | $49.89 | |||||||||
| 1,001-2,000 work hours | $28.93 | $40.41 | $51.89 | |||||||||
| 2,001-3,000 work hours | $29.93 | $41.91 | $53.89 | |||||||||
| 3,001-4,000 work hours | $31.92 | $44.89 | $57.87 | |||||||||
| comment | make up day allowed | |||||||||||
| 4 10s allowed M-Th or T-F; inclement weather makeup day Friday | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| LHAZ-Z9-B | 11/13/2017 | |||||||||||
| Class B Laborer - performing work in conjunction with the removal, | $33.92 | $47.90 | $61.87 | H | H | H | H | H | H | H | D | Y |
| handling, or containment of hazardous waste substances when the use | ||||||||||||
| of personal protective equipment levels "A", "B" or "C" is required. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $28.68 | $40.03 | $51.39 | |||||||||
| 1,001-2,000 work hours | $29.73 | $41.61 | $53.49 | |||||||||
| 2,001-3,000 work hours | $30.78 | $43.19 | $55.59 | |||||||||
| 3,001-4,000 work hours | $32.87 | $46.32 | $59.77 | |||||||||
| comment | make up day allowed | |||||||||||
| 4 10s allowed M-Th or T-F; inclement weather makeup day Friday | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ========================================================================================================= | ||||||||||||
| Official Request #: | 71 | Official Rate Schedule | ||||||||||
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted | ||||||||||
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy | ||||||||||
| of all prevailing wage and fringe benefit rates | ||||||||||||
| Project Number: | To be determined | prescribed in a contract. | ||||||||||
| County: | Cass | |||||||||||
| Page 8 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 9 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Laborer Underground - Open Cut, Class I | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| LAUC-Z4-1 | 9/7/2017 | |||||||||||
| Construction Laborer | $33.67 | $43.98 | $54.27 | X | X | X | X | X | X | X | D | Y |
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $29.17 | $37.22 | $45.27 | |||||||||
| 1,001-2,000 work hours | $30.07 | $38.58 | $47.07 | |||||||||
| 2,001-3,000 work hours | $30.97 | $39.92 | $48.87 | |||||||||
| 3,001-4,000 work hours | $32.77 | $42.62 | $52.47 |
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Laborer Underground - Open Cut, Class II | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| LAUC-Z4-2 | 9/5/2017 | |||||||||||
| Mortar and material mixer, concrete form man, signal man, well point | $33.80 | $44.17 | $54.53 | X | X | X | X | X | X | X | D | Y |
| man, manhole, headwall and catch basin builder, guard rail builders, | ||||||||||||
| headwall, seawall, breakwall, dock builder and fence erector. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $29.26 | $37.36 | $45.45 | |||||||||
| 1,001-2,000 work hours | $30.17 | $38.72 | $47.27 | |||||||||
| 2,001-3,000 work hours | $31.08 | $40.09 | $49.09 | |||||||||
| 3,001-4,000 work hours | $32.89 | $42.80 | $52.71 |
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Laborer Underground - Open Cut, Class III | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| LAUC-Z4-3 | 9/7/2017 | |||||||||||
| Air, gasoline and electric tool operator, vibrator operator, drillers, pump | $33.91 | $44.34 | $54.75 | X | X | X | X | X | X | X | D | Y |
| man, tar kettle operator, bracers, rodder, reinforced steel or mesh man | ||||||||||||
| (e.g. wire mesh, steel mats, dowel bars, etc.), cement finisher, welder, | ||||||||||||
| pipe jacking and boring man, wagon drill and air track operator and | ||||||||||||
| concrete saw operator (under 40 h.p.), windlass and tugger man, and | ||||||||||||
| directional boring man. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $29.35 | $37.50 | $45.63 | |||||||||
| 1,001-2,000 work hours | $30.26 | $38.86 | $47.45 | |||||||||
| 2,001-3,000 work hours | $31.17 | $40.22 | $49.27 | |||||||||
| 3,001-4,000 work hours | $33.00 | $42.97 | $52.93 |
| .................................................................................................................................................................................................................................. | ||
| ========================================================================================================= | ||
| Official Request #: | 71 | Official Rate Schedule |
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted |
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy |
| of all prevailing wage and fringe benefit rates | ||
| Project Number: | To be determined | prescribed in a contract. |
| County: | Cass | |
| Page 9 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 10 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Laborer Underground - Open Cut, Class IV | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| LAUC-Z4-4 | 9/7/2017 | |||||||||||
| Trench or excavating grade man. | $33.98 | $44.44 | $54.89 | X | X | X | X | X | X | X | D | Y |
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $29.40 | $37.57 | $45.73 | |||||||||
| 1,001-2,000 work hours | $30.32 | $38.95 | $47.57 | |||||||||
| 2,001-3,000 work hours | $31.23 | $40.32 | $49.39 | |||||||||
| 3,001-4,000 work hours | $33.06 | $43.06 | $53.05 |
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Laborer Underground - Open Cut, Class V | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| LAUC-Z4-5 | 9/7/2017 | |||||||||||
| Pipe Layer | $34.10 | $44.62 | $55.13 | X | X | X | X | X | X | X | D | Y |
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $29.49 | $37.70 | $45.91 | |||||||||
| 1,001-2,000 work hours | $30.41 | $39.08 | $47.75 | |||||||||
| 2,001-3,000 work hours | $31.33 | $40.46 | $49.59 | |||||||||
| 3,001-4,000 work hours | $33.18 | $43.24 | $53.29 |
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Laborer Underground - Open Cut, Class VI | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| LAUC-Z4-6 | 9/7/2017 | |||||||||||
| Grouting man, top man assistant, audio visual television operations and | $31.32 | $40.45 | $49.57 | X | X | X | X | X | X | X | D | Y |
| all other operations in connection with closed circuit television inspection, | ||||||||||||
| pipe cleaning and pipe relining work & the installation and repair of | ||||||||||||
| water service pipe and appurtenances. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $27.40 | $34.57 | $41.73 | |||||||||
| 1,001-2,000 work hours | $28.19 | $35.76 | $43.31 | |||||||||
| 2,001-3,000 work hours | $28.97 | $36.92 | $44.87 | |||||||||
| 3,001-4,000 work hours | $30.54 | $39.28 | $48.01 |
| .................................................................................................................................................................................................................................. | ||
| ========================================================================================================= | ||
| Official Request #: | 71 | Official Rate Schedule |
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted |
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy |
| of all prevailing wage and fringe benefit rates | ||
| Project Number: | To be determined | prescribed in a contract. |
| County: | Cass | |
| Page 10 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 11 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Laborer Underground - Open Cut, Class VII | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| LAUC-Z4-7 | 9/7/2017 | |||||||||||
| Restoration laborer, seeding, sodding, planting, cutting, mulching and | $29.66 | $37.96 | $46.25 | X | X | X | X | X | X | X | D | Y |
| topsoil grading and the restoration of property such as replacing mail | ||||||||||||
| boxes, wood chips, planter boxes, flagstones etc. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $26.16 | $32.71 | $39.25 | |||||||||
| 1,001-2,000 work hours | $26.86 | $33.76 | $40.65 | |||||||||
| 2,001-3,000 work hours | $27.56 | $34.81 | $42.05 | |||||||||
| 3,001-4,000 work hours | $28.96 | $36.91 | $44.85 |
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Laborer Underground - Tunnel, Shaft & Caisson | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| LAUCT-Z2-1 | 9/7/2017 | |||||||||||
| Class I - Tunnel, shaft and caisson laborer, dump man, shanty man, | $36.82 | $48.70 | $60.57 | X | X | X | X | X | X | X | D | Y |
| hog house tender, testing man (on gas), and watchman. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $31.52 | $40.75 | $49.97 | |||||||||
| 1,001-2,000 work hours | $32.58 | $42.34 | $52.09 | |||||||||
| 2,001-3,000 work hours | $33.64 | $43.93 | $54.21 | |||||||||
| 3,001-4,000 work hours | $35.76 | $47.11 | $58.45 |
| .................................................................................................................................................................................................................................. | ||||||||||||
| LAUCT-Z2-2 | 9/7/2017 | |||||||||||
| Class II - Manhole, headwall, catch basin builder, bricklayer tender, | $36.91 | $48.83 | $60.75 | X | X | X | X | X | X | X | D | Y |
| mortar man, material mixer, fence erector, and guard rail builder | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $31.58 | $40.84 | $50.09 | |||||||||
| 1,001-2,000 work hours | $32.65 | $42.45 | $52.23 | |||||||||
| 2,001-3,000 work hours | $33.71 | $44.03 | $54.35 | |||||||||
| 3,001-4,000 work hours | $35.84 | $47.23 | $58.61 |
| .................................................................................................................................................................................................................................. | ||
| ========================================================================================================= | ||
| Official Request #: | 71 | Official Rate Schedule |
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted |
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy |
| of all prevailing wage and fringe benefit rates | ||
| Project Number: | To be determined | prescribed in a contract. |
| County: | Cass | |
| Page 11 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 12 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| LAUCT-Z2-3 | 9/7/2017 | |||||||||||
| Class III - Air tool operator (jack hammer man, bush hammer man and | $37.01 | $48.98 | $60.95 | X | X | X | X | X | X | X | D | Y |
| grinding man), first bottom man, second bottom man, cage tender, car | ||||||||||||
| pusher, carrier man, concrete man, concrete form man, concrete repair | ||||||||||||
| man, cement invert laborer, cement finisher, concrete shoveler, | ||||||||||||
| conveyor man, floor man, gasoline and electric tool operator, gunnite | ||||||||||||
| man, grout operator, welder, heading dinky man, inside lock tender, | ||||||||||||
| pea gravel operator, pump man, outside lock tender, scaffold man, top | ||||||||||||
| signal man, switch man, track man, tugger man, utility man, vibrator | ||||||||||||
| man, winch operator, pipe jacking man, wagon drill and air track | ||||||||||||
| operator and concrete saw operator (under 40 h.p.). | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $31.66 | $40.96 | $50.25 | |||||||||
| 1,001-2,000 work hours | $32.73 | $42.57 | $52.39 | |||||||||
| 2,001-3,000 work hours | $33.80 | $44.17 | $54.53 | |||||||||
| 3,001-4,000 work hours | $35.94 | $47.38 | $58.81 |
| .................................................................................................................................................................................................................................. | ||||||||||||
| LAUCT-Z2-4 | 9/7/2017 | |||||||||||
| Class IV - Tunnel, shaft and caisson mucker, bracer man, liner plate | $37.17 | $49.22 | $61.27 | X | X | X | X | X | X | X | D | Y |
| man, long haul dinky driver and well point man. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $31.78 | $41.14 | $50.49 | |||||||||
| 1,001-2,000 work hours | $32.86 | $42.76 | $52.65 | |||||||||
| 2,001-3,000 work hours | $33.93 | $44.37 | $54.79 | |||||||||
| 3,001-4,000 work hours | $36.09 | $47.61 | $59.11 |
| .................................................................................................................................................................................................................................. | ||||||||||||
| LAUCT-Z2-5 | 9/7/2017 | |||||||||||
| Class V - Tunnel, shaft and caisson miner, drill runner, keyboard | $37.43 | $49.62 | $61.79 | X | X | X | X | X | X | X | D | Y |
| operator, power knife operator, reinforced steel or mesh man (e.g. wire | ||||||||||||
| mesh, steel mats, dowel bars) | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $31.97 | $41.43 | $50.87 | |||||||||
| 1,001-2,000 work hours | $33.06 | $43.06 | $53.05 | |||||||||
| 2,001-3,000 work hours | $34.16 | $44.71 | $55.25 | |||||||||
| 3,001-4,000 work hours | $36.34 | $47.98 | $59.61 |
| .................................................................................................................................................................................................................................. | ||
| ========================================================================================================= | ||
| Official Request #: | 71 | Official Rate Schedule |
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted |
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy |
| of all prevailing wage and fringe benefit rates | ||
| Project Number: | To be determined | prescribed in a contract. |
| County: | Cass | |
| Page 12 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 13 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| LAUCT-Z2-6 | 9/7/2017 | |||||||||||
| Class VI - Dynamite man and powder man. | $37.74 | $50.08 | $62.41 | X | X | X | X | X | X | X | D | Y |
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $32.20 | $41.77 | $51.33 | |||||||||
| 1,001-2,000 work hours | $33.31 | $43.43 | $53.55 | |||||||||
| 2,001-3,000 work hours | $34.42 | $45.10 | $55.77 | |||||||||
| 3,001-4,000 work hours | $36.63 | $48.41 | $60.19 |
| .................................................................................................................................................................................................................................. | ||||||||||||
| LAUCT-Z2-7 | 9/7/2017 | |||||||||||
| Class VII - Restoration laborer, seeding, sodding, planting, cutting, | $30.01 | $38.48 | $46.95 | X | X | X | X | X | X | X | D | Y |
| mulching and topsoil grading and the restoration of property such as | ||||||||||||
| replacing mail boxes, wood chips, planter boxes and flagstones. | ||||||||||||
| Apprentice Rates: | ||||||||||||
| 0-1,000 work hours | $26.41 | $33.09 | $39.75 | |||||||||
| 1,001-2,000 work hours | $27.13 | $34.17 | $41.19 | |||||||||
| 2,001-3,000 work hours | $27.85 | $35.25 | $42.63 | |||||||||
| 3,001-4,000 work hours | $29.29 | $37.41 | $45.51 |
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Landscape Laborer | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| LLAN-Z2-A | 10/13/2015 | |||||||||||
| Landscape Specialist: includes air, gas, and diesel equipment operator, | $28.25 | $39.04 | $49.82 | X | X | H | X | X | X | H | D | Y |
| skidsteer (or equivalent), lawn sprinkler installer on landscaping work | ||||||||||||
| where seeding, sodding, planting, cutting, trimming, backfilling, rough | ||||||||||||
| grading or maintenance of landscape projects occurs. | ||||||||||||
| comment | ||||||||||||
| Sundays paid at time & one half. Holidays paid at double time. | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| LLAN-Z2-B | 10/13/2015 | |||||||||||
| Skilled Landscape Laborer: small power tool operator, lawn sprinkler | $24.05 | $32.74 | $41.42 | X | X | H | X | X | X | H | D | Y |
| installers' tender, material mover, truck driver on when seeding, | ||||||||||||
| sodding, planting, cutting, trimming, backfilling, rough grading or | ||||||||||||
| maintaining of landscape projects occurs | ||||||||||||
| comment | ||||||||||||
| Sundays paid at time & one half. Holidays paid at double time. | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| Operating Engineer | ||||||||||||
| ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ | ||||||||||||
| EN-AC | 6/7/2017 | |||||||||||
| Compressor or Welding Machine | $46.07 | $57.38 | $68.68 | X | X | H | H | D | D | D | D | Y |
| ========================================================================================================= | ||||||||||||
| Official Request #: | 71 | Official Rate Schedule | ||||||||||
| Requestor: | Dowagiac Union School District | Every contractor and subcontractor shall keep posted | ||||||||||
| Project Description: | To be determined | on the construction site, in a conspicuous place, a copy | ||||||||||
| of all prevailing wage and fringe benefit rates | ||||||||||||
| Project Number: | To be determined | prescribed in a contract. | ||||||||||
| County: | Cass | |||||||||||
| Page 13 of 25 |
| Official 2018 Commercial Prevailing Wage Rates for State Funded Projects | ||||||||||||
| Issue Date: | 1/17/2018 | |||||||||||
| Contract must be awarded by: | 4/17/2018 | |||||||||||
| Page 14 of 25 | ||||||||||||
| Classification | Last | Straight | Time and a | Double | Overtime | |||||||
| Name | Description | Updated | Hourly | Half | Time | Provision | ||||||
| ========================================================================================================= | ||||||||||||
| comment | make up day allowed | |||||||||||
| Friday, Four 10 hour days may be scheduled Monday-Thursday or Tuesday-Friday. | ||||||||||||
| Work not performed due to weather, Monday-Thursday may be scheduled on Friday. | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| EN-F | 6/7/2017 | |||||||||||
| Forklift or Straight Mast | $47.52 | $59.55 | $71.58 | X | X | H | H | D | D | D | D | Y |
| comment | make up day allowed | |||||||||||
| Four 10 hour days may be scheduled M-Th or T-F. Work not performed due to weather | ||||||||||||
| on M-Th may be scheduled on Friday | ||||||||||||
| .................................................................................................................................................................................................................................. | ||||||||||||
| EN-FO | 6/7/2017 | |||||||||||
| Fireman or Oiler | $45.04 | $55.83 | $66.62 | X | X | H | H | D | D | D | D | Y |
| comment | make up day allowed |
This is the start of the file's text. The full file is on GovTribe.
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .